MB Knit Fashion LTD

This document summarizes the results of a structural safety inspection of MB Knit Fashion Ltd factory in Bangladesh. It identifies 5 issues found during the inspection including incomplete as-built drawings, uncontrolled floor loading above 2kPa, construction materials stored on the roof and 7th floor, and a lack of a loading management plan. For each issue, the inspection recommends actions, timelines, and updates the progress including submitting drawings and an engineering assessment report. The factory has addressed some issues but further work is needed to fully implement the recommendations.

Uploaded by

Masum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views3 pages

MB Knit Fashion LTD

This document summarizes the results of a structural safety inspection of MB Knit Fashion Ltd factory in Bangladesh. It identifies 5 issues found during the inspection including incomplete as-built drawings, uncontrolled floor loading above 2kPa, construction materials stored on the roof and 7th floor, and a lack of a loading management plan. For each issue, the inspection recommends actions, timelines, and updates the progress including submitting drawings and an engineering assessment report. The factory has addressed some issues but further work is needed to fully implement the recommendations.

Uploaded by

Masum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Structural Safety Inspection

Factory Name MB Knit Fashion Accord ID 12502


Ltd
Factory Address B/164-166, B/185-187 BSCIC, Fatullah, Narayanganj
Inspection Date 06/09/2016
Date of Review
26-Sep-17
Inspection
Inspected by Abu Zafar-Al-Mansur & Sourav Dutta

Final
Item Accord Accord Timeline( Progress
Accord Timeline Final Action Plan Comments after Physical Inspection Pictorial Evidence
No Observation Recommendation DD/MM/ Status
YYYY)
1 Incompletion of As- Building Engineer to (within 6-weeks) It was submitted to 31/12/2016 On 12/06/2017: No as-built drawings were In Progress
Built Drawing of produce a set of As ACCORD on available on site. Factory is required to
generator building Built drawing 02.08.2017. As more produce as built drawings along with
(Architectural & documents were Engineering Assessment report.
Structural) of needed, ACCORD has On 26/09/2017: As built drawing has been
generator building. advised us for produced and this issue is required to be
resubmission. We have covered in DEA. During inspection some
consulted with the discrepancies have been found between
consultancy and they provided drawing and as built condition.
will provide us the Factory management submitted DEA on 25th
whole package within Sept 2017 which is under review.
15.09.2017. After
receiving the packege,
we will submit it as
soon as possible.

2 Uncontrolled Reduce floor loading (Immediate - Now) As per building 13/11/2016 On 12/06/2017: No Floor load plan was Corrected
loading on floor down to 2Kpa. strenght our floor found. Floor load was observed below 2
area loading capacity would kPa.Factory is required to produced floor load
be above 3Kpa. plan along with EA.EA should be submitted
Calculation will be immediately.
provided during as-built On 26/09/2017: During inspection floor
design submission. loading was observed below 2kPa at all floor
levels.
Final
Item Accord Accord Timeline( Progress
Accord Timeline Final Action Plan Comments after Physical Inspection Pictorial Evidence
No Observation Recommendation DD/MM/ Status
YYYY)
3 Uncontrolled Remove all (Immediate - Now) Done 25/11/2016 On 12/06/2017: No action has been taken In Progress
loading on floor construction materials against this issue.
area from roof On 26/09/2017: Construction materials were
found on roof as well as on 7th floor. Factory
management must remove all materials from
those area.

4 Uncontrolled Produce and actively (within 6-weeks) It was submitted to 21/12/2016 On 12/06/2017: No Floor load plan was In Progress
loading on floor manage a loading ACCORD on found. Floor load was observed below 2
area plan for all 02.08.2017. As more kPa.Factory is required to produced floor load
floor plates within the documents were plan along with EA.EA should be submitted
factory giving needed, ACCORD has immediately.
consideration to advised us for On 26/09/2017: Factory has submitted Floor
floor capacity and resubmission. We have load plan along with DEA. During inspection
column capacity. consulted with the floor loading was observed below 2kPa at all
consultancy and they floor levels. Final load plan will be followed
will provide us the after DEA acceptance.
whole package within
15.09.2017. After
receiving the packege,
we will submit it as
soon as possible.

5 Uncontrolled Continue to implement (within 6-months) Continuing to 11/05/2017 On 12/06/2017: No Floor load plan was In Progress
loading on floor load plan implement load plan found. Floor load was observed below 2
area kPa.Factory is required to produced floor load
plan along with EA.EA should be submitted
immediately.
On 26/09/2017: Factory management will be
able to implement final load plan after DEA
acceptance. Meanwhile they have to maintain
load below 2kPa at all floor levels.
Final
Item Accord Accord Timeline( Progress
Accord Timeline Final Action Plan Comments after Physical Inspection Pictorial Evidence
No Observation Recommendation DD/MM/ Status
YYYY)
6 Dampness found Building Engineer to (within 6-weeks) DONE on 20.03.2017 15/11/2016 On 12/06/2017: Dampness has been Corrected
on the bottom slab investigate the extent repaired.
of RCC water Tank of On 26/09/2017: This issue has been
dampness and corrected from the previous inspection. During
recommend the inspection it was observed that dampness was
suitable repair on it repaired.

7 Dampness found Take remedial action (within 6-months) Repair DONE on 30/04/2017 On 12/06/2017: No investigation report was Corrected
on the bottom slab as per investigation 25.03.2017. Crack available on site. Dampness has been
of RCC water Tank report wiil be submitted repaired. Factory is required to submit crack
to ACCORD with the investigation report.
As-built design On 26/09/2017: During inspection it was
submission observed that dampness was repaired.
Assessment report was also provided by the
consultant.

8 Provision for future If vertical extension is (within 6-weeks) We have a meetting at 10/11/2016 On 11/06/2017: No vertical extension was In Progress
vertical Extension intended, to conduct 10.11.2016 with the top observed. Factory must be provided a consent
its feasibility management of the letter if they were not interested to extend the
conduct DEA for the company that NO building vertically.
factory building vartical extention will On 26/09/2017: During inspection no vertical
following BNBC. be done in future as extension was found. This issue is required to
the building plan is be covered in DEA. DEA under review.
G+7(8 strored) building
and it has been
completed before
march 2015.

9 Provision for future Implement necessary (within 6-months) We have a meetting at 10/11/2016 On 11/06/2017: No vertical extension was Corrected
vertical Extension remedial actions 10.11.2016 with the top observed. Factory must be provided a consent
recommended in DEA. management of the letter if they were not interested to extend the
company that NO building vertically.
vartical extention will On 26/09/2017: During inspection no vertical
be done in future as extension was found. This issue is required to
the building plan is be covered in DEA. DEA under review.
G+7(8 strored) building
and it has been
completed before
march 2015. Consent
letter will be submitted
during the next as built
design submission.