Check list for Pre-cast - Manufacturing level
Project Name - Date of insp -
Inspection at factory level
Sl No. Description
Pass Not pass Remarks
Mould Inspection
1 Critical dimensions within
1.1 Length
1.2 Width
1.3 Height
1.4 Squareness
1.5 Openings
2 Mould Condition
2.1 Plate Thickness
2.2 Base mould support
2.3 No twisting and unevenness
2.4
Fitting
Provision for bar protrusion and
3 opening
4 level and anchorage
5 Mould Cleanliness
6 Form release agent (oil)
Reinforcement and connection
7 No., Size and position
8 Lifting hooks & inserts
9 Corrugated pipes
10 Starter bars
11 Anchourage and lapping
12 Cover
Pretessing Tendons
13 No, Size and profiles of
14 Stressing pressure
15 Elongation
M & E Services
16 Recessess or block out or openings
Electrical services - Power
16.1 points,cast in switches and
internet cable
Plumbing Services - Groove lines,
16.2
waste pipes, water pipes
16.3 gas pipes and aircon ducts
provision for groove line, water
16.4
drip line and fittings
Concreting
17 Concrete Slump & Cube Sampling
18 Compaction & curing condition
19 Demoulding strength
Final Inspections
20 Surface Condition
20.1 No honeycomb
20.2 No chipping
20.3 Straight edges
20.4 No exessive pin holes
20.5 Flat and even surface
21 Dimension checks on elements
22 Recess groove line, water drip line
Properly transported with good
23 condition
24 Finishing and defects (if any)
25 Load test
26 Conctrete strength as per specs
27 Protection works for delivery
Manufacturer - Buyer & supplier- Received on site-