100% found this document useful (1 vote)
251 views1 page

RIZHLE Construction & Development Corp

The document is a letter from Lycon Asia Construction Inc. to RIZHLE Construction & Development Corp regarding outstanding DOLE requirements for a project. Lycon is requesting a response with a handover date for an installation schedule that was previously requested, as this information is critical for planning labor resources, material ordering, factory production slots, and installation lead times. Lycon asks RIZHLE to respond to the prior request for the installation schedule.

Uploaded by

Nick Latumbo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
251 views1 page

RIZHLE Construction & Development Corp

The document is a letter from Lycon Asia Construction Inc. to RIZHLE Construction & Development Corp regarding outstanding DOLE requirements for a project. Lycon is requesting a response with a handover date for an installation schedule that was previously requested, as this information is critical for planning labor resources, material ordering, factory production slots, and installation lead times. Lycon asks RIZHLE to respond to the prior request for the installation schedule.

Uploaded by

Nick Latumbo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

LYCON ASIA CONSTRUCTION INC.

IT OFFICE, 11/F, SM Aura Office Tower,


McKinley Parkway,BGC, Taguig
www.lyconasia.com | [email protected]

Ref. No.: LGC_LTR_RZL_0001 Date: 20th January 2020

RIZHLE Construction & Development Corp.


Punta Engaño, Lapu-lapu City

Attention : Kimwell Gonzales


Project In Charge - RIZHLE

Subject: DOLE Requirements

Further to our previous request for the above mentioned schedule and our
submitted letter under Ref. No. LGC_LTR_L3PT_002 dated 29 th April 2019, we
advise this vital information is still outstanding and critical for our planning and
preparation of foreign & domestic labour resources, material ordering and delivery,
production / manufacturing slots within our supply chain factories, and may prolong
the lead time required before site installation.

Please advise the handover date of the above installation schedule by responding to
our above RFI for our further coordination and actions.

Best Regards,
On behalf of Lycon Asia Inc.,

______________
Dennis Elton
Project Manager