Packing, Marking & Load-Out Instructions

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
200 views11 pages

Packing, Marking & Load-Out Instructions

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

3769 VAALCO ETAME PROJECT

PURCHASE ORDER NO. 200002186-001


3 OFF 5” ID PRODUCTION FLOWLINES

PACKING, MARKING & LOAD-OUT INSTRUCTIONS

NOV DOC.NO. 3769-DOC-MNL-300


CLIENT DOC.NO. N/A

A Issued for Review 27-08-2013 LLA FFA BRH FFA


Project
Rev. Purpose of issue Date Originator Checker Approver Approver

National Oilwell Varco Denmark I/S


Certified according to:
Production Facility located at
Sydhavnen 5, DK-4400 Kalundborg 17J-0004

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 2 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

THIS DOCUMENT IS GENERATED BY NATIONAL OILWELL VARCO DENMARK I/S (HEREAFTER


REFERRED TO AS NOV FLEXIBLES OR ALTERNATIVELY ABBREVIATED TO NOV).
THIS DOCUMENT IS ELECTRONICALLY GENERATED. THE DOCUMENT IS CHECKED AND APPROVED
ACCORDING TO INTERNAL PROCEDURES IN OUR BUSINESS MANAGEMENT SYSTEM THAT ARE
PART OF NOV FLEXIBLES’ OVERALL QUALITY SYSTEM.
AN ELECTRONIC SIGNED DOCUMENT IS FILED AT NOV FLEXIBLES’ AND IS AVAILABLE UPON
REQUEST.

REVISION HISTORY
This is the first issue of this document.

LIST OF HOLDS
There are holds in this document
[HOLD]´s are specified in the present revision for issues that await clarification. The following HOLD-points are
effective at the time of issue of this document.
Table of HOLD-Items awaiting clarification.
Section Description Action
1 introduction Transportation vessel name Vaalco
TBA
3.2 Destination of delivery Vaalco
6.1 Confirmation of which end NOV
fitting shall be off first
11.1 Contact details to be filled in Vaalco
by client

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 3 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

TABLE OF CONTENTS

1 INTRODUCTION............................................................................................................................................4
2 ADDITIONAL DOCUMENTS.........................................................................................................................4
3 SCOPE OF SUPPLY .....................................................................................................................................4
3.1 DELIVERY TERMS ....................................................................................................................................4
3.2 DESTINATION OF DELIVERY ......................................................................................................................4
3.3 DELIVERY ARRANGEMENTS .............................................................................................................4
4 TECHNICAL DATA .......................................................................................................................................5
4.1 PIPE DATA...............................................................................................................................................5
4.2 REEL DATA..............................................................................................................................................5
5 MARKING OF PIPE .......................................................................................................................................6
5.1 NOV AXIAL MARKING ON PIPE .................................................................................................................6
5.2 MARKING OF END FITTINGS .................................................................................................................6
5.3 MARKING OF DELIVERY FOR TRANSPORT ...................................................................................................6
5.4 ADDITIONAL MARKING ..............................................................................................................................6
5.5 REEL MARKING........................................................................................................................................7
6 PACKING AND LIFTING DETAILS ..............................................................................................................7
6.1 PACKING OF PIPES .................................................................................................................................7

6.2 PACKING LISTS ........................................................................................................................................7


6.3 LIFTING OF REEL ......................................................................................................................................7
7 HIRING OF NOV EQUIPMENT .....................................................................................................................8
8 SEA FASTENING ON THE VESSEL ............................................................................................................8
9 THE HARBOUR AT NOV IN KALUNDBORG ..............................................................................................8
10 SAFETY AND REGULATIONS, GENERAL .................................................................................................8
11 HAND-OVER CERTIFICATE ........................................................................................................................8
11.1 CONTACT PERSONS ..................................................................................................................................9

APPENDIX A; SKETCH OF NOV NAME PLATE ON END FITTING ................................................................ 10


APPENDIX B; REEL DIMENSIONS / LIFTING DETAILS ................................................................................. 11

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 4 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

1 INTRODUCTION
The objective of this document is to summarise necessary data regarding products, packing, reel,
and give an overview of the handling requirements for NOV reel and pipes.

Transportation Vessel for this job TBA.


Load out/delivery will take place from NOV’s facilities at the Harbour of Kalundborg, Denmark.
Delivery terms and arrangements are described in section 3.

2 ADDITIONAL DOCUMENTS
For a full package the following additional documents compile a complete overview of information
relevant to load-out. NOV recommend the load-out team to be in possession of this package:

3769-DOC-MNL-400 Packing list for Production Flowlines


3769-DOC-MNL-100 Installation Limitation
3769-DOC-ENG-701 Data List
3769-DWG-PCK-100 General Packing Arrangement

3 SCOPE OF SUPPLY
3.1 DELIVERY TERMS
For this project the contractual terms of delivery (Incoterms 2000) is:

FAS: Free Alongside Ship (Kalundborg, Denmark).


The Seller delivers the goods when the goods have been placed reachable for the vessel at the
named port of shipment, and the title to and the risk for the goods has passed to the Purchaser.

3.2 DESTINATION OF DELIVERY


Consignee of the delivery
Name, Address and Country: [To be informed by Client]
Port of discharge: [To be informed by Client]

3.3 DELIVERY ARRANGEMENTS


The pipes will be delivered packed on reel to Transportation Vessel. The deliveries will be
according to 3769-DOC-MNL-400 Packing list for 5” ID Production Flowlines.

The delivery includes:

Flexible Pipe Pipe Serial no. Length [m] Delivery Method


5” Production flowline 3769NKT001 860m
5” Production flowline 3769NKT002 590m NOV Reel # 1
5” Production flowline 3769NKT003 170m

Auxiliary Equipment: Tag No.: Delivery Method


Anodes N/A Mounted on pipes
Pull Heads N/A Mounted on pipes

Spare parts Tag No. Delivery Method


Spare parts for installation N/A Box

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 5 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

4 TECHNICAL DATA
The technical data for the NOV scope of supply for this Project is flexible pipes as specified below:
4.1 PIPE DATA
The flexible pipes have the following main characteristics (nominal values):

Description/Pipe 5” PF
Pipe serial number 3769NKT001 3769NKT002 3769NKT003
Data sheet no. 3769-DOC-ENG-701
Length; m 860 590 170
Pipe ID; mm 127.0
Pipe OD; mm 306.2
MBR storage; m 1.99
Pipe weight in air; kg/m (empty) 99.2
Pipe weight in seawater; kg/m 23.8
(empty)
Pipe weight in air; kg/m (filled 99.2
with delivery medium)
Pipe weight in seawater; kg/m 23.8
(filled with delivery medium)
End fittings weights; kg (in air) 679 (A end)
679 (B end)
Pull head weight; kg 69 (A end)
and locatio 69 (B end)
Total weight of pipe; kg (in air, 86,808.0 60,024.0 18,360.0
filled with delivery medium incl. 2 end
fittings + pull head)
Delivery medium Empty

4.2 REEL DATA

Text: Reel #1
Reel Tag No TBA
Weight of Reel; kg TBA
Cradle Tag No TBA
Weight of Cradle; kg TBA
Lifting Beam Tag No TBA
Weight of Lifting Beam; kg TBA
Divider Ring TBA
Weight of Divider Ring; kg TBA
Pipe serial no. TBA
Weight of Pipe(s); kg TBA
Weight of Rigging; kg TBA
Weight of Core Extension; kg TBA

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 6 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

Total Weight; kg 0
Weight Safety Margin (5%); kg 0
Total weight incl. safety margin 0

The reel supplied for the flexible pipes is a special built 10.2m reel purchased by Vaalco.
See Appendix B for typical example of Reel dimensions/ Lifting details.

5 MARKING OF PIPE
5.1 NOV AXIAL MARKING ON PIPE
Every 10 meters of the pipe is marked at circumferential position 4, 8 and 12 o’clock. The following
text is written in 50 mm black letters:

NOV 3769FS001 2013 0010 I


Point of meterage
NOV meterage (i.e. 0010 for 10 meters)
Year of manufacture
Fabrication Specification Number
NOV

Each pipe is marked with Fabric Specification no., (3769FS001) and the end fittings are marked
with a unique pipe no. Below a list of pipe numbers made with design 3769FS001.

5” pipe 3769NKT001

3769FS001 5” pipe 3769NKT002

5” pipe 3769NKT003

5.2 MARKING OF END FITTINGS


Both end fittings are marked with a water resistant plate attached to the outer casing. The text,
abbreviations and order are - with minor adjustments and additions - in accordance with API 17J
section 11.1.
The end fittings are designated with extension A & B to the serial number.

Details of the end-fitting name plates are included in Appendix A.

5.3 MARKING OF DELIVERY FOR TRANSPORT


A note with the delivery address will be attached to the reel.
A packing list and a delivery address will be attached to each box.
Delivery address will be according to Client information given in section 3.2.
5.4 ADDITIONAL MARKING
The Client and the installation contractor may mark the outer sheath of the pipe with fiber-tip pen,
aerosol spray or paint compatible with MDPE.
Removal of Marking on outer sheath with solvent shall be compatible with MDPE.

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 7 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

5.5 REEL MARKING


The NOV reel is marked with unique Reel Tag numbers. The reel Tag number is painted with white
colour on the flange on each side of the reel.

6 PACKING AND LIFTING DETAILS


6.1 PACKING OF PIPES
Delivered on reels:
The flexible pipes are packed on the reels as per 3769-DWG-PCK-100 General Packing
Arrangement.
.
End-fitting A is first off the reel [TBC].

The pipes are packed and delivered on a 10.2m reel including end-fittings and Pull heads.
• The end fittings are secured to the side of the reel with steel chains. See NOV standard
rigging in packing drawings.
Note: Soft slings/chains have been used to hold the flexible in place during reeling/packing
but are not designed for sea fastening purposes. Slings and straps shall be removed
carefully during installation.
• The cradle is clipped to the reel.

The flexibles is packed/coiled so that the specified minimum bending radius (MBR), is not violated”.
In order to have both end fittings accessible a ramp of polystyrene foam is assembled on the reels.

NOTE: Additional foam blocks have been used for the packing/protection of the reel. NOV would
highlight that although these blocks are securely fastened, some of these blocks may (although
unlikely) become loose during transportation. When the flexible pipe is spooled from the reel there
is a potential but unlikely risk of falling items. A safety distance is required and no personnel shall
stay underneath the reel or between the reel flanges during spooling.

Drawing of typical lifting arrangement and drawing of Reel dimensions are shown in appendix B.

Ancillary equipment /Deliveries:


Spare parts are delivered in boxes according to Packing Lists document no. 3769-DOC-MNL-400.

Repair kit:
1 set of repair kit will not be loaded out with the deliveries, selected items for the Repair kit will be
transported to Gabon, when the installation period start. Part list for the repair kit is given in packing
list document no. 3769-DOC-MNL-401. The Repair kit shall be returned according to agreement.
(See also section 7).

Spares :
Spare parts are delivered in boxes or pallets according to Packing Lists document no. 3769-DOC-
MNL-400.
6.2 PACKING LISTS
Packing lists are prepared for transport and shipping purpose. They describe all items to be
delivered and delivery form e.g. pipe on reel or items in boxes. See separate document covering
the packing lists 3769-DOC-MNL-400.
6.3 LIFTING OF REEL
Lifting of reel is not part of NOV scope of work.

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 8 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

All lifting of the reel shall be performed in accordance with the drawing in 3769-DWG-LFT-100
(Lifting equipment).
The applied lifting beam with shackles and wires must have a sufficient rating for the applicable
lifting operation. The wires must only be attached to the reel as shown on the drawing. The wire
size shall be suitable for the rim on the reel. The lifting beam must have a sufficient length to avoid
the wires touching the sides of the reel.
During lifting operations, care must be exercised to ensure the safety and protection of all involved
personnel, equipment and the environment.
All lifting operations must be conducted in accordance with company safety procedures and
national regulations and supervised and handled by qualified personnel only.

NOTE: If NOV lifting beam and rigging are used it should be noted that this equipment are property
of NOV Flexibles and is not part of the delivery.

7 HIRING OF NOV EQUIPMENT


Care and custody of NOV’s equipment such as reels, accessories, etc. will be the full responsibility
of the Client from the agreed Delivery Date in Kalundborg and until returned Incoterms 2000 DEQ
Kalundborg.

8 SEA FASTENING ON THE VESSEL


The sea fastening is not a part of NOV scope of work.

9 THE HARBOUR AT NOV IN KALUNDBORG


NOV’s factory in Kalundborg is located at a harbour and has 2 quaysides. A map shoving the
quaysides is given in appendix C.

10 SAFETY AND REGULATIONS, GENERAL


Care must be exercised to ensure the safety and protection of all involved personnel, equipment
and the environment. No part of any operation may be in conflict with the internal NOV safety policy
and procedures as well as the Danish legislation for occupational health and safety.
Any command, request or recommendation from the NOV HSE organization must be immediately
complied with.
All personnel entering NOV location to be checked in via NOV reception or Gate and have
suitable PP equipment (personal protection equipment).

11 HAND-OVER CERTIFICATE
Upon delivery of the goods a representative for the client/ship will be required to sign off the
Packing List (3769-DOC-MNL-400) certifying the take-over of possession of the products.
Subsequently the signed Packing List will become a Handover Certificate.

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 9 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

11.1 CONTACT PERSONS


The following persons have responsibility and authority to take action during the load-out:

Representative Title Name Phone no e-mail


Client Vaalco
Gabon

Agent TBA

Project Frode +45 [email protected]


Manager Andreasen 2466 5241
Load Out Brian Hansen +45 [email protected]
NOV Manager 3037 2876
Load Out Henrik Weeke +45 [email protected]
Assistant Andersen 4191 4744

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 10 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

APPENDIX A; SKETCH OF NOV NAME PLATE ON END FITTING

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11
Vaalco Etame project Page 11 of 11
Packing, Marking & Load-Out
Doc. no. 3769-DOC-MNL-300 Rev. A
Instructions

APPENDIX B; REEL DIMENSIONS / LIFTING DETAILS

Example of typical reel dimensions

This document contains confidential information. All rights (including copyright, confidential information, trade secrets, and design rights) are
owned by National Oilwell Varco Denmark I/S
No use or disclosure is to be made without the prior written permission of National Oilwell Varco Denmark I/S. All rights reserved.

TM-PRO-121 Rev 11