A. General Requirements
1. All construction activities within public areas are required to be secured with a LAWA
approved barrier as described in this section. The barricade plan shall be a component of
the Project Site Logistics Plan. The plan shall include directional/way-finding needs and
probable location of any access doors for equipment and crews and fire watch windows
where required. The phasing plan for temporary barricades must be provided as part of
the Project Site Logistics Plan as described below in A2. In some cases, the LAWA Project
Manager may require temporary partition walls to be used during barricade construction.
2. The initial barricade plan is part of the Project Site Logistics Plan and is submitted to the
LAWA Project Manager prior to installation of any enclosure or barrier. Further changes will
be submitted to the LAWA Project Manager for review and approval prior to field changes,
additions and/or removals.
3. The contractor must coordinate enclosures that encompass Automated External Defibrillators
(AED), Fire Pull Boxes, Cameras, Fire Sprinklers, Pay Phones, and Exit Doors with the
LAWA Project Manager at least two weeks in advance of barricade placement.
4. Existing floor and carpet areas beneath panels and within barrier and enclosure areas shall be
protected with Masonite-type board, polyethylene sheeting, cardboard, carpet or other
suitable material.
5. A straight, clean and uniform appearance of all barricades shall be maintained at all times.
Scuffed, dirty, punctured, or discolored barricades shall be cleaned, painted or replaced as
required. Each barrier shall be inspected daily with repairs made immediately. It is the
contractor’s responsibility to maintain the aesthetic integrity of the barricades throughout the
life of the project.
6. Project renderings may be requested for large scale installation on barricades that are visible
to the visiting public. These renderings will be included in various LAWA outlets including,
but not limited to, website information, presentation documents, press releases, and social
media. Renderings submitted for use must satisfy the following conditions:
a. Rendered depictions of people must either depict unrecognizable features so as not to
be identifiable as any specific individual (e.g., “ghosted” images, silhouettes, or blurred
faces are acceptable); or the people in the rendering must consist of stock images
purchased from a reputable CGI vendor.
b. LAWA has the right to refuse any renderings that do not satisfy this requirement.
7. Provide electrical power outlets for any advertising, safety and/or exit signs to be relocated
from their existing locations in or on walls that would be covered by the temporary barricade.
8. The Contractor shall construct barricades with the least possible obstruction and
inconvenience to LAWA, its occupants and the public.
9. Existing signage and lighting systems in operation as the work proceeds shall be maintained
unless otherwise approved by the LAWA Project Manager.
10. Barricades shall neatly adjoin existing walls. Existing finishes shall be protected prior to
installation of partitions. Gaps between existing walls and enclosures shall be 1 ½ inches
maximum. Provide braces as necessary to support enclosure, flush with surface of panels.
11. No unapproved signage shall be affixed to the public side of doors, barricades or fence as
stated in Temporary Signage Standards. No unapproved graphics shall be placed, installed, or
otherwise affixed to the public sides of doors, barricades, or fences. Contractors may propose
graphics for the aforementioned areas, and may present such proposal to the attention of the
Alicia Robertson ([email protected]). The proposal will undergo committee review for
incorporation into the LAWA brand, and if approved production and installation will
commence. The LAWA Project Manager will notify the Contractor of any Airport approved
graphics and messaging.
12. Concerning Unauthorized Work, after NTP, and during all phases of construction, the
Applicant and the Applicant’s contractor must not deviate from the approved plan. The
applicant shall resubmit any changes to the Barricade Plan for approval to the LAWA Project
Manager. If Applicant deviates from the approved plan, it will be considered Unauthorized
Work and subject to remediation at the Applicant’s expense. Please keep in mind that if the
deviations from the approved plans cause an unsafe condition, impacts other Tenants,
Customers, or other construction Projects, the Applicant and the Applicant’s Contractor are
subject to a “Stop Work Notice” until the condition has been remedied.
13. Interior and Exterior windows exposing a construction area to the general public, shall be
covered with Glass Masking Paint applied in an even and smooth coat to entirely cover each
exposed window. Glass Masking Paint like that manufactured by DBox Inc. is acceptable.
Paper and plastic coverings are not acceptable.
B. Interior/Fixed Barricades
1. Shall be constructed of metal studs at 16 inches on center with gypsum board affixed by
means of drywall screws. When possible the barricades should reach and be even along the
ceiling. Ideal barricade installation should extend from floor to ceiling; for instances when the
barricade is precluded from extending floor to ceiling, the top edges of the barricade should
be even throughout the extension of the barricade.
2. When floor to ceiling barricades are not feasible, the Airport Project Team shall review and
approve polyethylene enclosures from the top of the gypsum wall to the ceiling to mitigate
dust exposure to areas outside the work space. The use of polyethylene shall be minimized
except as required for dust control. Plastic sheeting/polyethylene is not used in lieu of
gypsum board and shall not be used to enclose a work zone, only to mitigate dust in an
already acceptably barricaded work area. The top of the wall shall be level horizontally with a
metal strip painted to match for an even finish.
3. The Airport Project Team may approve the use of polyethylene sheeting at the top of the
barricade and continuously at the deck or soffit above the barricade. Polyethylene enclosures
shall be white in color, at least 6 mil thick and fire retardant. Fire rated white tape shall be
used to continuously secure the sheeting. Tape in any other color is not permitted. There shall
be no wrinkles, holes, tears, patch work pieces, shredded sheets or gathered sections.
Polyethylene enclosures shall be supported by framework and be capable of supporting .5 psf
applied over the entire surface of each side, separately.
4. All joints shall be smooth and free from tool marks and ridges. A drywall primer prior to two
coats of flat paint for a Level 4 finish is required.
5. Gypsum board paint color is to match adjacent, existing walls and approved by the Airport
Project Team. Paint shall extend continuously to the next intersection in the wall for a
uniform finish to the existing facility. Barricades shall have 4 inch high vinyl base moldings,
wall color to match adjacent and existing walls and base molding color to match adjacent and
existing moldings.
2. Fire retardant treated plywood fastened to light gauge metal studs or 2 inch by 4 inch fire
retardant treated timber studs with continuous level framing at top and bottom may be used at
curbs and where the LAWA Project Manager deems appropriate.
3. The face of the barricades shall be smooth and free from protrusions with edges and corners
eased with no gaps. Nails, screws and other fasteners shall be installed flush with the face of
the barricade.
4. Paint on barricades shall match existing walls. Paint must be applied in two coats minimum.
Interior barricades shall have four inch high vinyl base moldings, wall color to match
adjacent and existing walls and base molding color to match adjacent and existing moldings.
5. Barricades shall be constructed with integral base or other devices to resist an overturning
moment created by the force of 50 pounds per lineal foot applied horizontally at the height of
3 feet 6 inches perpendicular to the partition for the full length of the partition. Posts and
other ground fastening options should be considered depending on the circumstances of the
area and the scale of the barricade. Any implemented fastening shall not present a trip hazard.
D. Doors
1. All interior and exterior doors leading into construction areas and build outs must be self-
closing, self-locking and open inward towards the construction area.
2. Interior doors shall be a pair of pre-hung and of hollow or solid core with three hinges (1 ½
pair) with levered lock set. Doors shall be painted and framed to prevent warping, and shall
be mounted flush to the barricade walls.
3. Exterior doors shall be a pair of pre-hung hollow or solid core doors or two 4-foot wide
plywood doors, optional to Contractor. One door leaf will be stationary with cane bolt or
similar device to keep door closed when not in use. Operating second door shall have three
hinges (1 ½ pair) with levered lock set. Hardware should match existing hardware.
4. All interior and exterior doors must remain locked at all times. When doors are open for
delivery of materials, the entrance must be staffed to prevent public entry into the
construction area. Cipher Locksets must be attached to the door. Hasp and locks shall not be
used on interior or exterior doors or near the doors. Other methods for securing or locking
the door (i.e., LAXPD-required Cyber Locks, or similar mandates) may be approved on a
case-by-case basis by the LAWA Project Manager.
5. Maintenance, cleaning, painting, patching or replacement of interior and exterior doors, door
frames and hardware is required on a regular basis during the duration of the construction
project.
6. The interior and exterior door signage is a component of Temporary Signage Standards. No
unapproved signage shall be affixed to the public side of the door. If the contractor
determines that additional types of signage are necessary (e.g., “laser in use,” “wet paint,”
“do not enter,” etc.), the CALM Sign Shop should be notified. Contractor shall not affix any
paper or laminated signs of any type.
E. Exterior Fencing
1. Contractor fencing shall be used at exterior construction locations as approved by the LAWA
Project Manager. All fencing installation will be secured or anchored using approved means
and methods at the discretion of the Project Management Team. Two types of fencing may
be feasible depending on the location and conditions. Standard 6 or 8-foot construction
fencing with post buried in the ground are required. Where K-rails or concrete barriers are
used, screened chain link fencing shall be secured atop the barrier in order to reach the
appropriate height. Screened 4-foot chain link fence shall be secured along the top of concrete
barriers. The top of the fence should be uniform and even along the entire length of fence.
2. The screen shall be an 85% closed woven panel made from polypropylene and blue in color.
All edges will be hemmed and grommeted. There shall be no wrinkles, holes, tears, patch
work pieces, shredded sheets or gathered sections in the screen. Wind slits are generally not
needed within the Central Terminal Area. However, if necessary, wind slits should only be
made at the discretion of the CALM Sign Shop.
3. Areas outside of the CTA (i.e. laydown areas) requiring mesh fence shall be green in color
and adhere to the same standards as outlined above in E2.
4. Construction entrances shall be constructed of framed and screened chain linked gates. The
gate width shall be approved by the LAWA Project Manager. Gates shall be chained and
locked at all times.
F. Other Barricades
1. If approved by the LAWA Project Manager the following can be used on a temporary short
term basis:
a. Stanchions with retractable barrier tape;
2. Caution tape is not an approved barrier for any Construction. Caution tape shall only be used
in an emergency situation. If used, caution tape must be replaced within 24-hours with an
Airport approved barricade. No orange cones or other, non-specified barricades are allowed
within passenger areas of the Terminals and/or other public buildings. In an emergency
situation when caution tape is implemented, the tape must be presented neatly and sparingly.
Plastic yellow chain is preferable over any other type of rope or tape.
3. Barricades used on the airfield must have red flashers and comply with the FAA
Specifications and be submitted for review and approval to Airport Operations.