USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 1 of 27
No. 20-2039
IN THE UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
SIERRA CLUB, CENTER FOR BIOLOGICAL DIVERSITY, WEST VIRGINIA
RIVERS COALITION, WEST VIRGINIA HIGHLANDS CONSERVANCY,
INDIAN CREEK WATERSHED ASSOCIATION, APPALACHIAN VOICES,
and CHESAPEAKE CLIMATE ACTION NETWORK,
Petitioners
v.
UNITED STATES ARMY CORPS OF ENGINEERS; RYAN D. MCARTHY, in
his official capacity as Secretary of the U.S. Army; LIEUTENANT GENERAL
SCOTT A. SPELLMON, in his official capacity as U.S. Army Chief of Engineers
and Commanding General of the U.S. Army Corps of Engineers; MAJOR
GENERAL ROBERT F. WHITTLE JR., in his official capacity as Division
Commander of the U.S. Army Corps of Engineers, Great Lakes and Ohio River
Division; COLONEL JASON A. EVERS, in his official capacity as District
Commander of the U.S. Army Corps of Engineers, Huntington District, and
THERESA SPAGNA, in her official capacity as Chief, North Branch, U.S. Army
Corps of Engineers, Huntington District
Respondents
PETITIONERS’ MOTION FOR STAY PENDING REVIEW
DEREK O. TEANEY
APPALACHIAN MOUNTAIN ADVOCATES, INC.
Post Office Box 507
Lewisburg, West Virginia 24901
Telephone: (304) 646-1182
E-Mail: [email protected]
Counsel for Petitioners
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 2 of 27
INTRODUCTION
Here we go again. In 2018, this Court told Respondent United States Army
Corps of Engineers (the “Corps”) “an individual [Section 404] permit will likely be
necessary” for the Mountain Valley Pipeline (hereinafter, the “Pipeline”). Sierra
Club v. U.S.A.C.O.E., 909 F.3d 635, 655 (4th Cir. 2018). Nonetheless, on September
25, 2020, the Corps’ Huntington District once more unlawfully verified that
Mountain Valley Pipeline, LLC (“MVP”), is authorized to use the streamlined Clean
Water Act (“CWA”) permit known as Nationwide Permit (“NWP”) 12. Ex. 1
(hereinafter, the “Verification”). As explained below, that action is unlawful because
(1) the Corps failed to comply with the Endangered Species Act (“ESA”) when it
issued NWP 12 in 2017, and (2) the Corps’ effort to remove a permit condition this
Court determined MVP cannot satisfy was ineffective.
MVP intends to blast and trench through “critical” streams “as quickly as
possible before anything is challenged.”1 Moreover, MVP maintains that it does not
need the Federal Energy Regulatory Commission’s approval to perform activities
authorized under the verification. Ex. 2 at 2 n.8. Yet it requested permission from
1 Equitrans Midstream Corp. (ETRN) Q2 2020 Earnings Call Transcript (Aug. 4,
2020) (statement of Diana Charletta, President and C.O.O., Equitrans Midstream
Corp.), available at https://www.fool.com/earnings/call-
transcripts/2020/08/04/equitrans-midstream-corp-etrn-q2-2020-earnings-
cal.aspx.
—1—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 3 of 27
the Commission to resume construction activities—including stream crossing—by
September 25, 2020. Id. at 5. Such authorization could come at any minute and
without warning. MVP’s haste necessitates this stay motion. The Corps and MVP
oppose the motion.2
BACKGROUND
The Corps permits fill material discharges under CWA Section 404 in two
ways: through individual permits tailored to specific projects, or through general,
nationwide permits. 33 U.S.C. §1344(a), (e)(1). Many NWPs require would-be-
permittees to submit certain projects for “verification” using a pre-construction
notification (“PCN”).” 82 Fed. Reg. 1860, 1985 (Jan. 6, 2017).
An NWP’s term cannot exceed five years. 33 U.S.C. §1344(e)(2). In January
2017, the Corps reissued its suite of NWPs. See generally 82 Fed. Reg. 1860. One
of those permits, NWP 12, authorizes discharges related to utility lines, including
natural gas pipelines. Id. at 1985. For projects like the Pipeline that require approval
under the Rivers and Harbors Act, NWP 12 requires PCNs. Id. at 1986.
NWP 12’s 2017 reissuance triggered ESA Section 7. The Corps erroneously
maintains NWP 12’s reissuance complied with that provision because, in its view,
2 On September 25, 2020, Petitioners asked the Corps to stay the Verification
pending review. Ex. 3. The Corps refused. Ex. 4.
—2—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 4 of 27
the “reissuance of an NWP ... results in ‘no effect’ to listed species or critical
habitat[.]” Ex. 5 at 63-64.
NWP 12’s reissuance also triggered CWA Section 401, which prohibits
federal authorizations resulting in waterbody discharges without “certification” by
the affected state that the discharges will comply with water quality standards. States
can impose conditions through certifications, which become conditions of the
federal permit. 33 U.S.C. §1341(d). The West Virginia Department of
Environmental Protection (“WVDEP”) certified NWP 12’s reissuance under Section
401 in April 2017, subject to conditions to protect water quality. Those conditions
became conditions of NWP 12 itself under 33 U.S.C. §1341(d). Sierra Club, 909
F.3d at 650.
In 2017 and 2018, the Corps issued verifications to MVP, concluding the
Pipeline complied with NWP 12’s terms and conditions. Id. at 641. On October 2,
2018, this Court vacated the Huntington District’s verifications, Sierra Club v.
U.S.A.C.O.E., 905 F.3d 285 (4th Cir. 2018), holding that the conditions of West
Virginia’s Section 401 certification became conditions of NWP 12 by operation of
law, that MVP could not satisfy two of those conditions, and that the Corps’ efforts
to excuse that noncompliance were unlawful. Sierra Club, 909 F.3d at 645, 650-51,
654-55. The conditions MVP could not satisfy are Special Condition A, which
requires pipelines 36 inches or greater in diameter to possess an individual Section
—3—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 5 of 27
401 water quality certification, and Special Condition C, which requires stream
crossings to be completed within 72 hours. Id. at 640-41. 3 MVP still has no
individual Section 401 certification.
After this Court vacated MVP’s verification, WVDEP proposed to relax
Special Condition A of its 2017 water quality certification so that MVP might satisfy
it. Ex. 6.4 WVDEP’s proposed revision to Special Condition A would expand NWP
12’s applicability to include pipelines in West Virginia equal to or greater than 36
inches in diameter or that cross a Section 10 river, even if those pipelines lack
individual water quality certifications.5 On April 24, 2019, WVDEP asked the Corps
3 The four stream crossings that implicated Special Condition C were the Gauley,
Greenbrier, Elk, and Meadow Rivers crossings. Sierra Club, 909 F.3d at 642. As
Petitioners currently understand the Verification, it does not authorize open-
trench crossings of those rivers because MVP now intends to bore under three of
those rivers and has already tunneled under the fourth. Ex. 7 at 5, 7. As a result,
Special Condition C will not be discussed further in this motion.
4 Although WVDEP had proposed modifying its water quality certification’s
conditions at the time this Court decided Sierra Club, it subsequently issued a
revised proposal in January 2019. 909 F.3d at 648 n.2; Ex. 6.
5 Revised Special Condition A provides, in relevant part:
The Secretary of the West Virginia Department of Environmental
Protection, in the Secretary’s sole discretion, reserves the right to
require an individual water quality certification for any of the following
facilities or impacts:
i. Pipelines equal to or greater than 36 inches in diameter; [or]
ii. Pipelines crossing a Section 10 river ... [.]
—4—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 6 of 27
to “incorporate this modification into its NWPs for West Virginia, in accordance
with 40 C.F.R. §121.2(b)[.]” Ex. 8 at 1.
In two sets of comments submitted on June 27 and July 26, 2019, Petitioners
informed the Corps that approving WVDEP’s purported modification would be
unlawful. Exs. 10 & 11. Nonetheless, on January 15, 2020, the Division Engineer
for the Corps’ Great Lakes and Ohio River Division purported to grant WVDEP’s
modification request. Ex. 12 at 1. Thereafter, on September 25, 2020, the Corps’
Huntington District issued the Verification subject to this petition for review,
expressly relying on the Division Engineer’s unlawful modification of NWP 12’s
conditions. Ex. 7 at 26.
STANDARD OF REVIEW
Four factors govern a stay pending review:
(1) whether the stay applicant has made a strong showing that he is
likely to succeed on the merits; (2) whether the applicant will be
irreparably injured absent a stay; (3) whether issuance of the stay will
substantially injure the other parties interested in the proceeding; and
(4) where the public interest lies.
Hilton v. Braunskill, 481 U.S. 770, 776 (1987). In Natural Gas Act proceedings, this
Court applies the Administrative Procedure Act. Sierra Club, 909 F.3d at 643. Under
Ex. 8 at 10-11. In contrast, Special Condition A as originally incorporated into
NWP 12 provides, in relevant part, that “Individual Water Quality Certification
is required for ... [p]ipelines equal to or greater than 36 inches in diameter ...
[and] [p]ipelines crossing a Section 10 river ... .” Ex. 9 at 4 (emphasis added).
—5—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 7 of 27
that standard, the Court must set aside any agency action that is “arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C.
§706(2)(A).
ARGUMENT
I. Petitioners Are Likely To Succeed On The Merits.
Petitioners are likely to succeed on the merits for two reasons. First, the
Verification is unlawful because the Corps violated the ESA with its 2017 NWP 12
reissuance. N. Plains Res. Council v. U.S.A.C.O.E. (“N.P.R.C.”), ___ F.Supp.3d
___, 2020 WL 1875455 (D. Mont. 2020); appeal filed, No. 20-35412 (9th Cir.).6
Second, the Verification is unlawful because it relies on a legally defective attempt
to modify NWP 12’s conditions.
A. The Corps Violated the ESA With Its 2017 NWP 12 Reissuance.
In 2017, the Corps reissued NWP 12 without engaging in formal
programmatic consultation with the federal wildlife services (hereinafter, the
6 If Petitioners’ ESA arguments were to require a 60-day notice of intent (“NOI”)
under 16 U.S.C. §1540(g)(2)(A)(i), Petitioners would satisfy that requirement by
reliance on the July 1, 2019 NOI sent to the Corps by Petitioners Sierra Club and
Center for Biological Diversity. Ex. 13. That all of the Petitioners were not
signatories to the July 1, 2019 NOI is of no import because the notice requirement
is satisfied so long as one petitioner gives notice. Citizens for a Better Env’t-
Calif. v. Union Oil Co. of Calif., 861 F.Supp. 889, 913 (N.D. Cal. 1994); E.D.F.
v. Tidwell, 837 F.Supp. 1344, 1352-53 (E.D.N.C. 1992); S.C. Wildlife Fed’n v.
Alexander, 457 F.Supp. 118, 123-24 (D.S.C. 1978).
—6—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 8 of 27
“Services”)—on the NWP program generally or NWP 12 specifically—to consider
the cumulative impacts of NWP-authorized activities on protected species or their
critical habitat. That failure—which stands in contrast to the Corps’ 2007 and 2012
reissuances wherein it did conduct programmatic consultation with one of the
Services—violates the ESA, as the federal district court in Montana recently held.
N.P.R.C., 2020 WL 1875455. Indeed, because of that legal defect, the Montana
federal district court has declared NWP 12 unlawful and remanded it “to the Corps
for compliance with the ESA.” Id. at *8.7 Accordingly, the Verification is arbitrary,
capricious, an abuse of discretion, and otherwise not in accordance with law. See,
7 The Montana district court initially remanded NWP 12 to the Corps, vacated the
permit, and enjoined the Corps from authorizing any activities under it until
consultation was complete. N.P.R.C., 2020 WL 1875455, at *8. The Court
subsequently narrowed the scope of the vacatur and the injunction to oil and gas
pipelines, but left its remand order untouched. Northern Plains Res. Council v.
U.S.A.C.O.E., Civ. No. 19-44-GF-BMM, 2020 WL 3638125, at *14 (D. Mont.
May 11, 2020). The Ninth Circuit denied emergency motions for a partial stay of
the district court’s orders on May 28, 2020, holding that the Corps had not
“demonstrated a sufficient likelihood of success on the merits and probability of
irreparable harm to warrant a stay pending appeal.” Order, N. Plains Res. Council
v. U.S.A.C.O.E., No. 20-35412, Doc. 58 (9th Cir. May 28, 2020). The Supreme
Court ultimately narrowed the scope of the district court’s order to the Keystone
XL pipeline. Order in Pending Case, A.C.O.E. v. N. Plains Res. Council, No.
19A1053 (U.S. July 6, 2020). The district court’s declaratory judgment and
remand order were unaffected by the appellate orders.
—7—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 9 of 27
e.g., L.E.A.F. v. E.P.A., 118 F.3d 1467, 1473 (11th Cir. 1997) (reviewing substance
of prior agency action in later as-applied challenge).
Under ESA Section 7(a)(2), the Corps has a duty to ensure any action it
authorizes is not likely to jeopardize the continued existence of threatened or
endangered species, or result in the destruction or adverse modification of critical
habitat. 16 U.S.C. §1536(a)(2). The ESA’s implementing regulations define the
types of “action[s]” subject to this requirement to include “all activities or programs
of any kind authorized, funded, or carried out, in whole or in part, by Federal
agencies.” 50 C.F.R. §402.02 (emphasis added). Importantly, the Services have
concluded the Corps’ NWP program is a federal program subject to the
programmatic consultation requirement. 80 Fed. Reg. 26,832, 26,835 (May 11,
2015).
Federal agencies cannot take actions that “may affect” listed species without
first consulting with the Services under ESA Section 7(a)(2). 50 C.F.R. §402.14(a).
For broad federal programs—like the Corps’ nationwide permit program—action
agencies and the Services must engage in “programmatic consultation” to consider
the program’s cumulative impacts and to guide implementation by establishing
—8—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 10 of 27
criteria to avoid, minimize, or offset the program’s adverse effects on listed species
and critical habitat. See id. §§402.02, 402.14(i)(6); see also 80 Fed. Reg. at 26,837.
This is where the Corps violated the ESA in issuing NWP 12. N.P.R.C., 2020
WL 1875455, at *7-8. NWP 12’s reissuance was an action that “may affect” listed
species, and thus was subject to the programmatic consultation requirements. Id.;
see also 16 U.S.C. §1536(a)(2); 50 C.F.R. §§402.02 & 402.14(a); N.P.R.C., 2020
WL 1875455, at *4; N.W.F. v. Brownlee, 402 F.Supp.2d 1, 9-11 (D.D.C. 2005).
The NWP 12 decision document establishes conclusively that NWP 12 “may
affect” listed species and habitat. N.P.R.C., 2020 WL 1875455, at *4-5. In that
document, the Corps acknowledged
[s]essile or slow-moving animals in the path of discharges, equipment,
and building materials will be destroyed. Some aquatic animals may be
smothered by the placement of fill material .... Activities that alter the
riparian zone, especially floodplains, may adversely affect populations
of fish and other aquatic animals, by altering stream flow, flooding
patterns, and surface and groundwater hydrology.
*****
Activities authorized by this NWP will result in adverse effects to other
wildlife associated with aquatic ecosystems, such as resident and
transient mammals, birds, reptiles, and amphibians, through the
destruction of aquatic habitat, including breeding and nesting areas,
escape cover, travel corridors, and preferred food sources.
Ex. 5 at 76 (emphasis added).
“The ESA provides a low threshold for Section 7(a)(2) consultation[.]”
N.P.R.C., 2020 WL 1875455, at *5. Based on the foregoing, the Corps knew NWP
—9—
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 11 of 27
12 activities would certainly affect species of aquatic life and wildlife that depend
on the waters of the United States, including any of the 1,666 species listed as
endangered or threatened in the United States among them.8 N.P.R.C., 2020 WL
1875455, at *7. Indeed, the Corps has acknowledged that it conducts thousands of
project-specific Section 7 consultations each year on NWP-authorized activities. 82
Fed. Reg. at 1873-74. Accordingly, the record for NWP 12 by itself establishes the
permit “may affect” listed species and their critical habitat.
Despite its recognition of the devastating effects of NWP 12 activities on
aquatic species, the Corps nonetheless concluded NWP 12 would have “no effect”
on listed species and their habitat. Ex. 5 at 63-64. NOAA Fisheries—one of the
expert agencies charged by Congress with implementing the ESA—disagreed with
the Corps’ proposed 2017 “no effect” determination and recommended the Corps
initiate formal consultation on the 2017 NWPs. Ex. 14 at 4-5. NOAA Fisheries
concluded, “[w]ithout a large-scale examination of the aggregate effects of the
activities authorized by NWPs and the procedures established under the NWPs to
address potential effects to listed species and critical habitat, we do not believe that
8 U.S. Fish & Wildlife Serv., Listed Species Summary (Boxscore), available at
https://ecos.fws.gov/ecp0/reports/box-score-report.
— 10 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 12 of 27
the [Corps] can arrive at the conclusion that there is “no effect” from these NWPs
on ESA-listed species or designated habitat.” Id.
Against that backdrop, the Corps’ final “no effect” conclusion and its refusal
to engage in programmatic consultation is remarkable. Ex. 5 at 63-64. The Corps
relied on the NWPs’ General Condition 18 to justify its determination, which
requires would-be-permittees to determine whether their activities might affect listed
species and, if so, submit a PCN. Id. Based on that information, the Corps would
initiate project-specific consultation “as appropriate.” Id. at 64.
At least two federal courts have told the Corps its reliance on project-specific
consultation under the general condition is inadequate to fulfill the agency’s ESA
duties and programmatic consultation is required. N.P.R.C., 2020 WL 1875455, at
*6; Brownlee, 402 F.Supp.2d at 9-11 (“[O]verall consultation for the NWPs is
necessary to avoid piece-meal destruction of [species] habitat through failure to
make a cumulative analysis for the program as a whole.”). Project-specific
consultation cannot cure the failure to conduct programmatic consultation. 50 C.F.R.
§402.14(c)(4); see also Lane Cty. Audubon Soc’y v. Jamison, 958 F.2d 290, 294 (9th
Cir. 1992); Conner v. Burford, 848 F.2d 1441, 1453-58 (9th Cir. 1988). That is
particularly true with respect to the Corps’ NWPs because NOAA Fisheries
determined the NWP program was jeopardizing listed species in 2012. Ex. 15.
Project-specific consultation, therefore, cannot relieve the Corps of its duty to
— 11 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 13 of 27
consult on the NWPs’ issuance at the programmatic level, and cannot justify a “no
effects” determination for NWP 12.
The problem with relying on project-specific consultation is it ignores the
cumulative effects on listed species and critical habitat from the thousands of NWP
projects conducted each year. N.P.R.C., 2020 WL 1875455, at *7 (“Project level
review, by itself, cannot ensure that the discharges authorized by NWP 12 will not
jeopardize listed species or adversely modify critical habitat.”). Programmatic
consultation is the only way to ensure the piecemeal destruction of habitat from the
thousands of activities authorized by NWPs each year will not cumulatively
jeopardize listed species. For those reasons, NOAA Fisheries told the Corps in
response to its proposed 2017 “no effects” determination that “individual activity-
specific consultations ... cannot substitute for a broad-scale consultation on the
NWPs overall.” Ex. 14 at 33. The Corps’ “no effect” determination did not address
NOAA Fisheries’ comments. Ex. 5 at 63-64. Instead, the Corps chose to refuse
programmatic consultation until it was ordered to do so by the federal courts. Ex.
16.
If the Corps’ position were correct, there would never be any programmatic
consultations despite the Services’ regulations, since all programmatic consultations
also require project-specific review. The ESA regulations contemplate that
programmatic consultation will assess how the program will track impacts to prevent
— 12 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 14 of 27
jeopardy to listed species and their habitat, and that subsequent project-specific
consultation will authorize incidental take. 80 Fed. Reg. at 26,835-36. By skipping
programmatic consultation, the Corps short-circuits the regulatory program and
leaves the cumulative effect of thousands of NWP-authorized activities unassessed
in violation of 50 C.F.R §402.14(c)(4), which provides that consultation on
individual actions “does not relieve the Federal agency of the requirements for
considering the effects of the action or actions as a whole.”
The Corps’ reliance on General Condition 18 also unlawfully delegates the
Corps’ ESA duties to permittees. N.P.R.C., 2020 WL 1875455, at *7. The ESA
requires the Corps to determine “at the earliest possible time” whether its actions
“may affect listed species or critical habitat.” 50 C.F.R. §402.14(a). By relying on
project applicants to determine whether an activity might affect species or habitat,
“General Condition 18 turns the ESA’s initial effect determination over to non-
federal permittees, even though the Corps must make that initial determination.”
N.P.R.C., 202 WL 1875455, at *7. Such delegation is impermissible under the ESA.
Id.
In short, the Corps’ 2017 NWP 12 reissuance violated the ESA, and that defect
fatally infects the Verification. Accordingly, Petitioners is likely to succeed on the
merits.
— 13 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 15 of 27
B. The Verification Impermissibly Relies on Unlawful Modifications.
To bypass Sierra Club, the Corps attempted to change the rules of the game
by purporting to modify NWP 12’s Special Condition A. That modification was
unlawful for at least two reasons. First, the Division Engineer lacks the authority to
modify NWP 12. Second, the Division Engineer abused whatever discretion he may
have when he purported to modify NWP 12. Because the purported modification
was ultra vires, it was ineffective to change NWP 12’s conditions. U.S. v. Cortez,
930 F.3d 350, 357 (4th Cir. 2019) (“[B]ecause the power of administrative agencies
... is prescribed entirely by statute, any ‘improper’ agency action is ‘ultra vires[.]’”
(Emphasis original.)); U.S. v. Smithfield Foods, Inc., 191 F.3d 516, 526 (4th Cir.
1999) (holding ineffective a purported permit modification that was legally
defective). As a result, the Pipeline remains ineligible for NWP 12 because it cannot
satisfy the permit’s terms and conditions.9
1. The Division Engineer Lacks the Authority to Modify NWP
12’s Conditions.
The Division Engineer does not have the authority to incorporate the
purported modification to Special Condition A into the Corps’ 2017 NWPs. The
9 Specifically, because it lacks an individual Section 401 water quality certification
from the State of West Virginia, MVP cannot satisfy Special Condition A. Sierra
Club, 909 F.3d at 651-54.
— 14 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 16 of 27
chain of command is crucial within the Corps, and the purported modification
violates that chain of command.
The CWA authorizes the Secretary of the Army, acting through the Chief of
Engineers, to issue NWPs. 33 U.S.C. §§1344(d)-(e). The Chief Engineer has
delegated some—but not all—of his NWP authority to Division and District
Engineers. 33 C.F.R. §§330.1(d), 330.2(g), 330.4(e), 330.5.
The Division Engineer’s discretionary authority regarding NWPs is expressly
limited by §330.5(c) to modifying, suspending, or revoking “NWP authorizations.”
33 C.F.R. §330.5(c); see also id. §330.1(d); §330.2(g); §330.4(e). Authorizations are
distinct from the nationwide permits themselves. Sierra Club, 909 F.3d at 651. The
Corps’ regulations at 33 C.F.R. §330.2(c) provide, “Authorization means that
specific activities that qualify for an NWP may proceed, provided that the terms and
conditions of the NWP are met.” In briefing before this Court in Sierra Club, the
Corps conceded the discretionary authority discussed in 33 C.F.R. §330.5 “applies
to the ‘authorization,’ not to the broader Nationwide Permit.”10 In other words, the
Chief Engineer has delegated to the Division Engineer the authority to modify
authorizations only; the Division Engineer cannot modify the broader NWP’s terms
and conditions. Sierra Club, 909 F.3d at 650 (recognizing the discretionary authority
10 Br. for the Federal Respondents at 23, Sierra Club v. U.S.A.C.O.E., No. 18-
1173(L) (4th Cir.), cited in Sierra Club, 909 F.3d at 651.
— 15 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 17 of 27
described in 33 C.F.R. §330.5(c) and (d) “specifically refer[s] to the Corps’ ability
to modify ‘authorizations under an NWP’ (Section 330.1(d)) and ‘NWP
authorizations’ (Section 330.4(e))”).
That distinction is crucial because, here, by operation of CWA Section 401(d),
Special Condition A in WVDEP’s 2017 Certification became a condition of the
broader NWP 12, not a condition on authorizations. See 33 U.S.C. §1341(d)
(providing state water quality certification conditions “shall become a condition on
any Federal license or permit” (emphasis added)). This Court expressly held in
Sierra Club that “state conditions must be conditions of the NWP.” 909 F.3d at 645
(emphasis original).
Thus, only the Chief Engineer may modify the conditions of an existing NWP,
as opposed to an authorization, and only in compliance with the procedures in 33
C.F.R. §330.5(b). And, as this Court held in Sierra Club, Special Condition A is a
condition of the existing NWP 12. Accordingly, if the Corps wanted to grant
WVDEP’s request to modify Special Condition A, only the Chief Engineer could do
so and only by reissuing NWP 12 anew by invoking and implementing the
procedures set out in 33 C.F.R. §330.5(b) that require, inter alia, compliance with
the National Environmental Policy Act and the CWA Section 404(b)(1) guidelines.
33 C.F.R. §330.5(b)(2)-(3).
— 16 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 18 of 27
Petitioners told all this to the Division Engineer. Ex. 11 at 4-7. But the
Division Engineer purported to launder Special Condition A’s requirement of an
individual water quality certification from NWP 12 anyway. That action was
unlawful because it was taken “without observance of procedure required by law”
and without statutory or regulatory authority. 5 U.S.C. §706(2); Cortez, 930 F.3d at
357. That unlawful action in turn infects the Verification. See L.E.A.F., 118 F.3d at
1473.
2. The Division Engineer Cannot Relax Conditions.
Even if the Division Engineer had discretion to modify NWP 12’s Special
Condition A, his action here would abuse that discretion. That is because the Corps’
regulations—as interpreted by this Court in Sierra Club—unambiguously prohibit
the Division Engineer from replacing Special Condition A with WVDEP’s relaxed
conditions.
In Sierra Club, this Court construed the discretionary authority delegated to
Division and District Engineers to be a one-way ratchet, authorizing only
modifications that make an NWP more restrictive and prohibiting modifications that
would expand its applicability. 909 F.3d at 650-51. This Court expressly stated that
the regulations limit the Division and District Engineers “to providing additional
conditions, above and beyond those found in the NWP,” such that “revised”
— 17 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 19 of 27
conditions can only be more stringent than the original condition. Id. at 650-51
(emphasis original).
The express limits on the Corps’ discretionary authority imposed by 33 C.F.R.
§330.1(d)—limiting modifications to those that “further condition or restrict”—
conclusively demonstrate that “revised” conditions under 33 C.F.R. §330.4(e) can
only be more stringent than the original condition, never less so. Sierra Club, 909
F.3d at 651. And the Corps itself has explained that the Division Engineer’s
discretionary action “can not expand a nationwide permit.” 56 Fed. Reg. 59,110,
59,110 (Nov. 22, 1991).
As explained above, the purported modification to Special Condition A would
expand NWP 12’s applicability in West Virginia and make NWP 12 less restrictive.
Indeed, the Corps acknowledges as much when it cites the purported modification
as a basis for the Verification. Ex. 7 at 26. As a result, the purported modification is
not the type the Division Engineer is authorized to make under 33 C.F.R. §330.5(c)
because it would not “further condition or restrict” NWP 12, as required by 33 C.F.R.
§330.1(d) and as held by this Court in Sierra Club, 909 F.3d at 650-51. Accordingly,
the Division Engineer unlawfully accepted the modified Special Condition, and that
unlawful act was void ab initio.
— 18 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 20 of 27
II. Petitioners Will Suffer Irreparable Harm.
Absent a stay, MVP will complete its unlawful stream and river crossings
before resolution of this petition. MVP’s operator announced in early August 2020
that MVP intends to trench through “critical” streams “as quickly as possible before
anything is challenged.”11 And MVP predicts it will be fully in service in early 2021.
Ex. 17.
When it granted a stay the last time this controversy was before it, this Court
necessarily concluded MVP’s plans to trench and blast through the streams in its
path would cause irreparable environmental harm. Order, Sierra Club v.
U.S.A.C.O.E., No. 18-1173(L), Docket No. 58 (4th Cir. June 22, 2018). That remains
so today.
The Supreme Court holds environmental harms “by [their] very nature, can
seldom be adequately remedied by money damages and [are] often permanent or at
least of long duration, i.e., irreparable.” Amoco Prod. Co. v. Vill. Of Gambell, 480
U.S. 531, 545 (1987). The “dredging and filling of [waterbodies] that may occur
while [a c]ourt decides [a] case cannot be undone.” Sierra Club v. U.S.A.C.O.E., 399
11 Equitrans Midstream Corp. (ETRN) Q2 2020 Earnings Call Transcript (Aug. 4,
2020) (statement of Diana Charletta, President and C.O.O., Equitrans Midstream
Corp.), available at https://www.fool.com/earnings/call-
transcripts/2020/08/04/equitrans-midstream-corp-etrn-q2-2020-earnings-
cal.aspx.
— 19 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 21 of 27
F.Supp.2d 1335, 1348 (M.D. Fla. 2005). And the Pipeline construction’s lethal effect
on aquatic life “is, by definition, irreparable.” Humane Soc’y v. Gutierrez, 523 F.3d
990, 991 (9th Cir. 2008).
The Final Environmental Impact Statement for the Pipeline (“FEIS”)
identifies scores of stream-crossings in areas of shallow bedrock. Ex. 18 at
AR006323-437. Expert geologist Pamela Dodds predicts blasting is likely in all
areas “less than 10 feet to bedrock,” (Ex. 19 at AR021905-06), which would include
those stream crossings in shallow bedrock. Such blasting will cause irreparable harm
to the streams and the life within them because of its lethal effects on aquatic
organisms. Ex. 18 at AR005236.
One stream located in shallow bedrock—and therefore likely to be blasted—
is TTWV-S-108, or the Narrows of Hans Creek. Id. at AR006396. Petitioners’
members Herman and Paula Mann have recreated along and enjoyed the Narrows of
Hans Creek at the proposed crossing location throughout their lives. Ex. 20, ¶¶9-12;
Ex. 21, ¶¶13-19. In fact, Herman Mann used to own property on the Narrows of
Hans Creek near the proposed Pipeline crossing. Ex. 20, ¶9. He recalls seeing an
amazingly colorful fish in that stream in the 1960s, and he is now pretty sure what
he saw was a candy darter (id., ¶11)—an endangered species historically found in
the Indian Creek watershed. Ex. 22 at 35. Mr. Mann would like to see candy darters
— 20 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 22 of 27
in the Narrows of Hans Creek again, but fears pipeline construction will make that
impossible. Ex. 20, ¶11.
Mr. and Mrs. Mann also enjoy visiting Indian Creek—another stream that
MVP will blast through under the Verification. Id., ¶¶13-15; Ex. 21, ¶¶20-25. As
with the Narrows of Hans Creek, the Indian Creek crossing is in an area of shallow
bedrock and will, therefore, require blasting. Ex. 18 at AR006394; Ex. 19 at
AR021905-06. The Pipeline threatens the aquatic life in Indian Creek that Mrs.
Mann photographs, and would interfere with the reintroduction of endangered candy
darters to Indian Creek. Ex. 21, ¶¶22-25.
The Manns’ concerns about losing the opportunity to see candy darters in the
Narrows of Hans Creek and Indian Creek if MVP is permitted to blast its way
through those streams are well-founded. The candy darter was once found in the
Indian Creek watershed, but has been extirpated. Ex. 22 at 35. The Fish and Wildlife
Service, in its Species Status Assessment (SSA) Report for the Candy Darter,
predicted that the Pipeline would degrade the habitat of the streams that it crossed,
including those—like Indian Creek—“potentially suitable for future candy darter
reintroduction.” Id. at 39. Because “excessive sedimentation was a likely primary
cause of the historical decline of the candy darter,” the Mann’s enjoyment of the
species and its potential reintroduction to the Indian Creek watershed are threatened
with irreparable harm. Id.
— 21 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 23 of 27
Finally, Pipeline completion threatens the Manns with irreparable harm from
displacement. Ex. 20, ¶8; Ex. 21, ¶9. They will most likely move away from the farm
on which Ms. Mann has lived her entire life because of its proximity to the Pipeline
and the threats is poses to their lives and lifestyle. Ex. 20, ¶8; Ex. 21, ¶9. Such harm
is permanent and irreparable.
III. Preliminary Relief Will Not Substantially Harm the Corps or MVP.
Equitable relief would pose only minimal injury to the Corps. Although the
Corps has interests in defending its permits, “the effect of an injunction on these
interests seems rather inconsequential.” O.V.E.C. v. U.S.A.C.O.E., 528 F.Supp.2d
625, 632 (S.D.W.Va. 2007).
Moreover, MVP cannot object that a stay would cause it harm because, in the
equitable analysis, harms caused by parties’ failures to “avail[] themselves of
opportunities to avoid the injuries” are not cognizable. Di Biase v. SPX Corp., 872
F.3d 224, 235 (4th Cir. 2017). In Sierra Club, this Court informed MVP “an
individual permit will likely be necessary” for the Pipeline. 909 F.3d at 655.
Nevertheless, in the intervening two years MVP did not seek an individual permit.
Rather, it persisted in pursuing NWP 12 authorization, notwithstanding the legal
infirmities in the “fix” devised by the Corps and WVDEP. Having decided to risk
continuing on the NWP 12 path, MVP cannot now claim the Court should protect it
from the consequences of that choice.
— 22 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 24 of 27
Moreover, losing its NWP 12 verification will not cause substantial harm to
MVP because its operator has publicly stated that, “[i]f for some reason there is
another challenge ... with the Nationwide 12, then we can fall back to the options
that we talked about, I believe last time, which are some different crossing methods
and individual permit options.”12
IV. The Public Interest Favors Preliminary Relief.
The “public has an interest in the integrity of the waters of the United States
and in seeing that administrative agencies act within their statutory authorizations
and abide by their own regulations.” O.V.E.C. v. Bulen, 315 F.Supp.2d 821, 831
(S.D.W.Va. 2004). Ensuring Congressional mandates are carried out is always in the
public interest. See, e.g., Johnson v. U.S.D.A., 734 F.2d 774, 788 (11th Cir. 1984).
Finally, this Court necessarily concluded the public interest lies in a stay of the
Pipeline’s invalid NWP 12 authorization when it issued a stay the last time this
controversy was before it. Order, Sierra Club, No. 18-1173(L), Docket No. 58.
CONCLUSION
For the foregoing reasons, this Court should stay the Verification pending
review.
12 Equitrans Midstream Corp. (ETRN) Q2 2020 Earnings Call Transcript (Aug. 4,
2020) (statement of Diana Charletta, President and C.O.O., Equitrans Midstream
Corp.), available at https://www.fool.com/earnings/call-
transcripts/2020/08/04/equitrans-midstream-corp-etrn-q2-2020-earnings-
cal.aspx.
— 23 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 25 of 27
Dated: October 5, 2020 Respectfully submitted,
/s/ Derek O. Teaney
DEREK O. TEANEY
APPALACHIAN MOUNTAIN ADVOCATES, INC.
Post Office Box 507
Lewisburg, West Virginia 24901
Telephone: (304) 646-1182
E-Mail:
[email protected] Counsel for Petitioners
— 24 —
USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 26 of 27
CERTIFICATE OF COMPLIANCE WITH TYPE VOLUME LIMIT
This motion complies with the type-volume limits because, excluding the
parts of the document exempted by Federal Rule of Appellate Procedure 32(f) (cover
page, disclosure statement, table of contents, table of citations, statement regarding
oral argument, signature block, certificates of counsel, addendum, attachments), this
brief contains 5,198 words. This brief has been prepared in a proportionally spaced
typeface using Microsoft Word for Mac 2019 in Times New Roman, 14 point.
/s/ Derek O. Teaney
DEREK O. TEANEY
APPALACHIAN MOUNTAIN ADVOCATES, INC.
P.O. Box 507
Lewisburg, WV 24901
Telephone: (304) 646-1182
Email:
[email protected]USCA4 Appeal: 20-2039 Doc: 20-1 Filed: 10/05/2020 Pg: 27 of 27
CERTIFICATE OF SERVICE
I hereby certify that, on October 5, 2020, I electronically filed the foregoing
with the Clerk of the Court for the United States Court of Appeals for the Fourth
Circuit by using the appellate CM/ECF system. The participants in the case are
registered CM/ECF users and service will be accomplished by the appellate
CM/ECF system.
/s/ Derek O. Teaney
DEREK O. TEANEY
APPALACHIAN MOUNTAIN ADVOCATES, INC.
P.O. Box 507
Lewisburg, WV 24901
Telephone: (304) 646-1182
Email:
[email protected]