DESIGN SUMMARY
for
Construction of ONE (1) – STOREY R.C. EMERGENCY BUILDING
@ DRSTMH Compound, Kalibo, Aklan
Design Stresses:
fc’ =20.7 MPa for concrete
fy = 276 MPa for 16mm φ & larger rebars
fy = 228 MPa for smaller than 16 mm φ rebars
Dead Loads:
Unit Weight of Concrete 24kN/m3
Ceiling Finishes 0.15kPa
MEP 0.10kPa
Extra Movable Loads 1.00kPa
Live Loads:
Corridors above ground floor 3.8kPa
1. ROOF DECK
2-WAY SLAB: Thickness = 125mm
Rebars: Use 12 mm φ, S = 150mm
MAIN BEAM : 300 mm x 600 mm, Span L = 7600mm/7000mm
Rebars @ Support
use 8-20 mm φ top bars
use 5-20 mm φ bottom bars
Rebars @ Midspan
use 5-20 mm φ top bars
use 8-20 mm φ bottom bars
Use 10 mm φ stirrups, place 1st stirrup @ 50mm from the face of the support
For L = 7600mm Span stirrups spaced: 5 @ 50mm, 7 @ 100mm, 9 @ 150mm, rest @ 200mm O.C.
For L = 7000mm Span stirrups spaced: 5 @ 50mm, 7 @ 100mm, 9 @ 150mm, rest @ 200mm O.C.
SECONDARY BEAMS : 250 mm x 450 mm, Span L = 4500m/1000m
Rebars @ Support
use 4-20 mm φ top bars
use 2-20 mm φ bottom bars
Rebars @ Midspan
use 2-20 mm φ top bars
use 4-20 mm φ bottom bars
Use 10 mm φ stirrups, place 1st stirrup @ 50mm from the face of the support
For L = 4500mm Span stirrups spaced: 3 @ 50mm, 5 @ 100mm, 7 @ 150mm, rest @ 200mm O.C.
For L = 1000mm Span stirrups spaced: 2 @ 50mm, 4 @ 100mm, 6 @ 150mm, rest @ 200mm O.C.
TERIARY BEAMS : 200 mm x 450 mm, Span L = 3800m/3500m
Rebars @ Support
use 4-20 mm φ top bars
use 2-20 mm φ bottom bars
Rebars @ Midspan
October 30, 2020 1
use 2-20 mm φ top bars
use 4-20 mm φ bottom bars
Use 10 mm φ stirrups, place 1st stirrup @ 50mm from the face of the support
For L = 3800m Span stirrups spaced: 2 @ 50mm, 4 @ 100mm, 6 @ 150mm, rest @ 200mm O.C.
For L = 3500m Span stirrups spaced: 2 @ 50mm, 4 @ 100mm, 6 @ 150mm, rest @ 200mm O.C.
LINTEL BEAMS : 150 mm x 300 mm
Rebars
use 2-16 mm φ top bars
use 2-16 mm φ bottom bars
Use 10 mm φ stirrups, place 1st stirrup @ 50mm from the face of the support
Spaced: 2 @ 50mm, 4 @ 100mm, 6 @ 150mm, rest @ 200mm O.C.
2. MAIN COLUMN : 400 mm x 600 mm concrete section
use 12-20 mm φ bars
use 10 mm φ lateral ties
spacing of 50mm O.C. @ Core; 150 mm O.C. @ middle 3rd of Col. Ht., & the rest @ 100mm O.C.
LINTEL COLUMN : 150 mm x 400 mm concrete section
use 6-16 mm φ bars
use 10 mm φ lateral ties
spacing of 50mm O.C. @ Core; 150 mm O.C. @ middle 3rd of Col. Ht., & the rest @ 100mm O.C.
3. TIE BEAMS : 250 mm x 450 mm, Span L = 7600mm/7000mm/4500m
Rebars
use 4-20 mm φ top bars
use 4-20 mm φ bottom bars
Use 10 mm φ stirrups, place 1st stirrup @ 50mm from the face of the support
For L = 7600mm Span stirrups spaced: 5 @ 50mm, 7 @ 100mm, 9 @ 150mm, rest @ 200mm O.C.
For L = 7000mm Span stirrups spaced: 5 @ 50mm, 7 @ 100mm, 9 @ 150mm, rest @ 200mm O.C
For L = 4500mm Span stirrups spaced: 3 @ 50mm, 5 @ 100mm, 7 @ 150mm, rest @ 200mm O.C..
Note: Location of the underside of beam is 1000mm below the N.G.L.
4. ISOLATED CONCRETE FOOTING OF MAIN COLUMN (ASB = 75 kPa)
Thickness = 400mm
Width = 2000 mm
Length = 2000 mm
Top Matting Rebars = 12-16 mm φ rebars o.c.b.w.
Bottom Matting Rebars = 12-20 mm φ rebars o.c.b.w.
October 30, 2020 2