Time & Action Calendar: Buyer Order Qty. Ex-Factory Date (On PO) Style # Ex-Factory Date (As Per Plan)

The document is a time and action calendar for a style 4041 dress order by Greece of 2000 units. Key dates include the buyer's order date of November 20th, a planned ex-factory date of January 8th, and a lead time of 49 days. The calendar outlines 16 key processes for fulfilling the order, including receiving the order, generating production documents, procuring fabrics and trims, cutting, sewing, finishing, packing, inspecting, and dispatching the order. Responsibilities for each process are assigned with target start and end dates.

Uploaded by

karthikeyan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
73 views1 page

Time & Action Calendar: Buyer Order Qty. Ex-Factory Date (On PO) Style # Ex-Factory Date (As Per Plan)

The document is a time and action calendar for a style 4041 dress order by Greece of 2000 units. Key dates include the buyer's order date of November 20th, a planned ex-factory date of January 8th, and a lead time of 49 days. The calendar outlines 16 key processes for fulfilling the order, including receiving the order, generating production documents, procuring fabrics and trims, cutting, sewing, finishing, packing, inspecting, and dispatching the order. Responsibilities for each process are assigned with target start and end dates.

Uploaded by

karthikeyan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Time & Action Calendar

Buyer Greece Order Qty. 2000 Ex-factory date (on PO)


Style # 4041 Merchant Aman Ex-factory date(as per plan) 8-Jan

Style Description Dress Recvd Date 20-Nov Lead Time (days) 49

Planned Start

Planned End

Actual start

Actual End
Duration
Duration
(days)

(days)
Key Processes Responsibility Remarks

1 Order receipt (Buyer PO) 20-Nov Merchant


2 Consumption calculation 21-Nov Pattern master
3 BOM generation 23-Nov Merchant
4 PO issue for Fabric, trims 24-Nov Store Mngr. (Fabric/Trim)
5 Size set submission 25-Nov Merchant
6 Size set Comments 28-Nov Merchant
7 PP meeting planning
Production 1-Dec Merchant
8 updates and circulation 11-Dec 10 Production Manager
9 Fabric in-house 24-Nov 8-Dec 15 Store Mngr. (Fabric/Trim)
10 Trims In-house 24-Nov 3-Dec 10 Store Mngr. (Fabric/Trim)
11 Cutting 11-Dec 12-Dec 3 Cutting in charge
12 Fabrication/stitching 26-Dec 30-Dec 5 Production Manager
13 Finishing 31-Dec 3-Jan 4 Finishing In charge
14 Packing 2-Jan 6-Jan 5 Finishing In charge
15 Inspection 7-Jan QC
16 Dispatch 8-Jan Finishing In charge