This document outlines responsibilities for project and business unit teams on a project. It lists 10 key stages of a project including process design, equipment selection, construction, commissioning, and training. For each stage, it assigns deliverables and sign-offs required from both the project and business unit teams to ensure responsibilities are clearly defined and approved.

Uploaded by

Noël Viljoen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
228 views1 page

Project Responsibility Matrix 2018

This document outlines responsibilities for project and business unit teams on a project. It lists 10 key stages of a project including process design, equipment selection, construction, commissioning, and training. For each stage, it assigns deliverables and sign-offs required from both the project and business unit teams to ensure responsibilities are clearly defined and approved.

Uploaded by

Noël Viljoen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT RESPONSIBILITY MATRIX

PROJECT NO & NAME : BUSINESS UNIT:

PROJECTS DEPARTMENT RESPONSIBILITIES BUSINESS UNIT RESPONSIBILITIES

1 EXTERNAL PROCESS DESIGN DELIVERABLE INTERNAL PROCESS DESIGN DELIVERABLE


EQUIPMENT SIZING CALCULATIONS EQUIPMENT SIZING CALCULATIONS
P&ID P&ID
Signature:
OR PROCESS DESIGN APPROVAL DELIVERABLE
APPROVED P&ID

Signature: Signature:

2 MECHANICAL DESIGN DELIVERABLE PLANT LAYOUT APPROVAL DELIVERABLE


PLANT LAYOUT APPVD PLANT LAYOUT
Signature: Signature:
INSTRUMENTATION DESIGN DELIVERABLE INSTRUMENT DESIGN APPROVAL DELIVERABLE

Signature: Signature:
ELECTRICAL DESIGN DELIVERABLE ELECTRICAL DESIGN APPROVAL DELIVERABLE

Signature: Signature:

3 MECHANICAL EQUIPMENT SELECTION DELIVERABLE MECHANICAL EQUIPMENT SELECTION APPROVADELIVERABLE


EQUIPMENT LIST APPVD EQUIPMENT LIST
Signature: Signature:
INSTRUMENT EQUIPMENT SELECTION DELIVERABLE INSTRUMENT EQUIPMENT SELECTION APPROVADELIVERABLE
EQUIPMENT LIST APPVD EQUIPMENT LIST
Signature: Signature:
ELECTRICAL EQUIPMENT SELECTION DELIVERABLE ELECTRICAL EQUIPMENT SELECTION APPROVADELIVERABLE
EQUIPMENT LIST APPVD EQUIPMENT LIST
Signature: Signature:

4 MECHANICAL SPARES SELECTION DELIVERABLE MECHANICAL SPARES PLAN APPROVAL DELIVERABLE


SPARES LIST
Signature: Signature:
INSTRUMENTATION SPARES SELECTION DELIVERABLE INSTRUMENT SPARES PLAN APPROVAL DELIVERABLE
SPARES LIST APPVD SPARES LIST
Signature: Signature:
ELECTRICAL SPARES SELECTION DELIVERABLE ELECTRICAL SPARES PLAN APPROVAL DELIVERABLE
SPARES LIST APPVD SPARES LIST
Signature: Signature:

5 MASTER DATA PREPARATION DELIVERABLE MASTER DATA APPROVAL DELIVERABLE


FUNCTION LOCATIONS APPVD FUNC LOCATION STRUCTURE
BILL OF MATERIALS APPVD BILL OF MATERIALS
SCOPE OF WORK MAINTENANCE PLANS
MAINTENANCE MANUALS
Signature: STATUTORY DOCUMENTATION Signature:

6 QUALITY MANAGEMENT PLAN PREPRATION DELIVERABLE QUAILITY MANAGEMENT PLAN APPROVAL DELIVERABLE
QUALITY MANAGEMENT PLAN APPVD QUALITY MANAGEMENT PLAN

Signature: Signature:

7 MECH CONSTRUCTION MANAGEMENT DELIVERABLE MECHANICAL CONSTRUCTION SIGN OFF DELIVERABLE


C1 SIGN OFF DOCUMENTATION APPVD C1 DOCUMENTATION
Signature: Signature:
INSTR CONSTRUCTION MANAGEMENT DELIVERABLE INSTR CONSTRUCTION SIGN OFF DELIVERABLE
C1 SIGN OFF DOCUMENTATION APPVD C1 DOCUMENTATION
Signature: Signature:
ELECT CONSTRUCTION MANAGEMENT DELIVERABLE ELECTRICAL CONSTRUCTION SIGN OFF DELIVERABLE
C1 SIGN OFF DOCUMENTATION APPVD C1 DOCUMENTATION
Signature: Signature:

8 PROVIDE PROCESS CONTROL PHILOSOPHY DELIVERABLE APPROVE PROCESS CONTROL PHILOSPHY DELIVERABLE
REVIEW AND APPROVE CONTROL PHILOSOPHY AND
ATTEND SOFTWARE FAT
PROVIDE UPDATED CONROL PHILOSPHY
FROM OEM / PLANT PROCESS DESIGN TEAM Signature:

OR
PROVIDE SOFTWARE UPDATE RESOURCE PROVIDE PROCESS CONTROL PHILOSOPHY DELIVERABLE
PROVIDE CONTROL PHILOSOPHY
Signature: ARRANGE SOFTWARE FAT Signature: ATTEND SOFTWARE FAT

9 NEW PLANT RISK ASSESSMENT & SWP DELIVERABLE NEW PLANT RISK ASSESSMENT & SWP DELIVERABLE

PROVIDE MAINTENANCE MANUALS, P&ID, COMPILE RISK ASSESSMENTS AND SWP FOR NEW
PROCESS DESIGN EQUIPMENT

Signature: Signature:

10 OPERATIONS TRAINING SUPPORT DELIVERABLE PROJECT TRAINING PLAN DELIVERABLE

ARRANGE OEM TRAINING AS PER TRAING


PLAN PROJECT TRAINING PLAN & REQUIREMENTS

UPDATE TRACESS
Signature: Signature:

11 HOT COMMISSIONING SUPPORT DELIVERABLE HOT COMMISSIONING DELIVERABLE


A+B PUNCHLIST ITEMS COMPLETE HOT COMMISSIONING PLAN

COMMISSIONING TEAM MANAGEMENT OF HOT COMMISSIONING PROCESS


Signature: Signature: