Method Statement For Air Handling Unit

This document outlines the method for installing air handling units (AHUs) at the Brigade WTC project in Chennai. It describes storing the AHUs properly, preparing for installation by checking drawings and foundations, and installing according to drawings using vibration isolators and ensuring proper drain piping and electrical connections. Records of material inspections, installation checks, and fan performance tests must be kept.

Uploaded by

Binod Davis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
186 views7 pages

Method Statement For Air Handling Unit

This document outlines the method for installing air handling units (AHUs) at the Brigade WTC project in Chennai. It describes storing the AHUs properly, preparing for installation by checking drawings and foundations, and installing according to drawings using vibration isolators and ensuring proper drain piping and electrical connections. Records of material inspections, installation checks, and fan performance tests must be kept.

Uploaded by

Binod Davis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

STERLING AND WILSON DOC. No.

:
METHOD STATEMENT FOR AIR
SW-MS-AHU-03
HANDLING UNIT REV. No.: 00

PROJECT: BRIGADE WTC@CHENNAI

METHOD STATEMENT FOR

AIR HANDLING UNITS

INDEX
STERLING AND WILSON DOC. No.:
METHOD STATEMENT FOR AIR
SW-MS-AHU-03
HANDLING UNIT REV. No.: 00

PROJECT: BRIGADE WTC@CHENNAI

1. PURPOSE
2. MATERIAL
3. REFERENCES
4. PROCEDURE
4.1. STORAGE
4.2. PREPARATION
4.3. INSTALLATION
5. RECORDS

1. PURPOSE
Purpose of this SOP is to outline the method of storage, handling and installation of Air
Handling units, valve package.
STERLING AND WILSON DOC. No.:
METHOD STATEMENT FOR AIR
SW-MS-AHU-03
HANDLING UNIT REV. No.: 00

PROJECT: BRIGADE WTC@CHENNAI

2. MATERIAL
1. Air Handling Units
2. Rubber Pads / Vibration isolator’s etc. as per approval
3. Drain Pipes

3. REFERENCES

1. Manufactures catalogues and approval technical submittal.


2. Approved construction drawings.

4. PROCEDURE
4.1.STORAGE
4.1.1. AHU’s shall be stored on flat surface with suitable packing below the units.
4.1.2. All AHU’s shall be covered and shall not be exposed directly to the outside
Condition.
4.1.3. If AHU’s received in dismantled condition, then ensure that all loose parts like fans,
coils, base frame, panels… etc. received shall have unique numbers as per models
and shall be segregated and stored accordingly for easy retrieval.
4.2.PREPARTION
4.2.1. Check and ensure all drawings used for installation are latest and approved for
construction.
4.2.2. Check the foundations prepared if any, for installation are as per drawings.
4.2.3. If AHU’s to be hanged from the slab, check the supporting details.
4.2.4. Check the availability of space for removal of coils, filter, motors etc.

4.3.INSTALLATION
4.3.1. Install Air Handling Units as per approved drawings, duct orientation and model
nos. mentioned on the drawings. Use rubber pads or vibration isolator springs as per
STERLING AND WILSON DOC. No.:
METHOD STATEMENT FOR AIR
SW-MS-AHU-03
HANDLING UNIT REV. No.: 00

PROJECT: BRIGADE WTC@CHENNAI

approved drawing.
4.3.2. Check the slope of the drain tray in the direction of drain pipe connection.
4.3.3. Flow tests the drain tray and ensures water is drained out completely.
4.3.4. Complete the valve package and piping connections as per approved drawings.
Check the coil inlet and outlet with respect to the direction of air flow.
4.3.5. Use unions or flanges at the equipment connections for easy removal of pipe etc.
4.3.6. Ensure 3-way / 2-way valves, strainer are installed correctly as per direction of the
flow.
4.3.7. Connect the drain piping with U trap as per approved drawings or manufacture’s
recommendation depending upon the static of the fan.
4.3.8. Install the electrical power connections as per approved drawings.
4.3.9. Provide earthing as per approved drawings/manufacturers instruction.
4.3.10. Clean the interiors of AHU drain tray, ‘U’ trap in the drain piping.
4.3.11. Follow the manufacturer’s instructions while installing the AHU.

5. RECORDS
5.1.Signed off Material Inspection Request.
5.2.Signed off Installation request with installation check list
5.3.Fan Performance Test reports from Manufacturer.
STERLING AND WILSON DOC. No.:
METHOD STATEMENT FOR AIR
SW-MS-AHU-03
HANDLING UNIT REV. No.: 00

PROJECT: BRIGADE WTC@CHENNAI

FIG. OF AIR HANDLING UNITS DRAIN PIPE CONNECTION


STERLING AND WILSON DOC. No.:
METHOD STATEMENT FOR AIR
SW-MS-AHU-03
HANDLING UNIT REV. No.: 00

PROJECT: BRIGADE WTC@CHENNAI

For Sterling & Wilson For Consultant For Client


Name and
Signature
STERLING AND WILSON DOC. No.:
METHOD STATEMENT FOR AIR
SW-MS-AHU-03
HANDLING UNIT REV. No.: 00

PROJECT: BRIGADE WTC@CHENNAI