NCR No.: TSSA / ELECTRICAL / ALIBAG /----059--- Date : 09/10/2020
Name of Work Conversion of Existing 22KV and LT Power Distribution Network with
Underground Power Cable Network and Construction of 22 KV Switching
Station at Alibaug Town on Turnkey Basis Under NCRMP-II Maharashtra.
Client National Cyclone Risk Mitigation Project NCRMP-II
Contractor Leena Power Tech Engineer PVT .Ltd
Inspection Location Sai Nagar Alibag Date:
09/10/2020
Non-Conformity Report
Type of Non-Conformity:
1- Contractor have not sealed with capping by plastic half glass at Sai Nagar and not done proper
dressing.
Kuldeep Kumar
Senior Electrical Engineer
Contractor Client TUV SUD
Date : Date : Date :09/10/2020
Requirement as per Approved QAP /Drawing :
1 - Contractor should be seal with capping by plastic half glass at Sai Nagar and proper dressing.
2-As per agreement the sealing and resealing of cables after pulling is required to maintain cable
integrity during construction, ultimately preventing water ingress.
Senior Electrical Engineer
Contractor Client TUV SUD
Date : Date : Date :09/10/2020
Action Taken by Contractor:
Kuldeep Kumar
Senior Electrical Engineer
Contractor Client TUV SUD
Date : Date : Date :
Photo of NCR
LT UG Cable have not sealed and proper dressing
Photo of NCR
LT UG Cable have not sealed and proper dressing
TUV SUD / NCRMP NCR / 001 Ver 0.0 /dt. 10-01-2020