INSPECTION AND TEST PLAN
Project: LMNHP -EW II WB-4
Client: National Highways Authority of India
Engineer: RI & CEG Jv.
Contractor: Hindustan Construction Co. Ltd.
Activity: ITP for Material Testing of Piling Works
Inspec.Category
S. Controlling
Inspection and Testing Description Verifying Document Frequency of Inspec./Testing Remarks
No. Specification. HCC Engineer
01 CEMENT
MTC/
MORTH, Table:900-6
a. Compressive Strength HCC F 40 14 Once per each source/batch W R RI Min 53 MPa
IS:4031(Part-6)
27
MTC/
Consistency , Initial and Final Setting MORTH, Table:900-6
b. HCC F 40 14 Once per each source/batch W R RI Not specified
Time test IS:4031(Part-5)
50
MTC/
MORTH, Table:900-6
c. Fineness test by dry sieving HCC F 40 14 Once per each source/batch W R RI % retained on 90 m sieve = Max 10
IS:4031(Part-1)
49
MTC/
MORTH, Table:900-6
d. Soundness test HCC F 40 14 Once per each source/batch W R RI Le-Chatelier expansion (mm)-Max 10
IS:4031(Part-3)
51
e. Determination of Chemical properties IS-455;1989 External Lab Report As & when required R R RI As per IS: 455-1989
02 REINFORCEMENT (TMT-BAR)
MTC /
MORTH, Clause-1009 MTC /
a. Ultimate Tensile Strength Confirmity test as per R R RI For Fe: 415: Min 485 MPA
IS:1786 External Lab Report
Engr.
MORTH, Clause-1009 MTC / Once per each lot /
b. Yield Strength R R RI For Fe: 415: Min 415 MPA
IS:1786 External Lab Report As required
MORTH, Clause-1009 MTC / Once per each lot /
c. Percentage of Elongation test R R RI For Fe: 415: Min 14.5 %
IS:1786 External Lab Report As required
MORTH, Clause-1009 MTC / Once per each lot /
d. Bend and Rebend test External Lab Report As required
R R RI If O.K.
IS:1786
Individual
Nominal size Batch
sample
Determination of Cross sectional area & MORTH, Clause-1009 upto & 10mm +/- 7 -8
e. Internal report 3 Samples per lot W R RI
mass IS:1786 >10 & 16 mm +/- 5 -6
Over 16 mm +/- 3 -4
MORTH, Clause-1009 MTC / Once per each lot / As
f. Chemical test R R RI As per IS:228 & IS: 1786
IS:1786 External Lab Report required
Page1
INSPECTION AND TEST PLAN
Project: LMNHP -EW II WB-4
Client: National Highways Authority of India
Engineer: RI & CEG Jv.
Contractor: Hindustan Construction Co. Ltd.
Activity: ITP for Material Testing of Piling Works
Inspec.Category
S. Controlling
Inspection and Testing Description Verifying Document Frequency of Inspec./Testing Remarks
No. Specification. HCC Engineer
03 COARSE AGGREGATE
MORTH, Table:900-6 ST &
a. Water Absorption & Specific Gravity HCC F 40 14 02 1 per source /month W R Max 2%
IS:2386(Part-3) IP
% Passing (aggregate aggregate)
Sieve size
40mm 20mm 12.5mm
63 100 - -
MORTH, Table:900-6 40 95-100 100 -
b. Gradation Analysis IS:383-1970; Table: 3 HCC F 40 14 05 Once /day during concreting W R IP 20 30-70 95-100 100
12.5 - - 90-100
10 10-35 25-55 40-85
4.75 0-5 0-5 0-10
Soundness in sodium sulphate/Magnesium MORTH, Table:900-6 Max 12% with NA2SO4
c. External testing Once /source R R ST
sulphate IS:2386(Part-5) Max 18% with Mg SO4
MORTH, Table:900-6 ST &
d. Aggregate Impact Value HCC F 40 14 07 1 per source /month W R Max 45%
IS:2386(Part-4) IP
MORTH, Table:900-6 ST &
e. Aggregate Abrasion Value HCC F 40 14 08 1 per source /month W R Max 30% for wearing course & Max 50% for works
IS:2386(Part-3) IP
f. Flakiness index IS:2386 , Part-1 HCC F 40 14 10 1 per source /month W R IP Max 35%
g. Moisture content IS:2386 , Part-3 Internal Report Prior to concreting as required W R IP Not specified
MORTH, Table:900-6 Once per source in case of
h. Alkali Aggregate Reactivity External Lab Report R R ST Non-reactive
IS:2386(Part-7) Doubt
I. Total of all Deleterious constituents IS: 2386-Part-2 External Lab Report External testing R R ST Max 5%
Page2
INSPECTION AND TEST PLAN
Project: LMNHP -EW II WB-4
Client: National Highways Authority of India
Engineer: RI & CEG Jv.
Contractor: Hindustan Construction Co. Ltd.
Activity: ITP for Material Testing of Piling Works
Inspec.Category
S. Controlling
Inspection and Testing Description Verifying Document Frequency of Inspec./Testing Remarks
No. Specification. HCC Engineer
04 FINE AGGREGATE
% passing
Sieve size
Zone-I Zone-II Zone-III
10.00 mm 100 100 100
4.75 mm 90-100 90-100 90-100
b. Grading analysis IS: 383-1970 ; Table: 4 HCC F 40 14 04 1 per day during concrete W R IP 2.36 mm 60-95 75-100 85-100
1.18 mm 30-70 55-90 75-100
600 mic 15-34 35-59 60-79
30 mic 5-20 8-39 12-40
150 mic 0-10 0-10 0-10
Soundness in sodium sulphate/Magnesium Max 10% with NA2SO4
c. IS: 2386-Part-5 External Lab Report once per source R R ST Max 15% with Mg SO4
sulphate
d. Specific gravity IS: 2386-Part-3 HCC F 40 14 03 Once , as & when required W R IP Not specified
e. Water absorption IS: 2386-Part-3 HCC F 40 14 03 Once , as & when required W R IP Max 2%
Prior to concreting & as
f. Surface moisture content IS: 2386-Part-3 Internal Record W R IP Not specified
required
h. Alkali aggregate reactivity IS: 2386-Part-7 External Lab Report once per source R R ST Non-reactive
I. Total of all Deleterious constituents IS: 2386-Part-2 External Lab Report Once per each source R R ST Max 5%
Page3
INSPECTION AND TEST PLAN
Project: LMNHP -EW II WB-4
Client: National Highways Authority of India
Engineer: RI & CEG Jv.
Contractor: Hindustan Construction Co. Ltd.
Activity: ITP for Material Testing of Piling Works
Inspec.Category
S. Controlling
Inspection and Testing Description Verifying Document Frequency of Inspec./Testing Remarks
No. Specification. HCC Engineer
05 WATER
MORTH Clause: 1010
pH value of water External Lab Report Once per each source R R ST Min 6
(IS :3025)
a.
MORTH Clause: 1010
Alkalinity limit by titration External Lab Report Once per each source R R ST Max 10ml HCL to neutralise 200ml water
(IS :3025)
b.
MORTH Clause: 1010
Acidity limit by titration External Lab Report Once per each source R R ST Max 2ml NaOH to neutralise 200ml water
(IS :3025)
c.
Permissiable limit (Max)
Organic: 200 mg/ltr
MORTH Clause: 1010 Inorganic: 3000 mg/ltr
d. Soilds in water External Lab Report Once per each source R R ST
(IS :3025)
Sulphates 500 mg/ltr
Chloride: 500 mg/ltr
Suspended matters: 2000 mg/ltr
06 CONCRETE
MORTH, Table:900-6 One test per each Batch of
a. Workability of Fresh Concrete(Slump) Internal record W S IP Slump requirement 150-200 mm
IS:1199 Concrete
MORTH MORTH
b. Compressive Strength of Concrete (Cubes) HCC F 40 14 25 W WR AT Min- 35mpa
Clause-1716 Table:1700-8
Page4
INSPECTION AND TEST PLAN
Project: LMNHP -EW II WB-4
Client: National Highways Authority of India
Engineer: RI & CEG Jv.
Contractor: Hindustan Construction Co. Ltd.
Activity: ITP for Material Testing of Piling Works
Inspec.Category
S. Controlling
Inspection and Testing Description Verifying Document Frequency of Inspec./Testing Remarks
No. Specification. HCC Engineer
08 CONCRETE ADMIXTURES
One test / batch & MTC
a. Dry material content IS 9103: 1999 Inetrnal record & MTC W/R R AT Within 3% of the value stated by the manufacturer
verification
MTC & External test as per MTC Verification & External
b. Ash content IS 9103: 1999 Engineers discretion R R AT Within 1% of the value stated by the manufacturer
testing
One test / batch & MTC
c. Relative density IS 9103: 1999 Inetrnal record & MTC W/R R AT Within 0.02% of the value stated by the manufacturer
verification
MTC & External test as per MTC Verification & External Within 10% of the value or within 0.2% ,whichever is greater as
d. Chloride ion content IS 9103: 1999 Engineers discretion R R AT stated by the manufacturer
testing
One test / batch & MTC
e. pH IS 9103: 1999 Inetrnal record & MTC W/R R AT Within +/-1 of the value stated by the manufacturer
verification
09 BENTONITE
a. Silt content determination Clause 115.2.3 of MOST Internal Record As & when required W R ST Silt content = < 1%
HCC F 40 14 37
b Liquid Limit Clause 115.2.3 of MOST As & when required W R ST LL = < 400%
LEGEND: H: Hold Point; W: Witness S: Surviellance Inspection; R: Review of Reports; MTC: Manufacturer's Test Certificate;MORTH: Ministry of Road Transport & Highways
Note: Receiving Inspection: (RI) Visual Inspection and Verification of Manufacturer Test Certificate.
Acceptance Test: (AT) Accpetance of the activity, Material
Screening Test: (ST) Tests during Source / Material Approval
In-Process: (IP) Tests during the Process / execution of the work
Format No: HCC T 40 17 16, Rev No: 00, Rev Date: 28.08.06
Page5