FGHC Manual
FGHC Manual
www.pumpsgp.com
Horizontal split case Fire pump
FGHC
Contents 1. Symbols used in this document
13. Disposal 13
Warning
Prior to installation, read these installation and
operating instructions. Installation and
operation must comply with local regulations
and accepted codes of good practice.
EN-1
Horizontal split case Fire pump
FGHC
3.2 Handling 3.3 Temporary storage
If the pump is not to be installed and operated soon after
When unloading the pump, lift equally at four or arrival, store it in a clean, dry place with slow, moderate
more points on the base frame. Do not lift by changes in ambient temperature. Protect the pump from
the motor or pump. Do not lift by the flanges or moisture, dust, dirt and foreign bodies. Prior to and
by the eye bolts on the motor. during storage we recommend these precautions:
4. Applications
General Pumps FGHC Horizontal split case Fire pumps are
typically used for
EN-2
Horizontal split case Fire pump
FGHC
5. Operating conditions
A A
5.1 Ambient temperature
Maximum +40°C.
Make sure there is a suitable electricity supply available The expansion joints should be fitted at a minimum distance
for the motor. of 1 to 1.5 flange diameters away from the pump, both on
the suction and the discharge sides. This prevents
6.2 Foundation turbulence in the joints, thus ensuring optimum suction
We recommend that you install the pump on a concrete conditions and minimum pressure drop on the discharge
foundation which is heavy enough to provide permanent side.
and rigid support for the entire pump. The foundation
must be capable of absorbing any vibration, normal At high water velocities (> 2.5 m/s), we recommend you to
strain or shock. As a rule of thumb, the weight of the fit larger expansion joints & connection pipe.
concrete foundation should be 1.5 times the weight of the
pump or unit. For further information on the building of If the pump is installed on a foundation with
the foundation, see section 6.5 Foundation and alignment vibration dampers, fit expansion joints on both
procedure. sides of the pump. The pump must have these
flexible connections both at the discharge side
and the suction side to allow the pump to move
up and down.
EN-3
Horizontal split case Fire pump
FGHC
6.5 Foundation and alignment procedure 1. Lift/jack up the base frame to the final level, 15-25 mm
The foundation and alignment procedure has five steps: above the concrete foundation, and support the base
frame by means of blocks and shims both at the
1. Pouring of foundation foundation bolts and midway between bolts, see fig. 5.
2. Shimming of base frame
3. Preliminary alignment 2. Level the base frame by adding or removing shims under
4. Grouting the base frame, see fig. 5.
5. Final alignment
3. Tighten the foundation bolts nuts against the base frame.
6.5.1 Pouring of foundation Make sure the piping can be aligned to the pump flanges
We recommend the following procedure to ensure a without putting strain on pipes or flanges.
good foundation.
6.5.3 Preliminary alignment
1. Pour the foundation without interruptions to within
15-25 mm of the final level. Use compactors to ensure Before starting work on the pump, make sure
that the concrete is evenly distributed. The top that the electricity supply has been switched
surfaces should be well scored and grooved before the off and that it cannot be accidentally swithched
concrete sets. This provides a bonding surface for the on.
grout.
2. Embed foundation bolts in the concrete as shown in The pump and motor are correctly aligned on the base
fig. 4. Allow enough bolt length to reach through grout, frame from the factory. Some deformation of the base frame
shims, lower base frame, nuts and washers. may occur during transport and it is therefore essential to
check alignment at the installation site prior to final grouting.
Base frame or
vibration damper A flexible coupling will only compensate for minor
Thickness of misalignments and should not be used to compensate for
base frame or excessive misalignment of the pump and motor shafts.
vibration Inaccurate alignment results in vibration and excessive
damper flange
Leveling wedges
wear on the bearings, shaft or wear rings.
15 to 25 mm
allowance for Top of foundation Carry out alignment of motor and pump by placing shims of
grout left rough different thickness under motor and pump, respectively. If
possible, replace several thin shims with one thick shim.
Anchor 4 nos.
EN-4
Horizontal split case Fire pump
FGHC
Base frame
or vibration
damper
Grout
Leveling
wedges
15 to 25 mm or shims
Fig. 6 Checking parallel alignment grout
Top of
foundation
Form work
(rough)
3. Checking angular alignment
Insert a pair of inside calipers or a taper gauge at four
points at 90° intervals around the coupling, see fig. 7.
Angular alignment is correct when the measurements Fig. 8 Sectional view of foundation with foundation
show that all points of the coupling faces are within bolt, grouting and base frame
±0.2 mm of each other.
EN-5
Horizontal split case Fire pump
FGHC
The coupling alignment procedure has four steps: 1. Mount dial gauge (1) in position 90° (3 o’clock) see fig. 9.
2. Make index lines on the two coupling halves, see fig. 9.
1. Parallel alignment - vertically 3. Set the dial gauge pointer to zero, turn motor and pump
2. Parallel alignment - horizontally shaft simultaneously until dial gauge is in position 270°
3. Angular alignment - horizontally (9 o’clock) and check that the index lines are still in line.
4. Angular alignment - vertically. 4. Read dial gauge (1). If the dial gauge shows a deflection
exceeding ±0.2 mm, move the motor sideways until the
1. Parallel alignment - vertically deflection is halves.
5. Set the dial gauge point to zero, turn motor and pump
shaft simultaneously until dial gauge is in position 90°
(3 o’clock) and read dial gauge (1) again.
6. Now the reading should be within the allowable tolerance
of ±0.2 mm. If not - repeat the procedure.
EN-6
Horizontal split case Fire pump
FGHC
7. Piping
Air pocket
7.1 System types
The General Pumps FGHC Horizontal split case Fire pumps
can be installed in two types of system:
Many NPSH (Net Positive Suction Head) problems can • Make sure that liquid flow is evenly distributed to both
be avoided if the suction piping is properly installed. sides of the double suction impellers.
There is always an uneven, turbulent flow through an
• Ensure that pressure losses are minimized and elbow. So if an elbow is installed in the suction pipe
sufficient liquid will flow into the pump. near the pump in a position other than vertical, more
• Make the suction piping is as short in length and as liquid will enter one side of the impeller than the other,
direct as possible, and never smaller in diameter than
see fig. 13. This will result in heavy, unbalanced thrust
the pump suction port.
• Avoid air pockets or turbulence in the suction pipe, loads overheating the bearings, causing rapid wear
see fig. 10. and reducing the hydraulic performance.
EN-7
Horizontal split case Fire pump
FGHC
Water pressure increases here causing Generally recommended suction pipe installations
a greater flow to one side of the
impeller than to the other
Uneven flow
Eccentric
reducer
10 x DN
Avoid high spots, such as loops, as they will collect air and
Fig. 16 Pump installation with suction diffuser (1) throttle the system or lead to uneven pumping.
EN-8
Horizontal split case Fire pump
FGHC
8. Electrical connection 9. Start-up
The electrical connections should be carried out by an The start-up procedure for FGHC pumps has three steps:
authorised electrician in accordance with local
regulations. 1. Pre-start checks, see section 9.1 Pre-start checks.
Before removing the terminal box cover and 2. Starting, see section 9.2 Starting
before any removal/dismantling of the pump, 3. Operating checks, see section 9.3 Operating checks.
make sure that the electricity supply has been
switched off and that it can not be accidently Do not start the pump until you have gone
switched on. through all the pre-start checks.
The operating voltage and frequency are marked on the 9.1 Pre-start checks
nameplate. Pre-start checks has six steps:
Make sure that the motor is suitable for the electricity 1. Bearings
supply of the installation site. 2. Stuffing boxes
3. Pressure gauge
The electrician connections should be carried out as 4. Priming
shown on the motor nameplate or in the wiring diagram 5. Direction of rotation
on the back of the terminal box cover. 6. Operating of valves
Whenever powered equipment is being used in
9.1.1 Bearings
explosive surroundings, the rules and
Check that all bearings are properly lubricated, see
regulations generally or specifically imposed by
section 10.3 Lubrication.
the relevant responsible authorities or trade
organizations must be observed.
9.1.2 Stuffing boxes
8.1 Frequency converter operation Check that the stuffing boxes have been properly
All three-phase motors can be connected to a frequency tightened.
converter.
Does not apply to pumps with mechanical
Note
Frequency converter operation will often expose the shaft seal.
motor insulation system to a heavier load and cause the
motor to be more noisy than usual due to eddy currents 9.1.3 Pressure gauge
caused by voltage peaks. Check that the pressure gauge connection is closed.
EN-9
Horizontal split case Fire pump
FGHC
Open systems where the liquid is below the pump overloaded.
inlet: 4. Measure motor current consumption and compare the
result with the rated current stated on the motor
The suction pipe and the pump must be filled with liquid nameplate. In the event of motor overload, throttle the
and vented before the pump is started. Proceed as discharge isolating valve until the motor is no longer
follows: overloaded.
5. Check bearings for lubrication and temperature.
1. Close the discharge isolating valve and open the Normal temperature is 80°C (176°F). Maximum
isolating valve in the suction pipe. temperature depends on the type of lubrication, see
2. Remove the air vent screw. the lubrication nameplate on the pump.
3. Pour liquid through the vent hole until the suction pipe Stop the pump immediately if any defects are
and the pump are completely filled with liquid. noticed. Do not start the pump unless defects
4. Refit the air vent screw and tighten securely. Caution have been corrected, see section 12. Fault
finding. Report immediately to the supplier if
The suction pipe can to some extent be filled with liquid it is not possible to remedy the defects.
and vented before it is connected to the pump. A priming
device can also be installed before the pump. The operating checks apply not only to the
Note start-up procedure, but should be used when
9.1.5 Direction of rotation checking the pump during normal operation.
Direction of rotation is checked in the following way:
9.4 Operating at reduced flow and/or head
1. Remove coupling pins and check that the motor shaft
can turn freely. Do not operate the pump at a flow below 30% of flow at
2. Start motor briefly to check direction of rotation. The best efficiency point or with the discharge isolating valve
correct direction of rotation is indicated by arrows on closed. Operating the pump in such condition may
the pump housing. involve the risk of the pump being overheated.
The direction of rotation of the pump is not If a pump is operated at reduced head, the flow will
Note increase and the motor will consume more current than
always the same as the flow direction.
normal; this will result in overheating of the motor. In
If direction of rotation is wrong, correct it by such situations, throttle the valve on the discharge side
interchanging two phases in the motor. Check direction either manually or automatically.
of rotation again
3. Reassemble coupling with pins and guards. 9.5 Frequency of starts and stops
EN-10
Horizontal split case Fire pump
FGHC
10. Maintenance For every 10,000 operating hours or every two years,
Before starting work on the pump, make sure • Remove bearing housing from pump.
that the electricity supply has been switched • Remove old grease.
off and that it cannot be accidently switched • Throughly clean bearing housings.
on. • Refill bearings with fresh grease.
• Refit bearing housings in accordance with assembly
10.1 General information instructions.
Routine maintenance is essential to maintain the pump in
a good condition. Ball bearing grease
Use Lithium based grease suitable for temperature from
A high degree of cleanliness should be maintained during -30°C to +140°C.
all maintenance procedures.
11. Frost protection
10.2 Frequency of inspections Pumps which are not being used during periods of frost
Inspections should be carried out in accordance with the should be drained to avoid damage.
routine maintenance chart below.
Drain the pump by loosening the air vent screw at the top
Depending on operation and environmental conditions of the pump housing and by removing the drain plugs
together with a comparison of previous inspections, the from the bottom of the pump housing, see fig. 18.
frequency of inspections may be altered to maintain
satisfactory operation of the pump. Ensure that the escaping water does not cause
injury to persons or damage to the motor or
Every week a. Visually check for leaks.
b. Check for vibrations.
other components.
c. Hand test bearing housing for any In hot-water installations, pay special attention
sign of temperature rise. to the risk of injury caused by scalding hot
water.
Every month Check bearing temperature.
Every 3 months Check whether the grease in the
bearings has hardened.
Every 6 months a. Check shaft for scoring.
b. Check alignment of pump and motor.
c. Check fixing bolts and tighten, if
necessary
d. Check coupling for wear.
Every year a. Check rotating assembly for wear.
b. Check wear ring clearances.
Between regular maintenance inspections, be aware of
signs of motor or pump trouble.
Pump Bearing Do not tighten the air vent screw and refit the drain plug
Pump bearings are lubricated during manufacture and until the pump is to be used again.
prior to delivery.
EN-11
Horizontal split case Fire pump
FGHC
12. Fault finding chart
Before removing the terminal box cover and before any removal/dismantling of the pump, make sure that the
electricity supply has been switched off that it cannot be accidently switched on.
Faults Causes
The pump does not create
Reference numbers to
The pump delivers no
Motor overloaded
enough pressure
Cavitation noise
Pump bearings
much power
overheated
remedies
Vibration
liquid
EN-12
Horizontal split case Fire pump
FGHC
No. Causes Remedy
1. Pump not primed, lack of priming liquid, Fill pump and suction pipe completely with pumped liquid.
incomplete priming.
2. Loss of priming liquid. Mend possible leaks in suction pipe, joints and fittings; vent pump
housing to remove accumulated air.
3. Suction lift/static lift too high. Reduce the difference in height between the water reservoir/water
supply and the pump.
4. Discharge pressure too high. Make sure that valves in discharge pipe are fully open.
5. Speed too low. 1. Make sure the motor receives full voltage.
2. Make sure the frequency is correct.
3. Make sure all phases are connected.
6. Wrong direction of rotation. Compare direction of rotation with directional arrow on pump housing. If
required, change direction of rotation by interchanging two phases in the
motor.
7. Impeller completely clogged. Dismantle pump and clean impeller.
8. Suction pipe partially blocked. Remove any obstructions in the suction pipe.
9. Air leak in suction pipe or flange. Replace or repair defective pipe section or flange.
10. Air leak in stuffing box. Clean flushing channel. Replace stuffing box packing rings, if necessary.
11. Cavitation; insufficient NPSH 1. Increase net positive suction head by placing the pump in a lower
(depending on installation). position.
2. Pressurize suction vessel.
12. Impeller or wear ring worn. Replace impeller and/or wear rings. If necessary, also replace bearings
and shaft.
13. Defective packing rings. Replace packing rings.
14. Non-return valve too small or partially obstructed. Replace or clean non-return valve.
15. Suction pipe not immersed deeply enough. Extend the suction pipe so that the risk of sucking air is eliminated.
16. Impeller diameter too small. Check with factory if a larger impeller can be used; if not, reduce
discharge pipe friction losses. But be careful not to seriously overload
motor.
17. Obstruction in pump housing. Dismantle pump and remove obstruction.
18. Air or gases in liquid. Remove gas or air from pumped liquid. Possibly, see 11 above.
19. The actual duty point of the pump lies to the right Install an orifice plate immediately after the discharge flange. The orifice
of the specified duty point on the pump curve. The plate will raise the system characteristic/increase the counter pressure
result is lower head, higher flow and higher power thus increasing the head and lowering the flow. The size of the orifice
consumption. plate must be adapted so that the pressure corresponds to the required
duty point.
20. Viscosity or specific gravity of pumped liquid is Use larger motor. Consult factory for recommended size. Test liquid for
higher than that of water. viscosity and specific gravity.
21. Shaft bent due to damage. Check deflection of shaft by turning on bearing journals. Total indicator
runout should not exceed 0.05 mm on shaft and 0.1 mm on impeller
wearing surface. Possibly replace shaft.
22. Mechanical failure of bearing and/or impeller. Check bearings and impeller for damage.
Possibly replace bearing or impeller.
23. Misalignment. Realign pump and motor.
24. Electrical defects. Check that volatge and frequency of the electricity supply are correct.
Check for possible defects in the motor.
Check that the motor is properly ventilated.
25. Speed too high. Check that frequency of electricity supply corresponds to frequency
stated on motor nameplate.
26. Foundation not rigid enough. Retighten foundation bolt nuts. Check that foundation was made
according to installation and operating instructions.
27. Lubricating oil/grease dirty or contaminated. 1. Clean bearings and bearing housings according to instruction and
relubricate bearings.
2. Check that the V-ring (extended and two-stage, through-bore versions)
is working properly.
13. Disposal
This product or parts of it must be disposed of in an
environmentally sound way:
1. Use the public or private waste collection service.
EN-13
Horizontal split case Fire pump
FGHC
14. Spare parts list 3032 3016
3014 3033
3031 3001 3006
3011
3007 3004
3017 3002 3013
3012 3010
3003 3020
3018
3005
3029
3009
3028
3008 3023
3015
3021 3024
3022
3026 3027
3025
3030
3019
Sectional drawing
Spare parts list
Part nos. Parts name Part nos. Parts name
3001 Split casing 3018 Water thrower
3002 Impeller 3019 Water plug with 'O' ring
3003 Bearing housing 3020 'O’ ring
3004 Back cover 3021 Cap screw with spring washer
3005 Shaft 3022 Cap screw
3006 Wear ring 3023 Cap screw
3007 Gland 3024 Ball bearing
3008 Internal bearing cover 3025 Key
3009 External bearing cover 3026 Graphite packing
3010 External bearing cover(drive) 3026.1 Mechanical seal
3011 R.H. Nut 3027 Hex nut
3012 L.H. Nut 3028 Key
3013 Shaft sleeve 3029 Grease nipple
3014 Shaft sleeve 3030 Dowel pin
3015 Stud 3031 Hose pipe
3016 Key 3032 Nipple 1/4”-1/8” BSP
3017 Lantern ring 3033 Air cock with ‘O’ ring
Ordering note: While ordering spare parts kindly mention pump type, sr. no., part no, part name, material specification
& quantity in the order. While ordering impeller kindly mention the impeller diameter.
Example: Pump type Sr. No. Part no. Part name Material Impeller dia. Qty.
FGHC 80 300 31012001 3002 Impeller Bronze 300 mm 1 No.
EN-14
Note
EN-15
Note
EN-16
Warranty Certificate
General Pumps warrants this product to be free from any defects in material and
workmanship under normal use and service for twelve (12) months from the date of
purchase by the end user, or 18 months from date of invoice whichever is earlier.
Products that fail during this period will be repaired or replaced at General Pumps’s discretion,
with the same or a functionally equivalent product, provided that;
(A) The product is returned freight paid to our factory or any General Pumps Authorized Service
Station.
(B) A copy of sales invoice indicating the date of sale to the end user is provided.
This warranty does not apply to products that are found by us to be damaged;
The maximum liability of this warranty is limited to the purchase price of this product.
In no event, regardless of the cause shall General Pumps be liable;
The original purchaser of the product from General Pumps must obtain a Return Material
Authorisation (RMA) number from General Pumps prior to returning any defective product to the
factory. In case of an end user wanting to return a defective product he must obtain
an RMA number by contacting our dealer or distributor from whom he purchased the
product, General Pumps will not accept any defective product sent to it’s factory without an RMA
number.