Duration
Task Name (Working) Start Finish
LRT DEPOT Building
Works_B0R0_190716 642 days Sat 6/1/19 Wed 7/21/21
RENOVATION OF ADMINISTRATION
BUILDING 473 days Sat 6/1/19 Wed 12/23/20
Project Milestone 473 days Sat 6/1/19 Wed 12/23/20
Notice to Proceed (NTP) 1 day Sat 6/1/19 Sat 6/1/19
Work Permit (Right of Access to the Site) 6 days Mon 6/10/19 Mon 6/17/19
Site Mobilization 0 days Thu 6/13/19 Thu 6/13/19
Building Permit Application 0 days Sat 8/10/19 Sat 8/10/19
Building Permit Approval 0 days Sat 9/14/19 Sat 9/14/19
Completion of Renovation Works 0 days Wed 12/23/20 Wed 12/23/20
Building Permit Preparation 81 days Mon 6/10/19 Sat 9/14/19
Site Structural Investigation 17 days Mon 6/10/19 Sat 6/29/19
Design Drawing Development 33 days Tue 7/2/19 Thu 8/8/19
Architectural & MEP Drawings 51 days Mon 6/10/19 Thu 8/8/19
Building Permit Application 0 days Sat 8/10/19 Sat 8/10/19
Building Official Assessment 27 days Mon 8/12/19 Fri 9/13/19
Building Permit Approval 0 days Sat 9/14/19 Sat 9/14/19
Design Works 59 days Sat 8/10/19 Sat 10/19/19
Structural Drawings 59 days Sat 8/10/19 Sat 10/19/19
Architectural & MEP Drawings 36 days Sat 8/10/19 Mon 9/23/19
For Construction Drawings 0 days Tue 9/24/19 Tue 9/24/19
Procurement 159 days Mon 8/5/19 Sat 2/15/20
Demolition Works 47 days Mon 8/5/19 Mon 9/30/19
Internal Finishing 87 days Mon 8/5/19 Sat 11/16/19
MEP Works 88 days Mon 9/2/19 Sat 12/14/19
Metal Roof 99 days Tue 10/1/19 Fri 1/31/20
External Finishing 101 days Mon 9/16/19 Sat 1/18/20
Miscellaneous RC Works 85 days Sat 11/2/19 Sat 2/15/20
ADMINSTRATION BUILDING RENOVATION 430 days Tue 7/23/19 Wed 12/23/20
Temporary Facilities Set-up 22 days Tue 7/23/19 Fri 8/16/19
Dismantling of Temporary Facilities 31 days Mon 12/23/19 Sat 2/1/20
Area 1 & 2 303 days Wed 7/31/19 Mon 8/3/20
Preparation of New Area for Client Transfer
at Area 3 38 days Wed 7/31/19 Sat 9/14/19
MEP Adjustments of Electrical Power and
other Utilities Prior to Demolition 37 days Thu 8/15/19 Sat 9/28/19
Clearing Works at Area 1 & 2 for Handing
Over by Client 87 days Mon 9/30/19 Thu 1/16/20
Installation of Board Up / Temporary
Partition Enclosing Area 1 & 2 27 days Tue 10/1/19 Thu 10/31/19
First Floor At Area 1 & 2 184 days Thu 12/19/19 Fri 7/31/20
Demolition Works 50 days Thu 12/19/19 Thu 2/20/20
Demolition of Existing CHB Partition
(including opening requirements) 17 days Sat 2/1/20 Thu 2/20/20
Demolition of Existing Drywall Partition 2 days Thu 12/19/19 Fri 12/20/19
Removal of Existing Ceiling Board and
Frame 7 days Sat 12/21/19 Fri 1/3/20
Re-adjustment / Removal of Existing
MEP Facilities 14 days Sat 1/4/20 Mon 1/20/20
Removal of Existing Floor Finishing 16 days Tue 1/21/20 Fri 2/7/20
Structural and Architectural Repair 65 days Sat 2/15/20 Tue 5/5/20
Masonry Works 36 days Mon 3/2/20 Wed 4/15/20
CHB Work 26 days Mon 3/2/20 Tue 3/31/20
Plastering Work 24 days Mon 3/16/20 Wed 4/15/20
Installation of New Door and Windows
Frame 17 days Wed 5/6/20 Mon 5/25/20
Mechanical and Electrical Works 90 days Wed 4/15/20 Thu 7/30/20
Electrical Works 90 days Wed 4/15/20 Thu 7/30/20
Lighting / Power System 77 days Wed 4/15/20 Wed 7/15/20
Mechanical Secondary Power 77 days Wed 4/15/20 Wed 7/15/20
Telephone / Lan System 90 days Wed 4/15/20 Thu 7/30/20
Fire Alarm System 90 days Wed 4/15/20 Thu 7/30/20
CCTV System 90 days Wed 4/15/20 Thu 7/30/20
Security Access Control System 90 days Wed 4/15/20 Thu 7/30/20
Mechanical Works 77 days Wed 4/15/20 Wed 7/15/20
Airconditioning System 77 days Wed 4/15/20 Wed 7/15/20
Ventillation System 77 days Wed 4/15/20 Wed 7/15/20
Fire Protection 77 days Wed 4/15/20 Wed 7/15/20
Ceiling Works 38 days Sat 5/16/20 Tue 6/30/20
Floor Finishing Works 17 days Mon 6/1/20 Sat 6/20/20
Internal Painting of CHB Plastered Wall 59 days Thu 4/16/20 Thu 6/25/20
Installation of Door and Window Panels
including its Accessories 13 days Sat 5/16/20 Sat 5/30/20
Installation of Tables and Chairs for Area
1&2 26 days Fri 6/26/20 Sat 7/25/20
Installation of Temporary Partition for
Partial Handing Over 5 days Mon 7/27/20 Fri 7/31/20
Second Floor At Area 1 & 2 187 days Mon 12/16/19 Fri 7/31/20
Demolition Works 57 days Mon 12/16/19 Tue 2/25/20
Client Handing Over of Area 2 (Server
Room) 0 days Thu 1/16/20 Thu 1/16/20
Demolition of Existing CHB Partition
(including opening requirements) 14 days Mon 2/10/20 Tue 2/25/20
Demolition of Existing Drywall Partition 6 days Mon 12/16/19 Sat 12/21/19
Removal of Existing Ceiling Board and
Frame 7 days Mon 12/23/19 Sat 1/4/20
Re-adjustment / Removal of Existing
MEP Facilities 11 days Mon 1/6/20 Fri 1/17/20
Removal of Existing Floor Finishing 17 days Sat 1/18/20 Thu 2/6/20
Structural and Architectural Repair 57 days Tue 2/25/20 Tue 5/5/20
Repainting / Rehabilitation of Existing
Steel Structure 58 days Thu 3/5/20 Fri 5/15/20
Masonry Works 36 days Mon 3/2/20 Wed 4/15/20
Installation of New Door's Frame 5 days Wed 4/1/20 Mon 4/6/20
Installation of New Aluminum Window
Frames 17 days Wed 5/6/20 Mon 5/25/20
Installation of Dry Wall Structural Support
and Frame 13 days Thu 4/16/20 Thu 4/30/20
Installation of Drywall Board 13 days Sat 4/25/20 Mon 5/11/20
Mechanical and Electrical Works 90 days Thu 4/16/20 Fri 7/31/20
Electrical Works 90 days Thu 4/16/20 Fri 7/31/20
Mechanical Works 77 days Thu 4/16/20 Thu 7/16/20
Ceiling Works 63 days Thu 4/16/20 Tue 6/30/20
Floor Finishing Works 17 days Mon 6/1/20 Sat 6/20/20
Internal Painting of CHB Plastered Wall 59 days Thu 4/16/20 Thu 6/25/20
Installation of Door and Window Panels
including its Accessories 13 days Sat 5/16/20 Sat 5/30/20
Installation of Tables and Chairs for Area
1&2 23 days Tue 6/30/20 Sat 7/25/20
Installation of Temporary Partition for
Partial Handing Over 5 days Mon 7/27/20 Fri 7/31/20
Roof Level At Area 1 & 2 109 days Mon 1/6/20 Fri 5/15/20
Roofing Replacement 109 days Mon 1/6/20 Fri 5/15/20
Exterior Finishing Area 1 & 2, 1F and 2F 187 days Mon 12/16/19 Fri 7/31/20
Punchlisting Works 27 days Tue 6/30/20 Thu 7/30/20
Handing Over of Area 1& 2, 1F and 2F 0 days Fri 7/31/20 Fri 7/31/20
Moving Office Furniture / Stuffs from
Area 3, 1F to 2F to Area 1 & 2, 1F and 2F 2 days Sat 8/1/20 Mon 8/3/20
Area 3 265 days Wed 2/5/20 Thu 12/17/20
First Floor Area 3 116 days Mon 8/3/20 Thu 12/17/20
Demolition Works 41 days Mon 8/3/20 Sat 9/19/20
Desk Transfer and Clearing of Area 3
For Handing Over - by Client 13 days Mon 8/3/20 Mon 8/17/20
Demolition of Existing CHB Partition
and Vault (including opening requirements) 20 days Sat 8/15/20 Tue 9/8/20
Demolition of Existing Drywall Partition 4 days Sat 8/15/20 Wed 8/19/20
Removal of Existing Ceiling Board and
Frame 8 days Thu 8/20/20 Sat 8/29/20
Re-adjustment / Removal of Existing
MEP Facilities 9 days Mon 8/31/20 Wed 9/9/20
Removal of Existing Floor Finishing 9 days Thu 9/10/20 Sat 9/19/20
Structural and Architectural Repair 39 days Thu 9/10/20 Sat 10/24/20
Masonry Works 17 days Thu 9/10/20 Tue 9/29/20
Installation of New Door and Windows
Frame 9 days Sat 9/19/20 Tue 9/29/20
Mechanical and Electrical Works 65 days Wed 9/30/20 Tue 12/15/20
Electrical Works 64 days Wed 9/30/20 Mon 12/14/20
Lighting / Power System 60 days Wed 9/30/20 Wed 12/9/20
Mechanical Secondary Power 60 days Wed 9/30/20 Wed 12/9/20
Telephone / Lan System 60 days Wed 9/30/20 Wed 12/9/20
Fire Alarm System 64 days Wed 9/30/20 Mon 12/14/20
CCTV System 64 days Wed 9/30/20 Mon 12/14/20
Security Access Control System 64 days Wed 9/30/20 Mon 12/14/20
Mechanical Works 65 days Wed 9/30/20 Tue 12/15/20
Airconditioning System 65 days Wed 9/30/20 Tue 12/15/20
Ventillation System 65 days Wed 9/30/20 Tue 12/15/20
Fire Protection 65 days Wed 9/30/20 Tue 12/15/20
Ceiling Works 36 days Sat 10/31/20 Sat 12/12/20
Floor Finishing Works 17 days Mon 11/16/20 Sat 12/5/20
Internal Painting of CHB Plastered Wall 61 days Wed 9/30/20 Thu 12/10/20
Installation of Door and Window Panels
including its Accessories 12 days Sat 11/28/20 Sat 12/12/20
Installation of Tables and Chairs for Area
3 6 days Fri 12/11/20 Thu 12/17/20
Toilet A3 , 1F Construction 83 days Fri 9/11/20 Thu 12/17/20
Earthworks 2 days Fri 9/11/20 Sat 9/12/20
Reinforced Concrete Works 14 days Mon 9/14/20 Tue 9/29/20
Steel Rafter Installation including
Purilins and Accessories 3 days Wed 9/30/20 Fri 10/2/20
Installation of Roofing with Wire Mesh
and Insulation 3 days Sat 10/3/20 Tue 10/6/20
CHB including Wall Footing at 1F 12 days Wed 10/7/20 Tue 10/20/20
Installation of New Door Frames 4 days Thu 10/15/20 Mon 10/19/20
Installation of New Aluminum Window
Frames 2 days Sat 11/28/20 Tue 12/1/20
Plastering Works 4 days Thu 11/26/20 Tue 12/1/20
Wall Tiling Works 30 days Wed 11/4/20 Wed 12/9/20
Mechanical and Electrical Works 33 days Thu 10/29/20 Mon 12/7/20
Electrical Works 21 days Thu 10/29/20 Sat 11/21/20
Lighting / Power System 21 days Thu 10/29/20 Sat 11/21/20
Fire Alarm System 21 days Thu 10/29/20 Sat 11/21/20
Mechanical Works 33 days Thu 10/29/20 Mon 12/7/20
Plumbing and Sanitary 33 days Thu 10/29/20 Mon 12/7/20
Ceiling Works 6 days Wed 11/11/20 Tue 11/17/20
Waterproofing Works 4 days Tue 11/17/20 Fri 11/20/20
Painting of Walls and Ceiling 4 days Sat 11/21/20 Wed 11/25/20
Floor Tiles Installation 4 days Thu 11/26/20 Tue 12/1/20
Installation of Door and Window Panels
including its Accessories 4 days Wed 12/2/20 Sat 12/5/20
Installation of Toilet Partition 5 days Tue 12/8/20 Sat 12/12/20
Dismantling of Board-up and Temporary
Partition 5 days Sat 12/12/20 Thu 12/17/20
Second Floor At Area 3 265 days Wed 2/5/20 Thu 12/17/20
Demolition Works 47 days Mon 8/3/20 Sat 9/26/20
Desk Transfer and Clearing of Area 3
For Handing Over - by Client 13 days Mon 8/3/20 Mon 8/17/20
Demolition of Existing CHB Partition
(including opening requirements) 12 days Tue 8/18/20 Tue 9/1/20
Demolition of Existing Drywall Partition 4 days Tue 8/18/20 Sat 8/22/20
Demolition of Suspended Slab at Vault
Area 5 days Fri 9/11/20 Wed 9/16/20
Removal of Existing Ceiling Board and
Frame 9 days Wed 9/2/20 Fri 9/11/20
Re-adjustment / Removal of Existing
MEP Facilities 8 days Sat 9/12/20 Mon 9/21/20
Removal of Existing Floor Finishing 10 days Wed 9/16/20 Sat 9/26/20
Structural and Architectural Repair 39 days Sat 9/12/20 Tue 10/27/20
Repainting / Rehabilitation of Existing
Steel Structure 13 days Sat 9/12/20 Sat 9/26/20
Masonry Works 17 days Sat 9/12/20 Thu 10/1/20
Installation of New Door and Windows
Frame 10 days Mon 9/21/20 Thu 10/1/20
Installation of Dry Wall Structural Support
and Frame 14 days Thu 10/29/20 Fri 11/13/20
Installation of Drywall Board 13 days Sat 11/14/20 Sat 11/28/20
Mechanical and Electrical Works 82 days Sat 9/12/20 Thu 12/17/20
Electrical Works 82 days Sat 9/12/20 Thu 12/17/20
Lighting / Power System 82 days Sat 9/12/20 Thu 12/17/20
Mechanical Secondary Power 82 days Sat 9/12/20 Thu 12/17/20
Telephone / Lan System 82 days Sat 9/12/20 Thu 12/17/20
Fire Alarm System 82 days Sat 9/12/20 Thu 12/17/20
CCTV System 82 days Sat 9/12/20 Thu 12/17/20
Security Access Control System 82 days Sat 9/12/20 Thu 12/17/20
Mechanical Works 59 days Sat 9/12/20 Thu 11/19/20
Airconditioning System 59 days Sat 9/12/20 Thu 11/19/20
Ventillation System 59 days Sat 9/12/20 Thu 11/19/20
Fire Protection 59 days Sat 9/12/20 Thu 11/19/20
Ceiling Works 76 days Wed 9/16/20 Mon 12/14/20
Floor Finishing Works 14 days Tue 11/10/20 Wed 11/25/20
Painting of Walls 52 days Thu 10/15/20 Tue 12/15/20
Installation of Door and Window Panels
including its Accessories 12 days Fri 12/4/20 Thu 12/17/20
Toilet A3 , 2F Construction 84 days Thu 9/10/20 Thu 12/17/20
Mechanical and Electrical Works 47 days Thu 9/10/20 Tue 11/3/20
Electrical Works 42 days Thu 9/10/20 Wed 10/28/20
Lighting / Power System 40 days Thu 9/10/20 Mon 10/26/20
Fire Alarm System 40 days Sat 9/12/20 Wed 10/28/20
Mechanical Works 45 days Sat 9/12/20 Tue 11/3/20
Plumbing and Sanitary 45 days Sat 9/12/20 Tue 11/3/20
Wall Tiling Works 9 days Sat 9/26/20 Tue 10/6/20
Ceiling Works 9 days Fri 10/9/20 Mon 10/19/20
Waterproofing Works 3 days Tue 10/20/20 Thu 10/22/20
Floor Tiles Installation 5 days Fri 10/23/20 Wed 10/28/20
Installation of Toilet Fixtures 4 days Thu 10/29/20 Mon 11/2/20
Installation of Tables and Chairs at Area
3 8 days Sat 12/5/20 Mon 12/14/20
Dismantling of Board-up and Temporary
Partition 6 days Fri 12/11/20 Thu 12/17/20
Roof Level At Area 3 58 days Fri 9/11/20 Tue 11/17/20
Roofing Replacement 58 days Fri 9/11/20 Tue 11/17/20
Exterior Finishing Area 3, 1F and 2F 100 days Tue 8/18/20 Mon 12/14/20
Punchlisting Works 15 days Tue 12/1/20 Thu 12/17/20
Lobby, Stairs and Entry Porch 100 days Sat 8/15/20 Fri 12/11/20
Removal of Existing Ceiling Board and
Frame 4 days Sat 8/15/20 Wed 8/19/20
Re-adjustment / Removal of Existing
MEP Facilities 4 days Thu 8/20/20 Tue 8/25/20
Removal of Existing Floor Finishing 5 days Wed 11/18/20 Mon 11/23/20
Structural and Architectural Repair 10 days Sat 9/5/20 Wed 9/16/20
Waterproofing Works 7 days Thu 9/17/20 Thu 9/24/20
Mechanical and Electrical Works 52 days Fri 9/25/20 Tue 11/24/20
Electrical Works 52 days Fri 9/25/20 Tue 11/24/20
Lighting / Power System 45 days Fri 9/25/20 Mon 11/16/20
Mechanical Secondary Power 45 days Fri 9/25/20 Mon 11/16/20
Telephone / Lan System 52 days Fri 9/25/20 Tue 11/24/20
Fire Alarm System 52 days Fri 9/25/20 Tue 11/24/20
CCTV System 52 days Fri 9/25/20 Tue 11/24/20
Security Access Control System 52 days Fri 9/25/20 Tue 11/24/20
Mechanical Works 52 days Fri 9/25/20 Tue 11/24/20
Airconditioning System 52 days Fri 9/25/20 Tue 11/24/20
Ventillation System 52 days Fri 9/25/20 Tue 11/24/20
Fire Protection 52 days Fri 9/25/20 Tue 11/24/20
Ceiling Works 36 days Fri 9/25/20 Thu 11/5/20
Installation of Handrail including
Accessories 5 days Wed 11/11/20 Mon 11/16/20
Install Aluminum Frame and Glass 5 days Wed 11/11/20 Mon 11/16/20
Painting of Walls and Ceiling 5 days Fri 11/6/20 Wed 11/11/20
Floor Finishing Works 8 days Tue 11/17/20 Wed 11/25/20
Main Entrance Door Replacement 5 days Wed 11/25/20 Tue 12/1/20
Installation of Guard Counter Top 9 days Wed 12/2/20 Fri 12/11/20
Roof Level Lobby 17 days Mon 9/7/20 Fri 9/25/20
Roofing Replacement 17 days Mon 9/7/20 Fri 9/25/20
Main Toilet 265 days Wed 2/5/20 Thu 12/17/20
Ground Floor 207 days Wed 2/5/20 Fri 10/9/20
Installation of Board Up / Temporary
Partition Enclosure 5 days Wed 2/5/20 Mon 2/10/20
Dismantling of Toilet Partition and
Fixtures 5 days Tue 2/11/20 Sat 2/15/20
Dismantling of Ceiling 4 days Mon 2/17/20 Thu 2/20/20
Re-adjustment / Removal of Existing
MEP Facilities 5 days Fri 2/21/20 Wed 2/26/20
Dismantling of Floor Tilea 3 days Thu 2/27/20 Sat 2/29/20
Dismantling of Wall Tiles 8 days Mon 3/2/20 Tue 3/10/20
Perform Structural Retrofitting Activity
Above Ceiling 4 days Wed 3/11/20 Sat 3/14/20
Mechanical and Electrical Works 24 days Mon 3/16/20 Wed 4/15/20
Mechanical and Electrical Works 171 days Mon 3/16/20 Wed 10/7/20
Electrical Works 30 days Thu 9/3/20 Wed 10/7/20
Lighting / Power System 30 days Thu 9/3/20 Wed 10/7/20
Fire Alarm System 30 days Thu 9/3/20 Wed 10/7/20
Mechanical Works 171 days Mon 3/16/20 Wed 10/7/20
Plumbing and Sanitary 74 days Mon 3/16/20 Mon 6/15/20
Ventillation System 30 days Thu 9/3/20 Wed 10/7/20
Restoration of Slab on Grade 2 days Thu 4/16/20 Fri 4/17/20
Installation of New Wall Tiles 14 days Sat 4/18/20 Tue 5/5/20
Ceiling Works 8 days Thu 10/1/20 Fri 10/9/20
Waterproofing Works 9 days Wed 5/6/20 Fri 5/15/20
Floor Tiles Installation 14 days Sat 5/16/20 Mon 6/1/20
Installation of Toilet Fixtures and
Accessories 11 days Tue 6/2/20 Mon 6/15/20
Installation of Toilet Partition 13 days Tue 6/16/20 Tue 6/30/20
Wall Painting 8 days Wed 7/1/20 Thu 7/9/20
Dismantling of Board-up and Partition 5 days Fri 7/10/20 Wed 7/15/20
Installation of LRTA Staff Safety
Access from Area 1 & 2 14 days Thu 7/16/20 Fri 7/31/20
Second Floor 105 days Sat 8/15/20 Thu 12/17/20
Dismantling of Toilet Partiiton and
Fixtures 5 days Sat 8/15/20 Thu 8/20/20
Dismantling of Ceiling 3 days Sat 8/22/20 Tue 8/25/20
Re-adjustment / Removal of Existing
MEP Facilities 5 days Wed 8/26/20 Mon 8/31/20
Dismantling of Wall Tiles 5 days Tue 9/1/20 Sat 9/5/20
Dismantling of Floor Tilea 4 days Mon 9/7/20 Thu 9/10/20
Perform Structural Retrofitting Activity
Above Ceiling 4 days Fri 9/11/20 Tue 9/15/20
Mechanical and Electrical Works 72 days Sat 8/15/20 Sat 11/7/20
Electrical Works 43 days Sat 8/15/20 Mon 10/5/20
Lighting / Power System 43 days Sat 8/15/20 Mon 10/5/20
Fire Alarm System 43 days Sat 8/15/20 Mon 10/5/20
Mechanical Works 72 days Sat 8/15/20 Sat 11/7/20
Plumbing and Sanitary 50 days Fri 9/11/20 Sat 11/7/20
Ventillation System 23 days Sat 8/15/20 Fri 9/11/20
Installation of New Wall Tiles 9 days Mon 9/28/20 Wed 10/7/20
Ceiling Works 11 days Fri 9/11/20 Wed 9/23/20
Waterproofing Works 10 days Tue 10/6/20 Fri 10/16/20
Floor Tiles Installation 15 days Sat 10/17/20 Tue 11/3/20
Installation of Toilet Fixtures and
Accessories 12 days Wed 11/4/20 Tue 11/17/20
Installation of Toilet Partition 13 days Wed 11/18/20 Thu 12/3/20
Wall Painting 8 days Fri 12/4/20 Sat 12/12/20
Dismantling of Board-up and Partition 4 days Mon 12/14/20 Thu 12/17/20
External Works 245 days Thu 3/5/20 Wed 12/23/20
Temporary Septic Tank 44 days Tue 3/10/20 Mon 5/4/20
New Septic Tank Construction 39 days Sat 8/15/20 Wed 9/30/20
PWD Ramp Construction 234 days Mon 3/9/20 Mon 12/14/20
Client Handing Over (Removal of PLDT
Fiber Optic Cables) 0 days Mon 3/9/20 Mon 3/9/20
Earthworks 23 days Tue 5/5/20 Sat 5/30/20
Reinforced Concrete Works 52 days Mon 6/1/20 Fri 7/31/20
Steel Rafter Installation including Purilins
and Accessories 25 days Sat 8/1/20 Mon 8/31/20
Installation of roofing with Wire Mesh and
Insulation 14 days Tue 9/1/20 Wed 9/16/20
Demolition of Ramp Opening at 2F 11 days Tue 8/4/20 Sat 8/15/20
CHB and Plastering Works including Wall
Footing 40 days Wed 7/1/20 Sat 8/15/20
Electrical Works 61 days Thu 8/20/20 Fri 10/30/20
Lighting / Power System 61 days Thu 8/20/20 Fri 10/30/20
Fire Alarm System 61 days Thu 8/20/20 Fri 10/30/20
Ceiling Works inside the Ramps 17 days Fri 9/11/20 Wed 9/30/20
Painting of Walls and Ceiling 17 days Thu 10/1/20 Tue 10/20/20
Installation of Handrail including
Accessories 23 days Wed 10/21/20 Mon 11/16/20
Floor Finishing Works 23 days Tue 11/17/20 Mon 12/14/20
Removal of Board-up at Ramp Openings 5 days Sat 12/12/20 Thu 12/17/20
Fire Exit Stair 245 days Thu 3/5/20 Wed 12/23/20
Area 1 & 2 118 days Thu 3/5/20 Sat 7/25/20
Area 3 109 days Mon 8/17/20 Wed 12/23/20
External Mechanical and Electrical
Works 142 days Wed 4/15/20 Wed 9/30/20
External Electrical Works 74 days Wed 4/15/20 Sat 7/11/20
Power Incoming Underground Ductbank
and Manholes 74 days Wed 4/15/20 Sat 7/11/20
External Mechanical Works 142 days Wed 4/15/20 Wed 9/30/20
EXTENSION OF EXISTING BACLARAN
DEPOT 574 days Mon 6/3/19 Mon 5/3/21
Project Milestone 529 days Mon 6/24/19 Thu 3/25/21
Permit Application 102 days Mon 6/3/19 Wed 10/2/19
Design Works 117 days Tue 7/2/19 Mon 11/18/19
Procurement 315 days Mon 9/16/19 Thu 10/1/20
Construction Works 475 days Mon 9/30/19 Mon 5/3/21
Temporary Facilities Set-up 50 days Thu 10/3/19 Mon 12/2/19
Dismantling of Temporary Facilities 24 days Wed 3/31/21 Mon 5/3/21
Building and Facilities 447 days Mon 9/30/19 Thu 3/25/21
B01 Light and Heavy Maintenance
Workshop 447 days Mon 9/30/19 Thu 3/25/21
Design Review 42 days Mon 9/30/19 Mon 11/18/19
Pre- Construction Tasks of Bored Piling
Works 115 days Thu 10/3/19 Fri 2/21/20
Bored Piling Works 79 days Mon 2/24/20 Fri 5/29/20
Excavation 24 days Fri 4/24/20 Fri 5/22/20
Backfill & Compaction 66 days Tue 6/23/20 Tue 9/8/20
Reinforced Concrete Works 122 days Fri 5/8/20 Tue 9/29/20
Zone 1 66 days Fri 5/8/20 Fri 7/24/20
Zone 2 68 days Fri 5/29/20 Mon 8/17/20
Zone 3 68 days Sat 6/20/20 Tue 9/8/20
Zone 4 68 days Sat 7/11/20 Tue 9/29/20
Steel Structure Works 108 days Wed 7/8/20 Wed 11/11/20
Zone 1 68 days Wed 7/8/20 Fri 9/25/20
Zone 2 72 days Wed 7/22/20 Wed 10/14/20
Zone 3 72 days Wed 8/5/20 Wed 10/28/20
Zone 4 72 days Wed 8/19/20 Wed 11/11/20
Overhead Crane Installation 30 days Thu 9/10/20 Wed 10/14/20
Roofing 48 days Tue 10/13/20 Tue 12/8/20
Exterior Finishing Works 91 days Thu 9/10/20 Mon 12/28/20
Maintenance Area 166 days Wed 8/5/20 Mon 2/22/21
Interior Finishing Works 104 days Fri 10/16/20 Sat 2/20/21
MEPF WORKS 166 days Wed 8/5/20 Mon 2/22/21
Ventillation System 45 days Mon 11/16/20 Wed 1/13/21
Fire Protection System 66 days Mon 11/2/20 Sat 1/23/21
Plumbing and Sanitary Works 136 days Wed 8/5/20 Mon 1/18/21
Compressor System 45 days Mon 11/16/20 Wed 1/13/21
Feeder Line 80 days Sat 10/31/20 Mon 2/8/21
Lighting System 66 days Tue 11/17/20 Mon 2/8/21
Small Power System 66 days Tue 11/17/20 Mon 2/8/21
FDAS 66 days Tue 11/17/20 Mon 2/8/21
Telephone System 66 days Tue 11/17/20 Mon 2/8/21
Lightning Protection/ Grounding
System 56 days Mon 11/23/20 Tue 2/2/21
Duct Bank from Substation to Light /
Heavy Maintenance 0 days Sat 8/8/20 Sat 8/8/20
Internal Testing and Commisioning 12 days Mon 2/8/21 Sat 2/20/21
Electrical Power On 0 days Mon 2/22/21 Mon 2/22/21
EPC Contractor Access to
Mainternace Area 0 days Mon 2/22/21 Mon 2/22/21
Office Area 203 days Fri 7/24/20 Thu 3/25/21
Interior Finishing Works 111 days Wed 11/4/20 Fri 3/19/21
MEPF WORKS 203 days Fri 7/24/20 Thu 3/25/21
Ventillation System 101 days Wed 11/4/20 Mon 3/8/21
Fire Protection System 101 days Wed 11/4/20 Mon 3/8/21
Plumbing and Sanitary Works 187 days Fri 7/24/20 Sat 3/6/21
Feeder Line 90 days Fri 11/6/20 Thu 2/25/21
Lighting System 90 days Sat 11/14/20 Fri 3/5/21
Small Power System 90 days Sat 11/14/20 Fri 3/5/21
FDAS 80 days Sat 11/28/20 Mon 3/8/21
Telephone System 75 days Sat 12/5/20 Mon 3/8/21
Lightning Protection/ Grounding
System 75 days Sat 12/5/20 Mon 3/8/21
Overall Testing and Commissioning 15 days Tue 3/9/21 Thu 3/25/21
B02 Substation 388 days Mon 9/30/19 Fri 1/15/21
Design Review 42 days Mon 9/30/19 Mon 11/18/19
Bore Pling Works and Earthworks 116 days Mon 2/24/20 Mon 7/13/20
Reinforced Concrete Works 96 days Mon 5/11/20 Tue 9/1/20
Exterior Finishing 89 days Wed 7/29/20 Tue 11/10/20
Interior Finishing 95 days Mon 9/21/20 Fri 1/15/21
MEPF WORKS 167 days Sat 6/27/20 Fri 1/15/21
Ventillation System 47 days Tue 10/27/20 Mon 12/21/20
Fire Protection System 11 days Mon 1/4/21 Fri 1/15/21
Plumbing and Sanitary Works 163 days Sat 6/27/20 Mon 1/11/21
Feeder Line 85 days Thu 8/27/20 Fri 12/4/20
Lighting System 60 days Thu 9/17/20 Wed 11/25/20
Small Power System 60 days Thu 9/17/20 Wed 11/25/20
FDAS 60 days Thu 9/17/20 Wed 11/25/20
Telephone System 60 days Thu 9/17/20 Wed 11/25/20
Lightning Protection/ Grounding System 60 days Thu 10/1/20 Thu 12/10/20
B03 Motor Pool 373 days Mon 9/30/19 Wed 12/23/20
Design Review 42 days Mon 9/30/19 Mon 11/18/19
Earthworks 54 days Wed 6/24/20 Wed 8/26/20
Reinforced Concrete Works 105 days Wed 7/1/20 Sat 10/31/20
Exterior Finishing 57 days Fri 9/11/20 Mon 11/16/20
Interior Finishing 60 days Sat 10/10/20 Sat 12/19/20
MEPF WORKS 68 days Mon 10/5/20 Wed 12/23/20
AC System 25 days Sat 10/31/20 Sat 11/28/20
Ventillation System 25 days Sat 10/31/20 Sat 11/28/20
Fire Protection System 46 days Mon 10/5/20 Thu 11/26/20
Plumbing and Sanitary Works 44 days Thu 10/8/20 Fri 11/27/20
Feeder Line 68 days Mon 10/5/20 Wed 12/23/20
Lighting System 35 days Mon 10/12/20 Fri 11/20/20
Small Power System 35 days Mon 10/12/20 Fri 11/20/20
FDAS 35 days Mon 10/19/20 Fri 11/27/20
Telephone System 35 days Mon 10/19/20 Fri 11/27/20
Lightning Protection/ Grounding System 35 days Mon 10/19/20 Fri 11/27/20
B04 Material Storage 395 days Mon 9/30/19 Sat 1/23/21
Design Review 42 days Mon 9/30/19 Mon 11/18/19
Earthworks 54 days Tue 7/7/20 Tue 9/8/20
Reinforced Concrete Works 105 days Tue 7/14/20 Fri 11/13/20
Exterior Finishing 64 days Thu 9/24/20 Tue 12/8/20
Interior Finishing 67 days Sat 10/31/20 Sat 1/23/21
MEPF WORKS 109 days Mon 8/24/20 Mon 1/4/21
AC and Ventillation System 25 days Tue 12/1/20 Mon 1/4/21
Fire Protection System 46 days Sat 10/17/20 Thu 12/10/20
Plumbing and Sanitary Works 94 days Mon 8/24/20 Fri 12/11/20
Feeder Line 35 days Sat 10/17/20 Thu 11/26/20
Lighting System 35 days Sat 10/24/20 Fri 12/4/20
Small Power System 35 days Sat 10/24/20 Fri 12/4/20
FDAS 35 days Sat 10/31/20 Fri 12/11/20
Telephone System 35 days Sat 10/31/20 Fri 12/11/20
Lightning Protection/ Grounding System 35 days Sat 10/31/20 Fri 12/11/20
B05 Guard House 433 days Mon 9/30/19 Tue 3/9/21
Design Review 42 days Mon 9/30/19 Mon 11/18/19
Earthworks 27 days Tue 11/17/20 Fri 12/18/20
Reinforced Concrete Works 66 days Tue 11/24/20 Mon 2/15/21
Exterior Finishing 36 days Thu 1/14/21 Wed 2/24/21
Interior Finishing 34 days Thu 1/28/21 Mon 3/8/21
MEPF WORKS 58 days Tue 12/29/20 Tue 3/9/21
Fire Protection System 10 days Sat 2/6/21 Wed 2/17/21
Plumbing and Sanitary Works 44 days Tue 12/29/20 Sat 2/20/21
Feeder Line 15 days Sat 2/6/21 Tue 2/23/21
Lighting System 15 days Sat 2/13/21 Tue 3/2/21
Small Power System 15 days Sat 2/13/21 Tue 3/2/21
FDAS 15 days Sat 2/20/21 Tue 3/9/21
Telephone System 15 days Sat 2/20/21 Tue 3/9/21
Lightning Protection/ Grounding System 15 days Sat 2/20/21 Tue 3/9/21
B06 & B07 Waste and Hazardous Material
Storage 395 days Mon 9/30/19 Sat 1/23/21
Design Review 42 days Mon 9/30/19 Mon 11/18/19
Earthworks 53 days Thu 7/9/20 Wed 9/9/20
Reinforced Concrete Works 104 days Thu 7/16/20 Sat 11/14/20
Exterior Finishing 64 days Thu 9/24/20 Tue 12/8/20
Interior Finishing 67 days Sat 10/31/20 Sat 1/23/21
MEPF WORKS 108 days Tue 8/25/20 Mon 1/4/21
Ventillation System 25 days Tue 12/1/20 Mon 1/4/21
Fire Protection System 46 days Mon 10/19/20 Fri 12/11/20
Plumbing and Sanitary Works 94 days Tue 8/25/20 Sat 12/12/20
Feeder Line 35 days Mon 10/19/20 Fri 11/27/20
Lighting System 35 days Mon 10/26/20 Sat 12/5/20
Small Power System 35 days Mon 10/26/20 Sat 12/5/20
FDAS 35 days Mon 11/2/20 Sat 12/12/20
Telephone System 35 days Mon 11/2/20 Sat 12/12/20
Lightning Protection/ Grounding System 35 days Mon 11/2/20 Sat 12/12/20
B08 Switch Room 317 days Mon 9/30/19 Sat 10/17/20
Design Review 42 days Mon 9/30/19 Mon 11/18/19
Earthworks 30 days Wed 6/24/20 Tue 7/28/20
Reinforced Concrete Works 75 days Wed 7/1/20 Sat 9/26/20
Exterior Finishing 32 days Wed 8/26/20 Thu 10/1/20
Interior Finishing 32 days Fri 9/11/20 Sat 10/17/20
MEPF WORKS 59 days Fri 8/7/20 Thu 10/15/20
Fire Protection System 10 days Fri 9/18/20 Tue 9/29/20
Plumbing and Sanitary Works 44 days Fri 8/7/20 Mon 9/28/20
Feeder Line 15 days Fri 9/18/20 Mon 10/5/20
Lighting System 15 days Fri 9/25/20 Mon 10/12/20
Small Power System 15 days Fri 9/25/20 Mon 10/12/20
FDAS 15 days Tue 9/29/20 Thu 10/15/20
Telephone System 15 days Tue 9/29/20 Thu 10/15/20
Lightning Protection/ Grounding System 15 days Tue 9/29/20 Thu 10/15/20
B09 IME Storage 317 days Mon 9/30/19 Sat 10/17/20
Design Review 42 days Mon 9/30/19 Mon 11/18/19
Earthworks 46 days Mon 4/27/20 Sat 6/20/20
Reinforced Concrete Works 111 days Sat 5/9/20 Thu 9/17/20
Exterior Finishing 46 days Sat 8/1/20 Thu 9/24/20
Interior Finishing 44 days Fri 8/28/20 Sat 10/17/20
MEPF WORKS 79 days Thu 7/9/20 Fri 10/9/20
Fire Protection System 10 days Fri 9/4/20 Tue 9/15/20
Plumbing and Sanitary Works 44 days Thu 7/9/20 Sat 8/29/20
Feeder Line 22 days Fri 9/4/20 Tue 9/29/20
Lighting System 22 days Fri 9/11/20 Tue 10/6/20
Small Power System 22 days Fri 9/11/20 Tue 10/6/20
FDAS 22 days Tue 9/15/20 Fri 10/9/20
Telephone System 22 days Tue 9/15/20 Fri 10/9/20
Lightning Protection/ Grounding System 22 days Tue 9/15/20 Fri 10/9/20
NEW SATELLITE DEPOT AT ZAPOTE 641 days Mon 6/3/19 Wed 7/21/21