0% found this document useful (0 votes)
19 views1 page

Pradhan Mantri Gram Sadak Yojana General Abstract Package No.: OR-19-694/PMGSY-III/Batch-I

This document is an estimate for road construction and maintenance under the Pradhan Mantri Gram Sadak Yojana (PMGSY) program. The estimate includes Rs. 293.02 for construction of a road from PWD Road to a papermill under Part I. An additional Rs. 120.69 is allocated for maintenance of the same road under Part II. The total estimated cost is Rs. 413.71.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views1 page

Pradhan Mantri Gram Sadak Yojana General Abstract Package No.: OR-19-694/PMGSY-III/Batch-I

This document is an estimate for road construction and maintenance under the Pradhan Mantri Gram Sadak Yojana (PMGSY) program. The estimate includes Rs. 293.02 for construction of a road from PWD Road to a papermill under Part I. An additional Rs. 120.69 is allocated for maintenance of the same road under Part II. The total estimated cost is Rs. 413.71.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PRADHAN MANTRI GRAM SADAK YOJANA

GENERAL ABSTRACT

Package No. : OR-19-694/PMGSY-III/Batch-I


PART - I

1. PWD Road to Papermill Rs. 293.02

Total cost of Part - I = Rs. 293.02

PART - II (MAINTENANCE)

2. PWD Road to Papermill Rs. 120.69

Total cost of Part - II = Rs. 120.69

Total cost of Estimate(Part-I+Part- II) Rs. 413.71

Junior Engineer Asst. Executive Engineer


R.W. Section,Jeypore R.W Sub Division,Jeypore

Executive Engineer Superintending Engineer


R.W Division, Jeypore R.W.S.C. Sunabeda