Gantt Chart, Productivity, Working Time Factor
Gantt Chart, Productivity, Working Time Factor
URP623:PROJECT PLANNING
AND MANAGEMENT
Unit III
Answer
• Factored productivity for Working at height
20-[(1-0.9)*20]-[(1-0.9)*20]-[(1-0.95)*20] = 15 Sqm/Day
Duration= 600 / (15*2)= 20 Days
Painting of a Bridge is being undertaken. The
average productivity of the crew is 25 sq mt/day.
Area of the bridge is 500 sq mt. What is the
estimated duration to complete the painting of
bridge?
Assume the factored productivity are:
Scaffolding and other equipment -0.75, Safety
precautions for working at height -0.4,
Movement of materials -0.8.
Working time factor
• 10 hr workday – productive time ?
• 9am-7pm
• Breaks 11-11:15am 1-1:45pm 4-4:15pm etc. the
effective working time is only 8.5 hours.
• Actual Working hours/Ideal Working hours 8.5/10 =
0.85
• Actual Duration = Ideal Duration/Working time Factor