NATIONAL GRID
Title: Index Number:
Check List of Overhead Lines Commissioning CL-NG-6460-002-044
Page Number:
1 of 2
1.0 Equipment General Data and Information
Substation
Bay/Panel
Equipment Serial No
2.0 Mechanical check and Visual inspection
Item Description Done Remarks
Before starting the electrical testing of OHL with CSD:
a. Project management department and OHL
maintenance division have confirmed that OHL has
been installed as per design and all mechanical tests
are OK and no swapping in OHL from GIS of two
1. ends with other circuit.
b. All labels for all circuits including gantry and GIS have
been provided and checked by project management
department.
c. CSD double check all labels of OHL from gantry to
GIS of this circuit.
3.0 Electrical Test
Item Description Done Remarks
1. Perform phase sequence / rotation check.
Perform sequence impedance and susceptances tests
2. and mutual impedances (both zero and positive sequence
for double circuits lines
Check tower foot earth resistance as per company
3.
standards.
Check the aircraft warning lights are properly functioning
4. (if applicable).
5. Perform continuity and conductivity test
6. Perform Phase conductor insulation resistance test.
7. In the case of induction voltage inducted from other OHL:
Archiving System Website: http://AMAS
NATIONAL GRID
Title: Index Number:
CL-NG-6460-002-044
Check List of Overhead Lines Commissioning Page Number:
2 of 2
a. Project management department have arranged
shutdown for OHL that cause induction voltage in order
to perform the above mentioned electrical tests.
b. If shutdown is not possible, the mentioned electrical
tests cannot be performed and the CSD is not
responsible for OHLs.
CSD Contractor T&C Contractor
Name
Sign.