National Cancer Institute Egypt Resources Calculation Sheet

The document is a resource calculation sheet for construction of the National Cancer Institute Egypt. It lists 31 different construction crews needed, including their staffing, expected productivity rates, quantities of work, and estimated duration to complete activities like excavation, concrete works, masonry, plumbing, and more. The purpose is to calculate the labor needs and durations for all construction activities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
306 views3 pages

National Cancer Institute Egypt Resources Calculation Sheet

The document is a resource calculation sheet for construction of the National Cancer Institute Egypt. It lists 31 different construction crews needed, including their staffing, expected productivity rates, quantities of work, and estimated duration to complete activities like excavation, concrete works, masonry, plumbing, and more. The purpose is to calculate the labor needs and durations for all construction activities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

National 

Cancer Institute Egypt
Resources Calculation Sheet

No. of Crews Productivity


SR Crew Name Description Activity Name Expected QTY Duration (Days)
(Average Per Day) Rate/Day

Excavation 2 750 45 8 M3
1 Excavation Crew 2 Labors
Backfilling 2 250 14 9 M3

2 Formwork Crew 1 Carpenter + 1 helper 3 700 59 4 M3


Concrete Works
3 Steel Fixing Crew 1 Steel fixer + 1 helper 2 700 109 3 M3

4 Concrete Placing Crew 2 Skilled + 2 Helper Concrete Works & Flooring Works 1 2,400 307 8 M2

5 Survey Crew 1 Skilled + 1 Helper Miscellaneous Activities 2

6 Masonry Crew 1 Skilled + 1 Helper Block Works 8 24,250 186 16 M2

7 Insulation Crew 1 Skilled + 1 Helper Insulation Works 4 17,300 224 19 M2

8 Plaster Crew 2 Skilled + 2 Helper Plaster Works 10 51,650 240 22 M2

9 Painting Crew 2 Skilled + 2 Helper Painting Works 8 29,600 234 16 M2

10 Gypsum Board Crew 2 Skilled + 2 Helper Gypsum Works 3 15,100 277 18 M2

11 Terrazzo Crew 1 Skilled + 1 Helper Terrazzo Flooring 2 5,500 105 26 M2

12 Marble Crew 1 Skilled + 1 Helper Marble Works (Floors & Walls) 2 12,700 320 20 M2

13 Tiles Placing Crew 1 Skilled + 1 Helper Ceramic / Porcelain Works 2 5,820 168 17 M2

14 Epoxy Crew 1 Skilled + 1 Helper Epoxy Flooring 1 250 10 25 M2


National Cancer Institute Egypt
Resources Calculation Sheet

No. of Crews Productivity


SR Crew Name Description Activity Name Expected QTY Duration (Days)
(Average Per Day) Rate/Day

15 Vinyl Crew 1 Skilled + 1 Helper Vinyl Flooring 4 4,000 40 25 M2

16 Aluminum Crew 1 Skilled + 1 Helper Aluminum Works (Windows) 2 3,600 150 12 M2

17 Wooden Works Crew 2 Skilled + 2 Helper Wooden Works (Doors) 2 513 91 3 Door

18 Glass Crew 1 Skilled + 1 Helper Glass Works 4 950 60 4 M2

19 Metal Crew 1 Skilled + 1 Helper Metal Works 3

20 Curtains Crew 1 Skilled + 1 Helper Curtain Works 1 1,000 119 8 M

21 Branding Crew 1 Skilled + 1 Helper Branding Works 1 200 20 10 No.

22 Furniture Crew 1 Skilled + 1 Helper Furniture Works 4

23 HVAC Crew 1 Skilled + 1 Helper HVAC Works (Pipes) 6 93,300 350 44 KG

24 Firefighting Crew 1 Skilled + 1 Helper Firefighting Works (1st Fix) 4 4,922 210 6 M

25 Electrician Crew 1 Skilled + 1 Helper Electrical Works (1st Fix) 5 6,783 294 5 Point

26 Light Current Crew 1 Skilled + 1 Helper LC Works (1st Fix) 3 2,200 210 3 Point

27 Data Crew 1 Skilled + 1 Helper Data Works (1st Fix) 4 832 120 2 Point

28 Elevator Crew 1 Skilled + 1 Helper Elevator Works 2

29 Medical Gas Crew 1 Skilled + 1 Helper Medical Gas Works (1st Fix) 4 8820 394 6 M
National Cancer Institute Egypt
Resources Calculation Sheet

No. of Crews Productivity


SR Crew Name Description Activity Name Expected QTY Duration (Days)
(Average Per Day) Rate/Day

30 Plumbing Crew 1 Skilled + 1 Helper Plumbing Works (1st Fix) 3 7,470 300 8 M

31 Unskilled Labor Miscellaneous Activities 10