QA & Control Program (21042003)
QA & Control Program (21042003)
1.1 GENERAL
The background to quality assurance is the client-contractor (in our case) relationship. The
ultimate purpose of any quality system is to ensure complete satisfaction by the customer
(client) with the products or services provided by the supplier (contractor). As such, quality
assurance requires the total integration and control of all elements within a particular area of
operation so that none is subservient to the other. In this project the elements we are
concerned are design, procurement (both material and subcontractors works), manufacture
(both on site and off site), installation and commissioning.
All activities and processes in the above elements need to be identified, planned,
implemented, monitored and controlled. Activities and processes that have quality
implication need to be verified at each stage of production and the results documented as
objective evidence. Similarly, incoming material that has quality implication need to be
accepted on a pre determined basis (i.e. inspection, test, manufacturer’s mill certificates, size,
grade, etc.). Subcontracted work at off site shall be accepted on established procedures (i.e.
manufacture’s certificate, random witnessing their test / inspection or random independent
test / inspection, etc).
The organization shall implement a Quality System that can effectively provide detailed
procedures for managing the quality of design, procurement (both material and services),
construction, commissioning. As such, it is the responsibility of the organization to perform
inspection and test to verify that performance and progress meet the contractual requirements.
During the inspection and test, the Resident Engineer (RE) may participate and it is the duty
of the organization to provide all the necessary assistance required. In activities (hold points)
where the RE is involved, the work can only proceed on the approval of the RE himself. All
nonconformances must be made good before proceeding to the next stage. Annexure ‘A’
shows the organization framework for the Quality Assurance.
In order to monitor and control the above requirements, each project shall have its own
quality plan which called “Project Quality Plan.” The Project Quality Plan (PQP) itself needs
the approval of the client prior to its implementation. The PQP must be submitted at different
stages as called for in the contract for approval. The PQP shall be project specific and shall
include all the vital elements that need to be monitored and controlled to accomplish the
project successfully. Annexure ‘B’ gives the content of the PQP.
Page 1 of 6
West Bengal Corridor Development Project
Package B [Km 193 to Km 297] Baharampur to Farakka
1.3 STANDARDS
The industry standards referred in the contract document (eg; MOST, PWD Spec, IRC, etc)
shall apply to all work under this contract and all such standards shall refer only to the current
editions of the industry standard, unless otherwise indicated.
Whenever it is specified, the production and or installation methods shall be approved by the
RE prior to implementation.
All workmanship and the quality level of each product shall be accepted as specified in these
standards.
The RE shall at all time have access to the work and work records whether on or off site.
Any work upon examination found not in accordance with the requirements of the contract
document, shall be made good by the organization.
1.5 WORKMANSHIP
All work shall be executed in accordance with the standards and specifications. In these
respects the workers are expected to be skilled and they shall be supervised by competent
supervisors.
All material, equipment and appliances shall be handled, used and installed as per the
manufacturer’s directions.
The organization shall provide labour and facilities to undertake the inspection and testing of
material and work whether on site or off site.
An Inspection and Test Plan shall be produced to identify the witness points, the nature of
inspection or test required as per the contract. The plan shall also detail, the standard used,
the acceptance criteria, and the witnesses required. Checklist shall be made available for the
purpose. Annexure ‘C’ gives a brief summary of tests to be conducted during construction
stage.
Inspection and Test are basically divided into three categories namely, incoming inspection,
in process inspection and final inspection.
Page 2 of 6
West Bengal Corridor Development Project
Package B [Km 193 to Km 297] Baharampur to Farakka
There are a number of methods which can be used to determine their acceptability.
Some of these methods are supplier certification of conformance, receiving,
inspection, surveillance, post-installation testing, or combinations of these.
1.6.1.1 Certificate of Conformance Method
Page 3 of 6
West Bengal Corridor Development Project
Package B [Km 193 to Km 297] Baharampur to Farakka
Acceptance by the in process inspection method may be most desirable when the item
or service:
1.6.2.2 Has quality characteristics that are difficult to verify after delivery.
The in process inspection method may not be warranted when the quality of the item
can be verified by review of tests reports, inspections upon receipt, or other means.
The in process inspection method activities may include checking that the following
has been accomplished:
1.6.2.4 Documentation on materials, inspections, and tests have been complied with
and that the applicable qualifications, process records, and certifications are
available;
1.6.2.5 Fabrication procedures and processes have been complied with and that the
applicable qualifications, process records, and certifications are available.
1.6.2.6 Components and assemblies have been inspected, examined and tested as
required and applicable inspection, test and certification records are
available;
1.6.2.8 Components and assemblies are cleaned, preserved, packed, and identified in
accordance with specified requirements.
Final inspection verifies that the completed systems and items are in conformance
with specified requirements. Thus it verifies the operational readiness of the systems
and items.
Page 4 of 6
West Bengal Corridor Development Project
Package B [Km 193 to Km 297] Baharampur to Farakka
1.7.1 Nonconformances
1.7.1.3 The non-conformance cannot be corrected by the subcontractor, that is, the
item cannot be reworked so that it will meet requirements.
The nonconformance and control methods should contain provisions for the
following:
1.7.1.6 The subcontractor’s verification that the nonconformance has been corrected;
The organization should verify that the subcontractor has in fact implemented the
corrective action approved by the organization. This may be done by verifying that
corrective action has been taken. Another method is to review and approve the
subcontractor’s written procedures for processing of nonconformances. The
organization would then verify implementation of the subcontractor’s
nonconformance system to obtain assurance that the subcontractor’s nonconformance
system is effective.
The organization shall implement an Environmental Mitigation Plan (EMP) that can
effectively provide compliance to the EIA already completed for the project. It is also the
responsibility of the organization to perform inspection and monitoring during the
construction and maintenance phase to verify the effectiveness of the EMP.
Page 5 of 6
West Bengal Corridor Development Project
Package B [Km 193 to Km 297] Baharampur to Farakka
During the entire duration of the project, the organization shall maintain a proper traffic
management plan to provide safe travel to the drivers of vehicles plying on the Project Road
at all times of the day, throughout the year and provide protection to the Project workers when
they are on the project site.
1.10 RECORDS
Certain records generated during the project cycle should be maintained by the organization
to provide evidence that the subcontractor complied with the contract documents and to track
nonconforming items. If the methods used to control and retain these records are specified in
written procedures, this work can be done more effectively. The records fall into two
categories, subcontractor-generated records and organization-generated records.
The records retained should be legible, identifiable, and retrievable to be of future value. The
record control methods should address these requirements.
1.11 AUDITS
The management should perform audits to verify compliance with the quality management
program and to measure the effectiveness of the program during all phases of the procurement
process. Typically, the essential steps of the audit are:
1.11.1. Planning the audit by means of a document which defines the organizations
and activities to be audited and the frequency of the audits;
1.11.2. Providing audit personnel who are familiar with the types of activities to be
audited and who do not have direct responsibilities in the areas being audited;
1.11.3. Performing the audit in accordance with guidelines which identify those
activities that affect quality;
1.11.4. Preparing the audit report which summarizes the audit results and details the
nonconformances observed;
1.11.5. Submitting the audit report to management responsible for the area audited
for review and corrective action for the nonconformances;
Page 6 of 6