0% found this document useful (0 votes)
119 views21 pages

EDG Corrosion Protection SOW

This document defines the scope of work for corrosion protection repairs to be performed on the emergency diesel generators and diesel tanks at the Yemen LNG Balhaf site. The scope of work includes scaffolding, surface cleaning, masking, and painting works. The applicator will be responsible for providing all necessary labor, equipment, materials, and following COMPANY requirements and referenced specifications to complete the corrosion protection repairs in a professional manner to the satisfaction of the COMPANY.

Uploaded by

Nabil Ibrahim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
119 views21 pages

EDG Corrosion Protection SOW

This document defines the scope of work for corrosion protection repairs to be performed on the emergency diesel generators and diesel tanks at the Yemen LNG Balhaf site. The scope of work includes scaffolding, surface cleaning, masking, and painting works. The applicator will be responsible for providing all necessary labor, equipment, materials, and following COMPANY requirements and referenced specifications to complete the corrosion protection repairs in a professional manner to the satisfaction of the COMPANY.

Uploaded by

Nabil Ibrahim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Document number

Scope of Work YE-001-35-BMI-SOW-00001


EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 2 of 16

CONTENTS

1. SUBJECT: ....................................................................................................................................................... 3
2. DEFINITIONS AND ABBREVIATIONS .......................................................................................................... 3
2.1 DEFINITIONS.......................................................................................................................................... 3
2.2 ABBREVIATIONS ................................................................................................................................... 3
3. DETAILED SCOPE OF WORK....................................................................................................................... 3
3.1 GENERAL ............................................................................................................................................... 3
3.2 REFERENCE DOCUMENTS .................................................................................................................. 4
3.3 SCAFFOLDING....................................................................................................................................... 5
3.4 SURFACES CLEANING ......................................................................................................................... 5
3.5 MASKING............................................................................................... ERROR! BOOKMARK NOT DEFINED.
3.6 PAINTING WORKS ................................................................................................................................. 7
4. INTERFACES AND DOCUMENTATIONS.................................................................................................... 10
4.1 INTERFACES........................................................................................................................................ 10
4.2 DOCUMENTATIONS ............................................................................................................................ 10
5. APPLICATOR RESPONSIBILITIES ............................................................................................................. 11
5.1 GENERAL RESPONSABILITIES.......................................................................................................... 11
5.2 DURATION AND TIMING...................................................................................................................... 11
5.3 PROVISION OF EDG - CORROSION PROTECTION REPAIRS ......................................................... 11
5.4 PROVISON OF EQUIPMENTS............................................................................................................. 11
5.5 PROVISION OF PERSONNEL ............................................................................................................. 12

Appendix 1: EDG Drawing - General Arrangement


Appendix 2: OHGPI - DGO 12

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 3 of 16

1. SUBJECT:
The scope of this document is to define the EDG - CORROSION PROTECTION REPAIRS for:
Scaffolding
Surface cleaning
Masking and containment
Anti-corrosion treatment by application of protective painting and coating,

To be executed by APPLICATOR on the EMERGENCY DIESEL GENERATOR (EDG) 35-DG-0501 A, B, C and


D with the diesel tanks and there structures located at YLNG Balhaf site.
It shall be the sole responsibility of APPLICATOR to ensure that all operations are performed in accordance with
COMPANY requirements stated here in.
APPLICATOR shall evaluate the requirements of this document and referenced specifications and propose
detailed procedures, skilled personnel and fit-for-purpose equipment and consumables. Nothing in this document
shall relieve the APPLICATOR of his responsibility to execute the EDG - CORROSION PROTECTION REPAIRS
in professional manner and achieve desired results as per the requirements of this SOW and up to COMPANY
complete satisfaction.

2. DEFINITIONS AND ABBREVIATIONS


For the purpose of this document only, the following terms, abbreviations and definitions apply.

2.1 DEFINITIONS
COMPANY Yemen LNG Company Ltd
STAFF COMPANY direct employees and contracted personnel
SUPPLIER This term designates the firm that produces the painting materials
APPLICATOR This term designates the contractor involve in surface preparation an
coating/painting applied

2.2 ABBREVIATIONS
OPS Operations Department
PPE Personal Protective Equipment
YLNG Yemen LNG Company Ltd
ITP Inspection Test Plan

3. DETAILED SCOPE OF WORK

3.1 GENERAL
The APPLICATOR shall perform all related functions, activities and EDG - Corrosion Protection Repairs of each
and every kind of to timely and successfully accomplish the EDG - CORROSION PROTECTION REPAIRS,
including, but not limited to:
Scaffolding works
Provide needed consumable, materials and equipment for the performance of scaffolding erection in accordance
with the present Scope of Work and relevant reference documents listed here in,

Cleaning Works
Provide needed labour, consumable, materials and equipment for the performance of the Surfaces before
cleaning with high pressure water cleaning equipment in accordance with the present Scope Of Work and
relevant reference documents listed here in,

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 4 of 16

Masking works
Provide needed labour, consumable, materials and equipment for the performance of the Masking and
containment in accordance with the present Scope of Work and relevant reference documents listed here in.

Painting works
Provide needed labour, consumable, materials and equipment for the performance of the surface preparation,
painting application and quality control in accordance with the present Scope Of Work and relevant reference
documents listed here in,

APPLICATOR shall provide the equipment, all qualified personnel, skilled labour, transport, materials and tools
required to provide the SERVICE, including personnel clearances permits and licenses with respect to
immigration, customs, or other requirements by government or local authorities.
APPLICATOR shall perform the above listed EDG - CORROSION PROTECTION REPAIRS in strict
compliance with applicable COMPANY specifications, rules and standards. Failing written technical instruction in
COMPANY documentations, APPLICATOR shall be responsible to provide technical alternate solutions in
accordance with recognized international standards and to follow the best industry practice. Any alternate
technical proposal from APPLICATOR shall be submitted in writing to COMPANY which shall revert in writing
prior to any site implementation. APPLICATOR shall consider that the activities included in this document are not
intended to be exhaustive. Any activity not included in this document but necessary to complete the EDG -
CORROSION PROTECTION REPAIRS in a successful manner, in accordance with the requirements of this
CONTRACT, shall be deemed to be included in APPLICATOR's scope of work and APPLICATOR will carry out
everything that is necessary to timely and successfully complete the EDG - Corrosion Protection Repairs up to
the complete COMPANY satisfactions. Should some additional information be required to clarify the scope of
work, APPLICATOR shall request these clarifications in writing and will obtain such information from COMPANY.

3.2 SURFACES EVALUATION


The surfaces of the EDG 35-DG-0501 A, B, C and D, giving for information, are:
Carbone steel 600 x 4 = 2400 sqm
Hot deep galvanize 75 x 4 = 300 sqm

3.3 REFERENCE DOCUMENTS


These painting works shall be executed in strict compliance with requirements stated here in and with the
following COMPANY General Specifications and international reference documents listed in these General
Specifications:

Company Documents
- YE-001-00-BMI-PRC-13001 “Protective coating for equipments piping and structure”.
- YE-001-00-BMI-PRC-55040 “Use and Control of Scaffoldings”
- YE-002-00-MGT-PRC-31203 “Work Permit Procedure”
- YE-001-30-POC-JBS-13001 “Job Specification for Design-Painting”
- YE-001-00-BSA-PRC-30425 “Scaffoldings and Ladders“
- YE- 001-35- 358- LAY- 13001 “Erection General Arrangement drawing” (Appendix 1)
- YLNG Inspection Reports.

Group documents
- TOTAL GS EP COR 450 “External protection of structures and equipment by painting - maintenance
works”
- TOTAL GS EP COR 350 “External protection of off-shore and coastal structures and equipment by
painting”
- TOTAL GS EP ELE 079 “Electrical apparatus for potentially explosive atmosphere”
- TOTAL GS EP ELE 011 “Electrical equipment for package unit”
- TOTAL GS EP ELE 161 “Electrical cables”

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 5 of 16

APPLICATOR shall refer to COMPANY and Group documents listed above as well as to all International
standards, Codes, Rules and Professional documents taken as reference in these COMPANY General
Specifications.
Any derogation or deviation to the above listed COMPANY and Group documents as well as to all International
standards, Codes, Rules and Professional documents shall be submitted in writing and shall not be implemented
without written agreement from COMPANY.

3.4 SCAFFOLDING

DEFINITION OF WORK
APPLICATOR shall be responsible for the scaffolding works.

TECHNICAL CONTENT OF TENDER


Tenders shall include the following information:
Material technical data
Inspection test plan with acceptance criteria and frequency of inspection
A list of material and equipment to be used
The typical of reception form
Method statement for scaffolding works
Risk assessment for scaffolding works
Qualifications of scaffolders involved in scaffolding works
Certification of scaffolding supervisor involved in scaffolding works
• “Advance Scaffold Erection” course certification (less than 3 years).
• "Advance Scaffold Inspection" course. (Less than 3 years).

PREPARATION OF WORK
APPLICATOR shall identify and prepare the area where the scaffolding shall be erected, dismantled, and
material stored
Personnel shall wear the adequate PPE related to the EDG - CORROSION PROTECTION REPAIRS activities
they are intended for.

EXECUTION OF WORK
The scaffolding shall be erected in accordance with the COMPANY reference documents, keep a safe and good
access for all activities defined in this document included the modification and dismantling of equipments and
structures defined during the pre-job meeting and inspection, controls.

VERIFICATION AND CERTIFICATION


All scaffolding shall be verified and certified in accordance with the COMPANY reference documents and re-
verified all 7 days.

MATERIAL DELIVERY AND MAINTENANCE


APPLICATOR shall be providing the scaffolding material in accordance with the COMPANY reference
documents.
APPLICATOR shall provide the scaffolding material maintenance for keeping the material in good condition as
per COMPANY reference documents.

3.5 SURFACES CLEANING

DEFINITION OF WORK
APPLICATOR shall be responsible for the cleaning and HP washing before started the surfaces preparations.

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 6 of 16

TECHNICAL CONTENT OF TENDER


Tenders shall include the following information:
Product data sheets and MSDS (Material safety Data sheets)
Proposed qualification program if any
Inspection test plan with acceptance criteria and frequency of inspection
A list of consumables and equipment to be used
The typical of reception form
Method for the protection of equipment to be preserved against moisture/water contact
Qualifications of operators involved in cleaning works

PRODUCT DELIVERY AND STORAGE


Degreasing / de-oiling shall be such that it will not degrade the protective paints applied on the steels surfaces by
alkaline emulsion as VANABAN (Contact CORROBAN – 400 Bd Jules Durand – 76085 Le Havre Cedex -
France) or equivalent product capable of removing grease, oil, hydroxides and salts, without damaging paints
shall be used.

All aluminium alloys equipments shall be protected of the alkaline emulsion and cleaned by Acid cleaner as
ALUMINIUM 101 (Contact Elmer Wallace Ltd, 30 Nasmyth Rd. South, Colquhoun Park, Hillington Park, Glasgow
G52 4RE) or equivalent product.

COMPANY reserves the right to modify the degreasing / de-oiling product following testing of alternate supply, in
particular to enhance biodegradability and minimise environmental impact.
* All chemical products used on this works will be 90% biodegradable.

PREPARATION OF WORK
APPLICATOR shall identify and prepare the area where cleaning work will be executed taking into account of the
nature of the surface or equipment to be wash cleaned and the environment surrounding the surface to be
treated
Personnel shall wear the adequate PPE related to the EDG - CORROSION PROTECTION REPAIRS activities
they are intended for.

EXECUTION OF WORK
The cleaning sequence shall consist of the application of a proper degreasing / de-oiling agent followed by the
washing of the surface with clean fresh water through High Pressure (HP) equipment (150 barg maximum).

All surface must be cleaned before started the painting application.

TESTS AND INSPECTIONS


Inspection and tests frequency shall be clearly indicated in an Inspection and Test Plan (ITP).
A visual inspection of the cleaned surface shall be done on 100% of the treated surface.

WORK ACCEPTANCE
Before provisional acceptance, COMPANY shall check that all the inspections set out above have been carried
out and that all the results are satisfactory.

3.6 MASKING AND CONTAINMENT


APPLICATOR shall be responsible for the masking and containment of all instrumentation, electrical equipments
will be protected.

EXECUTION OF WORK
All instrumentation, electrical equipments shall be protected by polyester cloth 600 deniers minimum against the
abrasive projections and plastic film against projections of paints and corrosive products.

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 7 of 16

WORK ACCEPTANCE
Before starting the cleaning and surface preparation, APPLICATOR shall check the protection of all
instrumentation, electrical equipments, and COMPANY shall check that all the inspections set out above have
been carried out and that all the results are satisfactory.

3.7 PAINTING WORKS

DEFINITION OF WORK
APPLICATOR shall be responsible for the execution of the painting works on the EMERGENCY GENERATOR
(EDG) 35-DG-0501 A, B, C and D without the diesel tanks and there structures located at YLNG Balhaf site.

The containers and paint structures shall be paint on site, and the sensitive material and hot dip galvanized
structures dismantled and painted in the YLNG painting yard.
This shall include both paint touch-up on localized coating defects as well as larger surface defect repairs which
may require full paint refurbishment to ensure adequate corrosion protection of the surfaces.

TECHNICAL CONTENT OF TENDER


Tenders shall include the following information:
− Proposed paint systems for each category/location of item to be painted
− Product data sheets and MSDS (Material safety Data sheets)
− Proposed qualification program if any
− List of derogations to the applicable COMPANY General Specification, if any. Derogations will not be
granted for painting systems after Contract award.

TERMS AND CONDITIONS OF GUARANTEES


A statement showing that all parties involved (SUPPLIER and APPLICATOR) will be carrying out the work
according to the present CONTRACT, or if relevant, to the project particular specification, including derogations
duly agreed by COMPANY before contract award. This statement shall also show that the guarantee is jointly
underwritten by all parties and specify the durations and performance levels of the guarantee. This statement can
consist in a certificate of homologation by OHGPI (Organisme d’Homologation des Garanties en Peinture
Industrielles), Appendix 2, or a letter signed by the head office of each party involved
Maximum thickness tolerable for each coat and for the each full painting system
Surface preparation and painting procedures, including confinement and used abrasive recovery methods, and
waste disposal options. A surface preparation procedure shall be prepared for each surface preparation
technique proposed.
Inspection test plans with acceptance criteria and frequency of inspection
A list of inspection and painting equipment to be used
The list of Coating log reports used for daily work reporting
Colours to be used for each item of equipment and for the different coats, in accordance with the colour chart
chosen for the project by COMPANY
Methods of protection of items to be painted against adverse weather conditions
Methods of protection of sensitive equipment
Method of confinement of the working area, when necessary
Certificates of painting operators and inspectors (FROSIO, NACE International minimum level 3 - peer review,
etc.).

PREPARATION OF WORK
APPLICATOR shall identify and prepare the area where paint work will be executed taking into account of the
nature of the equipment to be painted, the environment surrounding the surface to be treated, and the technique
that will be selected for surface preparation and paint application.
Prior to commencement of EDG - CORROSION PROTECTION REPAIRS, APPLICATOR shall ascertain that all
necessary protection and confinement of the area to be treated are in place and secured. All sensible equipment

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 8 of 16

that may suffer from painting activities shall be adequately protected. All identification of the working area shall
be in place. All necessary equipment shall be available at the working place.
Any paint work other than localised paint-touch-up and covering extended surface reparation shall be subject to a
Kick-Off meeting during which all the procedures to be implemented until completion of work and demobilization
from the area shall be documented by the APPLICATOR. The COMPANY technical representative shall be
informed in due time in order to attempt this meeting.
APPLICATOR shall make provision for the paint Supplier technical assistance that may be found necessary for
any WORK covered by this CONTRACT.
Personnel shall wear the adequate PPE related to the paint activity they are intended for.

EQUIPMENTS, TOOLS AND CONSUMABLES


APPLICATOR shall be provide all necessary equipments, tools and consumables that may be found necessary
for EDG - CORROSION PROTECTION REPAIRS covered by this CONTRACT.
The equipments and shall be conform as per YLNG rules and specifications.
COMPANY reserve the right to reject any equipment, tools and consumables delivered by APPLICATOR in case
optimal safety conditions are not conform with YLNG rules and specifications.

PAINT PRODUCT DELIVERY AND STORAGE


Reference shall be made to applicable General Specifications. COMPANY reserve the right to reject any paint
product delivered by APPLICATOR in case optimal storage condition would not be respected.
Abrasive:
Abrasive shall be of mineral type, Grit shape, free from contaminant such as ferrous pollutant and shall be
chlorine/chloride free. Proposed abrasive to complete the WORK shall received COMPANY written approval
before use.
Abrasives shall be delivered in watertight packaging (1.5 T big bags) and stored protected from the weather.
COMPANY reserves the right to reject any product found with defective packing or improperly stored.
Conductivity of abrasives shall be less than 150.10-6 SIEMENS/cm as per ASTM D 4940 and salt contamination
of the surface shall be less than 30 mg/m² (ISO 8503-6 & 9).

SURFACE PREPARATION
Surface preparation method by abrasive projection is the unique method able to achieved a satisfactory level of
surface preparation and as such, shall be considered as the principal mean to perform surface preparation during
Maintenance Painting and Touch-up painting Works.
APPLICATOR shall be responsible to select and use the most adapted abrasive blasting equipment for the
intended work according to extend of surface to be treated, accessibility and considering the requested level of
surface preparation quality.
For minor spot repairs, Vacuum Blasting technique must be privileged. Conventional blasting technique must be
privileged only for extended surface repair and shall be subject to a proper area confinement which shall
limit/avoid spread of dust and abrasive to the surrounding.
In area of limited access and localized repair, Sand blasting Gun equipment can be used like the Clemco Power
Gun, suction blast tool designed for dry abrasive blasting or equivalent equipment.
Power tool cleaning can be permitted on area where any alternate abrasive blast cleaning method can not be
implemented in a safe and adequate manner. In that case, only the grade of cleanliness St 3 will be accepted.
Power tool method providing pseudo-roughness such Rodcraft MBX or grinding discs must be privileged.
Manual mechanical cleaning will be only exceptionally accepted where accessibility and configuration of the
surface to be treated leave no alternative.
Grade of cleanliness: The Grade of cleanliness to be achieved for each system is given in each paint system
referenced in applicable COMPANY General Specification.
Roughness: The roughness Ra will be measured with roughness meter (ISO 8503-4) with an adapted cut-off.
The measured Ra value shall be between 10 to 13 µm. The roughness may also be compared with Viso-tactile
comparator (ISO 8503-1). The grade of roughness to be achieved for each system is given in each paint system
referenced in applicable Reference Documents.
Surface contamination: types of contamination are defined with International Standards: dust, soluble salt, oil and
grease, etc. Removal of surface contamination prior to, during and after surface preparation shall be performed

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 9 of 16

systematically with the adapted means and methods given in International Standards, to the satisfactory levels
requested in COMPANY General Specifications. A particular effort must be given to dust and soluble salt
contamination removal. Vacuum cleaning and air blowing are the recommended techniques for dust removal.
Surface preparation shall not commence when climatic conditions are not satisfied or susceptible be become
unsatisfactory during the EDG - CORROSION PROTECTION REPAIRS.
A thorough degreasing and de-oiling using a degreasing agent followed by an abundant fresh water rinsing shall
be performed prior to any surface preparation work. HP washing shall be used with fresh water provided by the
plant.
Any prepared surface to the satisfactory level of quality shall be painted before the degradation of the surface
cleanliness as specified in the paint system data sheet. In any case all prepared surfaces shall be painted within
the same day or prior any change of climatic conditions.

PAINT APPLICATION CONDITIONS


Reference shall be made to applicable Reference documents.
All surfaces shall be degreased, cleaned and dried before paint application. The final coat shall be conforming to
the colour coding scheme in place to YLNG Balhaf site.
All successive coats shall be recorded for DFT and reported in the Daily Log. Each coat shall be of different
colour and the topcoat, conform the colour code of YLNG Balhaf site, shall be sufficiently opaque to cover the
previous coat.
Particular case of bolting: all visible surfaces of a bolted assembly shall be painted with the same system as the
surrounding surfaces.
When painting activity required removal of existing marking, the original marking shall be adequately identified
and new identification shall be provided after paint work is fully cured. This can be achieved with labels made
available by YLNG Balhaf site.
Any coating defect (bubble, orange peel, blister, etc) as covered by ISO 4628 found shall be adequately repaired
to the requested level of quality. Repair by full surface preparation to white metal on major defect or partially
removal and application of successive coat for minor repair shall be performed in that case. Repair, if any shall
also be reported in coating daily log.

TESTS AND INSPECTIONS


All inspections and tests as listed in GS EP COR 450 are applicable and shall be reported.
Inspection and tests frequency shall be clearly indicated in an Inspection and Test Plan (ITP).
All inspections and tests shall be reported in the daily coating report. In addition to the routine inspection and
tests, APPLICATOR shall provide an effective and efficient External QA/QC control by a certified Inspector who
will regularly perform QA/QC inspection to YLNG Balhaf site. Daily logs of all works performed by painting team
shall be duly signed by the APPLICATOR QA/QC Inspector during his routine visits.

WORK ACCEPTANCE AND GUARANTEE


Before provisional acceptance, COMPANY shall check that all the inspections set out above have been carried
out and that all the results are satisfactory.
The EDG - CORROSION PROTECTION REPAIRS shall be covered by a specific guarantee given by
APPLICATOR to complete Guarantees and warranties defined in the CONTRACT. APPLICATOR shall
guarantee that the EDG - CORROSION PROTECTION REPAIRS shall be covered by performance warranties in
accordance with the following requirements:
The maximum degree of rust shall be Ri2 according to ISO 4628.
The maximum degree of cracking, blistering, or flaking shall be 3S3 according to ISO 4628.
Guarantee shall be provided for duration as defined for each paint system defined in applicable COMPANY
General Specifications.
Beginning of Warranty Period as defined for each paint system starts from the effective date of the
PROVISIONAL ACCEPTANCE CERTIFICATE (this can be through dedicated Acceptance certificate or by the
daily coating report signed by the APPLICATOR QA/QC inspector and COMPANY representative).
A site Inspection visit will be conducted by the COMPANY representative at least at the end of the warranty
period of each system. APPLICATOR shall repair at his own cost any discrepancy and damaged parts found
during this inspection and imputable to APPLICATOR activities at the time of the application.

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 10 of 16

TESTS AND INSPECTIONS


Inspection and tests frequency shall be clearly indicated in an Inspection and Test Plan (ITP).
A visual inspection of the cleaned surface shall be done on 100% of the treated surface.

WORK ACCEPTANCE
Before provisional acceptance, COMPANY shall check that all the inspections set out above have been carried
out and that all the results are satisfactory.
4. INTERFACES AND DOCUMENTATIONS

4.1 INTERFACES
APPLICATOR shall undertake all necessary project management including, quality assurance/control, safety
management, procurement management (if any), reporting, interfaces with COMPANY and other APPLICATORs'
of COMPANY as necessary to ensure the proper performance and completion of the works to the quality,
standard and programme stipulated in this CONTRACT, as well as for obtaining permits, licences, authorisations,
as necessary to ensure the proper performance and completion of the works to the quality, standard and
program stipulated in this CONTRACT.
APPLICATOR shall assume, as a minimum that COMPANY will require progress and interface meetings with
APPLICATOR. COMPANY reserves the right to call APPLICATOR for meeting at any time to update itself on the
progress or any matter relating to the EDG - CORROSION PROTECTION REPAIRS. APPLICATOR is advised
that COMPANY shall be permitted to attend appropriate parts of the meetings.
APPLICATOR will also provide technical assistance and back up support to COMPANY, if and when required. In
particular, APPLICATOR will be required to assist COMPANY in getting the best solution for the EDG -
CORROSION PROTECTION REPAIRS required under the CONTRACT.
APPLICATOR shall address and ensure compliance to all statutory requirements, regulatory standards,
reference documents, in addition to the requirements of the EDG - CORROSION PROTECTION REPAIRS.

4.2 DOCUMENTATIONS
APPLICATOR shall be responsible to prepare all the necessary procedures and reports necessary for the
execution of the work. This will include but not limited to the following:
- Quality Control Plan (ITP),
- HSE Risk Assessments,
- Qualification of personnel,
- Daily Report,
- Coating log reports,
- Completion file.

Documents to be submitted to COMPANY at the tender phase are listed in the relevant sections describing each
work to be performed.

The Daily Report shall contain the summary of the main tasks performed, activities for the following day, number
of personnel, number of equipment and other information that may be requested by COMPANY. The format of
the daily report shall be proposed by APPLICATOR to COMPANY for approval prior commencement of the work.
The coating log report shall be issued for each job and shall contain all relevant quality control points. Format of
this report, conform to the typical FROSIO or NACE requirement, shall be submitted at the bid stage for approval.
The Completion File shall be submitted within three weeks after completion of the EDG - CORROSION
PROTECTION REPAIRS for COMPANY approval. Any other requirement included in this scope of work and in
the documentation included in the documents referenced in this CONTRACT. All the documents to be produced
before the commencement of CONTRACT shall be subject to review and approval of COMPANY. APPLICATOR
will also submit an electronic copy of the various documents to COMPANY in a format to be mutually agreed.
APPLICATOR shall provide all the relevant documentation according to ISO 9001.

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 11 of 16

5. APPLICATOR RESPONSIBILITIES

5.1 GENERAL RESPONSABILITIES


APPLICATOR shall be responsible for his equipment and personnel and shall abide by regulations and laws,
local and national, in force or may come into force during the execution of the EDG - CORROSION
PROTECTION REPAIRS.
APPLICATOR shall be responsible to gather any information with respect to site condition, necessary for the
assessment of the erection and operability of the equipment. APPLICATOR shall be responsible for any co-
ordination with COMPANY QA/QC and Plant inspectors and other APPLICATORS working in the area, employed
directly or indirectly by COMPANY in order to ensure execution of the work in a smooth, safe and timely manner.
APPLICATOR shall re-perform the EDG - CORROSION PROTECTION REPAIRS (or part of the EDG -
CORROSION PROTECTION REPAIRS), with no application of daily rate, as specified by COMPANY, in case
said EDG - CORROSION PROTECTION REPAIRS were performed unsatisfactory in relation to the applicable
procedures and specifications.

5.2 DURATION AND TIMING


The APPLICATOR will have to make the EDG - CORROSION PROTECTION REPAIRS for the deadline and
following conditions:
• The maximum duration allowed by EDG is 15 days including installation and transfer material in site.
• The mobilization, works preparation, scaffolding works, cleaning works must be done during night shift.
• The painting works shall be done one EDG by one EDG and the scaffolding shall be erected on the EDG
C during the painting works of the A and following for B and D.

5.3 PROVISION OF EDG - CORROSION PROTECTION REPAIRS


The EDG - CORROSION PROTECTION REPAIRS shall include but not be limited to:
Mobilisation and erection of appropriate equipment and spread and supply/storage of required material and
consumable, spares required for executing the works in a satisfactory manner complying with the scope of work
and accepted industry practice and to COMPANY's satisfaction.
The compilation of the relevant reports of the works carried out.
Co-ordination with COMPANY and other APPLICATORs working on the YLNG BALHAF PLANT concerned as
may be necessary for the completion of the EDG - CORROSION PROTECTION REPAIRS in a timely manner.
Removal of the extra material, consumable etc. brought at site by APPLICATOR, dismantling of any structure
(temporary or permanent) erected by APPLICATOR at the site and its removal from the site. Restoration of the
site to its original condition. Any scrap etc.., if to be discarded, shall be dumped only in COMPANY approved
place.
All the necessary procurement and transportation to execute the EDG - CORROSION PROTECTION REPAIRS.

5.4 PROVISON OF EQUIPMENTS

TOOLS AND EQUIPMENTS


APPLICATOR shall provide its PERSONNEL with all TOOLS and EQUIPMENTS necessary for the
accomplishment of EDG - CORROSION PROTECTION REPAIRS. It shall be APPLICATOR responsibility to
identify and provide all the items, which are deemed necessary to perform the works object of this CONTRACT.
TOOLS and EQUIPMENTS shall fulfil the requirements set in this document and in the documents referenced.
APPLICATOR shall provide any other TOOLS and EQIPMENTS necessary for the accomplishment of the EDG -
CORROSION PROTECTION REPAIRS.
APPLICATOR shall provide and make permanently available on YLNG BALHAF PLANT all necessary spare
parts and consumable necessary for the proper maintenance of the equipment and tools necessary for the
accomplishment of EDG - CORROSION PROTECTION REPAIRS.
APPLICATOR is responsible for the storage, control and supply of TOOLS and EQUIPMENTS and shall not
claim any stand-by cost for reason of missing TOOLS and EQUIPMENTS or that are unsuitable, improperly
maintained, with missing spare or damaged, or both.

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 12 of 16

Any electrical TOOL or EQUIPMENT necessary for the accomplishment of the EDG - CORROSION
PROTECTION REPAIRS on YLNG BALHAF PLANT shall comply with the GROUP General Specification GS EP
ELE 079 “Electrical apparatus for potentially explosive atmosphere”, ATEX Zone 2 certified and GS EP ELE 011
“Electrical equipment for package unit”.
Electrical cables shall comply with GROUP General Specification GS EP ELE 161 “Electrical cables”.
When power supply is needed, COMPANY will provide this power supply. APPLICATOR is responsible to define
his need and ascertain that equipment characteristics are compatible with the power supply sources available on
the YLNG BALHAF PLANT.
APPLICATOR shall provide all inspection tools and equipment necessary for a complete QA/QC inspection.
Equipment and tools for the performance of the whole inspection and tests as listed in COMPANY General
Specifications listed in this CONTRACT shall be made available by APPLICATOR.

TRANSPORTATION AND STORAGE


APPLICATOR shall provide all necessary equipment, tools and consumables in closed containers and shall
inform COMPANY about number of containers that APPLICATOR shall provide; in the Kick off meeting YLNG
BALHAF PLANT Management will explain rules for APPLICATOR storage.

INSPECTIONS
COMPANY and any regulatory authority, may inspect, test and audit APPLICATOR'S equipments, where
appropriate. COMPANY and the regulatory authorities shall be granted all co-operation and assistance by
APPLICATOR to ensure that all inspections, tests and audits can be executed in a complete and efficient
manner.

INSTRUMENTS CALIBRATION
Instruments provided by APPLICATOR shall be in good operating condition and be calibrated fully capable of
performing the work. All copies of calibration certificates shall be submitted to COMPANY for review and
approval before starting EDG - CORROSION PROTECTION REPAIRS. It shall be APPLICATOR responsibility
to integrate the equipment with all the items, which are deemed necessary to perform the works object of this
project.

5.5 PROVISION OF PERSONNEL


APPLICATOR shall provide personnel with experience and expertise to perform all required activities as per
Company Specification and applicable International Standards and Codes.
The maximum of persons who can work on this EDG - CORROSION PROTECTION REPAIRS is 20
including one or several superintendent (s) and the QA / QC inspector.

The standard manning for EDG - CORROSION PROTECTION REPAIRS team is defined as follows:

SUPERVISOR
The SUPERVISOR is responsible of the global supervision of EDG - CORROSION PROTECTION REPAIRS
TEAM, and routine quality control of the performance of the EDG - CORROSION PROTECTION REPAIRS. In
addition to the operational execution of the EDG - CORROSION PROTECTION REPAIRS, the Foreman is
responsible for the administrative activities, such as work permit, validation of scaffolding, timesheets, reporting,
etc…The SUPERVISOR is also in charge of the respect of the HSE aspects related to the performance of the
EDG - CORROSION PROTECTION REPAIRS and related to the working environment on YLNG BALHAF
PLANT.
English speaking. Mandatory individually certified to paint inspector level by an approved organization (FROSIO
level 3, NACE International minimum level 3 - peer review, etc.).
SCAFFOLDING FOREMAN
The SCAFFOLDING FOREMAN is responsible to assist the SUPERVISOR in his SCAFFOLDING activities. He
is able to supervise a team of 4 to 6 skilled workers.

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 13 of 16

English speaking. Individually “Advance Scaffold Erection” course certification (less than 3 years) and "Advance
Scaffold Inspection" course (less than 3 years) certified minimum or equivalent from an international recognized
organisation.
SKILLED WORKERS – SCAFFOLDERS
Skilled Workers – Scaffolders are in charge of scaffolding erection and dismantling and are supervised by
Foreman.
Mandatory individually attested by the APPLICATOR after international recognized organisation course
(Conform, Setho; etc.).
PAINTING FOREMAN
The PAINTING FOREMAN is responsible to assist the SUPERVISOR in his PAINTING (cleaning, masking,
surfaces preparation and painting) activities. He is able to supervise a team of 4 to 6 skilled workers.
English speaking. Individually ACQPA Operator Level 2 certified minimum or equivalent from an international
recognized organisation.
SKILLED WORKERS – PAINTERS
Skilled Workers – Painters are in charge of the cleaning, masking, surfaces preparation and painting works to be
performed and are supervised by Foreman.
Mandatory, individually ACQPA Operator level 1 certified minimum (surface preparation and paint application) or
equivalent from an international recognized organisation.
QA/QC INSPECTOR
QA/QC Inspector will be in charge of the technical support and external quality control of the activities performed
by the team. QA/QC Inspector shall be involved in main technical decisions such as appropriate method of
surface preparation selection, application procedure, etc.
QA/QC Inspector shall be responsible to control the work performed from the last visit and countersign daily log /
completion report prior to submission to COMPANY representative.
English speaking. Mandatory individually certified to paint inspector level by an approved organization (FROSIO
level 3, NACE International minimum level 3 - peer review, etc.).

QUALIFICATION / CERTIFICATION OF PERSONNEL


APPLICATOR shall provide a comprehensive list of qualifications for all its PERSONNEL who could be assigned
to the EDG - CORROSION PROTECTION REPAIRS which shall be in strict compliance with the levels of
qualifications and certifications stated in the Applicable Reference documents and in the present CONTRACT.
This shall include evidence of all training given by APPLICATOR and others. The standard manning by YLNG
BALHAF PLANT as per table above shall be multi-skilled and qualified for the following trades: cleaning, painting
and scaffolding. Additional PERSONNEL must be properly qualified for their respective duties.
APPLICATOR shall provide COMPANY with its internal procedure regarding qualification and certification of
staff, qualification and certification for painters, and training and requirements for scaffolding). The procedure
shall be in line with Reference documents.

Cv SUBMITTAL AND APPROVAL OF PERSONNEL


All APPLICATOR personnel CV shall be submitted to COMPANY for approval.
APPLICATOR QA/QC Inspector shall schedule his visits based on a day trip every week. However according to
the ongoing painting activities and/or upon request of COMPANY, the frequency of visit and/or presence in YLNG
BALHAF PLANT may be increased.

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 14 of 16

PERFORMANCE
COMPANY reserves the right to reject any APPLICATOR personnel whose level of qualification and/or
performance is considered unsatisfactory. APPLICATOR shall promptly substitute the personnel refused by
COMPANY without any cost to COMPANY.
COMPANY reserves the right to reject any APPLICATOR tools or equipments whose level of performance,
suitability for the intended EDG - CORROSION PROTECTION REPAIRS and weather conditions or status is
considered unsatisfactory. APPLICATOR shall promptly substitute the personnel refused by COMPANY without
any cost to COMPANY.

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 15 of 16

APPENDIX 1: EDG GENERAL ARRANGMENT

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
SECTION B-B
Sun shade
Supplied by Contractor I : I
1

00
CN
/ Container 45' co
20V4000G61 o
•«-
37-DG|-0501A r
in
o

C
3800 2442 13716

Sun shade SCALE BAR


Supplied by Contractor SECTION A-A 0 2.5m 5m
y

o Vf,
ass. o
to
CM

355 D
•3S
too

?&' 1 London Operating Centre


ftftt I
2" NPS Manually operated
quick closing valve CONTRACTOR REVIEW AND COMMENTS SHALL NOT BE ASSUMED TO INDICATE
Symmetric coupling with cap EITHER RESPONSIBILITY DR LIABILITY FDR ACCURACY AND COMPLETENESS OF
THIS DOCUMENT OR TD ALTER ANY CONTRACTUAL TERMS AND CONDITIONS
U-section 4OxBOHt
i support with pipe CONTRACTOR DISPOSITION
o
o CO clamp LJ
RSB CDDE I D REJECTED (Revise I, resubntt)
in
(§§> Detail D Detail F I
•35 Scale : 1:25 Scale : 1:2O CODE 2 D COMMENTS AS NOTED '^c^nentTor^lnco
55- CODE 3 (T NO COMMENTS (No connerrts final issue)
£t
£
-a
SIGN41UBC > DATE
5
Outlet fuel genset: 2" NPS ANSI 150lb RF flange a>
o 1 Inlet fuel flenset: 2" NPS ANSI 1 SOIb RF flange o
in
CN oo
.
I (Print None)

CN
t

Fuel line single-skinned 00 Detail C


Scalet:20
Genset inlet: 2" NFS
O
Genset outlet: 2" NPS
Not supply SDMO CN
CN
Genset fuel return: 2" NPS ANSI single-skinned
C oo Genset fuel suction: 2" NPS ANSI single-skinned 00 20/06/07 IFC Modified / RTS-1916 FB YLH
C A Ol/OE/07 1FR FIRST ISSUE FB YLH
in
o Rev Date Status Revision Memo Issued by Checked by Approved by
2% slope C C
8
YEMEN LNG Project
Detail E

i
A Scale : 1:20 LNG Plant

o
885 865 W eootmcts/WSi YEMCAS Doc c SOI
m CONSTRUCTION NOTES:
D EMERGENCY DIESEL GENERATOR FDR CAMP
1- Unit will be installed on existing slab
2275 2- Electrical to be run above existing slab on trays ERECTION GENERAL ARRANGMENT DRAWING
Daily fuel tank 8000L
37-TZ-0501A
B but must pass through slabs by ducts from container
3- Bunded area around diesel tank will be
37-DG-0501
constructed above existing slab
Leakage gauge LM . / S-Syt- 05 »tln*i ICC Clcctonlc FR«r
37LSH71121
YE-I 3S8-LAY-13101 Rvq^cHon Not YE-001-3S-LDC-RCO-31004 Revision 1/50

Vtnrior ««f • AVI34S76-«-5D(eil P.O. Net 9493G PD 1140 01 00 0059 00 Folio* 1/1
Document number
Scope of Work YE-001-35-BMI-SOW-00001
EDG - Corrosion Protection Repairs Revision: 00 Status:
IFA
Document Type: SOW System/Subsystem : 35 Discipline : PAI Rev Date : 20 January 2011
Other References: Page 16 of 16

APPENDIX 2: OHGPI DOCUMENTATION

This document is the property of Yemen LNG Company. It must not be stored, reproduced or disclosed to others without written authorisation from the Company.
OFFICE FOR APPROVAL OF
INDUSTRIAL PAINT GUARANTEES
10, avenue de Salonique – 75017 PARIS
Tel. +33 (0)1 58 05 07 57 – Fax. +33 (0)1 56 68 00 48 – e-mail info@ohgpi.com

PAINT GUARANTEES
ON STEEL STRUCTURES :
CODE OF TECHNICAL CONDITIONS

D.G.O. 12

2006
This code supersedes
the previous edition of 2005

FIPEC GEPI
French Federation of Paint
Ink, Colour, Glue and Adhesive Industrial Paint Contractors Group
Industries; Anticorrosion and Marine Group

42, avenue Marceau – 75 008 PARIS 9, rue La Pérouse – 75 016 PARIS


Tel. +33 (0)1 53 23 00 00 Tel. +33 (0)1 40 69 53 74
e-mail. dirtech@fipec.org e-mail. gepi@gepi.ffbatiment.fr
D.G.O. 12

PAINT GUARANTEES
ON STEEL STRUCTURES
CODE OF TECHNICAL CONDITIONS
________________

SCOPE: This code governs the guarantees applicable to all work involving the protection of low-alloy
steels, irons and cast irons by liquid or powder paint coatings. It primarily applies to the anti-corrosion
protection and appearance functions of the paint system. Other codes or circulars, an exhaustive list of
which is available, provide additional indications specific to particular protection systems (aluminium
structures, galvanized or metallised steel, tanks or other storage capacities, colour, etc). Protection
against micro-organisms, resistance to mechanical actions or fire, or other specific functions, does not
fall within the scope of this code.

SECTION I

MANUFACTURER GUARANTEE
PRINCIPLE: The manufacturer guarantees his supply against all faulty manufacture or errors
in recommendation.

Article 1 – Conformity of supplied products. – The manufacturer guarantees that the


products supplied are suitable for the intended uses and are fully compliant with the product’s
technical specifications, with any samples supplied and with the indications figuring in the approval
certificate.

Article 2 – Case of an imposed composition. – If the composition of the product is imposed


by the customer in the form of physical or chemical specifications, thereby limiting the initiative of the
manufacturer, the guarantee provided by the latter relates solely to the conformity of the supply to the
specifications imposed upon him.

SECTION II

PAINT CONTRACTOR GUARANTEE

PRINCIPLE: The paint contractor guarantees his service against any form of faulty
craftsmanship.

Article 3 – The paint contractor undertakes to implement the process(es) defined in the
approval certificate in accordance with the rules of the trade (e.g. specifications, technical data sheets,
etc.) which address, in particular, issues such as surface preparation, preparation and application of
paints, as well as environmental conditions (climatic conditions, etc).

SECTION III

JOINT GUARANTEES

Article 4 – In accordance with the previously defined guarantees, the manufacturer and the
paint contractor jointly undertake, during the approved period of guarantee and barring circumstances
outside one’s control (“force majeure”), to bear the costs of any repair work to the defective coating
that may be deemed necessary in the event of damage due to an inherent defect in the coating, i.e.
failure to comply with the guarantees defined in sections I and II above.
Article 5 – Scope of the guarantee. – The guarantee relates to the behaviour of the coating,
which itself includes:
The effectiveness of protection against corrosion/rusting,
The non-deterioration of the appearance (blistering, cracking, flaking).
The agreed guarantee period and reference of the extent of each type of deterioration are examined
taking into account the technical rules defined by the OHGPI, including mainly the thickness
acceptance procedures (see current DRC). Both the period and reference of the extent of deterioration
are likely to be reviewed in all cases of unexpected modification of the normal site production
conditions (e.g. site interruption).

Article 6 – Start date of the guarantee. – The guarantee period shall start as from the time of
acceptance of the paint work by the principal and/or the contracting authority; this acceptance shall
take place at the latest within fifteen (15) days following the expiry of the drying period of the top coat
which constitutes the completion of the paint work (or of each work phase if work execution is not
continuous). If, by exception, a later date was adopted as the start date for the guarantee, the duration
of the latter would be decreased accordingly.

Article 7 – Application of the guarantee. – Throughout the entire stipulated guarantee


period, the guarantee applies as soon as the extent of one of the deteriorations mentioned in the
approval certificate (certificate H), and described in the annex, has been exceeded:

7-1 Anti-corrosion protection.


The guarantee applies when the stated degree of rusting is exceeded over the total visual perception
area of the work or reference area (see Annex).

7-2 Appearance (blistering, cracking, flaking).


The guarantee applies as soon as one at least of the stated degrees of deterioration is exceeded over
the total visual perception area of the structure or over the reference area.
The duration of the appearance guarantee cannot be longer than that of the anti-corrosion guarantee.

Article 8 – Obligations and limits of the guarantee. – The guarantee comprises the free
supply and application of the products required for repairing the defective areas. These products shall,
in principle, stem from the same source and be of the same nature as the selected initial coating. The
guarantee is expressly limited to the aforesaid supply and application, with the exclusion of all other
expenses, incidental operations, compensation or damages. Repairs carried out under the guarantee
cannot lead to an extension of its initial duration.

Article 9 – Exclusions. – The guarantee does not cover:


1) damage stemming from fortuitous or accidental causes such as: substrate deformations, impacts,
friction, leaks or run-outs, abnormal temperature rises, etc…
2) changes in the intended use of the work or the modification of the parameters used as a basis for
the issue of the approval,
3) deteriorations due to peeling of residual millscale, metallisation or galvanisation, or of a former paint
system if latter are retained during maintenance work,
4) deteriorations of systems in which the workshop primer(s) have not been implemented or accepted
by the contractor responsible for applying the final coat(s).
5) deteriorations occurring in areas where design considerations of the substrate do not comply with
ISO 12944-3.

Article 10 – Forfeiture of the guarantee. – The principal and/or the contracting authority is
held to report, as soon as it appears, any damage defined in article 7, so that the guarantor(s) are able
to immediately take the necessary measures.
The guarantee commitment will be considered as null and void in the event of other coatings,
applications or treatments being implemented on the same surfaces without the prior written consent
of the guarantor(s).

In the event of dispute concerning the interpretation of the English language text, only the original
French version prevails.

PARTIAL REPRODUCTION
IS PROHIBITED
Text adopted by the Board of Directors on 14/09/06
D.G.O. 12

ANNEX

Definitions of the deteriorations or concepts referred to in articles 5 and 7:

Rusting: Degree of rusting Ri 1, Ri 2, or Ri 3


See ISO 4628-3.

Blistering: Deterioration characterised by convex deformations of the film in the form of blisters,
correlative to the peeling of one or more of the film constituent layers.
See ISO 4628-2 degree 3 (S3)

Cracking: Deterioration characterised by the appearance of discontinuities in the coating,


depending on the defect types b and c.
See ISO 4628-4 degree 3 (S3)

Flaking: Peeling of the film in the form of scales, of varying distribution and size, depending on
the defect types a and b
See ISO 4628-5 degree 3 (S3)

Total visual perception area of the work or reference area:

According to the standard NF T34-554, the expression “total visual perception area of
a work” is termed as any part of this said work revealing an overall coherence with
regard to the "visual perception" function. In principal, an observer of the work
perceives the entire total visual perception area at a "single glance".

Two parts of a structure, treated with different products or under different work
execution conditions, constitute two different areas, even if these two parts are visible
simultaneously. Consequently, the assembly areas or rework areas are different total
visual perception areas.

It is therefore recommended to accurately define the total visual perception areas of


the work or the reference areas at the time of drawing up the contract, taking particular
account of the exposure conditions.

For each type of guarantee, the assessment of the condition of the coating is
conducted firstly on each total visual perception area of the thus defined work. Next, in
the case where the deteriorations are grouped together in limited surface area zones,
the assessment is carried out by fictitiously dividing the total visual perception area
into squares (or rectangles in the case of lengthwise surface areas) each having an
2
area of 1m , designated as the “reference area”.

You might also like