Fdocuments - in Design Gantry Crane Calculations
Fdocuments - in Design Gantry Crane Calculations
factors should be taken into consideration. It is important to D. Power Unit and Motor Selection
note that the moment is generally uniformly distributed Considering power calculations, a 7 KW diesel engine
across the girder when the load is at the crane central axis derived generator is used as a power unit for the crane to
and maximum on one of the legs when the load is at the feed the four 0.75 KW reduced electric motors that are used
other leg of the crane. Therefore, good support at both legs in the mobility system, the 3 KW reduced electric motor
is necessary to keep the system in balance. Lateral braces at that is used in the hoisting mechanism, and the 1 KW
the girder in addition to cross side braces at the top half and reduced electric motor that is used to drive the wheeled
bottom
On the half of hand,
other the pillars
it isoffer a solution
intended for such
to have problem.
the center of carriage.
swing All speeds
as well areeffects.
as inertia limited to 0.015 m/s to avoid load
gravity of the system located as near as can be to the bottom
of the crane chassis structure, and so the center of mass III. COMPUTER MODELING AND DESIGN VERIFICATION
obligates the system to remain in balance, regardless of the
In this stage of the design procedure, it is important to
magnitude of the load, which is expected to be less than the make sure that the crane chassis design is applicable. A
total mass of the crane. This can be achieved through complete stress analysis of the crane chassis structure is
designing the chassis structure base to cover an area that performed using a computer model that has been developed
keep appropriate position of the center of gravity along the for the crane chassis with all forces, moments and
chassis central axis. constraints distributed on it to calculate von mises stresses,
Other factors to be considered during the design of the first principal stresses and third principal stresses that
crane can be summarized in the resistance due to load influence the crane. The results show acceptable values of
swing, the influence of the wind, and the acceleration of the safety factors and strains, as shown in Fig. 3 to Fig.11.
moving masses. However, these factors can be ignored
considering lack of wind effect due to indoor operation, and
choosing low speeds for load hoisting and movement.
Another important factor is to ensure the operating safety as
a simple mistake can lead to tragic accidents most of which
are caused by unsecured load and load capacity exceeded
[13]. The chassis different parts are standard steel parts that
are connected using welding and bolted joints to form the
final chassis structure. All structure parts, welding and
bolted joints are checked for shear stresses, crushing
stresses and bending moment stresses using the
recommended factors of safety [9].
swing
results, and damping
shown in Fig. friction [17].
13, it can From loadthat
be concluded oscillation
the load
swing is within an acceptable range [2] without any further
requirements for anti-swing special controller.
control the two motors which drive the carriage and load
hoisting mechanism. The control circuit components
include breed board, wires with pushbuttons, 2 DC- geared
motors' drivers, resistors, encoder sensors, limit switch
sensors and 12v battery used as a power source. Each motor
is attached to two digital pins from the Arduino, one of
digital pins is used to control the speed through pulse width
modulation
motor shaft (PWM)
rotation variations
direction. and the other
However, to control
in this design the
the
motor speeds are selected such that their speeds are kept
low and constant to avoid load swing and inertia forces.
Two twelve step rotary encoders are used for controlling
the horizontal distance travelled by the carriage and the
vertical distance travelled by the wire during lifting or
Fig.12. Simulink Setup for gantry Crane lowering the load, same installation procedures from [18] is
used.
presented in this paper have been passed to a contractor The chassis is considered as the skeleton of the crane since
that is compliant to gantry crane manufacturers’ it holds all the crane systems together. It consists of the
requirements. The contractor builds the crane using a dated girder, 10 knees, 2 pillars, and four wheel mounted joints
working plan according to implements requirements base. The girder is made of a steel I-beam connected to the
criteria from [9-12]. The crane consists of five main two crane pillars that are made of hollow square cross
components which are the crane chassis, the hoisting section beam, which are supported together by 10 knees
mechanism, the crane mobility system, the control unit, and made also of hollow square cross section beam with the
CONCLUSIONS
This
duty paper presents
gantry crane the
thatdesign
can and implementation
be used to executeof indoor
a light
materials handling operations within small workshops. The
crane design, which includes the crane chassis structure
stress analysis as well as the construction of the crane
trolley mechanism and mobility system, has been discussed.
We have also discussed the design of the crane control
circuit that includes steps such as modeling of the dynamic
crane behavior, the selection of an appropriate control
Fig. 18. Crane control unit strategy, and validation of the control circuit using a
prototype of the gantry crane. All design reports, blueprints,