Building Projects
Building Projects
FOREWORD
This guideline outlines engineers' responsibilities related to the design and construction of
buildings. It replaces the following seven APEGGA guidelines that covered some, but not all, of
the engineering disciplines and phases of the design and construction process:
Commissioning;
Consultant Fees for Building Projects;
Professional Practice in Building Design;
Professional Practice in Building Projects Using Pre-manufactured Building Components;
Required Detail Content in Electrical Drawings and Specifications for Constructions or
Tender;
Responsibility for Structural Design on General Engineering and Building Projects; and
Review During Construction on Building Projects.
This document differs from the previous guidelines in that it:
Covers all of the major engineering disciplines involved in buildings;
Covers all of the different phases of design, construction, and post-construction; and
Deals with the concepts, which were introduced in the 1997 edition of the Alberta Building
Code, of registered professionals of record, engineers of record and coordinating registered
professionals for building projects.
The previous APEGGA guidelines had dealt primarily with the design-bid process. This
document is intended to be generally applicable, or at least adaptable, to many types of project
delivery methods.
This guideline is intended to satisfy the following objectives:
Enhance the quality of engineering services provided to the owner of a building project;
Maximize the safety of the public associated with engineering work on building projects;
Encourage consistent methodologies and practices that will have a positive effect on the
quality of the completed project;
Reflect the intent of the Engineering, Geological and Geophysical Professions Act and
Regulations; and
Serve as a reference for the Discipline Committee in adjudicating allegations of unskilled
practice of the profession.
i
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
PARTICIPANTS
APEGGA’s Practice Standards Committee (PSC) publishes practice standards, recommended
practices and guidelines to promote high levels of professional service. A PSC subcommittee of
the following individuals prepared the early drafts of this document:
Norm Webster, P.Eng., Chair
Mark Lasby, P.Eng.
Howard Leung, P.Eng.
Jim Sawers, P.Eng.
Dave Thurston, P.Eng.
Charlie Weir, P.Eng.
Through the later stages of development, additional individuals were added to provide technical
input. At the time the original document (v1.0) was completed in April 2001, the subcommittee
had the following membership:
Subsequent minor revisions were made by the Practice Standards Committee in March 2003
and March 2009.
Comments that may help to improve this document should be addressed to:
ii
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
TABLE OF CONTENTS
1 OVERVIEW............................................................................................................................. 1
1.1 Scope .......................................................................................................................... 1
1.2 Purpose ....................................................................................................................... 1
1.3 Qualification................................................................................................................. 2
2 DEFINITIONS ......................................................................................................................... 2
APPENDIX A
TYPICAL ORGANIZATION RELATIONSHIPS.......................................................................... 39
APPENDIX B
STRUCTURAL ENGINEERING CALCULATIONS AND DRAWINGS ...................................... 40
B-1 General...................................................................................................................... 40
B-2 Structural Calculations .............................................................................................. 40
B-3 Structural Drawings ................................................................................................... 41
APPENDIX C
MECHANICAL ENGINEERING CALCULATIONS AND DRAWINGS....................................... 44
C-1 General...................................................................................................................... 44
C-2 Site ............................................................................................................................ 44
C-3 Plumbing and Drainage............................................................................................. 45
C-4 Heating, Ventilating, Air conditioning, and Refrigeration (HVAC&R)/Controls .......... 47
C-5 Fire Protection ........................................................................................................... 48
iii
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
APPENDIX D
ELECTRICAL ENGINEERING CALCULATIONS AND DRAWINGS ........................................ 50
D-1 General...................................................................................................................... 50
D-2 Site ............................................................................................................................ 50
D-3 Power ........................................................................................................................ 50
D-4 Lighting...................................................................................................................... 51
D-5 Life Safety Systems................................................................................................... 51
D-6 Communications........................................................................................................ 52
D-7 Building control Systems ........................................................................................... 53
D-8 Grounding.................................................................................................................. 53
D-9 Special Systems........................................................................................................ 53
D-10 Risers and Single Lines............................................................................................. 54
D-11- Schedules.................................................................................................................. 54
APPENDIX E
GEOTECHNICAL ENGINEERING SERVICES .......................................................................... 56
E-1 Introduction................................................................................................................ 56
E-2 Reporting................................................................................................................... 57
APPENDIX F
POTENTIAL RESPONSIBILITY GAPS AND CONFLICTS ....................................................... 59
F-1 Introduction................................................................................................................ 59
F-2 Examples of Possible Responsibility Gaps ............................................................... 59
F-3 Cautionary Notes....................................................................................................... 63
APPENDIX G
LETTERS OF COMMITMENT, LETTERS OF COMPLIANCE, AND SCHEDULES ................. 64
G-1 Applicable Standata .................................................................................................. 64
G-2 Letters of Commitment and Compliance from Coordinating Registered
Professional, Registered Professional of Record and Specialty Professionals......... 64
iv
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
1 OVERVIEW
The Alberta Building Code requires that qualified professionals assume responsibility for
design of building projects that fall within the scope of the code. The concepts of
registered professional of record, engineer of record and coordinating registered
professional were introduced in the 1997 Alberta Building Code. This document provides
guidance on incorporating those professional responsibilities into the contractual and
organizational relationships typically used for building projects.
Notwithstanding their duties under common law, APEGGA members are subject to the
special responsibilities to protect the public interest as indicated in the Code of Ethics
under the Engineering, Geological and Geophysical Professions Act and the
Regulations. Professional engineers cannot contract out of those responsibilities.
This document addresses the responsibilities of all of the major engineering disciplines
involved in building projects. All phases of the basic engineering services that would
normally be provided under typical contractual arrangements are outlined. The
implications of alternative methods of project delivery, other than design-bid, are also
addressed.
The appendices provide further information with respect to:
Typical organizational relationships found on building projects;
The normal scope of engineering services for the engineers of record; and
Discussion of potential situations where responsibilities between disciplines may be
unclear.
1.1 SCOPE
This document sets out recommended practices related to the design and construction
of building projects that APEGGA members should meet and follow in providing
professional engineering services. It describes the roles and responsibilities of engineers
and outlines the professional services that the project team participants should generally
provide.
The scope does not extend to buildings that are exempt from the jurisdiction of the
Safety Codes Act, such as farm buildings and small buildings described in the Alberta
Building Code. Buildings that are exempt from the Safety Codes Act and the
Engineering, Geological and Geophysical Professions Act and Regulations do not
require the involvement of a professional engineer except in specific circumstances
dictated by the authority having jurisdiction. Nevertheless, work on exempted buildings
must be performed to the same standards applied to non-exempted buildings.
1.2 PURPOSE
This document is intended to establish minimum standards of practice for APEGGA
members to follow in fulfilling their professional obligations, especially in regard to their
primary duty to protect the public. Variations in the application of this document may be
required, but members must always exercise professional judgment in providing
services.
1
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
This guideline is intended not only to help avoid the recurrence of some problems that
have arisen in the past but also to help address changes in the Alberta Building Code
regarding definitions of the responsibilities of registered professionals.
1.3 QUALIFICATION
Notwithstanding the purpose and scope of this guideline, the decision by an engineer not
to use this document does not mean that he or she is negligent or unprofessional in the
performance of professional services. Any such judgment will depend upon a detailed
analysis of all the facts to determine if another qualified engineer in circumstances of a
similar nature would have conducted himself or herself in a similar manner.
2 DEFINITIONS
For the purposes of this document, the following terms and definitions apply.
2.1 As-Built Drawings
Drawings that are prepared from measurements taken on site to depict accurately the
actual characteristics (size, shape, depth, trade name, location, type, etc.) of elements of
the construction.
2.2 Association (APEGGA)
The Association of Professional Engineers, Geologists and Geophysicists of Alberta.
2.3 Authority Having Jurisdiction (Authority)
Authority having jurisdiction means a safety codes officer in the building discipline
appointed pursuant to the Safety Codes Act.
2.4 Basic Services
The services provided by the registered professionals of record, as defined in Section
4.0.
2.5 Building
Building means any structure used or intended for supporting or sheltering any use or
occupancy.
2.6 Client
The party who engages the coordinating registered professional or registered
professionals of record to provide professional engineering services for any work in
regard to the building.
2.7 Code
The current edition of the Alberta Building Code proclaimed under the Safety Codes Act.
2.8 Commissioning
Commissioning encompasses the architectural, structural, mechanical, electrical,
process and specialty systems, and is defined as "the process of proving the
performance of the equipment and systems to determine their capability to meet
performance requirements."
2
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
3
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
4
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
5
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
6
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
control procedures for the specific assignment and communicate with other members of
the project team. Finally, they must document their actions to provide a record for
checking purposes or audit by their professional peers.
1. Allocation of responsibilities on building projects is not always well defined.
2. On any particular building project, there are several engineering disciplines and
many contractual parties involved.
3. There can be various contractual parties and many potential types of contractual
arrangements. For example, a design professional could be a prime consultant or a
sub-consultant, and could be engaged by an owner, constructor or sub-constructor.
4. In addition, there are many types of “project delivery methods”, each with its
peculiarities (e.g. traditional design-bid, fast-tracked, design-build, etc.).
5. Some aspects of professional responsibilities are not always clearly defined – they
may not be specifically attached to a particular discipline or to a particular registered
professional of record.
6. Certain aspects of design for building construction are sometimes undertaken
without involvement of design professionals where, in fact, there should have been
such involvement.
Consequently, there is a potential for some responsibilities to be unassigned or to be
unclear.
APEGGA supports the proposition that members should receive fair and adequate
compensation for services rendered and that this principle applies to the services
outlined in this document. In no event will low fees be justification for services that do not
meet this guideline. Members may wish to discuss this document with owners or with
employers when receiving instructions for assignments and reaching agreements
regarding the work to be carried out and compensation.
APEGGA requires that its members, both individual and corporate, only undertake such
assignments for which they are qualified by virtue of their training and experience. If a
company’s area of professional practice is limited to structural engineering, it must
restrict its advertising and representations to reflect that limitation. Its proposals should
indicate the organizational arrangement with respect to professional services in the
geotechnical, electrical and mechanical engineering disciplines. Companies that offer
design-build services for a building project to the public are required to provide the
professional services to complete the project in accordance with the Alberta Building
Code, the Safety Codes Act and the Engineering, Geological and Geophysical
Professions Act. They are required to utilize registered professionals who will assume
responsibility for the various areas of practice in which they offer services.
7
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
professional assume responsibility for design of building projects that fall within the
respective sections of the code.
In addition, the coordinating registered professional named to assume responsibility for
the total project design must be capable of coordinating the design team made up of one
or more professional disciplines.
The Alberta Building Code also requires that a professional engineer undertake a field
review of the construction relative to the design.
8
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
The coordinating registered professional and the owner must recognize that, in selecting
pre-manufactured building component suppliers, they are also selecting the specialty
professionals employed by those suppliers. These specialty professionals must be
evaluated with respect to their competence and capacity to undertake the assignment.
Specialty professionals must be registered in the Province of Alberta, otherwise
professional responsibility could rest with the registered professional of record.
9
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
10
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
11
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
12
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
3.7.1 Owner
To carry out the design and construction of the project in a manner that meets
appropriate standards of public safety and the requirements of applicable building
regulations, the owner should take the following actions.
a) Obtain adequate financing before proceeding with the project.
b) Establish contractual relationships to ensure that the project team includes a
coordinating registered professional and registered professionals of record in the
applicable disciplines.
c) Co-operate with the coordinating registered professional to develop an adequate
written description of the needs, expectations and constraints to be considered in the
project assignment.
d) Co-operate with the coordinating registered professional and registered
professionals of record to set out a written description of the scope of service of the
coordinating registered professional and of the registered professionals of record.
e) Co-operate with the coordinating registered professional to establish a realistic
schedule for the provision of the coordinating registered professional's services.
f) Acquire the right to construct on the property.
g) Acquire the zoning approvals for the project.
h) Ensure that all required approvals, licences and permits from the authorities having
jurisdiction are obtained.
i) Enter into a contract with a constructor for the construction of the project.
j) Respond to the various reports and other recommendations by the coordinating
registered professional with decisions on all aspects of the project. (Owner decisions
that overrule public safety and environmental considerations must be dealt with by
any registered professional associated with the project, in accordance with the
applicable professional Code of Ethics.)
13
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
k) Recognize that, because code interpretation of the authority having jurisdiction may
differ from that of the coordinating registered professional and the registered
professionals of record, some changes may be required by the authority.
l) Provide for a reasonable contingency in the project budget, recognizing that
unforeseen circumstances can arise.
m) Authorize in writing any additional services that may be required.
n) Recognize that drawings, specifications and other documents prepared by the
coordinating registered professional and the registered professionals of record are
for the project. Such documents should not be used or copied for other projects
without the agreement of the coordinating registered professional and registered
professionals of record, and without advice from a qualified design professional.
o) Ensure that registered professionals are engaged to review during construction in
accordance with the requirements of the Alberta Building Code.
p) Assume the role of prime constructor, under Alberta Safety Codes Act, or delegate
this role to the constructor or other party that is qualified and engaged specifically for
that role.
q) Notify the authority in writing of any change in name of the registered professional
retained to review during construction.
r) Ensure that the registered professional of record or professional retained to review
during construction submits completed schedules. The schedules are to be signed
by the responsible professional in each of the applicable disciplines and should
indicate the review of construction conforms to the drawings, specifications and the
Alberta Building Code.
s) If required by the authority, make applications in writing, for an occupancy permit or
permission in writing to occupy part or all of the building, after determining that public
safety requirements of the Alberta Building Code have been met.
If the owner fails or refuses to carry out the obligations as set out in paragraph 3.7.1,
the coordinating registered professional should:
Give notice to the owner advising the latter of the coordinating registered
professional's recommendations; and
Consider whether the coordinating registered professional can continue with the
project, since the coordinating registered professional must comply with the minimum
requirements of applicable regulations and codes of ethics.
14
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
b) Direct and coordinate the design team through all phases of the project.
c) Establish procedures for timely and clear communication and documentation of
decisions by the owner, registered professionals and constructor that affect the other
parties.
d) Interpret and define for the registered professionals of record the needs of the owner
in order to assist the owner in defining his or her intended functions and needs.
e) Establish in conjunction with the registered professionals of record the scope of work
of each engineer of record for design, preparation of contract documents, field review
and contract administration, including definition of basic services and additional
services.
f) Establish contractual arrangements, and fees, and payment schedules. Association
of Consulting Engineers of Canada documents No. 31, 32 or 32-S are recommended
as a basis for such contracts.
g) Co-operate with the registered professionals of record to determine the design
criteria for the assignment, including the applicable codes or other regulatory
requirements.
h) Coordinate and review the designs, drawings and other contract documents
produced by all participants of the design team.
i) Advise the owner with respect to tendering procedures or other project delivery
methods.
j) Advise the owner of the requirements for field review.
k) Advise the owner with respect to the incorporation of commissioning into the design
and specifications for the project.
l) Prepare or assist the owner in preparing, tender and contract documents.
m) Prepare documents for submission to authorities for applicable permits at
appropriate stages of the work, including Schedule A-1, A-2, B-1, B-2, and C as
applicable, as required by the Alberta Building Code.
n) Monitor the scope, schedule and budget of the design and construction of the project
as it progresses. Resolve with the owner any changes needed to the scope,
schedule and budget.
If the coordinating registered professional fails or refuses to carry out the obligations as
set out in paragraph 3.7.2, the registered professional of record should:
Give notice to the coordinating registered professional advising the latter of the
registered professionals of record’s recommendations; and
Consider whether the registered professionals of record can continue with the
project. The registered professionals of record must comply with the minimum
requirements of applicable regulations and the Code of Ethics.
15
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
16
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
Responsibility for specification or field review of excavation and back-fill. (Either the
coordinating registered professional, architect of record, structural engineer of
record, or geotechnical engineer of record could be responsible for these particular
activities. Therefore, on a project, the responsibility must be clearly understood.);
Interface among disciplines (e.g. power requirements for mechanical controls);
Space requirements (e.g. for mechanical and electrical rooms); and
Responsibility for structural engineering input for secondary structural elements.
17
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
18
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
3.7.6.2 Commissioning
The commissioning of construction projects is a managed process that shares
responsibility for tasks between the owner, coordinating registered professional,
registered professionals of record, the constructor and specialty testing firms. The
responsibilities vary among projects and must be clearly defined, coordinated and
integrated into the normal project development process.
The commissioning procedures must be planned well in advance of the completion of
construction and implemented throughout the construction, start-up and post-
construction phases of the project. The commissioning process is closely associated
with the overall construction of the project and, in fact, is driven by the construction
schedule.
3.7.6.3 Environmental
Specialty professionals or other qualified consultants should be retained to perform
environmental audits where deemed necessary by a regulatory jurisdiction, coordinating
registered professional, registered professional of record or the owner.
3.7.8 Constructor
The constructor has a contract with the owner. This contract usually specifies that the
constructor is responsible for the labour, materials and equipment for the work and that
the constructor is responsible, as set out in the contract documents, for the construction
19
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
20
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
d) Inform the owner that the professional engaged to perform field reviews will be
required to submit a construction completion certificate (Schedule C in the Alberta
Building Code).
e) Inform the owner that an occupancy permit or permission in writing to occupy will be
required before permission will be granted to occupy the building.
f) Ensure that the registered professionals of record or another registered professional
has been engaged to perform field reviews.
g) Issue building permits.
h) Issue remedial orders if it is determined that:
The frequency or quality of field reviews are not adequate; and
Construction does not conform to the Alberta Building Code.
i) Issue stop-work orders on project under construction if it is determined that:
The professional engaged to perform field reviews is not performing that function;
The building permit is invalid;
Construction is unsafe;
Site conditions are unsafe.
j) Inform APEGGA of any concerns regarding unskilled practice or unprofessional
conduct by professional engineers.
k) Issue occupancy permits or permission in writing to occupy.
3.7.10 Manufacturer
In some cases, the manufacturer designs and constructs a component of a building. If
so, the manufacturer undertakes the responsibilities of a specialty professional and
should meet the following criteria.
a) Design the manufactured building component in conformance with the design criteria
supplied by the design professional (registered professionals of record or specialty
professional), the Alberta Building Code, other standards and good engineering
practice.
b) Prior to construction, supply shop drawings. This should include all necessary details
and other information that may be required for the registered professionals of record
or specialty professional to undertake his or her work. The manufacturer should
stamp these drawings when requested by the registered professionals of record or
specialty professional.
c) Supply, prior to construction, when requested by the registered professionals of
record or specialty professionals, a letter of certification (See Appendix D.) stamped
and signed by a registered professional. The letter of certification should state:
The requirements specified by the registered professionals of record or specialty
professionals, such as strength or performance, have been accommodated in the
design; and
21
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
The process used in the fabrication of the components being supplied conforms
to the Alberta Building Code.
3.7.11 Distributor
The distributor should:
Represent the manufacturer as an extension to the latter’s sales organization;
Maintain current technical information on the manufacturer’s products; and
Facilitate communications between the registered professionals of record or
specialty professionals and the manufacturer.
22
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
23
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
advantages and disadvantages. This will allow the owner to weigh the choices and
make an informed decision before the design team proceeds any further.
d) Determine the number and timing of project-team meetings during each phase of the
project.
e) Determine and maintain channels of communication.
f) Develop or review the project schedule, including any milestone dates.
g) Establish dates by when information affecting the individual discipline design will be
needed from other disciplines.
h) Determine drawing standards and specifications format.
i) Define the responsibility for showing overall and detail dimensions on the drawings.
j) Establish procedures for quality control for the assignment.
k) Co-operate with others preparing cost estimates and schedules.
l) Review conformance with the requirements of the environmental impact assessment
or environmental report on which designs are based.
24
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
25
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
26
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
d) Prepare their portion of the design development report and submit it to the
coordinating registered professional.
e) Finalize materials and systems for the project.
f) Consider the requirements of the other design professionals and provide the
information they require.
g) Identify deviations from and potential impact on owner’s program.
h) Establish procedures for quality control for the project.
i) Explain in writing to the owner all new construction materials or new techniques the
coordinating registered professional and registered professionals of record proposed
for use in the project. The alternatives, including the short and long-term risks,
advantages and disadvantages should be explained. This will allow the owner to
weigh the choices and make an informed decision before the design team proceeds
any further.
j) Co-operate with others responsible for preparing the cost estimate.
27
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
28
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
29
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
Specifications are written descriptions of all elements that are best described rather than
delineated. They include requirements related to the manufacture, methods of
installation, design, performance criteria and workmanship of materials and equipment.
30
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
31
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
d) Prepare Schedules A-2, B-1 and B-2 as required by the Alberta Building Code and
any other documents required by the authority having jurisdiction.
32
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
33
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
34
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
z) Report to the owner and the authority when construction review services are
withdrawn for any reason.
35
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
36
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
37
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
s) Providing renderings or models for use by the owner and the coordinating registered
professional.
t) Obtaining on the coordinating registered professional’s or owner’s behalf, required
approvals, licences and permits from municipal and governmental authorities having
jurisdiction over the project.
u) Performing analyses involving the use of computer programs to simulate building
energy use.
v) Commissioning of architectural, structural, mechanical and electrical systems,
including training and maintenance assistance.
w) Providing post-construction inspection services, if not specifically included in basic
services.
x) Resolving issues, other than those relating to the original design, arising during post-
construction inspections.
Supplemental services might entail providing additional or extended services made
necessary by:
Work damaged by fire or other causes during the term of the contract;
Defective work of the constructor;
Unreasonable prolongation of the contract time due to strikes and other reasons
beyond the control of the registered professional of record;
The constructor’s default under the contract arising from his or her delinquency or
insolvency, or the delinquency or insolvency of those employed by the constructor;
Incorrect information or defective work provided by the owner or by the coordinating
registered professional;
Emergencies on site;
Non-performance of work covered by warranty.
38
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
APPENDIX A
TYPICAL ORGANIZATION RELATIONSHIPS
Owner
Owner Constructor
Coordinating Coordinating
Registered Constructor Registered
Professional Professional
Registered Registered
Professionals Professionals
of Record of Record
Owner Owner
Communications
Contracts
39
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
APPENDIX B
STRUCTURAL ENGINEERING CALCULATIONS AND DRAWINGS
B-1 GENERAL
The structural engineer of record must prepare structural calculations to support all
structural designs. The structural calculations should be prepared legibly and
presentably, and be filed by the structural engineer of record for record purposes. A hard
copy of input and output of any computer analyses should be included and so should a
description of the software used.
40
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
41
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
Location of known existing services and existing foundations that conflict with
structural foundations, or the source where this information can be found should
be referenced; and
If underpinning or temporary shoring is specified to be designed by others, there
should be indication on the drawings of the areas designated to be shored or
underpinned. If shoring or underpinning is designed by the structural engineer of
record, there should be indication of all details and construction sequences.
d) Floor and roof framing plans and details should include:
General gridline dimensions and overall building dimensions;
Sizes, locations, dimensions and details of all structural elements;
Elevations, including slopes and depressions;
Lateral-load-resisting system;
Governing forces, moments, shears or torsion required for the preparation of
shop and detail drawings;
Reinforcing bar sizes and details with placing criteria;
Locations and details of control, construction, contraction and expansion joints;
Locations, sizes and reinforcing of significant openings; and
Provision for future extensions.
e) Schedules and details for columns, beams and walls should include:
Element sizes;
Anchorage to supporting elements;
Elevation of bottom of columns;
Reinforcing steel and splice details for concrete columns;
Splice locations for structural steel columns;
Structural details of masonry or reinforced concrete walls, including lintels, details
and reinforcing of significant openings; and
Stiffeners, lateral bracing and local reinforcements for steel members.
f) Connections
Where connections are specified to be designed by specialty structural engineers, the
contract drawings should indicate all required information and governing forces. In such
cases, the specialty structural engineer shall seal, sign and date the fabrication
drawings. Where connections are designed by the structural engineer of record, they
should show all dimensions and comprehensive connection details requiring no further
engineering input. Under these circumstances, the structural engineer of record retains
responsibility for these connections.
The structural engineer of record shall consider the design of the connections when
sizing the structural members, e.g. HSS truss joints, post-tensioned anchorages.
42
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
43
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
APPENDIX C
MECHANICAL ENGINEERING CALCULATIONS AND DRAWINGS
C-1 GENERAL
C- 1.1 Each mechanical drawing should include the following items:
name of the project
north arrow
scale of the plan
consultant's name
C-1.2 A set of mechanical drawings should include a summary of all symbols indicated on the
drawings.
C-1.3 All drawings, as well as details, elevations and sections should be properly cross-
referenced.
C-1.4 All equipment and devices that require connection to the electrical system must be
coordinated with the electrical engineer of record. At a minimum, the power, control and
interlock requirement for each load should be indicated. Trade responsibilities and trade
definition rules for the project should be established prior to passing information to the
electrical engineer of record.
C-1.5 The structural engineer of record should be provided with drawings and information
indicating concrete bases, curbs, roof openings, floor openings, wall openings, structural
member penetrations and equipment weights/dimensions. The structural engineer of
record also should be provided with details on the force imparted onto structural
members due to piping expansion and anchorage.
C-2 SITE
C-2.1 For clarity, the mechanical site plan should be superimposed on a
landscape/architectural site. plan.
C-2.2 The municipal address should be clearly indicated on the plan.
C-2.3 All mechanical utilities should be referenced to buildings, property line or other utilities.
All features and dimensional information affecting routing, placement and function of the
mechanical services should be indicated.
C-2.4 All invert information should be provided in metres (Geodetic).
C-2.5 Utility connection information should be provided for all services and information should
include, but not be limited to, the following:
1. Water supply, including:
Pipe size and routing;
Water meter/backflow preventor location and detail, if not shown on plumbing
drawings, and
Fire-protection demand where applicable.
44
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
45
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
On multi-story buildings, indicate risers on floor plans and provide riser diagrams
where appropriate; and
For clarity, provide larger-scale plans (1:50) for areas with a high density of fixtures.
Schematics and diagrams should be provided to fully describe the operation of all major
systems. Direction of flow and control points should be clearly indicated. The sequence
of operation should be provided on the schematics or included in the control-system
specifications.
C-3.10 Schedules
Schedules should be included to provide capacities and details for the performance of
fans, air-handling units, pumps, etc. Alternatively, these schedules may be included in
the specifications.
46
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
The design responsibility for the fire extinguishers should be confirmed with the
coordinating registered professional.
2. Standpipe and Sprinkler Systems
The following section assumes that a detailed set of sprinkler drawings will be provided
by a fire-protection specialty consultant. If the mechanical engineer of record’s scope of
services includes engineered fire-protection drawings, they shall be provided in
compliance with NFPA and the authority having jurisdiction. At a minimum, the
mechanical engineering drawings should include the following:
Specification of the zoning and hazard for each zone;
Calculations determining water demand and pressure requirements. (These
calculations should be used to determine if a fire pump is required);
Main service location and risers;
Details of main fire-protection components, including fire-pump information; and
Location, number and detail for interconnecting system devices to the fire or sprinkler
monitoring system.
3. Specialty Fire-Protection Systems
Plans, schematics and diagrams should be provided to fully describe the operation of all
specialty fire-protection systems. Direction of flow, control points and sequence of
operation should be clearly indicated by:
Calculations determining demand and pressure requirements;
Specifying the zoning and hazard for each zone;
Providing location, number and detail for interconnecting system devices to the fire
or sprinkler-monitoring system; and
Performance specification.
47
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
C4.6 Schedules
Schedules should be included to provide capacities and details for the performance of
fans, air-handling units, pumps, etc. Alternatively, these schedules may be included in
the specifications.
48
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
49
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
APPENDIX D
ELECTRICAL ENGINEERING CALCULATIONS AND DRAWINGS
D-1 GENERAL
Each electrical drawing should include the symbol schedule, the name of the project, a
north arrow and the scale of the plan. A set of electrical drawings should include a
summary of all symbols indicated on the drawings. All drawings as well as details,
elevations and sections should be properly cross-referenced.
D-2 SITE
D-2.1 Equipment
Locations of service points, power poles, transformers, grounding, lighting standards,
luminaries, distribution panels, parking outlets and other equipment should be shown.
D-2.2 Wiring
Location and routing of all wiring including services, feeders branch wiring and empty
conduit should be shown.
D-2.3 Details
The following should be provided:
Details, as required, for equipment pads and bases, vaults, grounding, duct banks,
manholes, parking lot distribution system and outlets, luminaries, and control circuits;
and
Information necessary for coordination of site services with utilities.
D-3 POWER
D-3.1 Service
Location and general arrangement of service equipment should be shown.
D-3.2 Distribution
The following should be shown:
Location and general arrangement of service and service equipment;
Location and general routing of bus duct, cable tray, under-floor raceway and
feeders; and
Equipment elevations and details where required by project size and complexity.
D-3.3 Equipment
Location, identification, type, rating, load, and circuiting for power receptacles,
equipment connections, convenience receptacles, motors, loose motor control,
disconnects and special outlets should be shown.
Outlet symbols should be properly identified and the applicable CSA designations
shown.
Feeder sizes on either floor plans, single-line or on schedules should be indicated.
50
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
D-4 LIGHTING
D- 4.1 Luminaries
Location, identification, type, circuiting, and switching should be shown. Luminaries
should be coordinated with ceiling and finished to ensure proper application and
accessibility for maintenance.
D-5.4 Equipment
Location, connection, and circuiting for emergency equipment, such as fire pumps,
should be shown.
51
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
D-5.7 Devices
Location, type, and zoning for manual stations, automatic detectors, signals, door
holders, door locks, flow switches, microphones, handsets, and speakers should be
shown.
D-5.8 Interface
Location of connections to other equipment such as fire dampers, air-handling units,
smoke doors, sprinkler pumps, elevators, etc. should be shown.
D-6 COMMUNICATIONS
D-6.1 Raceways and Wiring
The following should be shown:
Location, routing and sizes of risers, cable tray and distribution conduits; and
Wiring for home runs, runs with more than one zone, outlets and junction boxes.
D-6.4 Public Address (PA), Sound Masking, Sound Reinforcement, and Intercom
Equipment
Location, identification, type and approximate sizes of amplifiers, signal sources,
processors, switches, master stations and patch panels should be shown.
D-6.5 PA Outlets
Location, type, and zoning of speakers, microphones, jacks and outlets should be
shown.
52
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
Location, identification, type and zoning for control panels, door switches, motion
detectors, detection equipment, control stations and signals should be shown.
D-8 GROUNDING
The following should be shown:
Location, type and configuration of all grounding electrodes, mats, etc.;
Size, type and routing of all grounding conductors;
Location and connection of all air terminals, interconnections, horizontal and down
conductors for lighting protection, including antennae;
Details of all special grounding means, such as grids, high-impedance grounding,
computer floors and outlets, etc.; and
Details of cathodic protection.
53
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
Location, identification, type and approximate sizes of equipment, panels and outlets;
Adequate details for power supply systems such as stand-by generators,
uninterruptible power-supply systems, motor-generator sets, battery systems, etc.;
and
Wiring for home runs. For runs with more than one device, outlets and junction boxes
should be shown.
D-11 SCHEDULES
D-11.1 Luminaries
The type, description, lamps, voltage, diffusers, and mounting should be shown.
D-11.2 Panels
The type, circuits, voltage, amperage, breakers and space quantities and mounting
should be shown.
54
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
55
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
APPENDIX E
GEOTECHNICAL ENGINEERING SERVICES
E-1 INTRODUCTION
This appendix differs from other appendices in this document. Whereas Appendices B,
C, & D address the issue of what should be contained or shown within design
calculations and drawings, the geotechnical engineering process often involves the
subjective appraisal of geological and geomorphological conditions. Moreover,
compared to other professions, the design report often contains fewer calculated design
values and more qualitative recommendations for construction.
The objective of this appendix is to provide a listing of topics that could be addressed in
the design process. Those issues that may require supporting calculations have been
marked with an (*). The appendix also includes a listing of services that are commonly
provided by the geotechnical engineer of record, as noted below.
56
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
E-2 REPORTING
A report, summarizing the results of the site works, laboratory work, and analyses,
should be prepared. It should included recommendations for the geotechnical aspects of
design and construction of the project. Generally the report includes references to:
Recommended design parameters for pile and/or footing foundations;
Recommended design and construction provisions for control of groundwater;
Recommendations for construction of slabs-on-grade, grade beams, and sub grades;
Recommendations for design and construction of excavation support system;
Recommendations backfill material and compaction;
Recommendations for surface drainage criteria;
Recommendations for concrete types;
Recommendations for parking areas and access roadways; and
Recommendations for roadway design and construction, including surfacing type
(granular, concrete, asphalt).
Services beyond those outlined above are sometimes required and may be provided by
the geotechnical engineer of record under terms mutually agreed upon between the
client and the geotechnical engineer of record. They include:
Environmental testing to evaluate possible presence of hazardous or toxic materials
in soils or groundwater or design of mitigative measures;
Installation and monitoring of groundwater observation piezometers or slope
inclinometers;
Attending construction progress meetings;
Estimates or reviews of quantities and construction costs;
On-site sewage-disposal system studies;
Routine monitoring of excavations required by occupational health & safety or other
regulatory agencies with jurisdiction;
Quality-control testing, including inspection and testing of engineered fill and backfill;
Preparation or review of contract documents;
Design and monitoring of ground modification improvement;
Permanent dewatering or sub-drainage studies;
57
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
58
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
APPENDIX F
POTENTIAL RESPONSIBILITY GAPS AND CONFLICTS
F-1 INTRODUCTION
This appendix is intended to identify situations where there is a risk that responsibility
may fall between disciplines, or where historically there has been controversy as to who
should be responsible for an item.
The examples noted in Section 2 below are guidelines. Situations may arise where
responsibility should be allocated differently from that described below. The common
aspect of all examples is that the coordinating registered professional or the registered
professional of record should ensure that the responsibilities are defined and
understood.
This appendix also contains “Cautionary Notes” in Section 3.
59
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
60
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
Design of attachments that attract load, e.g. snow guards, antennae, lifeline anchors,
window washing equipment;
Design of secondary structural elements that form part of the cladding system (girts,
studs) in some cases the structural engineer of record will take on this role as a
supplementary service. (In other cases, the coordinating registered professional will
delegate this work to a specialty professional.); and
Design of attachment of the cladding system to the structural frame. (The division
line for responsibility needs to be established for the specific project e.g. ledger
angles, their attachment to the face of the structure, elements embedded within the
structure.)
61
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
F-2.6.2 Responsibilities
The structural engineer of record’s drawings, specifications, and details should make it
clear to the specialty professional how the truss system and load-carrying systems
supporting the trusses are coordinated.
The structural engineer of record should:
Provide a building layout showing truss bearing points, girder truss locations and
bearing points, material specifications, special framing details, permanent bracing
details, and nailing and framing instructions;
(Temporary locations and bracing or erection sequence required to provide stability of
individual members during construction is the responsibility of the constructor). The
constructor should obtain from the manufacturer any special requirements regarding
erection sequence or temporary bracing for the specific project.
Provide point load values and locations;
Review load-carrying mechanism taking loads down to the foundations;
Provide loading diagrams, including built-up loads from snow drifts;
Outline stamping requirements of the truss drawings;
Check that the wood-truss design drawings match the site-specific requirements,
including the assumed location of supports and the site specific design loads: and
Review diaphragm and overall building bracing design for compatibility with truss
bracing.
62
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
has quality-control standards in place that will ensure the finished product meets the
designer’s intent.); and
Design wood trusses and certify that they are designed and manufactured to meet
their intended use.
63
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
APPENDIX G
LETTERS OF COMMITMENT, LETTERS OF COMPLIANCE, AND
SCHEDULES
G-1 APPLICABLE STANDATA
At the time of writing of this guideline, a Standata Director’s Interpretation was being
prepared regarding the use of Schedules A-1, A-2, B-1, B-2, C-1 and C-2 in the Alberta
Building Code. Users of this guideline should obtain a copy of the final version of this
director’s interpretation. It would not change the requirements of the Alberta Building
Code or the Safety Codes Act. However, the aim of the Standata would be to clarify the
intent of the schedules and it may mention amendments to the wording of the schedules
that would be acceptable to the director.
64
APEGGA March 2009
Responsibilities for Engineering Services for Building Projects
V1.2
record. It also would help to clarify what is expected of the specialty professional and
would help ensure that all areas of responsibility are covered.
For example, the coordinating registered professional and registered professionals of
record could ask the specialty professional to provide:
A “Letter of Commitment” addressed to the coordinating registered professional or
registered professional of record as appropriate, in a form similar to Schedule B-1 or
B-2, to acknowledge responsibility for design by the specialty professional. If
required by the coordinating registered professional or registered professional of
record, the letter should also confirm that the specialty professional is undertaking
responsibility for field review of the applicable aspects of the project.
A “Letter of Compliance”, addressed to the coordinating registered professional or
registered professional of record as appropriate, in a form similar to Schedule C-1 or
C-2, to confirm that the specialty professional has performed the necessary field
review and that the applicable aspects of the project substantially comply with the
specialty professional’s design. (This letter would only be required in cases where
the specialty professional is required to perform field review).
65