Creating Filters in Primavera
Creating Filters in Primavera
Filters allow users to limit the data displayed to items of interest. For example, you can filter activities in
PM to display only those activities that are on the critical path or have resources assigned. Filters can
be used for the convenience of filtering out certain data that is not of immediate interest, but can also be
used to assist with quality control by displaying only data that meets certain criteria to look for
exceptions. Below is a suggested filter that accompanies the suggested layouts provided in the
Creating Layouts navigation document. The filter described in this document is not inclusive of all
possible types of filters.
The default is to display All Activities; several filters can be constructed and saved for future
(repeated) use.
This filter will show activities that have not yet started and are scheduled to start during the
period between the Data Date (DD) and 3 months after the Data Date (DD+3M).
Note: These parameters relate to basic queries of action, data element, operator and low and
high value.
9. Click OK.
10. Create the second filter for a 3-month look ahead at your project schedule.
12. Click New.
The 3 Month Look-ahead filter shows activities that have not yet finished and are scheduled to
finish during the period between the Data Date (DD) and 3 months after the Data Date
(DD+3M).
Configure settings for each project at the time the project status reaches Autolink Complete so that the
correct defaults are applied to new activities and resources, and the project behaves as expected when
scheduled.
2. Open the Projects window.
6. Configure Project Settings tab.
Verify that Summary project based on is set to Detail activity resource assignments.
Verify that the Fiscal year begins on the 1st day of <October>
Verify that the Baseline for earned value calculations is the Project Baseline.
Verify that the Total Float less than or equal to radio box is selected and 0.0d.
7. Configure Project Calculations tab
8. Verify Type of Funds.
Symptom: I have started a group of activities that should not have been started and I would like to
return the progress to 0 %, return the original duration and keep the original budgeted labor units.
3. Choose Format, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.
4. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule. To
find the Project Start date, chooseEnterprise, Projects. Click on the Dates tab and note the Planned
Start date.
5. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this
column and choose Edit, Fill Down.
6. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this
column and choose Edit, Fill Down.
7. Choose Tools, Global Change and run the 1st Global Change. (See below) This will set the
Actual Material Units to zero.
8. Run the 2nd global change (See below) which sets the activity status to Not Started.
Subject Area:
Then:
Subject Area:
Activities
If:
Then:
If this process is not used you may encounter the following error: