ABDULLAH HASHIM INDUSTRIAL GASES AND EQUIPMENT CO.LTD.
Doc. Ref.= RA-LFT/ ACCKH-01/20
Dated = 30/07/2020
RISK ASSESMENT
LIFTING LCO2 TANK FROM HORIZONTAL TO VERTICAL POSTION USING MAIN AND TAILING CRANE
ACCIONA KHOBAR
SR. Task or Activity Risk/Danger Initial Risk Control Measure Final Risk
NO. L M H L M H
01 Arrival of personal at Unfamiliar with local situation X Site and safety induction course. All x
site personal to be fully briefed on the task and
responsibilities together with correct use of
PPE
02 Check work location for Insufficient space to set up cranes X Plan in advance X
space and obstacles
Obstacle present X Temporary Remove Obstacle if possible
03 Enter work location Collide with equipment X Follow proper route. Tool box talk. Main
with crane controlling movement of vehicle(crane)
Risk of personal injury X Establish Safety Exclusion zone. Non-
essential personal kept clear
04 Rig cranes at Lifting Inadequate ground bearing capacity X Verify ground bearing capacity with client. x
location If required client to prepare ground in
advance
Incorrect crane configuration X Establish benchmark for crane in advance X
Incorrect crane position X Establish benchmark for crane in advance X
Working at height 2 meter or above X Clear instruction and communication. Use X
of man basket with safety harness.
ABDULLAH HASHIM INDUSTRIAL GASES AND EQUIPMENT CO.LTD.
Doc. Ref.= RA-LFT/ ACCKH-01/20
Dated = 30/07/2020
RISK ASSESMENT
LIFTING LCO2 TANK FROM HORIZONTAL TO VERTICAL POSTION USING MAIN AND TAILING CRANE
ACCIONA KHOBAR
SR. Task or Activity Risk/Danger Initial Risk Control Measure Final Risk
NO. L M H L M H
Unauthorized personnel in working area X Establish Safety Exclusion Zone and remove X
unauthorized personnel.
Load moves unexpectedly when lifting X Use tag lines. Tool box talk, clear X
communication and instruction, keep Hoist
ropes vertical.
05 Lifting of Tank from Unexpected movement of tank X Use tag lines. Tool box talk, clear
Horizontal to Vertical communication and instruction, keep Hoist
position ropes vertical.
Unequal lifting during tandem lift X Supervision/control of crane hoisting. Clear X
instruction and communication. Tool box
talk , crane hook position vertically above
lifting points on the item.
Obstruction in way of lifting from horizontal X Removal of transport saddles, support and X
to vertical trailer from area. Clear all obstruction.
Tailing crane tracking as item lifting form X Clear instruction and communication. Use X
horizontal to vertical, collide with experienced banksman/rigger.
equipment. Personal injury
Unauthorized personnel in working area X Establish Safety Exclusion Zone and remove X
unauthorized personnel.
ABDULLAH HASHIM INDUSTRIAL GASES AND EQUIPMENT CO.LTD.
Doc. Ref.= RA-LFT/ ACCKH-01/20
Dated = 30/07/2020
RISK ASSESMENT
LIFTING LCO2 TANK FROM HORIZONTAL TO VERTICAL POSTION USING MAIN AND TAILING CRANE
ACCIONA KHOBAR
SR. Task or Activity Risk/Danger Initial Risk Control Measure Final Risk
NO. L M H L M H
Adverse weather condition, strong wind X Monitor weather condition constantly, no X
lifting in adverse condition and strong wind
Failure of lifting tackle/equipment X Check all lifting tackle equipment visually to X
ensure proper and safe usage
Ground preparation will not sustain X Set up back filled 7 well compacted ground. x
outrigger loading. Risk of damage to Obtain information from client on
underground services underground services
06 Detach Tail rigging Risk of personal Injury X Clear instruction and communication. x
crane form assist crane Remove non-essential person not involve in
rigging
07 Slew over Construction Personnel working in construction area, risk X Establish Safety Exclusion Zone and remove X
area of personal injury unauthorized personnel from work area
Load moves unexpectedly X Use tag lines. Tool box talk, clear X
communication and instruction,
08 Position Tank in Risk of personal Injury X Tool box talk, clear communication and X
Foundation instruction,
Tank in wrong position or incorrect X Final check for location and orientation X
orientation with foundation against drawing prior to final position
ABDULLAH HASHIM INDUSTRIAL GASES AND EQUIPMENT CO.LTD.
Doc. Ref.= RA-LFT/ ACCKH-01/20
Dated = 30/07/2020
RISK ASSESMENT
LIFTING LCO2 TANK FROM HORIZONTAL TO VERTICAL POSTION USING MAIN AND TAILING CRANE
ACCIONA KHOBAR
SR. Task or Activity Risk/Danger Initial Risk Control Measure Final Risk
NO. L M H L M H
09 Detach lifting gear Risk of personal injury X Tool box talk, clear communication and X
instruction,
Working at height 2 meter or above X Clear instruction and communication. Use X
of man basket with safety harness.
10 Demobilize crane Collide with equipment X Tool box talk, clear communication and X
instruction,
Unauthorized personnel in working area X Establish Safety Exclusion Zone and remove X
unauthorized personnel.
Legend:
L Low
M MEDIUM
H HIGH