Subject: Procurement of Pre-Stressing Strand (Wires) for our bridge construction project at Aizawl-Mizoram
reg.,
Dear Sir,
We M/s Eco-Protection Engineers Private Limited requires the below noted material for one of construction
project consisting “Construction of Pre-Stressed Bridge for 35m span” at Aizawl-Mizoram.
S.No., Material Description /Property Quantity Confirming IS Code
1. Pre-Stressing Stand(wires) of 12.7mm
diameter 7-Ply Class 2 Uncoated
Stress relieved low relaxation strand 9650 meters (9.0 MT) IS 14268 – 1995.
with Ultimate Tensile Strength of
Single Strand to be not less than 183.7
kN.
Material Estimate Details with reference to Approved Drawings. A cable shall consist of 12 Nos 12.7mm
diameter 7-Ply Class 2 Uncoated Stress relieved low relaxation strand and 19 Nos 12.7mm diameter 7-Ply
Class 2 Uncoated Stress relieved low relaxation strand with Ultimate Tensile Strength of Single Strand to be
not less than 183.7 kN.
Span of the Bridge = 35 meters.
No of Girders = 3 Nos.,
No of Cables/Girder = 5 Nos.,
Actual length
of cables No of
Cable Total
S.No +1m strand Length in meters Weight in kg
Number Nos
per cable
in m
1 1 36.566 19 57 2084.262 1614.88
2 2 36.546 19 57 2083.122 1613.99
3 3 36.53 19 57 2082.21 1613.29
4 4 36.484 19 57 2079.588 1611.25
5 5 36.453 12 36 1312.308 1016.77
SUM 9641.49 7470.18
Therefore,
For 35 m span Quantity of Stand required = 7470.2 kg.
With 15% wastage Steel required = 8591 kg Say 9.00 Metric Ton
1.Cable Duct
For 19T12.7 – 420 mts. DUCT – 98mm (inner dimension).
2.Anchor Wedges – As per revised design requirement (24 additionally required).
3.Anchor Cone – As per revised design requirement.
4.Anchor head – As per revised design requirement.
5.Grout cap – As per revised design requirement.