Stee Vs Concrete Bridges
Stee Vs Concrete Bridges
In the good olden days, for higher spans, steel girders whether plate girders or
triangulated girders were pre-dominantly used. After the advent of pre-stressed concrete,
its use in higher span bridges increased tremendously. Main reason behind use of PSC
girders is due to its initial economical cost. No doubt, PSC girders are economical in the
initial stage of construction, but the same may not be true if we consider the life cycle
cost including other factors. In this paper, author is trying to explain the various factors,
which are mainly ignored while favouring PSC girders over steel girders.
1. Introduction:
In any infrastructural development of a country, Bridge construction is one of the most
important constructions. It is very costly structure as compared to others. Lot of
considerations are required in doing the investigation, deciding its configuration, type
span and final construction of the bridge. A Bridge properly constructed will serve the
cause successfully without any hindrance for a longer period and at the economical cost.
Changes in shape, material, configuration and practice have been a continuous process
for safe, expeditious, economical and elegant construction of a bridge. For higher spans,
in the olden days, steel girders were predominantly used, whether that was for Railway
Bridge or Road Bridge or Rail cum Road Bridge. Technology of pre stressed concrete
was developed around 1935. First bridge of pre-stressed concrete was constructed
simultaneously in many countries of Europe around 1940. India was not lagging behind
in adaptation of this technology. In India, first time, Indian Railways used PSC Girder
Bridge in 1949 on Assam Rail Link Project followed by another PSC girder bridge by
PWD/ Tamil Nadu. After that, a new era of bridge construction had started. Now, most
of the bridges particularly of higher spans are made of pre-stressed concrete.
Adaptation of new technology is always a good thing. In similar fashion, prestressed
concrete technology for bridges was not only welcomed but was also adapted in such a
way, which seems to be somewhat erroneous. Result is that, everywhere, PSC girder
bridges are being adopted without giving consideration to many factors.
Main reasons for not preferring steel girder bridges are:
v Its initial cost is more.
v It requires recurring expenditure in painting.
In contrary to that, about PSC girders, it is believed that:
v PSC girders are cheaper.
v It does not require any type of maintenance.
1
No doubt, PSC girder bridges are economical in initial cost, but the same may not be true
considering life cycle cost of a PSC girder bridge as compared to that of steel girder
bridge. To illustrate the matter, let us examine some of the aspects to visualise about the
factual position.
2. Availability of configuration and its repercussion on fixing the rail level:
Leaving about plate girders, which are adapted in Railway bridges upto 30.5m (100 ft)
spans, for 30.5 m span and above (it is worth while to point out that for 30.5 m span,
standard drawing for plate girder and triangulated girder, both are available), 3 types of
shapes are available in steel bridge i.e.
Ø Deck type of triangulated girder.
Ø Semi through type of triangulated girder
Ø Through type of triangulated girder
Adaptation of any of the above mentioned type depends upon the situation. Deck type
shape is adopted where HFL is much below the formation level of the approach
embankment of a bridge. Semi through and through type of triangulated girders are
adapted where HFL is high and as such, deck type of triangulated girder is not possible to
provide.
Let us look about the prestressed concrete girder bridge side. Most of the PSC girders are
of deck type. Hence, alternative to deck type of triangulated girder bridge is available in
PSC Girder Bridge also. Now think about alternative to semi through and through type of
steel girder bridges. In case of PSC girders, two alternatives are available, ie either to
adapt deck type of PSC girder or to go for special type PSC girders of bow- string
configuration. Due to special configuration, bow- string type may not have the same cost
advantage as in case of normal shape of PSC -I girders and box girders.
For a time being, overruling the possibility of bow- string girders, now again come to the
deck type of alternative. With the standard PSC girders and steel girders, a comparison
has been done among the two as per standard plan of RDSO and the same is shown in
table No.-1
From table No.-1, it is clear that total height from bed block to rail level in case of the
PSC girder bridges (particularly for PSC box girders), are almost matching with that of
steel girders for smaller spans i.e. for 12.2m and 18.3m spans. In case, I type of PSC
girders are selected, although total height from bed block to rail level will be more as
compared to that parameter of the corresponding spans of steel girders. Here, we see that
the rail level difference being of 740 mm and 846 mm for 12.2 m and 18.3 m spans
respectively. Since the differences are not of appreciable value, hence, the same can be
ignored.
As and when the spans are increasing, rail level difference between the PSC girders and
the steel girders are increasing tremendously for the same span. Due to increase in rail
level, particularly in case of adaptation of PSC girders, height of embankment will have
to be raised. Raising of embankment height will cause many complicacies. Let us come
to those complicacies and evaluate its repercussion.
2
Table No.1
Rail level difference in PSC girder and steel girder for different spans.
3
3. Repercussion of higher rail level in case of PSC girders:
From Table No.1, we have seen that in case of adaptation of PSC girders, rail level will
be more than that of steel girders of the same span. For this, we have to raise the
embankment height so as to provide the required vertical clearance with reference
particular HFL by certain amount as shown in the last column of table No.-1. Raising of
embankment by this additional height is with reference to the through type of triangulated
steel girder bridges of the same span. Additional raising of embankment will require
extra land width, extra earthwork and finally extra energy consumption in climbing of the
trains by that much extra height. It is worthwhile to point out that extra energy
consumption will be of recurring nature.
For comparison sake, calculation has been done regarding the extra energy consumption
in case of PSC girder bridges with reference to steel girder bridges for 4500 tonnes goods
train (a standard load configuration of a goods train) and 15 coaches of passenger train.
The same is reflected in table No.-2.
Table No.2
Details of extra energy consumption, extra land area required and extra
earthwork in case of PSC girder bridges for different spans.
Theoretical
Rail Extra
Extra energy consumption extra land
level earthwork in
and cost area in
differ cubic meter
square meter
ence
For 4500 For 15 coach
Span in
S tonnes goods passenger
in PSC
N train train For 1 For 1 For 1 For 1
meter and
Steel Ene Ene Appro in 100 in 150 in 100 in 150
Approx
gird -rgy -rgy ximate gradi gradi gradi- gradi
imate
-er in in in cost in -ent -ent ent -ent
cost in
meter Joule Joule Rup
6 Rupees
x10 x10 6 -ees
1 30.5 1.47 71.3 79.2 14.3 15.9 6406 9609 19985 29978
2 45.1 2.62 127.1 141.2 25.4 28.2 12624 18936 45571 68357
3 61.0 3.50 169.8 188.7 34.0 37.8 19485 29227 72301 108452
4 76.2 4.90 237.7 264.1 47.5 52.8 28077 42116 129794 194691
5 92.0 7.00 339.6 377.3 67.9 75.4 45990 68985 256435 384653
While calculating the extra energy consumption, theoretical value has been enhanced by
10.0% to accommodate the efficiency factor and additional resistance on account of
gradient due to climbing. Further more, cost of electricity has been taken as Rs. 4.0 per
unit (the cost taken from the Electrical department, which on an average basis, Railways
is paying to the Electricity Boards).
4
Due to fixing of higher embankment height, land requirement and earthwork in the
embankment will also be more. Hence, these two parameters have also been worked out
and shown in table No.2. Requirement of land width and earthwork is a function of bank
height. Hence, for calculation purpose, bank height of 3.0 m, just at the approach of the
river bridge has been taken, which can be considered as a representative height in most of
the bridges. With this reference, for single line having bank width of 6.85m for PSC
sleeper at the top and embankment slope of 2 H to 1 V, extra land requirement and
earthwork has been worked out.
Table No. 3
Cost of PSC girders:
There are so many factors affecting the cost. On an average, upto 30 m span, cost of PSC
girders are coming as 1.2 lacs /running meter including cost of sub structure and super
structure. Average cost of 92 m span is coming to Rs.3.86 lacs/m including cost of sub-
structure and super structure. Out of Rs. 3.86 lacs/m run, Rs. 1.83 lacs/m run is the cost of
substructure and Rs. 2.23 lacs/m run is the cost of super structure
5
4.2. Cost of steel girders:
Recently, Construction Organisation of the Northern Railway has called for tender for
steel girder bridges of various spans. Tender is under finalisation. Rate of the lowest
tenderer i.e. of M/s Triveni Structural, Allahabad is given in table No.-4
Table No.4
Cost of steel girders:
S Span Weight per Base price Quoted rate Total rate per tonne
N span tonnes per tonne above base price including launching
1 80.0m 350 Rs.61000/- 6.5% Rs.64,965/-
6
In the above table, in case of PSC girder bridge, extra cost of land at the rate of Rs. 10 per
sq.m. and extra cost of earthwork at the rate of Rs.50 per cubic meter has been taken.
4.4 Comment about initial high cost of steel bridges based on table No. 5:
We have discussed in the introduction part that first and foremost reason behind
discarding steel girder bridges are due to its initial high cost. Hence, it is necessary to
examine this aspect first
From table No.5, it is clear that for single span, even steel girder is cheaper as compared
to PSC Girder Bridge. For two spans and above, position reverses and PSC Girder
Bridge becomes cheaper than the steel girder bridge. This is so, since quantity of
earthwork and land width will remain the same for multi span bridge or single span
bridge. Hence, position reverses for multi span bridge in case of PSC girder and it seems
to be cheaper than the steel girder bridge. This aspect is clear from row no.1 & 2 of table
No.5.
Vide table No.2; we have already seen that in case of PSC girders one time extra
expenditure is there in extra land requirement and extra earthwork. This aspect has
already been accounted for in row No.2 of table No.-5.
To work out further, cost difference between steel girder and PSC girder has been worked
out in row No.3. This amount can be considered as an extra amount blocked in steel
girder bridges at the time of initial construction. Taking 10% as interest rate, in row
No.4, interest amount accrued on annual basis for different span has been worked out. In
table No. 2, it has already been worked out that for 45.72 m of span, extra cost incurred in
counteracting the extra height in case of PSC Girder Bridge for one goods train of 4500
tonnes (standard load configuration of goods train) is Rs.141.2 and for passenger train of
15 coach is Rs. 28.2. Combined extra operational cost of one goods train and one
passenger train is coming to Rs. 169.4. For comparison sake, combination of one goods
train and one passenger train has been taken as one pair of train.
In row No.5, it has been shown that the per year interest amount on the cost difference is
compensated if 3.2 pair of trains on an average basis is operating on daily basis in case of
two span bridge. In case of three, four and five spans bridge, numbers of pairs of trains
are coming to 7.7, 12.2 and 16.8 respectively. It mean to say that when calculated
numbers of pairs trains are in operation on steel girder bridge, then the interest amount of
the initial extra expenditure over the PSC girder bridge of the same span will be
neutralised. If the pairs of trains are more than the calculated one, then the steel girder
bridge will prove cheaper than the same span of PSC Girder Bridge
To have further better idea about the two types of bridges, in row No.-6,corresponding
annual Gross Million Tonnes of traffic requirement equivalent to the numbers of goods
train shown in row No.-5 has been worked out. Here, passenger trains figure has not been
taken into account, since passenger trains are not being counted while calculating the
gross million tonnes (GMT) of traffic in railway parlance.
7
After having a glance from beginning to the end of table No.-5, we come to the
conclusion that it is rightly said that:
“ ALL THAT GLITTERS IS NOT GOLD ”.
It means to say that even for multi span PSC Girder Bridge and even initial cost being
favorable to PSC girder bridge, in overall scenario, steel girder bridges may be cheaper if
we account for the other expenditure like additional operational cost.
In the above calculation, principal amount of cost difference has been kept reserved
purposely. We will consider it subsequently.
4.5 Review of recurring painting cost of steel girder bridges:
The second most important disadvantage of the steel girder bridges is said to be about its
recurring painting cost. This aspect has also been examined and the details worked out is
shown in table No.-6: Table No. 6
Examination of recurring painting cost
S Three
Item One span Two spans Four spans Five spans
N spans
1 Difference in cost of - 814500/-
steel girder and PSC (by this
girder as per table No.5. amount
steel bridge 1978300/- 4771100/- 7563900/- 10356700/-
is cheaper
at initial
stage itself)
2 Present cost of painting
(including labour and 66000/- 132000/- 198000/- 264000/- 330000/-
material.)
3 Cumulative capitalised
cost for 11 numbers of
13561680/- 27123360/- 40685040/- 54246720/- 67808400/-
paintings in the life of
bridge with 5% interest.
4 Sum of row 1 and 3. - 29101660/- 45456140/- 61810620/- 78165100/-
5 Scrap steel* after useful
115 tonnes 230 tonnes 345 tonnes 460 tonnes 575 tonnes
life
6 Present cost of scrap*
920000/- 1840000/- 2760000/- 3680000/- 4600000/-
@ Rs.8000 per MT.
7 Scrap value after 60
years life of the bridge
17185600/- 34371200/- 51556800/- 68742400/- 85928000/-
assuming the same
escalation i.e. @ 5%.
8 Percentage gain in steel Already
bridge over PSC girder cheaper in
(with reference to row the initial
18.1% 13.42% 11.21% 9.93%
no. 4 & 7 ) stage of
construct-
ion itself.
* Here, scrap value of channel sleepers has not been taken. However, for working
out of the initial cost of steel girder bridges, cost of steel channel sleepers has already
been taken.
8
In this table, row No.1 is the same as row No.3 of table No.5 and hence needs no
illustration. Row No.2 is the present painting cost including labour and material. For
working out row No.3, assuming life of steel bridge as 60 years (as specified in Financial
code of the Indian Railways), total 11 number of times paintings will be required.
Cumulative cost of all the paintings at the end of 60 years have been worked out
assuming escalation @ 5% per annum.
Since annual interest amount of the cost difference of steel girder and PSC girder bridge
has already been consumed in compensating extra fuel consumption, so after life of the
bridge, only principal amount of the cost difference will be available. Hence, in row
No.4, summation of row No.1 and 3 has been done. Row No.5 is the quantity of scrap
steel. Its present value is given in row No.6. Assuming escalation @ 5%, scrap value at
the end of life of the bridge has been worked out and shown in row No.7. In row No.8, it
has been tried to show that steel bridges are cheaper by different percentages varying
from 18.1% to 9.93% for 2 span bridges to 5 span bridges.
This table shows that steel bridges are still cheaper. Or, we can here safely conclude that:
On the initial extra expenditure in case of steel bridges, interest rate of 10% has been
taken, treating the initial extra expenditure as blocked amount. In near future, rate of
interest is likely to decrease. Decrease in interest rate will make the steel bridges more
favourable since in that case, even in lesser volume of traffic, steel and concrete bridge
will become at par. On painting cost, inflation rate of 5% has been taken on the following
consideration:
Ø On steel scrap value also, inflation rate of 5% has been taken which is based on
past experience and rough estimation.
4.7 Other parameters affecting cost of steel and PSC girders, whose exact amount
has not been worked out.
There are so many other items whose cost calculation is difficult but play an important
role in selection of a type of bridge. Some of those items are given in table No.-7
9
Table No.-7
Other factors governing cost of the bridge
S
Items Steel Girder PSC Girder Remarks
N
1 Change Normally not Elastomeric bearings Data is based on the idea taken
of required require replacement in from manufacturer of the
bearings during the 15-20 years and bearings. Here, exact cost of
. lifetime of the PTFE/POT bearings replacement of bearings of PSC
bridge. require replacement in girders is difficult to work out
about 20-25 years. due to vague idea of traffic loss,
resulting revenue loss
2 Life of Comparatively Comparatively less. More life of the steel bridge will
the more. make it more cost competitive
bridge. than the PSC girder bridge
3 Inspecti Easy, reliable Difficult, not so Even field maintenance staffs
. on and worth reliable and difficult can easily visualise the health of
understanding to understand for steel bridge, It is difficult for
even to skilled skilled artisans them to visualise the same for
artisans. PSC girder bridge
4 Repair Easy to repair Difficult to repair and Departmental field maintenance
. and and maintain. maintain. staffs are competent to do the
mainten maintenance of the steel
ance bridges, while the same may be
difficult for them to maintain
PSC girder bridges with the
same confidence
All the above factors show positive and favourable indication towards steel girder
bridges.
4.8 Cost difference in other spans higher than standard span of 45.72m:
Due to non-availability of exact cost of PSC Girder Bridge in case of higher spans i.e. of
61.0 m and 76.2m of standard Railway spans, precise comparison is not possible.
However, a rough estimate has been done for next higher standard span of 61.0m for a
two span bridge. Two span bridges has been taken purposely since in the above example,
we have seen that even initial cost wise, single span bridge of 45.72m of steel girder is
cheaper than that of PSC girder bridge. (After taking extra land and earthwork cost in
case of PSC Girder Bridge).
Fabrication, erection including provision of channel sleeper cost of two span of 61.0m
steel girder bridge is coming to Rs. 26740200/- (excluding cost of foundation common
land and common earthwork cost) Let us assume that the total cost of the bridge of two
spans of 61.0 m each of PSC girder and steel girder will be the same. After adjusting the
extra cost of land and earthwork, cost of each PSC girder is coming to Rs.10336000/-
Without having exact idea of cost of PSC girder of 61.0m span, it is difficult to comment
whether per girder cost of PSC girder of Rs.10336000/- is appropriate or not? With this
cost, its per meter cost is coming to Rs. 1.69 lacs/ m run.
10
However, one more exercise has been done for 61.0 m of PSC girder span assuming its
cost as Rs.7500000/-(i.e. Rs. 1.23 lacs/ m run). At this cost, cost difference between the
steel girder and PSC girder is coming to Rs.5672100/-. In the similar fashion, to offset
the interest amount of the cost difference with the extra haulage cost due to additional rise
in case of PSC girder, 6.9 pairs of train per day on an average basis will be sufficient.
6.1 Merits
As we have already mentioned in the introduction part that PSC girder bridges are having
so called following two merits:
v Initial construction cost is less.
v PSC girders are maintenance free.
Based on the discussion till now, we have seen that initial construction cost of PSC girder
bridges is less. But after including operational and life cycle cost, steel girder bridges
becomes cheaper than that of PSC girder bridges. Hence, first merit about less initial
construction cost has no relevance.
As far as so-called maintenance free aspects of PSC girders are concerned, that does not
seems to be justified. Further more, it is too early to say that PSC girder bridges will not
require any maintenance. Example of some of the PSC girder bridges reveals that
11
maintenance is also required for PSC girder bridges. Keeping in view these aspects only,
corrosion protection, durability criteria etc came up and now are being followed.
Further more, steel girder bridges are criticized for its regular maintenance, particularly
regarding painting aspects. But, normally we forget about the replacement of bearing
aspect part in case of PSC girder bridges. In the life of a PSC girder bridge, at least two
times bridge bearings will need replacement. Replacement of bearings will not only incur
extra expenditure but will also dislocate the traffic. This will further result inconvenience
to the public and also cause revenue loss.
One more merit of PSC Girder Bridge is about its facility of providing the same track
structure like in approaches. No doubt, this merit is excellent one. But in steel girder
bridge, no such disadvantages are there either in shape of speed restriction or any, which
may discourage the existing track structure on bridges. In addition, RDSO has
standardised and issued many steel girder drawings having ballasted deck. On
problematic locations, if any, one can adapt ballasted deck type of steel girders.
6.2 Demerits:
As far as demerits of the PSC girders are concerned, these are-
12
While in case of steel girder bridges, not only repair and maintenance is easy but also
after repair/maintenance/strengthening, field engineer will be 100% sure about restoration
of its potential. In case of steel girder bridges, even strength can be increased than the
existing strength.
In contrary to that, in case of steel girder bridges mostly roller-rocker type of bearings is
provided. These bearings normally serve upto the useful life of steel girder bridge. This
is also an added advantage in case of steel girder bridges.
7.1 Merits
There are many advantages of steel girder bridges, which is not available in PSC girder
bridges. Some of them are listed as below:
13
of money, otherwise new plate girder bridges had been fabricated spending not only
money but consuming appreciable time also. This time saving also ensure timely
completion of the gauge conversion projects.
There might be so many similar other examples also whose details are not readily
available to the author.
7.1.3 About re-use of the plate girders and triangulated girders for smaller spans:
Time to time, loading standard on railway was revised as per requirement. Due to
revision in loading standard, old bridge had become weak for the same span, even though
its condition was good. Instances are there, when such old bridges were removed from
the track, new bridges were provided on those locations and the released one were
modified to suit for smaller spans and accordingly used.
14
Such type of flexibility is only available in steel girder bridges. In PSC girder bridges,
thinking of such type of possibility is like a dream.
15
It is worthwhile to point out that modification works on most of the bridges have already
been completed except two, which will be taken in hand after completion of the works
already in progress.
Such type of repair and strengthening is only possible with steel bridges.
In case damage is very severe, and span needs to be replaced, then in case of PSC girder,
replacement of the span is very much cumbersome job and likely to take a longer time.
In present day situation, closure of bridge for longer time cannot be allowed. It may
result huge loss to the national economy.
Reserve stock for steel girder bridge can be maintained and its transportation is also
easier. Reserve stock of PSC girder is neither feasible nor easy since the transportation is
very difficult.
16
One burning example of Central Railway is worth mentioning. One of the bridge which
was having 14 nos. of spans of 24.4m (80 ft.) each and having pier height of about 18m,
met with an accident due to derailment of some of the goods train in 1994. All the 28
girders (up and down line both) of the bridge were affected due to derailment. Keeping
in view the quantum of work, Northern Railway bridge staffs were also deputed. It is
worthwhile to mention that all the girders were reused after some
rectification/strengthening.
If similar incidence has been taken place in case of PSC Girder Bridge, same type of
recovery is almost unthinkable.
7.1.7 Restoration of the bridge in case of washing away due to flood and breaches:
Indian Railway is having so many experiences wherein due to flash but welding piers had
been washed away resulting this location of the girder. In case of plate girder bridges,
girders have been recovered and after construction of a new pier the same has been again
put in position.
Details of some of the girder bridges recovered after washing away is given as below.
List might be very lengthy. But particulars of those bridges are not known to the author at
present.
Table No.-10
Details of steel girder bridges re-used after washing away
S Bridge
River Section Span Remarks
N No.
105x12.2
m (steel)
Mana Out of 105 no of spans of plate
+40x12.
Pamban Madurai- girder, 104 nos. washed away
1 2m
Viaduct Rameshwa out of 40 nos. of PSC girders, 19
(PSC)
ram nos. washed away
+1x61.0
m (steel)
196,
Local Pathankot- near Pier was washed away. Same
2 3x40 ft.
nala Jammu Vijay girders were reused.
Pur
216,
Local Pathankot- Pier was washed away. Same
3 near Bari 3x40 ft.
nala Jammu girders were reused.
Brahman
Under slung girder fell down
Local Allahabad- due to washing away of
4 -- 1x150 ft.
nala Mughal Sarai foundation. The same was
reused on new foundation.
Due washing away of the
foundation, girders fell down
Patiala- Rajpura- 35, near
5 5 x 40 ft. and were found about a 200 m.
ki-nadi Dhuri Patiala
on down stream side. Same
girders were reused.
17
Regarding this experience of Pamban viaduct of the Southern Railway is worth quoting.
Pamban viaduct is the bridge connecting Rameswaram with the mainland of the country.
In the night of 22nd/23rd December 1964, one cyclone unprecedented to the history of
region came. That cyclone washed away 104 nos. of steel girders of 12.2 m spans (out of
total 105 nos.) and 19 nos. of PSC girders out of total 40 nos. The only steel girder,
which remained intact, was the Sherzer span, which is a lift span. Probably that a span
could not be dislocated due to its heavy weight as well as due to its comparatively
stronger fixing arrangement. For restoration of Pamban viaduct, search of girders from
South (Kanyakumari) to North (Jalandhar) and from East (Guwahati) to West (Sabarmati)
were on. Meanwhile it was tried to recover the dislodged girders from the sea. To the
much strange, all the washed away plate girders were successfully recovered, given
proper treatment and again placed in the position. Such a massic damage required only
42 days of closure of traffic. Such a glorious achievement was only possible due to steel
girder bridge. It is worthwhile to point out that even washed away PSC girders were
recouped by new steel girders.
In case of PSC Girder Bridges reuse of the same is not possible at all due to most
probably damaging of the same beyond repair and due to further its relaunching problem.
In case of steel girder bridge particularly of smaller spans of plate girders, maximum
chances are there regarding reuse of the same.
18
Table No.-11
Details of Railway bridges now being used as road bridges
10. Recommendations:
11.Conclusion:
PSC girder bridges, which seem to be cheaper than the steel girder bridges on the initial
cost of construction basis, may prove even costlier after considering its life cycle cost.
Hence, consideration of life cycle cost is more realistic to arrive at the appropriate
alternative.
Note:
i) This paper was published in the Indian Institute of Bridge Engineers Seminar paper
held at Mumbai in April, 2002. Although, data about rates are about 3 years old, yet
conclusions and other facts derived in the paper still hold good.
ii) This paper presents views of the author and not views of Ministry of Railways.
19