CII National Award for Excellence in
Energy Management 2020
ICICI Bank – DRC Jaipur
August 25 - 27, 2020
Presented by:
Deepak Dhar – Retail Infra Head
Munish Behl – Chief Manager
ICICI Bank - Introduction
Agenda
Overview
Energy Usage
Beginning of Journey
Encon Projects Planned
Innovations
Way Forward
Overview: Disaster Recovery Center Jaipur
DRC : Overview
Commissioned Plot area Built up area
2012 75000 sft 25000 sft
Floors Orientation Density
G+1 North South 228 Racks
DRC : A Snapshot
Total Connected • 670 KW ( FY15) Total Connected • 785 KW ( FY20)
Load Load
Chillers (Air • 2 x 230 TR
Chillers (Air • 2 x 230 TR
Cooled) Cooled) • 1 x 250 TR
• 6 x 600 KVA
• 4 x 600 KVA
UPS • 1 x 60 KVA UPS • 2 x120 KVA
• 2 x 60 KVA
PAHU • 9 x 32 TR PAHU • 16 x 32 TR
• 2 x 1500 KVA
DG • 3 x 500 KVA DG • 3 x 500 KVA
Load Distribution in FY 17
Type of load Load KW % Load Lighting
2%
HVAC 230 29.56% Misc HVAC
11% 30%
IT 444 57.06%
IT
Misc 84 10.79% 57%
Lighting 19 2.44%
Total 778 100%
Load Distribution in FY 20
Type of load Load KW % Load
HVAC 127 16.17%
IT 542 69.04%
Misc 95 12.10%
Lighting 21 2.67%
Total 785 100%
SEC Reduction and Variation Trend
PUE FY17-18 1.67
PUE FY18-19 1.58
PUE FY19-20 1.54
• Annual Saving of INR 21.1 Lakhs
due to higher PF of 0.99
• Annual rebate of INR 20 Lakhs
due to 33KV line
PUE = Total load
----------------
8.4% improvement against FY 18 IT Load
Energy Usage (FY18) – Beginning of Journey
PUE 1.67
Where do we stand?
Internal & Global Benchmarking
Description FY 2017 • Benchmarking
Annual PUE 1.67
• Setting targets
• Budgeting & Planning
Internal Benchmarking 1.54
• Action
• Approach & Target
PUE needs reduction
Setting Targets – Road Map
We begin with benchmarking
and set checkpoints to
monitor progress
FY20 FY 21
PUE PUE
1.54 1.48
FY18
PUE FY19
1.67 PUE
1.58
• Benchmarking
• Setting targets
• Budgeting & Planning
• Action
• Approach & Target
Encon Projects planned
• Replacement of existing Hi-pulse UPS with modular UPS
• Use of waste air from IDEC in UPS and Battery rooms
• Chemical cleaning of chiller pipes
• Installation of DX machines in network and telco rooms to
reduce the chiller load
13
Long Term Vision to Reduce PUE by 2022
Replacement of Hi Pulse with Modular UPS
UPS 1- 400 UPS 2- 400 KVA
KVA
UPS UPS
O/P - A DRC IT LOAD O/P - B
UPS 3- 400
UPS 4- 400 KVA
KVA
UPS losses will be reduced from 13% to 4%
Projection post UPS Optimization
Energy saving projects implemented in last 3 years
Year No of Proposals Investment (Lakh) Savings (Lakh)
2017-18 6 21.5 42
2018-19 2 4.7 16
2019-20 2 56 41
Savings
Sr. No Projects details Investment (Lakh) (lakh/annum) Payback
1 Installation of LED lights 1.6 1.6 12 months
2 Optimization of space temp. set points 0 1.4 0
3 ECO-Mesh ( Adiabatic cooling pads ) 14 3.9 43 months
3.3
4 AC & Non AC area Segregation in server room 0.5 1.8 months
5 UPS Optimization 0 2.7 0
Channeling Air Flow below false floor for better Cooling
6 Efficiency 5.5 3.24 20 months
3.3
7 Installation of In house Adiabatic System at chiller 1.5 5.4 months
8 Installed Primary pump of chiller and water balancing 3.2 3.4 22 months
9 Indirect Direct Evaporative cooling 56 33.48 19 months
10 1 MW Solar 0 110 0
Innovative
Projects
8.4% Reduction in PUE
Indirect – Direct Evaporative Cooling
• Power saving upto 30% in summers
and 65% in winters on HVAC systems
• Works as a backup in case of HVAC
failure
• Complete system is integrated with
BMS
• Reuse of waste air
Year of Action FY 19-20
Total Capex of INR 56,00,000
Total cost saving INR 33,48,000
ROI of 19 months
IDEC Saving
Summer Winter
Reduction in TR(Per AHU) 13.83 25.6
Equivalent electrical
saving(per AHU) KW 15.21 28.16
No. of AHU 10 10
Total electrical saving(KW) 60 92
IDEC Electrical
consumption(KW) 19.32 19.32
Net Saving/month (KW) 28800 54000
Total saving(Per month) INR
@Rs.10/unit 288000 540000
Total running months 6 3
Yearly saving 1728000 1620000
Total Annual Savinf (INR) 33,48,000
Cost of Installation of IDEC
60K System (INR) 56,80,000
Payback 1.7 Year 19
Innovative Project - Installation of In house Adiabatic Pad on Chiller
• Low cost solution compared to standard
available solution in market
• Closed loop system (No Wastage of water)
• Easy to maintain
• 8 to 10 degree reduction in ambient temp
adjacent to chiller
Year of Action FY 18-19
Total Capex of INR 1.50,000
Total cost saving INR 5,40,000
ROI of 3.3 months
Innovative Project - Channeling of Air Flow
HOT
return air
• Channelized air flow at below deck
through ducting in server room
• Increased CFM delivery
Year of Action FY 17-18
Total Capex of INR 5,50,000
Total cost saving INR 3,24,000
Below deck ducting
ROI of 20 months
Renewable Energy – 1 MW Solar Project
Technology Type of Onsite/offs Installed Generation % of overall electrical
(Electrical) Energy ite capacity million kwh energy
Electrical Solar Onsite 1 MW 1.8 kwh 26%
Utilization of Renewable Energy – 1 MW Solar
Project
• 1MW onsite Solar power through PPA. Zero Investment
• Commissioned in Dec 19
• Power generation from Dec 19 till date – 11.60 Lakh Kwh
• Group total capacity – 2.8 MW
• Further reduction in GHG emissions
Waste Air Utilization
Waste air from IDEC is being further used to reduce the ambient temperature of Chiller
Duct has been created from IDEC to chiller and air at 16 degrees from blowers is supplied to
chiller through ducts
Type of waste Quantity of waste generated
SI.No. Year 19-20 generated (CFM/hour) Disposal method
Cool air is being used for
reducing the ambient
1 FY20 Cool Air 34800 CFM/hour temperature of Chiller
Waste utilization and management
Replication of best
practices across supply Waste Management
chain
• Our partner M/s.
Vertiv has suggested
similar initiatives at • e-Waste is handled
their other as per CPCB
customers locations guidelines
like National
Informatics DC at
Shashtri Nagar Delhi
GHG Emission Audit & Certification
FY 2017
5073 tCO2e
FY 2018
5390 tCO2e
FY 2019
5578 tCO2e
Audited & Certified
Green Initiatives
Natural topography
Solar Reflective paints
maintained
Exterior wall –
Plantation of tress reduction in thermal
conduction
Converted 55% land
area into landscaping Cool Roofs Terrace
Cross-functional Team managing EnCon
Head - Infrastructure Management &
services Group
Regional Head Head-
Head- Energy
Rest of North IT Group
DRC
Head - 3rd party IT Operations
Energy Manager Infrastructure
DRC Operations Team
Manager
Infrastructure
DRC Operations
Facilities Team
3rd party
Operations
Energy
IT
Cross Functional Training for Equipment
Cross Functional Training for Safety and Security
Awards & Certification
Awards
• BFSI Digital Innovation Award
for DRC, Storage and IOT
• DCD Global Award : Smart Data
Center
• DCD Award : The Smart Data
Center award. Best in India
• Data Center Summit and
Awards 2017 : Energy
Efficiency
• CII National Energy
Management Award 2019
Certificates
• ISO/IEC 27001:2013
• BCMS-ISO22301-2012
Thank You