Osterberg Cell
Osterberg Cell
Abstract
This paper describes the O-cell 'bottom-up' method for the static load testing of
bored piles and driven piles, presents its history and lists some of its special
advantages and limitations. This method has almost completely replaced the
previously conventional top-load-reaction testing of bored piles in the United
States. A review of LOADTEST, Inc. files shows two, perhaps previously
underappreciated, aspects of bored pile design and construction which the use of
O-cell testing demonstrates and counteracts: 1) The (measured/estimated) load
capacity ratio tends to increase dramatically with the increasing strength of the
surrounding soil or rock. 2) Several commonly used construction techniques can
dramatically reduce one or both components of shaft capacity.
1. Introduction
Thanks to the new Osterberg Cell (O-cell) testing method^ we can
now statically test full sized bored piles (also known as drilled shafts,
drilled piers, barrettes and caissons) to near their ultimate capacity.
Furthermore, we can do it more conveniently, economically arid safely
than ever before. We also obtain more information about shaft
performance. All this has led, and should lead further, to reducing over-
conservative design and improving construction methods, which in turn,
leads to increasing the use of bored pile foundations, resulting in more
testing, etc... O-cell testing and bored piles have a mutually beneficial,
cooperative relationship - or a "symbiosis."
1
Professor Emeritus University of Florida, Principal, Schmertmann and Crapps, Inc.,
Gainesville, Florida, USA
2
President, LOADTEST, Inc., Gainesville, Florida, USA
The Third International Geotechnical Engineering Conference • Cairo University - Egypt _________________ 5-8 January, 1997
River
level •
Hydraulic Supply
& ^ -i
30
10 15 20 25
Load(MN>
35.7m
Owner:
Kentucky Department of Highways
Contractor:
National Engineering and Contracting
Company.
Testing:
LOADTEST, Inc.
PILE DATA
460mmO.D. 13 mm.
wall concrete filled
pipe pile driven with a
Delmag D36-13
hammer to 10 blows
last 13 mm.
rJ^VVV Glacial Till j^HH^—Osterberg Load Cell
Weathered
Argilite
TEST RESULTS
Peak load = 1.9 MN (7.62 mm movement at failure)
Skin friction = 36.9 kPa. End bearing = 11.7
MPa (2.03 mm movement) Ultimate pile load
capacity > 3.80 MN
FIGURE 2
The Third International Geotechnical Engineering Conference - Cairo University - Egypt 5 - 8 January, 1997
REACTION SYSTEM
n
P=F+Q
1
' "
t
i
F F. Q
T A
EXPANDING
OSTERBERG
I^§§&$
JL CELL
T
Q Q
CONVENTIONAL nr.^nn^n ~ TOP LOAD
TEST OSTERBERG CELL TEST
FIGURE 3
37 The Third International Ceotechnical Engineering Conference - Cairo University - Egypt 5-8 January, 1997
m
57 -15.0
VIBRATING WIRE
DISPLACEMENT
fin* grained
36 TRANSDUCERS
m
Sandstone
a
25 coarse groined
Sandstone -17.0
50 /10
50 /" -19.0
62
49
-
moldic 22.0
65 Limestone
83 -25.0
LVWOT
l!
-27.5
-28.0
-20.0 -
29.0
-25.0
------ -30.0
FIGURE 4
The third International Ceotechnical Engineering Conference - Cairo University - Egypt 5-8 January, 1997
AIR DRIVEN
HYDRAULIC
PUMP WITH
PRESSURE
GUAGE
-Telltale Casing
-Reinforcing
Steel
LVWDT -
INDICATOR
ttiiitmiiiiitti
SHAFT END BEARING
FIGURE 5
The Third International Ceotechnical Engineering Conference - Cairo University - Egypt 5-8 January, 1997
three tests performed with the O-cell were on steel pipe piles. The next
sections describe some of the history of the Osterberg Cell and its
development, discuss some of its advantages and limitations and finally
present some informative case histories.
second test was then filled with cement grout and this pile was used in the
permanent foundation.
The O-cell test method has steadily gained popularity and, as of
September 1996, approximately 200 tests have been performed on bored
piles in the United States and Southeast Asia. LOADTEST, Inc. (LTI) in
Gainesville, Florida now distributes the O-cell and provides installation
and test support services. Dr. Osterberg continues to promote the O-cell
and provide consulting support.
4.1 Economy : The O-cell test is usually less expensive to perfoim than
a conventional static test despite sacrificing the O-cell. Savings are
realized through reduced construction time and capital outlay for a
test, no top-of-pile reaction equipment requirements and less test
design effort. O-cell tests are typically 1/3 to 2/3 the cost of
conventional tests. The comparative cost reduces as the load
increases.
4.2 High Load Capacity: Bored piles have been tested in Kentucky,
Massachusetts and Georgia to equivalent conventional test loads
of 54 MN, 56 MN and 66 MN respectively. A program is underway
in Florida to carry out a bored pile test with a group of O-cells that
have the capacity to reach a loading of 160 MN. Very high capacity
loading is also possible for large driven piles
4.4 Improved Safetv: The test energy lies deeply buried and there is
no overhead load.
4.6 Reduced Work Area: The work area required to perform an O-cell
test, both overhead and laterally, is much smaller than the area
required by a conventional load system. For example, a 56 MN
O-cell test, conducted in a 3-meter wide median strip of a busy
Interstate Highway, would have been impossible with any other
method.
4.8 Static Creep and Setup (Aging) Effects: Because the O-cell test
is static, and the test load can be held for any desired length of
time, the Engineer also obtains separate data about the creep
behavior of the side shear and end bearing components. Creep
load limits may be obtained which are similar to those from
pressuremeter tests as described in ASTM D4719. As explained
The Third International Geotechnical Engineering Conference - Cairo University - Egypt 5 - 8 January, 1997
5.1 Advance Installation Required: With bored piles and most driven
piles, the O-cell must be installed prior to construction or driving.
5.3 Equivalent Top Load Curve: Although the equivalent static top
load-deflection curve can be estimated with conservatism, it
remains an estimate. See Section 6 for more details.
5.5 Not suitable for certain types of piles: The O-cell cannot be used
to test sheet piles or H-piles. It will also not fully develop the side
shear of a tapered pile when loaded in compression. Installation
of an O-cell on a tapered wooden pile would be difficult.
subtract the buoyant weight of the test pile from the upward O-cell load.
Note that the movement curve for end bearing does not include elastic
pile compression because the load is applied directly.
The Engineer may further utilize the two component curves to
construct an equivalent top load-deflection curve and thereby investigate
the combined two-component pile capacity. Construction of the
equivalent top load curve begins by determining the side shear at an
arbitrary deflection point on the side shear-deflection curve. If the bored
pile is assumed rigid, its top and bottom move together and have the
same deflection at this load. By adding the side shear to the mobilized
end bearing at the chosen deflection, one determines a single point on
the equivalent top load curve. Additional points may then be calculated
to develop the curve up to the maximum deflection (or maximum
extrapolated deflection) of the component that did not reach ultimate
value. Figure 7 presents such an equivalent top-load curve obtained
from the test curves in Rqure 6. In this case both components
fortuitously reached near-ultimate simultaneously, which does not
normally occur.
Points beyond the maximum deflection of the component that
does not reach an ultimate may also be obtained by conservatively
assuming that at greater deflections it remains constant at the maximum
applied load. An example result using this method is shown on Figure 9.
based on the O-cell curves in Rqure 8. We also sometimes, but less
conservatively, extrapolate the non-ultimate component by using
hyperbolic curve fitting and then use this extrapolated curve in the
calculations to produce the equivalent curve, as also shown on Figure 9
for comparison.
As noted by Osterberg (1994), the above construction makes the
following three basic assumptions.
The Third International Ceotechnical Engineering Conference - Cairo University - Egypt 5-8 January, 199*
K|
,
0 -
5
e
?
?S§ -10 j
OOc ■0 = »
log
1 = -20
0
.0 2.5 5.0 75 10.0 125 15.0 175 20.0 225 25.0 275 30.0
Load(MN)
Figure 6
i -20.0 Equivalent Top Load-Settlement
I
Curve
Reference test 127
60
ill »
in •
h
I o
T
-5 -10
III:
■ -- :
•
Assumed compression of
disturbed loose material
| 1 -30
-35 -40
JL.
i^v ;
]
.0 0.5 .0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
1 Load(MN)
Figure 8
m 0 m T-
'f-
JL
31 ^
<D
1 1 \ .. ,r i.e.references.
2. M/E
il XI
'~*~"^««^ f*i\ /^o\ /sS \
^^^^Xr^V \TZS XL^/ \ (0 a.
2
Inc. file
antechnique.
^^ ca
1
ultimate,
Intermediate Mater<
rs are
denoted numbe due mponent
to poor LOADTEST
construction
reached
\ .2
cates neither co
cates low results
Y~0Q
fttoHardSoi
finYco
lo>I v
/cc\ ^j CO
2 =5 -5
(0,
£ £ £
O®
Figure 10
fpe Third International Geotechnical Engineering Conference - Cairo University - Egypt 5 -8 January, 1997
The O-cell testing shows that in "normal" soil conditions (sand, silt
and clay strata) the engineering estimates are usually reasonably good,
with M/E ranging from about 0.7 to 2.
In intermediate geomechanical materials (soft rocks, weathered
rocks, coarse dense soils, glacial tills) however, the measured/estimated
(M/E) ratio generally increases into the 2 to 5 range. This no doubt reflects
the difficulty in measuring and estimating the strength parameters of these
materials, coupled with natural engineering conservatism. In unweathered
competent rock formations the M/E ratios in Figure 10 are even higher,
from 7+ to 25+. We suspect that to some extent such high M/E ratios in
competent rock have resulted from the inability (prior to the O-cell) to test
the high capacity of these foundations.
The Third International Geotechnical Engineering Conference - Cairo University - Egypt_______________ 5-8 January, 1997
RESULTS Side shear Side shear 24.5 Side shear 25.8 Side shear 27.6
Stage 1, averaged MN (7 mm) MN (7 mm) MN (13 mm)
720 kPa End bearing End bearing End bearing 28.0
End Bearing = = 26.7MN = 27.6MN MN (20 mm)
8.6MN (81 mm) (34 mm) M/E = 3.3
Total shaft M/E>2 M/E>2
capacity exceeds Ultimate capacity Ultimate capacity
17.8 MN not reached not reached
M/E>2
FILE 35 31 129
REFERENCE
LOCATION Decatur, Alabama Burgin, Kentucky Stillwater, Minnesota
PURPOSE Verify design parameters, Proof test on a 0.9 meter Pre-design test to
leading to adjustments production shaft. (1.8 MN determine shear
where feasible 0.9 meter design load) parameters for axial test
diameter shaft on 1.2 m diameter shaft.
(Deep-seated lateral load
test also carried out).
METHOD Cased to top of rock Cased to top of rock at Cased to 15.0 m then
socket at 17.7 m then 3.0 m then cored *dry" to drilled to 55.0 m. O-cell
cored to 22.6 m under 6.1 m. O-cell set on s.et at 4.5 m from bottom
water. 26.7 MN O-cell bottom. Concreted to (i.e. 3.5 m socket above
placed at 22.1 m. form 2.0 m socket. O-cell)
Concrete filled rock
socket to 17.7 m level
(i.e. 4.4 m socket)
CONDITIONS Fill sand and clay to Earth fill and sand to Overburden to 15.0 m
8.2 m, then limestone 3.0 m then limestone. then dolostone over
with some voids and clay Unconfined Compressive sandstone.
seams. Unconfined Strength = Unconfined Compressive
Compressive Strength of' 100-140MPa Strength =
limestone = 50-58MPa
100-150MPa
[email protected]
RESULTS Shear Load 22.2 MN Shear Load 8.0 MN Shear Load 21.8 MN
(18 mm) (2 mm) (33 mm)
End Bearing Load End bearing Load Shear + End Bearing
22.7 MN (36 mm) 8.0 MN (4 mm) Load (lower socket)
M/E>5.5 M/E > 9.3 21.8 MN (15 mm)
only during drilling near the shaft base. Disturbance to the surrounding
soils' was massive, however, resulting in a failure load in side shear of
0.44 MN. A second test shaft constructed using water as a stabilizing fluid
resulted in an ultimate load of 6.1 MN in side shear.
In example SS 108 a rock socket test shaft was drilled "dry" with
casing extending to the bottom of the shaft but with no water inside the
casing. The hydrostatic head outside the casing was 12.2 m. The 3.7 m
rock socket was then filled with concrete followed by pulling the casing
back about 4.0 m. Virtually no side shear bond developed between the
shale and concrete. The test shaft was reconstructed with casing
extending only to the top of \be rock socket and with water inside the
casing to counteract hydrostatic pressures. Concrete was placed by
tremmie methods. The side shear capacity of the reconstructed shaft
exceeded the capacity of the O-cell (10 MN).
In example SS 93 the test shaft was drilled through 30.5 m of
saprolite clay using a rotating corebarrel type casing technique. The
material inside the casing was removed with a clam type digging tool. The
casing was pulled in sections as the concrete was placed. The O-cell was
set at a depth of 15 m. A special "rifling" tool was used to roughen the
side walls of the 15 m. section of shaft above the O-cell. The test results
showed that the lower smooth-walled section of the shaft failed at a load
of 7.1 MN and a movement of 84 mm. The upper rifled section, however,
sustained a shear load of 10 MN with a movement of less than 2 mm.
Examples EB 128, EB 141 and EB 142 illustrate the impact on end
bearing capacity of loose material at the base of the shaft. In all three
cases the test shafts were drilled "dry" (i.e. no stabilizing fluid) making it
possible to see the base of the shaft. The rough estimates of the depth of
loose material at the base were made by "sounding" with a weighted tape
and by visual observations.
fte Third International Ceotechnical Engineering Conference - Cairo University - Egypt 5-8 January, 1997
j|f
O
; S^ \
2b
-
25 s * i
. .
- - Assumed compression of . ..
50 disturbed loose material
:
-
' L '.''.*
75
- ;
10
12 .... ——_-... .-•-...
HT^ ^-—^
5
1C
A 4 5 8 9 10
6
Load (MN)
Figure 11
The Third International Geotechnical Engineering Conference - Cairo University - Egypt 5-8 January, lggj
9.2 The O-cell testing method has many significant advantages over
conventional top-load-reaction testing, and often makes practical
an otherwise impractical testing situation.
9.3 The O-cell testing method has found its greatest use in the testing
of bored piles. Approximately 90% of such tests in the United
States now utilize this method.
9.5 Our experience shows that generally the stronger the supporting
material, the larger the ratio between the measured shaft capacity
and the prior engineering estimate of capacity. This ratio often
exceeds 10 in rock sockets!
List of References