Cost Estimate for PT Natgas Indonesia

The document is a cost estimate form for 3D modeling of facilities, equipment, electrical systems, and pipelines at a natural gas facility in Indonesia. It provides estimated costs for piping modeling, civil works modeling, steel structure modeling, electrical modeling, and hydrant piping modeling. The total estimated cost is 8,230.50 Singapore dollars. The 3D models and reports will be submitted in Cardworx and Navisworx formats.

Uploaded by

MohamadSyahmi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
205 views1 page

Cost Estimate for PT Natgas Indonesia

The document is a cost estimate form for 3D modeling of facilities, equipment, electrical systems, and pipelines at a natural gas facility in Indonesia. It provides estimated costs for piping modeling, civil works modeling, steel structure modeling, electrical modeling, and hydrant piping modeling. The total estimated cost is 8,230.50 Singapore dollars. The 3D models and reports will be submitted in Cardworx and Navisworx formats.

Uploaded by

MohamadSyahmi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

COST ESTIMATE FORM

Prepared by Vetted by Approved by

Facility PT Natgas Indonesia Date : March 10, 2020 Mohamad Syahmi Ken Tan Simon Sim

Project : As-Built 3D Modelling - Facilities, Equipments, Electrical and Pipelines


Modelling Reference :

No Item Material Qty Unit Unit Amount Remarks


Price (IDR) SGD
MATERIAL COST

1 Piping Modelling
Create Piping Specification 32 Sheet P&ID IDR 470,000.00 $ 1,457.69
Create Piping Catalog and Accessories 32 Sheet P&ID IDR 390,000.00 $ 1,209.57
Route Piping 32 Sheet P&ID IDR 750,000.00 $ 2,326.10
Equipment Modelling 32 Sheet P&ID IDR 450,000.00 $ 1,395.66

2 Civil Modelling 1 Lump Sum IDR 5,000,000.00 $ 484.60

3 Steel Structure Modelling 1 Lump Sum IDR 5,000,000.00 $ 484.60

4 Electrical Modelling
Main cable Tray 1 Lump Sum IDR 3,000,000.00 $ 290.76
Panel Box 1 Lump Sum IDR 1,000,000.00 $ 96.92
Lighting Poles 1 Lump Sum IDR 1,000,000.00 $ 96.92

5 Hydrant Piping Modelling 1 Lump Sum IDR 4,000,000.00 $ 387.68


Sub-Total $ 8,230.50

Total Cost: $ 8,230.50

Remarks: Reports/3D Modelling to be summitted are Cardworx (Cardworx 2017) Model that can be edited, and viewer Navisworx