Construction Monthly Report: Project Title: Riyadh Clean Transportation Fuel
Construction Monthly Report: Project Title: Riyadh Clean Transportation Fuel
Prepared by:
AL HUSAM CONSTRUCTION COMPANY Owner: ARAMCO
Prepared for:
SAMSUNG EPC Co. Ltd
September 2014
OWNER CONTRACTOR SUB-
CONTRACTOR
1. CONTRACT PARTICULARS
2. EXECUTIVE SUMMARY
4. SCHEDULE
5. CONSTRUCTION
6. COMMISSIONING
7. QUALITY ASSURANCE
8. FINANCIAL SUMMARY
9. ATTACHMENTS
Variance / Slippage
Summary
Percent Complete : %
Achievements accomplished (Description):
1.
2.
3.
4.
1.
2.
3.
4.
Critical Issues
1.
2.
3.
4.
1.
2.
3.
4.
1.
2.
3.
4.
b. Toolbox Topics:
Week 1:
Week 2:
Week 3:
Week 4:
1.
2.
3.
4.
b. Schedule Analysis
5. Construction
Monthly Progress Report Page 7 of 12
September 2014
Accomplished this month
Areas of Concern
Areas of Concern
Areas of Concern
8. Financial Summary
General
4-Week Rolling Schedule
Contract Schedule
Change Order Log
Overall Progress S-Curve
Billings to Date versus Planned
Construction
Construction Progress S-Curve
Manpower & Equipment Utilization Curves
Progress Photos