Outputs - RT
Outputs - RT
GROUND WORKS
A. SITE CLEARANCE
B. EXCAVATIONS
3, Rock excavation
As above, but +1200% 1 Lab
C. DISPOSALS
BRICKWORK
Common brickwork:
In foundations,
Half brick thick 375/day
One brick thick 400/day
One and half brick thick 425/day
In superstructure up to 2 storeys,
Half brick thick 350/day
One brick thick 380/day
One and half brick thick 400/day
ESTIMATING DATA
In superstructure up to 2 storeys,
Half brick thick 300/day
One brick thick 325/day
In superstructure up to 2 storeys,
One brick thick 330/day
Mortar
Mixing by hand 8hrs/m3
BLOCKWORK
115mm blockwork:
In foundations 180/day
In superstructure 150/day
230mm blockwork:
In foundations 150/day
In superstructure 120/day
SUNDRIES
Beam filling 3m/hr/skin
Rough cutting 2.5hrs/m2
Cutting pipe chases 1.5hrs/m
Copings 0.75hrs/m
Fair cuttings 1hr/m
Cut small holes 1hr/skin
Cut large holes 2hrs/skin
Fix door and window frames 0.8hrs/m2
Unload and stack 3 lab hrs/1000
Painting around frames 3hrs/m
ESTIMATING DATA
BRICKWORK
CEMENT MORTAR
ESTIMATING DATA
CONCRETING
Labour
FORMWORK
PLASTERWORK
GRANO
Rhinosand 8m2/sack(25kg)
Rhinoset 20m2/sack
Rhino bond 6m2/sack
Cemwash 12m2/sack/coat 19.16667
1m3 cment = 30bags
PAINTING
Paint to ceiling
Paint to walls 60m2/day
Paint to frames 50m2/day
Paint to timber 45m2/day
Paint to small pipes 25m/hr/coat
Paint to large pipes 10m/hr/coat
NB. Add 10% to labour figures for turps,brushes etc.
PVA to plaster
PVA to blockwork:
PAINTING
To timber:
1st coat 35m2 7m2
2nd coat 40m2 8m2
Subsequent 50m2 10m2
REINFORCEMENT
DIAMETER ROUND PLAIN HIGH
MILD SQUARE YIELD
TWIST DEFORMED
(R) (X) (Y)
6mm 0.222 0 0.222
6.50mm 0.26 0.332 0
8mm 0.395 0.502 0.395
10mm 0.616 0.784 0.616
12mm 0.887 1.129 0.888
14mm 1.207 1.537 1.21
16mm 1.577 2.008 1.579
20mm 2.464 3.137 2.466
22mm 2.981 3.796 0
25mm 3.85 4.902 3.854
30mm 5.544 7.059 0
32mm 0 0 6.313
35mm 0 9.608 0
40mm 0 0 9.869
23.68
1.BASES 90kg/m3
2.COLUMNS 170kg/m3 17.36
3.WALLS 100kg/m3
4.SLABS 120kg/m3
5.BEAMS 150kg/m3
ESTIMATING DATA
Block Volumes
Practical Equivalents
Cement 1 sack 1 sack 1 sack 1 sack
Aggregate 3.5barrws 4.5barrws 6 barrows 7 barrows
Dry Volume 0.234 0.291 0.376 0.433
Waste 5% 0.012 0.015 0.019 0.022
0.222 0.276 0.357 0.411
ROOFING
Sheets 1+4 6sheets/hr
Mitring 1+1 20sheets/hour
Fix barge and fascia board 1+2 5m/hr
Fix IBR roof sheeting 1+4 6m2/hr
Fix tiling battens 1+2 10m2/3hrs
CARPENTRY
Fix purlins 1+2 20m/hr
Fix rafters 1+2 14m/hr
Fix trusses ( 8m ) 1+4 4No/day
Fix sprockets 1+2 3m/hr
Fix joists 1+2 15m/hr
Fix hangers 1+2 3m/hr
ESTIMATING DATA
CARPENTRY
JOINERY
Fix brandering one way 1+2 3m2/hr
Fix ceilings 1+3 2m2/hr
Fix cover strip 1+2 20m/hr
Fix cornice 1+2 15m/hr
Fix skirting 1+2 10m/hr
Fix framing 1+1 6m/hr
Cut and fix blocked shelving 1+1 2hrs/sheet
Fix pre-cut shelving 1+1 6m/hr
Hang doors 1+2 1No /hr
Plugging 1+1 8plugs/hr
Screwing 1+1 20/hr
ESTIMATING DATA
Wheelbarrow 0.057m3
Sack cement 0.034m3
Grout
Probable Stone Method of Cement : Mix proportions per sk of Materials per m3 Yield
minimum size compacti- Water cement m3/sk
28 day mm on ratio
strength Sand Stone Net water Cement Sand Stone
Mpa kg/sk kg/sk l/sk kg m3 m3
Mix per m3 of Half Brick HB Lining One Brick 1.5 Brick 280 Hollow 280 hollow Mass One Brick x
mortar Filled 1.5 Brick
Bricks 53 53 105 158 105 105 456 36
1:3 10.6 Cement 0.2131 0.3297 0.5428 0.8735 0.4262 0.9562 2.7836 0.1537
1.38 Sand 0.0278 0.0430 0.0707 0.1138 0.0555 0.1245 0.3624 0.0201
1:4 8.9 Cement 0.1789 0.2768 0.4557 0.7334 0.3578 0.8028 2.3372 0.1291
1.50 Sand 0.0302 0.0467 0.0768 0.1236 0.0603 0.1353 0.3939 0.0218
1:5 7.8 Cement 0.1568 0.2426 0.3994 0.6428 0.3136 0.7036 2.0483 0.1131
1.63 Sand 0.0328 0.0507 0.0835 0.1344 0.0656 0.1471 0.4281 0.0237
1:6 6.4 Cement 0.1287 0.1991 0.3277 0.5274 0.2573 0.5773 1.6807 0.0928
1.69 Sand 0.0340 0.0526 0.0866 0.1393 0.0680 0.1525 0.4438 0.0245
1:7 5.9 Cement 0.1186 0.1835 0.3021 0.4862 0.2372 0.5322 1.5494 0.0856
1.75 Sand 0.0352 0.0545 0.0896 0.1442 0.0704 0.1579 0.4596 0.0254
1:8 5.3 Cement 0.1066 0.1649 0.2714 0.4268 0.2131 0.4781 1.3918 0.0769
1.81 Sand 0.0364 0.0563 0.0927 0.1492 0.0728 0.1633 0.4753 0.0263
1:4 + 10% 2.9 Cement 0.0583 0.0902 0.1485 0.2390 0.1166 0.2616 0.7616 0.0421
cement 8.0 Lime 0.1608 0.2488 0.4096 0.6592 0.3216 0.7216 2.1008 0.1160
1.35 Sand 0.0272 0.0420 0.0692 0.1113 0.0543 0.1218 0.3546 0.0196
1:2:9 3.6 Cement 0.0724 0.1120 0.1844 0.2967 0.1448 0.3248 0.9454 0.0522
6.6 Lime 0.1327 0.2053 0.3380 0.5439 0.2654 0.5954 1.7332 0.0957
1.38 Sand 0.0278 0.0430 0.0707 0.1138 0.0555 0.1245 0.3624 0.0201
1:2:12 3.0 Cement 0.0603 0.0933 0.1536 0.2472 0.1206 0.2706 0.7878 0.0435
5.6 Lime 0.1126 0.1742 0.2868 0.4615 0.2252 0.5052 1.4706 0.0812
1.50 Sand 0.0302 0.0467 0.0768 0.1236 0.0603 0.1353 0.3939 0.0218
Production
Half 1 + 1.5 500 per shift
Robgrout
Cement 50kg
Robgrout 45kg
Sand 25kg 0.02m3
Stone chips 45kg 0.03m3
0.07m3 yield