Project: Conti'S Bakeshop & Restaurant - SM Bacoor: LOCATION: Unit 134, Upper Ground Floor, SM City Bacoor, Cavite

This Gantt chart provides a project schedule for Conti's Bakery & Restaurant in SM Bacoor over 45 days. It outlines 5 key areas of work - general requirements, civil/architectural, electrical, plumbing and punchlisting. The chart shows the planned timing of tasks such as masonry works, finishes, woodworks and more. It also schedules the manpower including supervisors, foremen, masons, carpenters and other roles needed each day to complete the works on schedule over the 45 day period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
275 views1 page

Project: Conti'S Bakeshop & Restaurant - SM Bacoor: LOCATION: Unit 134, Upper Ground Floor, SM City Bacoor, Cavite

This Gantt chart provides a project schedule for Conti's Bakery & Restaurant in SM Bacoor over 45 days. It outlines 5 key areas of work - general requirements, civil/architectural, electrical, plumbing and punchlisting. The chart shows the planned timing of tasks such as masonry works, finishes, woodworks and more. It also schedules the manpower including supervisors, foremen, masons, carpenters and other roles needed each day to complete the works on schedule over the 45 day period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

GANTT CHART - Project Schedule 17 LEGEND: 6/7/2019

PROJECT : CONTI'S BAKESHOP & RESTAURANT - SM BACOOR Schedule


LOCATION : Unit 134, Upper Ground Floor, SM City Bacoor, Cavite Actual

Total
ITEM ACTIVITY Duration
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 (45days)
I. GENERAL REQUIREMENTS
II CIVIL/ARCHITECTURAL WORKS
A MASONRY WORKS
A.1 CHB Wall construction

A.2 Wall Plastering


B FINISHES
B.1 Wall Finishes

B.2 Floor Finishes

B.3 Paint Finishes


C WOODWORKS
C.1 Ceiling Installation

C.2 Cabinetry
D DOORS AND WINDOWS
D.1 Installation of doors, windows.
III ELECTRICAL WORKS
A Roughing Ins
B Electrical Fixtures
B.1 Installation of lighting fixtures

B.2 Supply and installation of light switches

B.3 Supply and installation of convenience outlets

C Commisioning and testing


IV PLUMBING WORKS
A Roughing Ins

B Installation of plumbing fixtures

C Commisioning and testing

D Installation of fire protection

E Commisioning and testing


V Punchlisting
XIII MANPOWER
Supervisor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Foreman 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Safety Officer / Warehouseman / Time keeper 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Mason 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
Carpenter 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
Welder 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Installer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0 0 0
Electrician 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Plumber 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Painter 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1
Helper 3 3 3 3 3 3 3 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 2 2 2 2
Total 13 13 14 14 14 15 15 17 17 17 17 19 19 19 19 19 19 19 19 19 19 19 18 18 18 18 18 17 17 17 17 17 17 17 14 10 10 10

CONSTRUCTION SCHEDULE
CONTRACTOR : LFD GENCON, INC.
Date: 07 June 2019