Request For Inspection
Date: 2020.3.1
Request no. 000033
Project Title: Design, Procurement, Furnishing & Execution of Ethiopian Skylight 5-star Hotel Phase-2 Project
Employer: Engineer: Contractor:
We request your attendance to inspect the following works :
1. Type : Buildings Reinforcement work of columns and shear walls for basement 1 at part 1area
2. Inspection time: 10:00 am Date : 2020.3.2
3. Location :project site Building √ Floor Element Drawing no.
19AH03M-J2-23g2/24g2/25g2
4. Inspection First Second Third
5. Purpose of the inspection:
3. Structure
1. Surveying 5. Architecture
Setting out Formwork
Blockwork Floor Finish
Levels Reinforcement
Plaster False Ceilings
Verticality Concreting
Metals Roofing
Woods & Plastics Waterproofing
2. Earthworks 4. Electro-Mech.
Formation First Fix
Doors & Windows Painting
Sides of Excavation Second Fix
Wall Finish Furniture
Others (specify) -
We have complete the reinforcement work of columns and shear walls for basement 1 at part 1 area,here with
Particular Details the inspection request for form shutter close
Submitted by : Song Baoliang Signature
6. Inspection report Signature
Date/Time of inspection :
7. Engineer's Representative comments:
The works are : Approved Approved as Noted Rejected
Signature: Date:
Attach all relevant particular test forms IR-BLDG-1
Approval shall not relieve Contractor of his liabilities under the Contract or constitute authorization of any change to Contract Documents.
S-PRC-SS-02(F33) Rev 2