Chapter 6
Chapter 6
Soil Compaction
In the construction of highway embankments, earth
dams, and many other engineering
structures, loose soils must be compacted to increase
their unit weights. Compaction increases the strength
characteristics of soils, which increase the bearing
capacity of foundations constructed over them.
Compaction also decreases the amount of undesirable
settlement of structures and increases the stability of
slopes of embankments.
The degree of compaction of a soil is measured in
terms of its dry unit weight. When water is added to
the soil during compaction, it acts as a softening agent
on the soil particles. The soil particles slip over each
other and move into a densely packed position. The
dry unit weight after compaction first increases as the
moisture content increases.
Relative compaction
Where
Wc = weight of sand to fill the cone only
Ɣd (sand) = dry unit weight of Ottawa sand used
The dry unit weight of compaction made in the field
then can be determined as follows:
Solution
w% w Ɣzav
5 0.05 149.408
8 0.08 139.396
10 0.1 133.434
12 0.12 127.961
15 0.15 120.545
Solution
ρd=
S ρd
0.8 2001.87
w=10% 0.9 2059.13
1 2107.34
0.8 1601.2
w=20% 0.9 1675.73
1 1740.55
Solution
W
V (ft3) (Ib) w% Ɣ Ɣd
0.03333 3.26 8.4 97.8 90.2214
0.03333 4.15 10.2 124.5 112.976
0.03333 4.67 12.3 140.1 124.755
0.03333 4.02 14.6 120.6 105.236
0.03333 3.63 16.8 108.9 93.2363
140
120
100
80
60
40
20
0
5 10 15 20
1720
1700
1680
1660
1640
1620
1600
5 7 9 11 13 15 17 19 21 23
Solution
ρd=
R=
Solution
V=8000m3
e=0.7
0.7=
Vs=4705.88 m3
For A
e=0.82
Vt=8564.7016m3
Cost=Vt*Cost=$68517.6
e=1.1
Vt=9882.348m3
Cost=$49.411.74
For C
e=0.9
Vt=8941.172m3
Cost=$80470.548
For D
e=0.78
Vt=8376.4664m3
Cost=$100517.597
Choose B
Solution
R=??
Dr=0.78=
Ɣd=101.3624Ib/ft3
R=
Solution
Mass of dry soil excavated=
Mass of soil in the hole and cone=5.99-2.81=3.18Kg
Mass of soil in the hole= 3.18-.117=3.063Kg
( )
V=1.8374*10-3m3
Ɣd=
Solution
V=7500m3
Dr=94%
emax=0.73
emin=0.4
Gs=2.67
e=0.4198
Vs=5282.4341
For A
S.e=Gs.w
e=
Vt=8451.89456m3
Cost=Vt*cost=$84518.9456
Vt=8715.488m3
Cost=Vt*cost=$43577.440
Choose B