Weekly Report for SM MOM #111 of RWEP
(2016.10.14 - 2016.10.20)
1. Personnel
1.1 Personnel on Project Management Office (PMO)
No. Position Quantity Company
1 Project Manager 1 CIL
2 Operations Manager 2 CIL
3 Communications Manager 3 CIL
4 Site Manager 1 CNEEC
3 CIL
5 Engineer
7 CNEEC
6 Interpreter 3 CNEEC
7 Designing Representative 1 CNEEC
8 Accountant 1 CNEEC
9 Filing Management 2 CNEEC
10 Reception 2 CNEEC
11 Assistant 1 CNEEC
12 Chef 1 CNEEC
13 Housekeeper 3 CNEEC
14 Security Guard 2 CNEEC
15 Car Driver 2 CNEEC
Subtotal 0
1.2 Personnel for Civil Work on Reppie Site
No Type of Worker Chinese Ethiopian
1 Management 23 2
2 Rebar worker 1 2
3 Woodworker and scaffolder 2 6
4 Concrete worker 1 4
5 Welder 7 4
6 Fitter 2 0
7 Steel Structure flaw detection worker 1 0
8 Site construction helper 0 6
9 Erection worker 7 5
10 Operator 5 2
11 Electric worker 1 0
12 Equipment worker 1 0
13 Handyman 1 5
14 Security guard 0 9
15 Masonry worker 3 5
16 Decoration worker 7 15
Corrosion prevention and waterproof
17 3 10
worker
18 Others (kitchen helper and cleaner) 2 5
Subtotal 0 0
1 / 13
1.3 Personnel for M&E Erection Work on Reppie Site
No Type of Worker Chinese Ethiopian
1 Management 29 0
2 Welder 13 0
3 Fitter 71 0
4 Flaw detection worker 4 0
5 Adjustor 3 0
6 Turbine erection 0 0
7 Electrical erection 28 0
8 Insulation 5
Subtotal 0 0
2. Equipment
No Name Quantity
1. Concrete mixing station(750l) 1
2 Pump truck (37m) 1
3 Tanker (7m³) 2
4 Loader (ZL50) 1
5 Road roller(5T) 1
5 Mortar mixing machine (350) 3
6 Concrete vibrators 10
7 Vibrostand 7
8 Tower crane (MC80A) 1
9 Mobile crane (65t) 1
10 Mobile crane (25t) 1
11 Crawler crane (150t) 1
12 400t crane 1
13 Platform truck (10t) 1
14 Platform truck (5t) 1
15 Winch(JJ.M2t) 1
16 Forklift (3t and 5t) 2
17 Reinforcing steel cutter(6~40) 3
18 Steel bar bender(6~40) 3
19 Steel bar straightener(GF4-40) 1
20 Abrasive wheel cutting machine(CGT1-30) 1
21 Woodworking circular saw(MJ106) 2
22 Wood planer(MB104A) 1
23 Electric hand drill 10
24 Rock drill 1
25 Backhoe excavator(1m³) 3
26 Dump truck (15t) 8
27 Tamping machine 7
28 Breaker 1
29 AC welder (type 500) 8
2 / 13
No Name Quantity
30 DC welder(ZXS-630) 4
31 Electric threading machine(DN15-DN100) 1
32 Trigger squeeze 1
33 Manual pump(4D20Y-100/10) 1
34 Water pump (head 120m) 1
35 Pressure pump( head 50m) 1
36 Hydraulic pipe bender(DN15-DN125) 2
37 Volt-ammeter 1
38 Digital multimeter(F-87) 2
39 Angle grinder (100 and 180) 5
40 Spanner(QL1800 and QL2200) 2
41 Bolt spanner(M24,M20 and M16) 3
42 Diesel generator 4
43 Submerged pump 1
44 Light truck (2.8t) 1
45 Pickup truck 1
46 Electronic scale(200g-30Kg)(Soil test equipment) 1
47 Electronic scale (1Kg) (Soil test equipment) 1
48 Digital Ultrasonic Flaw Detector 1
3. Supply of Material
Material Material Material Material in Sample taken
name delivered consumed stock
Rebar 0t 0.5t 3t No sample was taken.
Cement 0t 20t 35t No need for sample taken.
Gravel 0m³ 57m³ 95m³ No need for sample taken.
Sand 150m³ 60m³ 121m³ No sample was taken.
3 / 13
4. Works completion status of this week
4.1 Civil work
Planned
Planned finish
WBS Construction task starting Days Remarks Completion status Next week plan
date
date
1 Main Building
1.1 Tipping Hall
Including To complete 60% of
scaffolding scaffolding for roof
installation, internal panel
Completed 30% of
set up installation.
scaffolding for roof
scaffolding To complete 30% of
Tipping Hall roof internal panel
1.1.1 2016/10/11 2016/11/3 24 while roof bottom panel
panel installation installation. Started
installing installation.
the installation of
panel and
roof bottom panel.
welding
stainless
gutter
To complete 100%
Removal of Tower Work ahead Removal is in
1.1.2 2016/11/1 2016/11/5 5 removal by 22 n d
Crane of time progress.
October.
Completed 100% for None.
Exterior wall stone-
1.1.10 2016/11/20 2016/12/20 31 sample wall (primer
like coating
and finish paint).
1.1.12 Small 2016/10/8 2016/12/30 84 Coordinating
4 / 13
installation( water
supply and Coordinating and
drainage, electrical alternative
construction.
lighting, firefighting, construction.
HVAC and lightning
protection
1.2 Waste Bunker
Remaining internal To complete 100%.
1.2.2 wall putty work in 2016/10/8 2016/10/20 13 Completed 95%
line 23
L+22.00m remaining To complete 100%.
1.2.3 interior wall putty 2016/10/12 2016/10/20 9 Completed 80%.
work
1.2.10 L+17.00m painting 2016/10/20 2016/11/2 14 - To complete 10%.
L0.00m Hall putty To complete 10%.
1.2.16 2016/10/25 2016/10/30 6 -
work
L0.00m line 19~20 To complete 20%.
1.2.20 2016/10/20 2016/11/5 17 -
putty work
Small In progress. Coordinating and
installation( water alternative
supply and construction.
Coordinating
1.2.29 drainage, electrical 2016/10/11 2017/2/28 141
construction
lighting, firefighting,
HVAC and lightning
protection
5 / 13
Remaining exterior - To complete 10%.
1.2.30 wall plastering and 2016/10/20 2016/11/30 42
putty work
2 Access Ramp
3 Boiler Hall
Last piece of steel To complete 100%.
3.1.2 2016/10/8 2016/10/22 15 No activity.
bracket installation
Completed 100% for To complete 95%.
Remaining wall
3.1.4(A remaining wall.
masonry and interior 2016/10/10 2016/10/25 16
) Completed 90% for
plastering
Putty work.
Exterior wall putty Discontinuous To complete 10%.
3.1.12 2016/10/20 2017/1/31 104 -
work and painting construction
Small Coordinating
installation( water construction
supply and
Discontinuous
3.1.13 drainage, electrical 2016/10/12 2016/12/30 80 -
construction
lighting, firefighting,
HVAC and lightning
protection
4 FGT Equipment Foundation
Completed 100% for To complete 70%.
Newly added
lean concrete and
4.1 equipment 2016/10/20 2016/10/30 11 -
50% for rebar
foundation
binding.
6 / 13
5 Turbine Deaerator Bay
6 Main Control Building
To complete 100% for
Fine aggregate L+4.00m fine concrete
6.2.1 2016/10/18 2016/10/21 4 None.
concrete floors aggregate floor
construction.
6.2.2 Floor tile application 2016/10/16 2016/11/20 37 None To complete 10%.
7 Leachate Treatment Station
7.1 Comprehensive Workshop
Roof handrail To complete 100%.
7.1.11 2016/10/10 2016/10/25 16 Completed 80%.
installation
Regulating Tank,
Primary Settling
7.2
Tank and Sludge
Storage Tank
Tank inside wall and To complete cleaning
bottom slab of inside water and
7.2.1 2016/10/10 2016/12/10 62 Inside cleaning.
anticorrosion waste.
application
Ground
7.3.1
construction
7.3.1.1 Acid resistant tile 2016/10/11 2016/12/16 67 Completed 100% for To complete 100% for
application to rooms acid resistant tile acid resistant tile
such as Dosing application in Acid ground leveling layer in
Room, Acid Storage Storage Room. Dosing Room.
7 / 13
Room and Membrane
Treatment Room
L+4.00m interior To complete 20% of
7.3.3 wall putty work and 2016/10/18 2016/11/5 19 None. L+4.00m putty work.
painting
Completed 100% of None
Doors and windows window frames at
7.3.4 2016/10/16 2016/11/15 41
installation ground floor and
L+4.00m.
8 Water Pond
Completed 100% for None.
interior wall
waterproof, bottom
Pond inside wall and
slab leveling layer;
8.1 bottom slab 2016/10/7 2016/10/30 24
And 100% for
waterproof
cement-based
capillary crystalline
application.
9 Water Pump Station
To complete 100% for
9.1.1 Waterproofing layer 2016/11/25 2016/11/30 6 -
roof waterproofing..
Completed 60% for To complete 100% for
Doors and Windows Discontinuous
9.3 2016/10/15 2016/12/30 77 window frames window frames.
installation construction
installation.
10 Cooling Tower
8 / 13
To complete 100% for
Collecting Tank leveling layer. To
Completed 70% for
inside wall and complete 40% for
10.1 2016/10/20 2016/11/25 37 bottom slab leveling
bottom slab bottom slab cement-
layer.
waterproof based capillary
crystalline application.
14 Whole Plant Underground Pipe Network
Underground pipe To complete 20%.
network at eastern
Completed 10% for
14.1 side of Water Pond 2016/10/15 2016/12/30 77
excavation.
and Water Pump
Station
Underground pipe To complete 100% for
Completed 50% for
network at western western side
14.2 2016/10/12 2016/12/30 80 western side
and southern side of excavation.
excavation.
Turbine Hall
15 Whole Plant Cable Trench
C o m p l e t e d 1 0 0 % o fTo complete 100%
Cable trench from
t h e r e m a i n i n g 1 0 m excavation for the
Main Control Building
l e n g t h o f l o n g c a b l e section along Water
to Water Pump Discontinuous
15.1 2016/10/12 2016/11/20 39 t r e n c h a n d w Pond
a t efrom
r - Main
Station, construction
collecting w f ellControl rom
Building to
And from Turbine
T u r b i n eWater Pump
H a Station.
l l t o
Hall to Switchyard
Switchyard.
9 / 13
4.2 Erection Work
Planned
Planned Completion status and the
WBS Construction task starting Days Remarks
finish date reason of unfinished works
date
2.1.2.3 #2 Boiler steam and water 2016/6/16 2016/11/17 155 Completed 80%.
10 / 13
system erection
#2 Boiler platform staircase Completed 10%.
2.1.3.6 #1 Boiler Deacidification 2016/8/11 2016/9/9 Completed 60%
30
Tower erection
2.1.3.12 Activated carbon storehouse Completed 60%.
2016/9/10 2016/9/29 20
erection
2.2.3.2 High pressure water supply Completed 80%.
2016/6/30 2016/8/3 35
pipeline installation
2.2.4 Low pressure pipeline Completed 30%
2016/6/30 2016/9/2 70
installation
2.3 Electrical system erection 2016/4/27 2017/3/31 339
2.3.3 132kV power distribution Complete 30%.
2016/7/22 2017/10/31 102
unit erection
3 Leachate Equipment
erection
3.1 Nitrification Tank erection 2016/7/15 2016/12/15 Completed 70%
Denitrification Tank erection Completed 80%
Anaerobic Tank erection Completed 20%
11 / 13
5. Inspection plan for next week
5.1 Civil Work
Construction area Sub-divisional Work Planned inspection date
1. Drainage Well Bottom Slab Rebar and formwork 26th October, 2016
2. Cooling Tower Bottom Basic layer treatment 23rd October, 2016
3. Water Pond Cement base 23rd October, 2016
4. FGT Area Newly Added Equipment Rebar and formwork 26th October, 2016
Foundations
5.2 Erection Work
5.2.1 Mechanical erection work
None
5.2.2 Electrical erection work
Area Inspection or Test Work Planned inspection date
1. 132kV Current Transformer and Routine testing 24th or 27th October , 2016
Voltage Transformer
6. HSE
HSE is under control this week and no accident or injury was reported. Special personal was assigned to
clear, sort out and store the removed materials from Main Building area, such as the scaffolding formwork
and timber. A safety meeting was held every morning from Monday to Friday. Keep pressure on
supervision of various violations and correct behaviors or places that violate regulations.
Detailed safety measures have been taken this week as follows,
1. Continue cleaning up construction materials at site and sort them out.
2. Safety supervision and protections on high-elevation activities.
3. Cleaning of site road.
4. Drain away water from site area.
12 / 13
7. Transport and delivery
Shipment No. Items ATD/ETD ATA/ETA Status
(Djibouti)
th
25 Cables and steel structure, frequency conversion Jun 15,2016 Jul 18, 2016 All arrived.
cabinet (Tianjin) Closed.
(43 packages and 2 containers in total)
th
26 Air pre-heater (was shut out on Jun 6), valves, steam July 9, 2016 Aug 03, 8 containers arrived.
soot-blower, pipes, windows and doors, etc. (Shanghai) 2016 Truck loading for bulk cargo
(101 packages and 8 containers in total) is undergoing. 98 packages
arrived.
th
27 Casting material, refractory bricks, anchor, calcium Aug 8, 2016 Sep 04, Truck loading is undergoing.
silicate board, flue gas on-line monitoring system (Shanghai) 2016 26 containers arrived.
(26 containers in total)
th
28 Windows and doors, working tools and equipment, Aug 15, 2016 Sep 18, Unloaded at the Djibouti
small distribution boxes, SNCR (Tianjin) 2016 port. Custom transit for 28-
(5 containers in total) 1 and 28-2 is undergoing.
th
29 Windows and doors, laboratory equipment, meters, Aug 18, 2016 Sep 25, Unloaded at the Djibouti
valves (Shanghai) 2016 port. Custom clearance is
(9 containers in total) undergoing.
th
30 Lighting, boiler parts, valves, electric throttle, tools Sep 1, 2016 Sep 21, Unloaded at the Djibouti
(6 containers in total) (Shanghai) 2016 port. Custom clearance for
30-1 is undergoing.
st
31 Ash conveyor Sep 1, 2016 Sep 27, Unloaded at the Djibouti
(4 packages in total) (Shanghai) 2016 port. Custom clearance is
undergoing.
nd
32 Truck scale Sep 21, 2016 TBC On the sea.
(Shanghai)
13 / 13