DRM/S T Acting For and On Behalf of The President of India Invites E-Tenders Against Tender No N-539-2-OT-19-20-11 Closing
DRM/S T Acting For and On Behalf of The President of India Invites E-Tenders Against Tender No N-539-2-OT-19-20-11 Closing
TENDER DOCUMENT
Tender No: N-539-2-OT-19-20-11 Closing Date/Time: 11/06/2019 15:00
DRM/S T acting for and on behalf of The President of India invites E-Tenders against Tender No N-539-2-OT-19-20-11 Closing
Date/Time 11/06/2019 15:00 Hrs. Bidders will be able to submit their original/revised bids upto closing date and time only. Manual offers
are not allowed against this tender, and any such manual offer received shall be ignored.
Contractors are allowed to make payments against this tender towards tender document cost and earnest money only through only
payment modes available on IREPS portal like net banking, debit card, credit card etc. Manual payments through Demand draft, Banker
cheque, Deposit receipts, FDR etc. are not allowed.
1. NIT HEADER
2. SCHEDULE
S.No. Item Item Qty Qty Unit Unit Rate Basic Value Escl.(%) Amount Bidding Unit
Code
Above/
Schedule A-Indoor Work 1093488.48
Below/Par
1 1.00 Job 575000.00 575000.00 AT Par 575000.00
1 Item Description:- Modification of existing interface & application logics circuits design including FAT & SAT as
per the modified and approved application logic.
2 1.00 Job 75000.00 75000.00 AT Par 75000.00
2
Item Description:- Modification to the application software of VDU & MT.
3 1.00 Job 350000.00 350000.00 AT Par 350000.00
3 Item Description:- Alterations to the relay rack wiring as per the modified interface circuits and the supply of
necessary wiring material.
4 1.00 Job 25000.00 25000.00 AT Par 25000.00
4
Item Description:- Commissioning of EI System.
5 1.00 Job 27140.00 27140.00 AT Par 27140.00
5
Item Description:- Modification in existing domino type operating cum indication panel.
6 1.00 Job 41348.48 41348.48 AT Par 41348.48
6 Item Description:- Database entry, Validation of inputs , Simulation modification, Fault Logics preparation and
Testing and commissioning of Datalogger.
S.No. Item Code Item Qty Qty Unit Unit Rate Basic Value Escl.(%) Amount Bidding Unit
Above/
Schedule B-Outdoor work 56469.29
Below/Par
1 1.00 Numbers 11522.91 11522.91 AT Par 11522.91
1 Item Description:- Supply of CLS unit 2 Aspect as per Drg No. 23003 A/M ( Adv ) but without lamp, lenses,
holder and signal transformer as per the technical specification attached, Inspection-Consignee.
2 1.00 Numbers 16150.47 16150.47 AT Par 16150.47
Item Description:- Supply of CLS unit 3 Aspect as per Drg No. 23002 A/M ( Adv ) but without lamp, lenses,
2
holder and signal transformer suitable for LED signal as per the technical specification attached, Inspection-
Consignee.
5 Item Description:- "Installation of Warning board along with supply of warning board. This includes concrete
foundation of 600 x 600 x 600 mm as per the technical specification attached, Inspection-Consignee. Note -Rail
post will be given by railway at the store of consignee."
6 2.00 Numbers 989.13 1978.26 AT Par 1978.26
6 Item Description:- Supply of and Fixing of MS Flat size 32 mm x 5 mm as Earth lead on Signal Post at CPR
station of BSB division as per the technical specification attached, Inspection-Consignee. All required materials
will be supply by the contractor.
Please see Item Breakup for details. 4248.94 AT Par 4248.94
7 Item Description:- Earthing of CT Rack, Relay Rack, DG sets etc. including supply of Earthing materials as per
tech. specification attached, inspection-Consignee.
Please see Item Breakup for details. 637.50 AT Par 637.50
8 Item Description:- Supply & Installation of Number Plate of Signals as per tech. specification attached,
inspection- Consignee.
9 50.00 CORE 13.72 686.00 AT Par 686.00
9
Item Description:- TERMINATION OF SIGNALLING CABLE as per tech. specification attached.
10 5.00 Numbers 113.74 568.70 AT Par 568.70
10 Item Description:- Fitting of LED signal with all accessories and its wiring as per tech. specification attached. All
material required for fitting and wiring except LED signal and PVC wire shall be supplied by the contractor.
11 2.00 Numbers 353.97 707.94 AT Par 707.94
11 Item Description:- Painting of Apparatus Cases Single including supply of Paint as per tech. specification
attached.
12 1.00 Numbers 262.20 262.20 AT Par 262.20
12
Item Description:- Painting of Apparatus Cases Half including supply of Paint as per tech. specification attached.
13 2.00 Numbers 237.69 475.38 AT Par 475.38
13 Item Description:- Painting of Main Signal Post , signal unit , surface bace and complete fitting as per NE.Rly
standard practice & as per tech. specification attached.
Please see Item Breakup for details. 9390.72 AT Par 9390.72
14 Item Description:- Dismantling of Existing signals, Apparatus Cases, Foundations etc as per tech. specification
attached.
3. ITEM BREAKUP
4. ELIGIBILITY CONDITIONS
5. COMPLIANCE
Commercial-Compliance
The tenderers are required to submit [scanned copy in PDF format] their Allowed
11 No No
Undertaking as per the document attached. (Mandatory)
General Instructions
The partnership firm should have been in existence or should have been
formed prior to submission of tender. Partnership firm should have either
12.2 been registered with the Registrar or the partnership deed should have No No Not Allowed
been notarized prior to date of tender opening as per the Indian
Partnership Act.
Separate identity / name should be given to the partnership firm. The
partnership firm should have PAN / TAN number in its own name and PAN /
12.3 No No Not Allowed
TAN number in the name of any of the constituent partners shall not be
considered. The valid constituents of the firm shall be called partners.
Once the tender has been submitted, the constitution of the firm shall not
be allowed to be modified / altered / terminated during the validity of the
tender as well as the currency of the contract except when modification
becomes inevitable due to succession laws etc., in which case prior
permission should be taken from Railway and in any case the minimum
eligibility criteria should not get vitiated. The re-constitution of firm in such
cases should be followed by a notary certified Supplementary Deed. The
approval for change of constitution of the firm, in any case, shall be at the
sole discretion of the Railways and the tenderer shall have no claims what-
so-ever. Any change in the constitution of Partnership firm after opening of
tender shall be with the consent of all partners and with the signatures of all
12.4 partners as that in the Partnership Deed. Failure to observe this No No Not Allowed
requirement shall render the offer invalid and full EMD shall be forfeited. If
any Partner/s withdraws from the firm after opening of the tender and
before the award of the contract, the offer shall be rejected. If any new
partner joins the firm after opening of tender but prior to award of contract,
his / her credentials shall not qualify for consideration towards eligibility
criteria either individually or in proportion to his share in the previous firm.
In case the tenderer fails to inform Railway beforehand about any such
changes / modification in the constitution which is inevitable due to
succession laws etc. and the contract is awarded to such firm, then it will be
considered a breach of the contract conditions liable for determination of
the contract under Clause 62 of General Conditions of Contract.
A partner of the firm shall not be permitted to participate either in his
12.5 No No Not Allowed
individual capacity or as a partner of any other firm in the same tender.
The tender form shall be submitted only in the name of partnership firm.
The EMD shall be deposited by partnership firm through e-payment
12.6 gateway or as mentioned in tender document. The EMD submitted in the No No Not Allowed
name of any individual partner or in the name of authorized partner (s)
shall not be considered.
One or more of the partners of the firm or any other person (s) shall be
designated as the authorized person (s) on behalf of the firm, who will be
authorized by all the partners to act on behalf of the firm through a "Power
of Attorney", specially authorizing him / them to submit & sign the tender,
sign the agreement, receive payment, witness measurements, sign
12.7 No No Not Allowed
measurement books, make correspondences, compromise / settle /
relinquish any claim (s) preferred by the firm, sign "No Claim Certificate",
refer all or any dispute to arbitration and to take similar such action in
respect of the said tender / contract. Such "Power of Attorney" shall be
notarized / registered and submitted along with the tender.
On issue of Letter of Acceptance (LOA) to the partnership firm, all the
guarantees like Performance Guarantee, Guarantee for various Advances
12.8 No No Not Allowed
to the Contractor shall be submitted only in the name of the partnership
firm and no splitting of guarantees among the partners shall be acceptable.
On issue of Letter of Acceptance (LOA), contract agreement with
12.9 partnership firm shall be executed in the name of the firm only and not in No No Not Allowed
the name of any individual partner.
In case the Letter of Acceptance (LOA) is issued to a partnership firm, the
12.10 following undertakings shall be furnished by all the partners through a No No Not Allowed
notarized affidavit, before signing of contract agreement.
(a)Joint and several liabilities: The partners of the firm to which the Letter of
Acceptance (LOA) is issued, shall be jointly and severally liable to the
Railway for execution of the contract in accordance with General and
12.10.1 Special Conditions of the Contract. The partners shall also be liable jointly No No Not Allowed
and severally for the loss, damages caused to the Railway during the
course of execution of the contract or due to non-execution of the contract
or part thereof.
(b)Duration of the partnership deed and partnership firm agreement: The
partnership deed/partnership firm agreement shall normally not be
modified/altered/ terminated during the currency of contract and the
maintenance period after the work is completed as contemplated in the
12.10.2 No No Not Allowed
conditions of the contract. Any change carried out by partners in the
constitution of the firm without permission of Railway, shall constitute a
breach of the contract, liable for determination of the contract under Clause
62 of the General Conditions of Contract.
(c)Governing laws: The partnership firm agreement shall in all respect be
12.10.3 No No Not Allowed
governed by and interpreted in accordance with the Indian laws.
(d)No partner of the firm shall have the right to assign or transfer the
12.10.4 interest right or liability in the contract without the written consent of the No No Not Allowed
other partner/s and that of the Railway.
The tenderer shall clearly specify that the tender is submitted on behalf of a
12.11 partnership firm. The following documents shall be submitted by the No No Not Allowed
partnership firm, with the tender:
12.11.1 (a)A copy of partnership deed. No No Not Allowed
(b)A copy of Power of Attorney (duly registered as per prevailing law) in
12.11.2 favour of the individual to tender for the work, sign the agreement etc. and No No Not Allowed
create liability against the firm.
(c)An undertaking by all partners of the partnership firm that they are not
blacklisted or debarred by Railways or any other Ministry / Department of
the Govt. of India / any State Govt. from participation in tenders / contracts
12.11.3 as on the date of opening of bids, either in their individual capacity or in any No No Not Allowed
firm in which they were / are partners. Concealment / wrong information in
regard to above shall make the contract liable for determination under
Clause 62 of the General Conditions of Contract.
Evaluation of eligibility of a partnership firm: Technical and financial
12.12 eligibility of the firm shall be adjudged based on satisfactory fulfillment of No No Not Allowed
the eligibility criteria laid down in Clause 10 above by the partnership firm.
Performance Guarantee:The procedure for obtaining Performance
13 No No Not Allowed
Guarantee is outlined below:
(a) The successful bidder shall have to submit a Performance Guarantee
(PG) within 21 (Twenty one) days from the date of issue of Letter of
Acceptance (LOA). Extension of time for submission of PG beyond 21
(Twenty one) days and upto 60 days from the date of issue of LOA may be
given by the Authority who is competent to sign the contract agreement.
However, a penal interest of 12% per annum shall be charged for the delay
beyond 21(Twenty one) days, i.e. from 22nd day after the date of issue of
LOA. Further, if the 60th day happens to be a declared holiday in the
concerned office of the Railway, submission of PG can be accepted on the
13.1 No No Not Allowed
next working day. In all other cases, if the Contractor fails to submit the
requisite PG even after 60 days from the date of issue of LOA, the contract
is liable to be terminated. In case contract is terminated railway shall be
entitled to forfeit Earnest Money Deposit and other dues payable against
that contract. In case a tenderer has not submitted Earnest Money Deposit
on the strength of their registration as a Startup recognized by Department
of Industrial Policy and Promotion (DIPP) under Ministry of Commerce and
Industry, DIPP shall be informed to this effect. The failed Contractor shall
be debarred from participating in re-tender for that work.
Security Deposit: The Earnest Money deposited by the Contractor with his
tender will be retained by the Railways as part of security for the due and
faithful fulfillment of the contract by the Contractor. The Security Deposit
shall be 5% of the contract value. Security Deposit may be deposited by the
Contractor before release of first on account bill in cash or Term Deposit
Receipt issued from Scheduled Bank, or may be recovered at the rate of
10% of the bill amount till the full Security Deposit is recovered. Provided
also that in case of defaulting Contractor, the Railway may retain any
amount due for payment to the Contractor on the pending "on account bills"
so that the amounts so retained (including amount guaranteed through
Performance Guarantee) may not exceed 10% of the total value of the
contract. Further, in case of contracts having value equal to or more than
50 crore (Rs Fifty crore) the Security Deposit may be deposited as Bank
14 No No Not Allowed
Guarantee Bond also, issued by a scheduled bank after execution of
contract documents, but before payment of 1st on account bill. Provided
further that the validity of Bank Guarantee Bond shall be extended from
time to time, depending upon extension of contract granted in terms of
Clause 17 of the Standard General Conditions of Contract. Further, in case
Security Deposit has been submitted as Term Deposit Receipt/Bank
Guarantee Bond in full amount, the Earnest Money deposited by the
Contractor with his tender will be returned by the Railways. Note: After the
work is physically completed as certified by competent authority, Security
Deposit recovered from the running bills of a Contractor can be returned to
him, if he so desires, in lieu of Term Deposit Receipt/irrevocable Bank
Guarantee for equivalent amount from Scheduled Bank, to be submitted by
him.
(i) Refund of Security Deposit: Security Deposit mentioned in sub clause (1)
above shall be returned to the Contractor after the following: (a)Final
Payment of the Contract as per clause 51.(1) and (b)Signature of Final
Supplementary Agreement or Certification by Engineer that Railway has No
Claim on Contractor and (c)Issue of Maintenance Certificate on expiry of
14.1 the maintenance period as per clause 50.(1). 16. (2) (ii) Forfeiture of No No Not Allowed
Security Deposit: Whenever the contract is rescinded as a whole under
clause 62 (1) of GCC, the Security Deposit already with railways under the
contract shall be forfeited. However, in case the contract is rescinded in
part or parts under clause 62 (1) of GCC, the Security Deposit shall not be
forfeited.
No interest shall be payable upon the Earnest Money and Security Deposit
or amounts payable to the Contractor under the Contract, but Government
14.2 No No Not Allowed
Securities deposited in terms of GCC-2018 Sub-Clause 16.(4)(b) of this
clause will be payable with interest accrued thereon.
(1) Adherence to Specifications and Drawings: The whole of the works shall
be executed in perfect conformity with the specifications and drawings of
the contract. If Contractor performs any works in a manner contrary to the
15 No No Not Allowed
specifications or drawings or any of them and without such reference to the
Engineer, he shall bear all the costs arising or ensuing therefrom and shall
be responsible for all loss to the Railway.
(2) Drawings and Specifications of the Works: The Contractor shall keep
one copy of Drawings and Specifications at the site, in good order, and
15.1 No No Not Allowed
such contract documents as may be necessary, available to the Engineer
or the Engineer's Representative.
(3) Ownership of Drawings and Specifications: All Drawings and
Specifications and copies thereof furnished by the Railway to the
Contractor are deemed to be the property of the Railway. They shall not be
15.2 No No Not Allowed
used on other works and with the exception of the signed contract set, shall
be returned by the Contractor to the Railway on completion of the work or
termination of the Contract.
(4) Compliance with Contractor's Request for Details: The Engineer shall
furnish with reasonable promptness, after receipt by him of the Contractor's
request, additional instructions by means of drawings or otherwise,
15.3 No No Not Allowed
necessary for the proper execution of the works or any part thereof. All
such drawings and instructions shall be consistent with the Contract
Documents and reasonably inferable therefrom.
Setting out of Works: The Contractor shall be responsible for the correct
setting out of all works in relation to original points, lines and levels of
reference at his cost. The Contractor shall execute the work true to
alignment, grade, levels and dimensions as shown in the drawing and as
directed by the Engineer's representative and check these at frequent
intervals. The Contractor shall provide all facilities like labour and
instruments and shall co-operate with the Engineer's representative for
20 checking of all alignment, grades, levels and dimensions. If, at any time, No No Not Allowed
during the progress of the works any error appear or arise in any part of
the work, the Contractor, on being required so to do by the Engineer's
representative shall, at his own cost rectify such errors, to the satisfaction
of the Engineer's representative. Such checking shall not absolve the
Contractor of his own responsibility of maintaining accuracy in the work.
The Contractor shall carefully protect and preserve all bench marks, sight
rails, pegs and other things used in setting out the work.
Workmanship and Testing: The whole of the works and/or supply of
materials specified and provided in the contract or that may be necessary
to be done in order to form and complete any part thereof shall be
executed in the best and most substantial workman like manner with
materials of the best and most approved quality of their respective kinds,
agreeable to the particulars contained in or implied by the specifications
21 and as referred to in and represented by the drawings or in such other No No Not Allowed
additional particulars, instructions and drawings given during the carrying
on of the works and to the entire satisfaction of the Engineer according to
the instructions and directions which the Contractors may from time to time
receive from the Engineer. The materials may be subjected to tests by
means of such machines, instruments and appliances as the Engineer may
direct and wholly at the expense of the Contractor.
Removal of Improper Work and Materials: The Engineer or the Engineer's
Representative shall be entitled to order from time to time: (a) The removal
from the site, within the time specified in the order, of any materials which
in his opinion are not in accordance with the specifications or drawings. (b)
The substitution of proper and suitable materials, and (c) the removal and
21.1 proper re-execution, notwithstanding any previous tests thereof or on No No Not Allowed
account payments therefor, of any work which in respect of materials or
workmanship is not in his opinion in accordance with the specifications and
in case of default on the part of the Contractor in carrying out such order,
the Railway shall be entitled to rescind the contract under Clause 62 of
these conditions.
22 Rates for Items of Works: No No Not Allowed
The rates, entered in the accepted Schedule of Rates of the Contract are
intended to provide for works duly and properly completed in accordance
with the General and Special (if any) Conditions of the Contract and the
Specifications and drawings together with such enlargements, extensions,
diminutions, reductions, alterations or additions as may be ordered in terms
of Clause 42 of these conditions and without prejudice to the generality
thereof and shall be deemed to include and cover superintendence and
labour, supply, including full freight of materials, stores, patterns, profiles,
moulds, fittings, centerings, scaffolding, shoring props, timber, machinery,
barracks, tackle, roads, pegs, posts, tools and all apparatus and plant
required on the works, except such tools, plant or materials as may be
specified in the contract to be supplied to the Contractor by the Railway, the
erection, maintenance and removal of all temporary works and buildings, all
watching, lighting, bailing, pumping and draining, all prevention of or
compensation for trespass, all barriers and arrangements for the safety of
the public or of employees during the execution of works, all sanitary and
medical arrangements for labour camps as may be prescribed by the
Railway, the setting of all work and of the construction, repair and upkeep
22.1 No No Not Allowed
of all centre lines, bench marks and level pegs thereon, site clearance, all
fees duties, royalties, rent and compensation to owners for surface damage
or taxes and impositions payable to local authorities in respect of land,
structures and all material supplied for the work or other duties or expenses
for which the Contractor may become liable or may be put to under any
provision of law for the purpose of or in connection with the execution of the
contract and all such other incidental charges or contingencies as may
have been specially provided for in the Specifications. However, if rates of
existing GST or cess on GST for Works Contract is increased or any new
tax /cess on Works Contract is imposed by Statute after the date of opening
of tender but within the original date of completion/date of completion
extended under clause 17 & 17A of GCC-2018 and the Contractor
thereupon properly pays such taxes/cess, the Contractor shall be
reimbursed the amount so paid. Further, if rates of existing GST or cess on
GST for Works Contract is decreased or any tax/cess on Works Contract is
decreased / removed by Statute after the date of opening of tender, the
reduction in tax amount shall be recovered from Contractor's bills/Security
Deposit or any other dues of Contractor with the Government of India.
1)Rates for Extra Items of Works: Any item of work carried out by the
Contractor on the instructions of the Engineer which is not included in the
accepted Schedules of Rates shall be executed at the rates set forth in the
"Schedule of Rates of Railway" modified by the tender percentage, and for
such items not contained in the latter, at the rate agreed upon between the
Engineer and the Contractor before the execution of such items of work
and the Contractors shall be bound to notify the Engineer at least seven
days before the necessity arises for the execution of such items of works
23 that the accepted Schedule of Rates does not include rate or rates for the No No Not Allowed
extra work involved. The rates payable for such items shall be decided at
the meeting to be held between the Engineer and Contractor, in as short a
period as possible after the need for the special item has come to the
notice. In case the Contractor fails to attend the meeting after being notified
to do so or in the event of no settlement being arrived at, the Railway shall
be entitled to execute the extra works by other means and the Contractor
shall have no claim for loss or damage that may result from such
procedure.
(2)Provided that if the Contractor commences work or incurs any
expenditure in regard thereto before the rates as determined and agreed
upon as lastly hereuntofore-mentioned, then and in such a case the
Contractor shall only be entitled to be paid in respect of the work carried
out or expenditure incurred by him prior to the date of determination of the
23.1 rates as aforesaid according to the rates as shall be fixed by the Engineer. No No Not Allowed
However, if the Contractor is not satisfied with the decision of the Engineer
in this respect, he may appeal to the Chief Engineer within 30 days of
getting the decision of the Engineer, supported by analysis of the rates
claimed. The Chief Engineer's decision after hearing both the parties in the
matter would be final and binding on the Contractor and the Railway.
(1)Handing over of Works: The Contractor shall be bound to hand over the
works executed under the contract to the Railway complete in all respects
to the satisfaction of the Engineer. The Engineer shall determine the date
on which the work is considered to have been completed, in support of
24 which his certificate shall be regarded as sufficient evidence for all No No Not Allowed
purposes. The Engineer shall determine from time to time, the date on
which any particular section of the work shall have been completed, and
the Contractor shall be bound to observe any such determination of the
Engineer.
(2)Clearance of Site on Completion: On completion of the works, the
Contractor shall clear away and remove from the site all constructional
plant, surplus materials, rubbish and temporary works of every kind and
leave the whole of the site and works clean and in a workman like condition
to the satisfaction of the Engineer. No final payment in settlement of the
accounts for the works shall be paid, held to be due or shall be made to
the, Contractor till, in addition to any other condition necessary for final
payment, site clearance shall have been affected by him, and such
24.1 No No Not Allowed
clearance may be made by the Engineer at the expense of the Contractor
in the event of his failure to comply with this provision within 7 days after
receiving notice to that effect. Should it become necessary for the Engineer
to have the site cleared at the expenses of the Contractor, the Railway shall
not be held liable for any loss or damage to such of the Contractor's
property as may be on the site and due to such removal there from which
removal may be affected by means of public sales of such materials and
property or in such a way as deemed fit and convenient to the Engineer.
Modification to Contract to be in Writing: In the event of any of the
provisions of the contract required to be modified after the contract
documents have been signed, the modifications shall be made in writing
and signed by the Railway and the Contractor and no work shall proceed
under such modifications until this has been done. Any verbal or written
25 arrangement abandoning, modifying, extending, reducing or supplementing No No Not Allowed
the contract or any of the terms thereof shall be deemed conditional and
shall not be binding on the Railway unless and until the same is
incorporated in a formal instrument and signed by the Railway and the
Contractor, and till then the Railway shall have the right to repudiate such
arrangements.
(1)Powers of Modification to Contract: The Engineer on behalf of the
Railway shall be entitled by order in writing to enlarge or extend, diminish or
reduce the works or make any alterations in their design, character
position, site, quantities, dimensions or in the method of their execution or
in the combination and use of materials for the execution thereof or to
26 No No Not Allowed
order any additional work to be done or any works not to be done and the
Contractor will not be entitled, to any compensation for any
increase/reduction in the quantities of work but will be paid only for the
actual amount of work done and for approved materials supplied against a
specific order.
(2)(i) Unless otherwise specified in the special conditions of the contract,
the accepted variation in quantity of each individual item of the contract
26.1 No No Not Allowed
would be upto 25% of the quantity originally contracted, except in case of
foundation work.
(ii) The Contractor shall be bound to carry out the work at the agreed rates
26.2 and shall not be entitled to any claim or any compensation whatsoever upto No No Not Allowed
the limit of 25% variation in quantity of individual item of works.
(iii) In case an increase in quantity of an individual item by more than 25%
26.3 of the agreement quantity is considered unavoidable, then same shall be No No Not Allowed
executed at following rates
(a)Quantities operated in excess of 125% but upto 140% of the agreement
26.3.1 quantity of the concerned item, shall be paid at 98% of the rate awarded for No No Not Allowed
that item in that particular tender;
(b)Quantities operated in excess of 140% but upto 150% of the agreement
26.3.2 quantity of the concerned item shall be paid at 96% of the rate awarded for No No Not Allowed
that item in that particular tender;
Provisions of Payments of Wages Act: The Contractor shall comply with the
provisions of the Payment of Wages Act, 1936 and the rules made
thereunder in respect of all employees employed by him either directly or
through petty Contractors or sub-contractors in the works. If in compliance
with the terms of the contract, the Contractor directly or through petty
Contractors or sub-contractors shall supply any labour to be used wholly or
partly under the direct orders and control of the Engineer whether in
connection with the works to be executed hereunder or otherwise for the
purpose of the Engineer, such labour shall nevertheless be deemed to
comprise persons employed by the Contractor and any moneys which may
28 No No Not Allowed
be ordered to be paid by the Engineer shall be deemed to be moneys
payable by the Engineer on behalf of the Contractor and the Engineer may
on failure of the Contractor to repay such money to the Railways deduct the
same from any moneys due to the Contractor in terms of the contract. The
Railway shall be entitled to recover the same from Contractor's
bills/Security Deposit or any other dues of Contractor with the Government
of India all moneys paid or payable by the Railway by way of compensation
of aforesaid or for costs of expenses in connection with any claim thereto
and the decision of the Engineer upon any question arising out of the effect
or force of this Clause shall be final and binding upon the Contractor.
28.1 A.Provisions of Contract Labour (Regulation and Abolition) Act, 1970: No No Not Allowed
A.(1)The Contractor shall comply with the provision of the contract labour
(Regulation and Abolition) Act, 1970 and the Contract labour (Regulation
28.1.1 and Abolition) Central Rules 1971 as modified from time to time, wherever No No Not Allowed
applicable and shall also indemnify the Railway from and against any
claims under the aforesaid Act and the Rules.
A.(2)The Contractor shall obtain a valid license under the aforesaid Act as
modified from time to time before the commencement of the work and
28.1.2 No No Not Allowed
continue to have a valid license until the completion of the work. Any failure
to fulfill the requirement shall attract the penal provision of the Act.
A.(3)The Contractor shall pay to the labour employed by him directly or
through sub-contractors the wages as per provision of the aforesaid Act
and the Rules wherever applicable. The Contractor shall notwithstanding
28.1.3 the provisions of the contract to the contrary, cause to be paid the wages to No No Not Allowed
labour, indirectly engaged on the works including any engaged by sub-
contractors in connection with the said work, as if the labour had been
immediately employed by him.
A.(4)In respect of all labour directly or indirectly employed in the work for
performance of the Contractor's part of the contract, the Contractor shall
28.1.4 No No Not Allowed
comply with or cause to be complied with the provisions of the aforesaid Act
and Rules wherever applicable.
A.(5)In every case in which, by virtue of the provisions of the aforesaid Act
or the rules, the Railway is obliged to pay any amount of wages to a
workman employed by the Contractor or his sub-contractor in execution of
the work or to incur any expenditure on account of the contingent, liability of
the Railway due to the Contractor's failure to fulfill his statutory obligations
under the aforesaid Act or the rules, the Railway will recover from the
Contractor, the amount of wages so paid or the amount of expenditure so
incurred and without prejudice to the rights of the Railway under the
Section 20, Sub-Section (2) and Section 2, Sub-Section (4) of the aforesaid
28.1.5 Act, the Railway shall be at liberty to recover such amount or part thereof No No Not Allowed
from Contractor's bills/Security Deposit or any other dues of Contractor with
the Government of India. The Railway shall not be bound to contest any
claim made against it under Sub-Section (1) of Section 20 and Sub-Section
(4) of Section 21 of the aforesaid Act except on the written request of the
Contractor and upon his giving to the Railway full security for all costs for
which the Railway might become liable in contesting such claim. The
decision of the Chief Engineer regarding the amount actually recoverable
from the Contractor as stated above shall be final and binding on the
Contractor.
(iii)(c): The Railway shall submit its defence statement and counter
30.6 claim(s), if any, within a period of 60 days of receipt of copy of claims from No No Not Allowed
Tribunal, unless otherwise extension has been granted by Tribunal
(iii)(d): Place of Arbitration: The place of arbitration would be within the
geographical limits of the Division of the Railway where the cause of action
30.7 No No Not Allowed
arose or the Headquarters of the concerned Railway or any other place
with the written consent of both the parties.
(iv): No new claim shall be added during proceedings by either party.
However, a party may amend or supplement the original claim or defense
30.8 No No Not Allowed
thereof during the course of arbitration proceedings subject to acceptance
by Tribunal having due regard to the delay in making it.
(v): If the Contractor(s) does/do not prefer his/their specific and final claims
in writing, within a period of 90 days of receiving the intimation from the
30.9 Railways that the final bill is ready for payment, he/they will be deemed to No No Not Allowed
have waived his/their claim(s) and the Railway shall be discharged and
released of all liabilities under the contract in respect of these claims.
Obligation During Pendency of Arbitration: Work under the contract shall,
unless otherwise directed by the Engineer, continue during the arbitration
proceedings, and no payment due or payable by the Railway shall be
30.10 No No Not Allowed
withheld on account of such proceedings, provided, however, it shall be
open for Arbitral Tribunal to consider and decide whether or not such work
should continue during arbitration proceedings.
30.11 Appointment of Arbitrator: No No Not Allowed
(a) : Appointment of Arbitrator where applicability of section 12 (5) of
30.11.1 No No Not Allowed
Arbitration and Conciliation Act has been waived off:
(a)(i): In cases where the total value of all claims in question added
together does not exceed 1,00,00,000/- (Rupees One Crore), the Arbitral
Tribunal shall consist of a Sole Arbitrator who shall be a Gazetted Officer of
30.11.2 Railway not below Junior Administrative Grade, nominated by the General No No Not Allowed
Manager. The sole arbitrator shall be appointed within 60 days from the
day when a written and valid demand for arbitration is received by General
Manager.
a)(ii): In cases not covered by the Clause 64(3)(a)(i), the Arbitral Tribunal
shall consist of a panel of three Gazetted Railway Officers not below Junior
Administrative Grade or 2 Railway Gazetted Officers not below Junior
Administrative Grade and a retired Railway Officer, retired not below the
rank of Senior Administrative Grade Officer, as the arbitrators. For this
purpose, the Railway will send a panel of at least four (4) names of
Gazetted Railway Officers of one or more departments of the Railway
which may also include the name(s) of retired Railway Officer(s)
empanelled to work as Railway Arbitrator to the Contractor within 60 days
from the day when a written and valid demand for arbitration is received by
the General Manager. Contractor will be asked to suggest to General
Manager at least 2 names out of the panel for appointment as Contractor's
30.11.3 No No Not Allowed
nominee within 30 days from the date of dispatch of the request by
Railway. The General Manager shall appoint at least one out of them as
the Contractor's nominee and will, also simultaneously appoint the balance
number of arbitrators either from the panel or from outside the panel, duly
indicating the 'presiding arbitrator' from amongst the 3 arbitrators so
appointed. General Manager shall complete this exercise of appointing the
Arbitral Tribunal within 30 days from the receipt of the names of
Contractor's nominees. While nominating the arbitrators, it will be
necessary to ensure that one of them is from the Accounts Department. An
officer of Selection Grade of the Accounts Department shall be considered
of equal status to the officers in Senior Administrative Grade of other
departments of the Railway for the purpose of appointment of arbitrator.
a).iii: The serving railway officer working in arbitral tribunal in the ongoing
30.11.4 arbitration cases as per clause 64.(3)(a)(i) and clause 64.(3)(a)(ii) above, No No Not Allowed
can continue as arbitrator in the tribunal even after his retirement.
b): Appointment of Arbitrator where applicability of Section 12 (5) of
30.11.5 No No Not Allowed
Arbitration and Conciliation Act has not been waived off:
b(i) In cases where the total value of all claims in question added together
does not exceed 50,00,000/- (Rupees Fifty Lakh), the Arbitral Tribunal shall
consist of a Retired Railway Officer, retired not below the rank of Senior
Administrative Grade Officer, as the arbitrator. For this purpose, the
Railway will send a panel of at least four (4) names of retired Railway
Officer(s) empanelled to work as Railway Arbitrator duly indicating their
30.11.6 No No Not Allowed
retirement dates to the Contractor within 60 days from the day when a
written and valid demand for arbitration is received by the General
Manager. Contractor will be asked to suggest to General Manager at least
2 names out of the panel for appointment as arbitrator within 30 days from
the date of dispatch of the request by Railway. The General Manager shall
appoint at least one out of them as the arbitrator.
b(ii) In cases where the total value of all claims in question added together
exceed 50,00,000/- (Rupees Fifty Lakh), the Arbitral Tribunal shall consist
of a Panel of three (3) retired Railway Officer, retired not below the rank of
Senior Administrative Grade Officer, as the arbitrators. For this purpose,
the Railway will send a panel of at least four (4) names of retired Railway
Officer(s) empanelled to work as Railway Arbitrator duly indicating their
retirement date to the Contractor within 60 days from the day when a
written and valid demand for arbitration is received by the General
Manager. Contractor will be asked to suggest to General Manager at least
30.11.7 2 names out of the panel for appointment as Contractor's nominee within No No Not Allowed
30 days from the date of dispatch of the request by Railway. The General
Manager shall appoint at least one out of them as the Contractor's nominee
and will, also simultaneously appoint the balance number of arbitrators
either from the panel or from outside the panel, duly indicating the
'Presiding Arbitrator' from amongst the 3 arbitrators so appointed. General
Manager shall complete this exercise of appointing the Arbitral Tribunal
within 30 days from the receipt of the names of Contractor's nominees.
While nominating the arbitrators, it will be necessary to ensure that one of
them has served in the Accounts Department.
c)(i): If one or more of the arbitrators appointed as above refuses to act as
arbitrator, withdraws from his office as arbitrator, or vacates his/their
office/offices or is/are unable or unwilling to perform his functions as
arbitrator for any reason whatsoever or dies or in the opinion of the
30.11.8 General Manager fails to act without undue delay, the General Manager No No Not Allowed
shall appoint new arbitrator/arbitrators to act in his/their place in the same
manner in which the earlier arbitrator/arbitrators had been appointed. Such
re-constituted Tribunal may, at its discretion, proceed with the reference
from the stage at which it was left by the previous arbitrator (s).
(c) (ii): (a) The Arbitral Tribunal shall have power to call for such evidence
by way of affidavits or otherwise as the Arbitral Tribunal shall think proper,
and it shall be the duty of the parties hereto to do or cause to be done all
30.11.9 No No Not Allowed
such things as may be necessary to enable the Arbitral Tribunal to make
the award without any delay. The proceedings shall normally be conducted
on the basis of documents and written statements.
c.ii(b) Before proceeding into the merits of any dispute, the Arbitral Tribunal
shall first decide and pass its orders over any plea submitted/objections
raised by any party, if any, regarding appointment of Arbitral Tribunal,
validity of arbitration agreement, jurisdiction and scope of the Tribunal to
deal with the dispute (s) submitted to arbitration, applicability of time
30.11.10 No No Not Allowed
'limitation' to any dispute, any violation of agreed procedure regarding
conduct of the arbitral proceedings or plea for interim measures of
protection and record its orders in day to day proceedings. A copy of the
proceedings duly signed by all the members of tribunal should be provided
to both the parties.
(vii) If at any time, any material or tool which the contractor would normally
have to arrange for himself for execution of the work is supplied by the
Railway either at the contractor's request or sub motto in order to prevent
possible delay in the execution of the work due to contractor's inability to
39.7 make adequate arrangements for the supply thereof or otherwise, such No No Not Allowed
materials or tools will be made available to the contractor in the Railway's
stores. All handling thereof will be the contractor's responsibility. Recovery
of the cost of such supply will be made from the contractor's bill as per
extent rules of the Railway.
(viii) If the material is however not available in Railway stock or the Railway
decides not to supply the same, whatever be the reason, the Railway shall
39.8 No No Not Allowed
not be bound to arrange for the supply nor will this fact be accepted as an
excuse for delay in the execution of the work.
(ix) The variation of quantity of work up to 25% shall in no degree affect the
validity of the contract and shall be performed by the contractor as provided
therein and be subject to the same conditions, stipulations and obligations
39.9 No No Not Allowed
originally included and approved for in specifications and drawings and the
amount to be paid thereof shall be calculated in accordance with the
accepted rates of the schedule.
(x) In the event of any reduction in the quantity of work to be executed for
any reason whatsoever the contractor shall not be entitled to any
39.10 No No Not Allowed
compensation but shall be paid only for the actual amount of work done in
accordance with the accepted rate of the schedule.
(xi) The contractor is bound to notify the Engineer at least seven days
39.11 before the necessity for the execution of any item in excess of 25% of the No No Not Allowed
quantity provided in the agreement.
(xii) In case the contractor fails to attend the meeting after being notified to
do so or in the event of no agreement being arrived at the Railway shall be
39.12 No No Not Allowed
entitled to execute the extra work by other means and the contractor shall
have no claim for loss or damage that may result from such procedure.
(xiii) The contractor has to return any cut pieces of wire, cables, rails etc.
that may be left out and any surplus materials from the work and other
39.13 No No Not Allowed
packing materials that might have been handed over to him. They shall be
taken over by the Railway's representative.
(xiv) The contractor shall take proper written acknowledgement from the
39.14 No No Not Allowed
Engineer's representative for all the materials returned by him.
(xv) All tools that are required by the contractor for the purpose of
transportation of materials, digging, concreting, welding etc. shall be
brought by the contractor himself. This shall include spare parts, fuel, and
39.15 No No Not Allowed
consumable stores. The rates quoted by the contractor shall be deemed to
be inclusive of all charges for such items and inclusive of labour required to
ensure efficient and methodical execution of work.
(xvi) Till the installation is completed and handed over in all respects to the
Railway Engineer and operating department for safe trains working, the
contractor shall be responsible for the equipment installed. However, no
installation should be commissioned without the same being taken over by
the Railway staff after proper testing of the equipment. For this purpose,
39.16 No No Not Allowed
the Railway Engineer will immediately after commissioning of the
equipment give in writing a list of deficiencies to be put right to the
contractor. Where disconnection of points, circuits is involved to put right
the deficiencies, such work shall be done by the contractor only under the
supervision of the Railway supervisory staff.
40 Consignee: The consignee for the Work will be as under: SSE/Sig/BSB No No Not Allowed
Special Conditions
(i)It shall be open to the Contractor to take specific objection to test checks of
any recorded measurement within 7 days of date of such test checks. Any re-
test check done by the concerned Railway's authority in the presence of the
2.4.1 Contractor or in his absence after due notice given to him in consequent of No No Not Allowed
objection made by the Contractor shall be final and binding on the Contractor
and no claim whatsoever shall thereafter be entertained regarding the
accuracy and classification of the measurements.
(ii)If an objection raised by the Contractor is found by the Engineer to be
2.4.2 incorrect the Contractor shall be liable to pay the actual expenses incurred in No No Not Allowed
measurements.
(b) Incorrect measurement, actions to be taken: If in case during test check or
otherwise, it is detected by the Engineer that agency has claimed any
2.5 exaggerated measurement or has claimed any false measurement for the No No Not Allowed
works which have not been executed; amounting to variation of 5% or more of
claimed gross bill amount, action shall be taken as following:
(i)On first occasion of noticing exaggerated/ false measurement, Engineer
2.5.1 No No Not Allowed
shall impose a penalty of 10% of claimed gross bill value.
(ii)On any next occasion of noticing any exaggerated/false measurement,
railway shall impose penalty of 15% of claimed gross bill value. In addition the
2.5.2 facility of recording of measurements by Contractor as well as release of No No Not Allowed
provisional payment shall be withdrawn. Once withdrawn, measurements shall
be done by railway as per GCC-2018 clause 45(i) above.
3 MODE OF PAYMENT: - No No Not Allowed
3.1 Payment for those items which involve both " Supply and Installation" : No No Not Allowed
(i) 80% of the cost of schedule item will be paid on receipt of materials at the
nominated stores depot duly inspected by inspecting authority subject to the
3.1.1 No No Not Allowed
furnishing of Inspection certificates, receipt certificate, Challans and all other
relevant documents as per rule.
3.1.2 (ii)10% of cost of schedule item will be paid after the installation of materials. No No Not Allowed
(iii) Balance 10% of the cost of material will be paid after the successful
3.1.3 commissioning of the work/part of work(i.e. commissioning of work at No No Not Allowed
individual station).
3.2 For those items involving "Supply only" : No No Not Allowed
(i) 90% of the cost of the material supplied will be paid on receipt of materials
3.2.1 at the nominated stores duly inspected by the inspecting authority subject to No No Not Allowed
furnishing of Inspection certificate.
(ii) Balance 10% of the cost of materials supplied will be paid after the
3.2.2 successful commissioning of the work/part of work(i.e. commissioning of work No No Not Allowed
at individual station).
3.3 For those items involving "Designing/Installation/Erection only": No No Not Allowed
3.3.1 (i) 90% of the cost will be paid after completion of activity/part of activity. No No Not Allowed
(ii) Balance 10% cost will be paid after the successful commissioning of the
3.3.2 No No Not Allowed
work/part of the work(i.e. commissioning of work at individual station)
No additional charges will be paid to the contractor for transporting to and
3.4 from stores depot of Railway to the site of work including Railway material, if No No Not Allowed
any.
Necessary RDSO, IRS/TEC/DOT specification/drawing, if any required shall
3.5 No No Not Allowed
be obtained by the tenderer at his own cost.
4 INSPECTION :- No No Not Allowed
a) Contractor shall submit call letter for inspection to consignee 7 ( Seven)
4.1 No No Not Allowed
days in advance with an intimation to Sr. DSTE, N.E. Railway , VARANASI ,
b) Contractor shall produce all other related materials required for the work at
4.2 site at his own cost for inspection by authorized representative of engineer-in- No No Not Allowed
charge.
c) All the materials inspected and passed shall be marked suitably by the
inspecting official and are to be kept under contractor custody which will be
4.3 used for execution only. However, Railway reserves the right to reject any No No Not Allowed
materials, if found spoiled/damaged during transportation, for which the
contractor shall replace at his cost within 15 days of detection.
d) Any materials reject by the inspecting official due to not being as per the
specification or not in proper condition, the same is to be removed by the
4.4 No No Not Allowed
contractor within 7 days at his cost. For this the decision of inspecting official
shall final and binding on the contractor.
In case the successful is not liable to be registered under
CGST/IGST/UTGST/SGST Act, the railway shall deduct the applicable GST
5 No No Not Allowed
from his/their under reverse charge mechanism (RCM) and deposit the same
to the concerned authority.
6 Conditions for Letter of Credit (LC) arrangement. No No Not Allowed
(i)For all the tenders having advertised cost of Rs 10 lakh or above, the
6.1 contractor shall have the option to take payment from Railways through a No No Not Allowed
letter of credit (LC) arrangement.
(ii) This option of taking payment through LC arrangement has to be
exercised in IREPS (Indian Railway Electronic Procurement System the e-
6.2 application on which tenders are called by Railways) by the tenderer at the No No Not Allowed
time of bidding itself, and the tenderer shall affirm having read over and
agreed to the terms and conditions of the LC option.
6.3 (iii)The option so exercised, shall be an integral part of the bidder's offer. No No Not Allowed
(iv)The above option of taking payment through LC arrangement, once
6.4 exercised by tenderer at the time of bidding, shall be final and no change shall No No Not Allowed
be permitted, thereafter, during execution of contract.
(v)In case tenderer opts for payment through LC, following shall be the
6.5 No No Not Allowed
procedure to deal release of payment through LC:
6.5.1 (a) The LC shall be a sight LC No No Not Allowed
(b)The contractor shall select his Advising/Negotiating bank for LC. The
6.5.2 incidental cost towards issue of LC and its operation thereof shall be borne by No No Not Allowed
the contractor.
(c)SBI, New Delhi, Main Branch will be the nodal branch for issue of LCs
based on online requests received from Railway Accounts Units for tenders
opened in financial year 2018-19. SBI branches where the respective Railway
Accounts Office has its Account (local SBI branch) will be the
6.5.3 No No Not Allowed
issuance/reimbursing branch for LC issued under this arrangement. The Bank
shall remain same for this tender till completion of contract. The incidental
cost @ 0.15% per annum of LC value, towards issue of LC and operation
thereof shall be borne by the contractor and shall be recovered from his bills.
(d)The LC shall be opened initially for duration of 180 to 365 days in
consultation with contractor. The LC shall be extended time to time as per the
progress of the contract, on the request of the contractor. The value of LC to
6.5.4 No No Not Allowed
be opened initially as well as extended thereafter shall be finalised by the
engineer in consultation with the contractor on the basis of expected progress
of work.
(e)The LC terms and conditions shall inter-alia indemnify and save harmless
the Railway from and against all losses, claims and demands of every nature
and description brought or recovered against the Railways by reason of any
6.5.5 No No Not Allowed
act or omission of the contractor, his ,agents or employees, in relation to the
Letter of Credit (LC). All sums payable/borne by Railways on this account
shall be considered as reasonable compensation and paid by contractor.
(f) The LC terms and conditions shall inter-alia provide that Railways will issue
a Document of Authorisation (format enclosed as Annexure 2) after passing
6.5.6 No No Not Allowed
the bill for completed work, to enable contractor to claim the authorized
amount from their bank.
(g)The acceptable, agreed upon document for payments to be released
6.5.7 No No Not Allowed
under the LC shall be the Document of Authorisation.
(h)The Document of Authorisation shall be issued by Railway Accounts Office
6.5.8 No No Not Allowed
against each bill passed by Railways.
(i)On issuance of Document of Authorisation, a copy of Document of
Authorisation shall be posted on IREPS for download by the contractor. A
6.5.9 No No Not Allowed
digitally signed copy of Document of Authorisation shall also be sent by
Railway Accounts Office to Railway's bank (Local SBI Branch).
(j)The contractor shall take print out of the Document of Authorisation
available on IREPS and present his claim to his bank (advising Bank) for
6.5.10 No No Not Allowed
necessary payments as per LC terms and conditions. The claim shall
comprise of copy of Document of Authorisation, Bill of Exchange and Bill.
(ii)Extension for Delay not due to Railway or Contractor: If in the opinion of the
Engineer, the progress of work has any time been delayed by any act or
neglect of Railway's employees or by other Contractor employed by the
Railway under Sub-Clause (4) of Clause 20 of GCC-2018 or in executing the
work not forming part of the contract but on which Contractor's performance
necessarily depends or by reason of proceeding taken or threatened by or
dispute with adjoining or to neighbouring owners or public authority arising
otherwise through the Contractor's own default etc. or by the delay authorized
by the Engineer pending arbitration or in consequences of the Contractor not
having received in due time necessary instructions from the Railway for which
he shall have specially applied in writing to the Engineer or his authorized
representative then upon happening of any such event causing delay, the
7.1.2 Contractor shall immediately give notice thereof in writing to the Engineer No No Not Allowed
within 15 days of such happening, but shall nevertheless make constantly his
best endeavours to bring down or make good the delay and shall do all that
may be reasonably required of him to the satisfaction of the Engineer to
proceed with the works. The Contractor may also indicate the period for which
the work is likely to be delayed and shall be bound to ask for necessary
extension of time. The Engineer on receipt of such request from the
Contractor shall consider the same and shall grant such extension of time as
in his opinion is reasonable having regard to the nature and period of delay
and the type and quantum of work affected thereby. No other compensation
shall be payable for works so carried forward to the extended period of time;
the same rates, terms and conditions of contract being applicable as if such
extended period of time was originally provided in the original contract itself.
(iii)Extension for Delay due to Railways: In the event of any failure or delay by
the Railway to hand over the Contractor possession of the lands necessary
for the execution of the works or to give the necessary notice to commence
the works or to provide the necessary drawings or instructions or any other
7.1.3 delay caused by the Railway due to any other cause whatsoever, then such No No Not Allowed
failure or delay shall in no way affect or vitiate the contract or alter the
character thereof or entitle the Contractor to damages or compensation
therefor, but in any such case, the Railway may grant such extension or
extensions of the completion date as may be considered reasonable.
B-Extension of Time for delay due to Contractor: (i) With liquidated Damage
(LD): The time for the execution of the work or part of the works specified in
the contract documents shall be deemed to be the essence of the contract
and the works must be completed not later than the date(s) as specified in the
contract. If the Contractor fails to complete the works within the time as
specified in the contract for the reasons other than the reasons specified in
Clause 17 and 17-A, the Railway may, if satisfied that the works can be
completed by the Contractor within reasonable short time thereafter, allow the
Contractor for further extension of time (Proforma) as the Engineer may
decide. On such extension the Railway will be entitled without prejudice to any
other right and remedy available on that behalf, to recover from the
Contractor as agreed damages and not by way of penalty for each week or
part of the week, a sum calculated at the following rates of the contract value
of the works. For the purpose of this Clause, the contract value of the works
shall be taken as value of work as per contract agreement including any
supplementary work order/contract agreement issued. Provided also, that the
total amount of liquidated damages under this condition shall not exceed 5%
of the contract value or of the total value of the item or groups of items of
work for which a separate distinct completion period is specified in the
7.2 No No Not Allowed
contract. S.No. Duration of extension of time under Clause 17-B of GCC-2018
Rate of Penalty (i)Up to Twenty percent of original period of completion
including period of extension of DOC granted under Section 17A(i)As decided
by Engineer, between 0.01% to 0.10% of contract value for each week or part
of the week (ii)Above Twenty percent but upto Thirty percent of original period
of completion including period of extension of DOC granted under Section
17A(i)0.20% of contract value for each week or part of the week (iii)Above
Thirty percent but upto Forty percent of original period of completion including
period of extension of DOC granted under Section 17A(i)0.30% of contract
value for each week or part of the week (iv)Above Forty percent of original
period of completion including period of extension of DOC granted under
Section 17A(i)0.50% of contract value for each week or part of the week
Provided further, that if the Railway is not satisfied that the works can be
completed by the Contractor and in the event of failure on the part of the
contractor to complete the work within further extension of time allowed as
aforesaid, the Railway shall be entitled without prejudice to any other right or
remedy available in that behalf, to appropriate the contractor's Security
Deposit and rescind the contract under Clause 62 of these Conditions,
whether or not actual damage is caused by such default.
8 Warranty: No No Not Allowed
i) The contractor shall guarantee satisfactory working of the entire installation
8.1 with all its equipment erected by them for a period of 12 months from the date No No Not Allowed
of commissioning of the work.
(ii) The contractor shall warrant that every thing to be furnished hereunder
shall be free from all latent and patent defects and faults in materials,
workmanship and manufacture and shall be of the highest grade and
8.2 consistent with the established and generally accepted standards for No No Not Allowed
materials of the type ordered and in full conformity with the contract
specifications, drawings or samples, any and shall if operable, operate
properly
(iii) The warranty shall survive inspection of payment of or/and acceptance of
the goods, but shall expire 12 months from the date of placing in service as
8.3 referred to in above clause. Any approval or acceptance by the Railway of the No No Not Allowed
stores or of the materials incorporated herein shall not in any way limit the
Contractor's liability
(iv) During the period of warranty the contractor shall remain responsible to
arrange replacement and for setting right at his own cost any equipment
installed by him which is of a defective material manufacture or design or
8.4 becomes unworkable due to any cause what-so-ever. The decision of the No No Not Allowed
DRM (S&T) BSB, N. E. Railway in this regard to direct the contactor to attend
to any damage or defect in work or arrange replacement of any part thereof
shall be final and binding on the contractor.
(v) The contractor shall, if required, replace or repair the goods or such
portion thereof as is rejected by the Railway, free of cost at the ultimate
8.5 destination or at the opinion of the Railway contractor shall pay to the Railway No No Not Allowed
value thereof at the contract price and such other expenditure and damages
as may arise by reason of the breach of the conditions herein specified.
(vi) All replacements and repairs that the Railway shall call upon the
contractor to deliver or perform under this warranty shall be delivered and
performed by the contractor promptly and satisfactorily. If the contractor so
8.6 desired the replaced parts can be taken over by him or his representative for No No Not Allowed
disposal as he deems fit within period of 3 months from the date of
replacement of goods/parts. At the expiry of this period no claim whatsoever
shall lie on the Railway.
(vii) The decision of the DRM (S&T) BSB, N. E. Railway in regard to
contractor's liability to attend to any damage or defect in work arrange or
8.7 No No Not Allowed
replacement of any part thereof and the amount, if any, payable under this
warranty shall be final binding and conclusive.
9 Inspection and testing of materials: No No Not Allowed
(a) Materials supplied by contractor shall be in accordance with standard
specifications and drawings as approved by the Railway. Inspection of
9.1 No No Not Allowed
materials will be done by the authorized representative of DRM (S&T) BSB, N.
E. Railway at the contractor's premises before dispatch.
(b) If a product, upon arrival at destination does not meet the requirements of
the specification, it may be rejected in spite of any inspection already
9.2 conducted and the decision of DRM (S&T) BSB, N. E. Railway or his nominee No No Not Allowed
shall be final and binding in that regard and the same shall not be called in
question.
(c) The representative appointed for conducting inspection and tests of the
materials supplied by the contractor shall have full powers to reject all or any
9.3 No No Not Allowed
that they may consider to be defective or of inferior in quality or material or
workmanship or design to what is called for in the specification.
9.4 (d) Inspection charges of RDSO / RITES shall be borne by railway. No No Not Allowed
10 Deployment of Qualified Engineers at Work Sites by the Contractor: No No Not Allowed
(i) The contractor shall employ the following technical staff during the
10.1 No No Not Allowed
execution of this work.
(ii) One Graduate Engineer when the cost of work to be executed is Rs.15
10.2 No No Not Allowed
lakhs and above.
(iii) One qualified Diploma holder (Overseer) when the cost of the work to be
10.3 No No Not Allowed
executed is more than Rs.5 lakhs but less than 15 lakhs.
(iv) Technical staff should be available at site whenever required by the
Engineer-in-charge to take instructions. In case contractor fails to employ the
technical staff as aforesaid, he shall be liable to pay a reasonable amount not
10.4 No No Not Allowed
exceeding a sum of Rs.2000/-(Rs. Two thousand only) for each month of
default in case of Graduate Engineer and Rs.1000/- (Rs. One thousand only)
for each month of default in case of Diploma holder (Overseer).
(v) The decision of the Engineer-in-charge as to the period for which the
required technical staff was not employed by the contractor and as the
10.5 No No Not Allowed
reasonableness of the amount to be deducted on this account shall be final
and binding on contractor.
This tender complies with Public Procurement Policy (Make in India) Order 2017, dated 15/06/2017, issued by
Department of Industrial Promotion and Policy, Ministry of Commerce, circulated vide Railway Board letter no.
2015/RS(G)/779/5 dated 03/08/2017 and 27/12/2017.
Designation : Sr.DSTEBSB