ITP for Acidification Vessel at RDMP
ITP for Acidification Vessel at RDMP
: 26071-203-V1A-MW00-00138
Page 1 of 8
Doc. No. : 26071-203-V1A-MW00-00138
REVISION LOG
Page 2 of 8
Doc. No. : 26071-203-V1A-MW00-00138
HOLD LIST
Page 3 of 8
INSPECTION & TEST PLAN - ACIDIFICATION VESSEL
Doc. No.: 26071-203-V1A-MW00-00138 Sheet: 1 of 5 Rev.: 00A Date: 08/03/2021
** IMPORTANT NOTE **
INSPECTION & TEST PLAN (ITP)
Job: P20268V
THE PRESENT INSPECTION & TEST PLAN IS ISSUED IN
Client: RDMP Balikpapan JO SIMPLIFIED VERSION LISTING THE KEY INSPECTION STEPS.
Project: RDMP RU-V Balikpapan Project ITP WILL BE ISSUED ON SUB-VENDOR'S FORMAT.
Revision Index
Page 4 of 8
INSPECTION & TEST PLAN - ACIDIFICATION VESSEL
Document No.: 26071-203-V1A-MW00-00138
Client: RDMP Balikpapan JO P.O.: 26071-203-POA-MW00-23001 Job: P20268V
Project: RDMP RU-V Balikpapan Project TAG No.: A-325-02-01-C3 S.N.: TBA
Code: ASME VIII Div.1 2019 Edition Remarks: ASME U Stamp Required - MIGAS Inspection Required
00A Issued for approval 08/03/2021 QCI - N. Capelli QA/QC Mgr. - L. Bensoni QA/QC Mgr. - L. Bensoni
Rev. Description-Descrizione Date-Data Prepared by-Preparato da Checked by-Controllato da Approved by-Approvato da
Page 5 of 8
INSPECTION & TEST PLAN - ACIDIFICATION VESSEL
Document No.: 26071-203-V1A-MW00-00138
Client: RDMP Balikpapan JO P.O.: 26071-203-POA-MW00-23001 Job: P20268V
Project: RDMP RU-V Balikpapan Project TAG No.: A-325-02-01-C3 S.N.: TBA
Reference Procedure /
Extension
Location
Required
Record
Acceptance Criteria SUB-VENDOR VENDOR CLIENT OWNER ASME A.I. GOVERN. INSP.
Step Stage Description NOTES
Project SPC. Ref. (To be assigned ) (3V Tech) (RDMP-JO) (PMC) (To be assigned ) (Migas)
A DOCUMENTS CONTROL
Mechanical Calculations D2 - C2
SUB
Page 6 of 8
INSPECTION & TEST PLAN - ACIDIFICATION VESSEL
Document No.: 26071-203-V1A-MW00-00138
Client: RDMP Balikpapan JO P.O.: 26071-203-POA-MW00-23001 Job: P20268V
Project: RDMP RU-V Balikpapan Project TAG No.: A-325-02-01-C3 S.N.: TBA
Reference Procedure /
Extension
Location
Required
Record
Acceptance Criteria SUB-VENDOR VENDOR CLIENT OWNER ASME A.I. GOVERN. INSP.
Step Stage Description NOTES
Project SPC. Ref. (To be assigned ) (3V Tech) (RDMP-JO) (PMC) (To be assigned ) (Migas)
B5 100% - H S S S -
(Before PWHT) INCOMING QC CHECK P14 - P16 - P17 - P22
During fabrication Materials C5 - C6 - D1 EN 10204 3.1 (Pressure parts and
SUB
B10 100% X H R R R R
(Before PWHT) MATERIAL TEST CERTIFICATES CHECK P16 materials welded to pressure parts)
During fabrication Welding P1
SUB
B15 100% - H S S S -
(Before PWHT) EP - FU P14 - P19
During fabrication Welding P1
SUB
B20 100% - H S S S -
(Before PWHT) WM P14 - P19
During fabrication Welding P2 - P4 X-Ray films shall be checked by 3V
SUB
B30 100% X H S S S R
Kg/cm2 for 15 minutes holding time
B35 100% X H H S S R
(Before PWHT) VE - DC P14 - P15 - P19
During fabrication Vessel complete D1
SUB
B40 100% X H H S S R
(Before PWHT) VE - DC - THK P14 - P15 - P19
Vessel complete P7
SUB
B50 (*) X H W S S R
(After PWHT) NDE EXAMINATIONS (VT,PT,MT,RT) P14 - P17 - P19 - P22 Tech before hydrostatic test
During fabrication Welding P7
SUB
B55 (*) X H W S S R
(After PWHT) HARDNESS CHECK P14 - P19
During fabrication All reinforcing pads with telltale holes (if any) P7 Soapy water solution at a pressure of 1
SUB
B60 100% X H W S S R
(After PWHT) AT P14 - P19 Kg/cm2 for 15 minutes holding time
During fabrication Vessel complete: Internal visit D1
SUB
B65 100% X H H W W R
(After PWHT) VE - DC P14 - P15 - P19
During fabrication Vessel complete D1
SUB
B70 100% X H H W W R
(After PWHT) VE - DC - THK P14 - P15 - P19
During fabrication Vessel complete D1 Pressure parts and materials welded to
SUB
B75 100% X H W S S R
(After PWHT) MC P16 pressure parts
During fabrication Vessel complete P5 Pressure indicated on GAD - Holding
SUB
B80 100% X H H W W W
(After PWHT) HYT P14 - P18 - P19 time: 2 hours
During fabrication Vessel complete P5
SUB
B85 100% X H S S S R
(After PWHT) DRAINING & DRYING P14 - P18 - P19
Page 7 of 8
INSPECTION & TEST PLAN - ACIDIFICATION VESSEL
Document No.: 26071-203-V1A-MW00-00138
Client: RDMP Balikpapan JO P.O.: 26071-203-POA-MW00-23001 Job: P20268V
Project: RDMP RU-V Balikpapan Project TAG No.: A-325-02-01-C3 S.N.: TBA
Reference Procedure /
Extension
Location
Required
Record
Acceptance Criteria SUB-VENDOR VENDOR CLIENT OWNER ASME A.I. GOVERN. INSP.
Step Stage Description NOTES
Project SPC. Ref. (To be assigned ) (3V Tech) (RDMP-JO) (PMC) (To be assigned ) (Migas)
C5 100% X H W S S R
(After hydrotest) PFA LINING CHECK P24
During fabrication Vessel complete P6 Final visual examination, DFT Check,
SUB
C10 100% X H W W W R
(After hydrotest) SURFACE PREP. & PAINTING CHECK P20 RAL check.
During fabrication Vessel complete D1
SUB
C25 100% X H W W W R
(Before shipment) PACKING CHECK P23 check, etc.
During fabrication Vessel complete MDB Index
SUB
C30 100% - H H R R R
(Before shipment) MANUFACTURER DATA BOOK REVIEW P23
Upon inspection activities are
Page 8 of 8