This document is a checklist for commissioning overhead power lines. It contains: 1) A section listing equipment details like substation, bay, and serial numbers to record. 2) A section for mechanical checks and visual inspections of items like labels and gantry connections. 3) A section detailing electrical tests to perform, including phase sequence checks, impedance tests, earth resistance checks, and insulation resistance tests. It notes the need to arrange line shutdowns if induction voltages prevent safe testing. The checklist is signed off by those completing the commissioning from the CSD, contractor, and transmission & connection contractor teams.

Uploaded by

essam khalil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
256 views2 pages

WI-NG-6460-044 Overhead Lines Commissioning

This document is a checklist for commissioning overhead power lines. It contains: 1) A section listing equipment details like substation, bay, and serial numbers to record. 2) A section for mechanical checks and visual inspections of items like labels and gantry connections. 3) A section detailing electrical tests to perform, including phase sequence checks, impedance tests, earth resistance checks, and insulation resistance tests. It notes the need to arrange line shutdowns if induction voltages prevent safe testing. The checklist is signed off by those completing the commissioning from the CSD, contractor, and transmission & connection contractor teams.

Uploaded by

essam khalil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

NATIONAL GRID

Title: Index Number:

Check List of Overhead Lines Commissioning CL-NG-6460-002-044


Page Number:
1 of 2

1.0 Equipment General Data and Information

Substation
Bay/Panel
Equipment Serial No

2.0 Mechanical check and Visual inspection

Item Description Done Remarks


Before starting the electrical testing of OHL with CSD:
a. Project management department and OHL
maintenance division have confirmed that OHL has
been installed as per design and all mechanical tests
are OK and no swapping in OHL from GIS of two
1. ends with other circuit.
b. All labels for all circuits including gantry and GIS have
been provided and checked by project management
department.
c. CSD double check all labels of OHL from gantry to
GIS of this circuit.

3.0 Electrical Test

Item Description Done Remarks


1. Perform phase sequence / rotation check.
Perform sequence impedance and susceptances tests
2. and mutual impedances (both zero and positive sequence
for double circuits lines
Check tower foot earth resistance as per company
3.
standards.
Check the aircraft warning lights are properly functioning
4. (if applicable).

5. Perform continuity and conductivity test


6. Perform Phase conductor insulation resistance test.
7. In the case of induction voltage inducted from other OHL:
Archiving System Website: http://AMAS
NATIONAL GRID

Title: Index Number:


CL-NG-6460-002-044
Check List of Overhead Lines Commissioning Page Number:
2 of 2

a. Project management department have arranged


shutdown for OHL that cause induction voltage in order
to perform the above mentioned electrical tests.
b. If shutdown is not possible, the mentioned electrical
tests cannot be performed and the CSD is not
responsible for OHLs.