Problems in PSA
Problems in PSA
Two generators rated 10 MVA, 13.2 KV and 15 MVA, 13.2 KV are connected
in parallel to a bus bar. They feed supply to 2 motors of inputs 8 MVA and 12
MVA respectively. The operating voltage of motors is 12.5 KV. Assuming the
base quantities as 50 MVA, 13.8 KV, draw the per unit reactance diagram.
The percentage reactance for generators is 15% and that for motors is 20%.
Solution:
The one line diagram with the data is obtained as shown in figure P1(a).
Calculation of pu values:
XG1 = j 0.15 (50/10) (13.2/13.8)2 = j 0.6862 pu.
Problem #2:
Draw the per unit reactance diagram for the system shown in figure below.
Choose a base of 11 KV, 100 MVA in the generator circuit.
Solution:
The one line diagram with the data is considered as shown in figure.
Calculation of pu values:
Calculation of pu values:
Problem #3:
A 30 MVA, 13.8 KV, 3-phase generator has a sub transient reactance of 15%.
The generator supplies 2 motors through a step-up transformer - transmission
line – step-down transformer arrangement. The motors have rated inputs of 20
MVA and 10 MVA at 12.8 KV with 20% sub transient reactance each. The 3-
phase transformers are rated at 35 MVA, 13.2 KV -∆ /115 KV-Y with 10 %
leakage reactance. The line reactance is 80 ohms. Draw the equivalent per unit
reactance diagram by selecting the generator ratings as base values in the
generator circuit.
Solution:
The one line diagram with the data is obtained as shown in figure P3(a).
Calculation of pu values:
XG = j 0.15 pu.
Xm1 = j 0.2 (30/20) (12.8/13.8)2 = j 0.516 pu.
Problem #4:
A 33 MVA, 13.8 KV, 3-phase generator has a sub transient reactance of 0.5%.
The generator supplies a motor through a step- up transformer - transmission
line – step-down transformer arrangement. The motor has rated input of 25
MVA at 6.6 KV with 25% sub transient reactance. Draw the equivalent per
unit impedance diagram by selecting 25 MVA (3φ), 6.6 KV (LL) as base
values in the motor circuit, given the transformer and transmission line data as
under:
Step up transformer bank: three single phase units, connected ∆–Y, each rated
10 MVA, 13.2/6.6 KV with 7.7 % leakage reactance and 0.5 % leakage
resistance; Transmission line: 75 KM long with a positive sequence reactance of 0.8 ohm/ KM
and a resistance of 0.2 ohm/ KM; and The Step down transformer bank: three single phase units,
connected ∆–Y, each rated 8.33 MVA, 110/3.98 KV with 8% leakage reactance and 0.8 % leakage
resistance;
Solution:
The one line diagram with the data is obtained as shown in figure P4(a).
3-phase ratings of transformers:
T1: 3(10) = 30 MVA, 13.2/ 66.4√3 KV = 13.2/ 115 KV, X = 0.077, R = 0.005
pu.
25 MVA, 6.6 KV in the motor circuit (Given); the voltage bases in other
sections are: 6.6 (110/6.8936) = 105.316 KV in the transmission line circuit
and 105.316 (13.2/115) = 12.09 KV in the generator circuit.
Calculation of pu values:
Problems
[Answers: XG1 = j 0.1778, Xg2 = j 0.089, Xg3 = j 0.16 all in per unit]