Pak Matiari-Lahore Transmission Company (Private) Limited

(1) Pak Matiari-Lahore Transmission Company requests completion of OPGW connections for communication channels by certain deadlines to ensure safe and stable grid operation for upcoming HVDC commissioning work in October 2020. (2) The connections are needed between converter stations and various power plants and substations to enable operation of Special Protection Schemes by certain dates. (3) OPGW connections are also required between converter stations and NPCC Islamabad for OWS monitoring by set deadlines. Delays could impact commissioning timelines and incur economic losses.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
196 views4 pages

Pak Matiari-Lahore Transmission Company (Private) Limited

(1) Pak Matiari-Lahore Transmission Company requests completion of OPGW connections for communication channels by certain deadlines to ensure safe and stable grid operation for upcoming HVDC commissioning work in October 2020. (2) The connections are needed between converter stations and various power plants and substations to enable operation of Special Protection Schemes by certain dates. (3) OPGW connections are also required between converter stations and NPCC Islamabad for OWS monitoring by set deadlines. Delays could impact commissioning timelines and incur economic losses.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Pak Matiari-Lahore Transmission Company (Private) Limited

巴基斯坦默蒂亚里-拉合尔直流输电项目公司

Ref. No.: PTC-04A-20200826-01 Dated: August 26th, 2020

Mr. Kamran Siddiqui


Chief Engineer (HVDC)
National Transmission & Despatch Company Limited (NTDCL)
Room 618, WAPDA House, Lahore

Project: ±660kV Matiari - Lahore HVDC Transmission Project


Subject: The Remainder of the Increased Risk for Communication Channels &
Necessity for OPGW Connection for OWS at NPCC and SCS Channels

Ref: (1) No. PTC-04A-20200811-01 dated 11.08.2020


(2) No. PTC-04A-20200318-01 dated 18.03.2020
(3) No. 9930-33/GM(SO)/NPCC/NRCC dated 06.08.2020

With reference to the above cited letters and coordinator meeting with HVDC office, NPCC,
Telecom, P&C and other related departments, we hereby clarify the increased risk for
communications channels and kindly request the completion of OPGW Connection for SCS
Channels and OWS at NPCC on time.

For the upcoming DC commissioning work in October, 2020, the precondition for High Load
Test of DC system is the SCS working correctly to keep the grid operation smoothly and stable in
case of unexpected fault. The OPGW communication channel is the necessary condition for the
operation of SCS. Thus the following OPGW channel must be finished to realize the SCS
function. Meanwhile, if the SCS cannot be put into operation on time, which will ultimately
affect the economic losses caused by DC commissioning delay,PMLTC disclaims liability and
reserves the right to claim compensation.

(1) OPGW Channel for SCS (Completion before October 1, 2020.)


A. OPGW connection from Matiari C/S to Engro Thar Power Plant
B. OPGW connection from Matiari C/S to Port Qasim Power Plant
C. OPGW connection from Matiari C/S to CFPP Hubco Power Plant
(The key issue is the OPGW connection from Jamshoro Substation to CFPP Hubco Power Plant)
D. OPGW connection from Matiari C/S to Moro Substation
E. OPGW connection from Matiari C/S to Dadu New Substation
Address: No.177-A, Street-6, DHA, Lahore, Pakistan
Tel: +92-42-3574 6855 Fax: +92-42- 3574 6869
Pak Matiari-Lahore Transmission Company (Private) Limited
巴基斯坦默蒂亚里-拉合尔直流输电项目公司

(The key issue is the OPGW connection from Matiari C/S to Moro Substation)

Required Completion Timeline: Prior to DC commissioning, no later than September 30,


2020.

The Sketch Map of the OPGW Connection from Matiari Converter Stations to Monitoring
Stations and Executive Station

(2) OPGW Connection for OWS at NPCC Islamabad (Completion before September 1,
2020.)

The precondition for OWS working correctly is the OPGW connection availability :

A. From Lahore C/S to NPCC Islamabad


The urgent issue is OPGW connection from Lahore C/S to Lahore (Sheikhpura) substation
(circuit 1 or circuit 2), and ensure the whole OPGW channel from Lahore C/S to NPCC
Islamabad by NTDC independently.

Address: No.177-A, Street-6, DHA, Lahore, Pakistan


Tel: +92-42-3574 6855 Fax: +92-42- 3574 6869
Pak Matiari-Lahore Transmission Company (Private) Limited
巴基斯坦默蒂亚里-拉合尔直流输电项目公司

B. From Matiari C/S to NPCC Islamabad


The urgent issues are OPGW connection from Matiari C/S to Moro substation & RY Khan
substation to Guddu 747 substation, and ensure the whole OPGW channel from Matiari C/S to
NPCC Islamabad by NTDC independently.

Required Completion Timeline: Prior to AC commissioning, no later than August 30, 2020.

The Sketch Map of the OPGW Connection from Converter Stations to NPCC Islamabad
(Only for reference)

Your cooperation in this regard shall be highly appreciated.

Sincerely Yours,

Chang Yong
Chief Engineer
Pak Matiari-Lahore Transmission Company (Private) Limited

C.C:
(1) GM (PD/GSC) NTDC, 219-WAPDA House, Lahore.
(2) CE (Telecom) NTDC, WAPDA House, Lahore.
(3) CE (Protection & Control) NTDC, WAPDA House, Lahore.

Address: No.177-A, Street-6, DHA, Lahore, Pakistan


Tel: +92-42-3574 6855 Fax: +92-42- 3574 6869
Pak Matiari-Lahore Transmission Company (Private) Limited
巴基斯坦默蒂亚里-拉合尔直流输电项目公司

(4) CE (T/L Designl) NTDC, WAPDA House, Lahore.


(5) CE (EHV-1&2) NTDC, WAPDA House, Lahore.

Address: No.177-A, Street-6, DHA, Lahore, Pakistan


Tel: +92-42-3574 6855 Fax: +92-42- 3574 6869