2.4 Line Balancing
2.4 Line Balancing
A Simple Precedence
0.1 min. 1.0 min. Diagram
a b
c d e
0.7 min. 0.5 min. 0.2 min.
Cycle Time
n
∑ ti Actual Maximum
i=1
N= Cycle = work station
Cd Time time
n
∑ ti Cycle Time = 1/Throughput rate
i=1
E=
nCa Where,
N = Minimum no. of workstations
Balance E = Efficiency
i = no. of work elements
Delay = 1 – Efficiency ti = completion time of element i
Cd = desired cycle time
Idle time = nc – t Ca = actual cycle time
n = actual no. of work stations
Line Balancing Rules
Some Heuristic (intuitive) Rules:
Most Following From the available tasks, choose the task with
Task the largest number of following tasks
0.2
B Precedence
Diagram
0.1 A D 0.3
C
0.4
Production time available 40 hours* 60 minutes/hour
Cycle Time = =
Desired units of outputs 6000 units
2400
= = 0.4 minutes
6000
n
∑ ti
i=1 0.1 + 0.2 + 0.4 + 0.3
N= = = 2.5 workstations ≈ 3 workstations
Cd 0.4
A, B C D
0.3 minute 0.4 minute 0.3 minute
Illustration 2:
480 available minutes per day
40 units required
Task Precedence Time
A - 10
B A 11
C B 5
D B 4
E A 12
F C, D 3
G F 7
H E 11
I G, H 3
Total Time 66
Precedence
4 Diagram
D
10 11 3 7
A B F G
5
C
12 11 3
E H I
Production time available 480 minutes
Cycle Time = = = 12 minutes/unit
Desired units of outputs 40 units
n
∑ ti
i=1 66
N= = = 5.5 workstations ≈ 6 workstations
Cd 12
2 B 1 C, D, E, F, G, H, I
3 C 7 E, G, H, I
D 3
F 0
4 E 0 G, H, I
5 G 5 H
I 2
6 H 1 None
Work
station 3
Work Work 4
station 1 station 2
D
10 11 3 7
A B F G
5
C
12 3
11
E H I
Work Work Work
station 4 Station 6 Station 5
Assembly line has an efficiency of -
n
∑ ti
i=1
E=
nCa
66
=
6*12
66
= = 0.917 = 91.7%
72
Balance
Delay = 1 – Efficiency
B D
5
A F 6
C E
13 7
Production time available 8 hour*60 min/hr
Cycle Time = = = 20 minutes/club
Desired units of outputs 24 clubs
n
∑ ti
i=1 44
N= = = 2.2 workstations ≈ 3 workstations
Cd 20
4 9
Work
station 1 B D Work
station 3
5
A F 6
10
F
50 5 25 15 12 18
A B C D E H I
15
G
15
Production time available 60 min/hour * 60 sec/min
Cycle Time = =
Desired units of outputs 60 units/hour
n
∑ ti = 60 sec/unit
i=1 165
N= = = 2.75 workstations ≈ 3 workstations
Cd 60
Work
Work 10
station 2
station 1 F
50 5 25 15 12 18
A B C D E H I
15
Idle Time = 5 mins
G Idle Time = 5 mins
15
Idle Time = 5 mins
Illustration 5: The precedence diagram for a
assembly activities A to G is shown in table. The
elements times required for the activities are in
minutes. The line operates for 7 hours per day and
the output of 550 units per day is desired.
Calculate
• The cycle time and
• The theoretical minimum number of work
stations
• Group the tasks into an appropriate number
of work stations.
• Calculate the balance efficiency.
Activities Immediate Task Time
Predecessor (Minutes)
A None 0.65
B A 0.40
C B 0.30
D C 0.20
E C 0.45
F D, E 0.40
G F 0.30
Total Time 2.70
Precedence Diagram
0.20
D
0.65 0.40 0.30 0.40 0.30
A B C F I
E
0.45
Production time available 7 hours/day*60 minutes/hour
Cycle Time = =
Desired units of outputs 550 units/day
n
∑ ti = 0.76 min/unit
i=1 2.7
N= = = 3.55 workstations ≈ 4 workstations
Cd 0.76
0.20
Work
Work Work
station 2
station 1 D Station 4
A B C F I
Idle Time =
0.11 mins Idle Time =
0.06 mins
E Idle Time =
0.06 mins
0.45
a b e
0.8 0.6
c d f g h
1.0 0.4 0.3
Station 1 Station 2 Station 3 Station 4
a b e
f g h
c d
Illustration 7
EXAMPLE
Green Grass’s plant manager just received marketing’s latest
forecasts of fertilizer spreader sales for the next year. She
wants its production line to be designed to make 2,400
spreaders per week. The plant will operate 40 hours per week.
a. What should be the line’s cycle time or throughput rate per hour be?
Work Immediate
Description Time (sec)
Element Predecessor(s)
A Bolt leg frame to hopper 40 None
B Insert impeller shaft 30 A
C Attach axle 50 A
D Attach agitator 40 B
E Attach drive wheel 6 B
F Attach free wheel 25 C
G Mount lower post 15 C
H Attach controls 20 D, E
I Mount nameplate 18 F, G
Total 244
b. What is the total number of stations or machines required?
TM (total machines) = total production time / cycle time = 244/60 = 4.067 or 5
Draw a Precedence Diagram
SOLUTION
The figure shows the complete diagram. We begin with work element A,
which has no immediate predecessors. Next, we add elements B and C, for
which element A is the only immediate predecessor. After entering time
standards and arrows showing precedence, we add elements D and E,
and so on. The diagram simplifies
interpretation. Work element F,
for example, can be done D
H
anywhere on the line after B 40
20
element C is completed. 30 E
However, element I must 6
await completion of A
F
elements F and G. 40 C 25
50
I
18
G
Precedence Diagram for
15
Assembling the Big Broadcaster
Allocating work or activities to
stations or machines
• The goal is to cluster the work elements into
workstations so that
1. The number of workstations required is minimized
2. The precedence and cycle-time requirements are not
violated
• The work content for each station is equal (or nearly so,
but less than) the cycle time for the line
• Trial-and-error can be used but commercial software
packages are also available
Finding a Solution
• The minimum number of workstations is 5 and the
cycle time is 60 seconds, so following represents
an optimal solution to the problem
D
H
B 40
20
30 E
6
A
F
40 C
25
50
I
18
G
15
t 244
Efficiency = nc (100) = = 81.3%
5(60)
H 72 ―
G I
I 35 G, H
J 60 I H
K 12 F, J
Total = 435
Solution
If the desired output rate is 30 units per hour, what are the cycle time
and theoretical minimum?
1 1
c= = (3600) = 120 sec/unit
r 30
t 435
TM = = = 3.6 or 4 stations
c 120
Solution
Suppose that we are fortunate enough to find a solution with just four
stations. What is the idle time per unit, efficiency, and the balance delay
for this solution?
t 435
Efficiency (%) = (100)
nc = (100) = 90.6%
480
Work
Elements Idle Time
Station Assigned Cumulative Time (c = 120)
1
2
3
4
5
Solution
Using trial and error, one possible solution is shown below.
Work
Elements Idle Time
Station Assigned Cumulative Time (c = 120)
1 H, C, A 120 0
2 B, D, G 98 22
3 E, F 110 10
4 I, J, K 107 13
5 A fifth station is not needed
Illustration 9
Calculate
I. Precedence diagram
ii. Theoretical no. of WS
iii. Line efficiency
CT = 0.70 min
Illustration 10: CT = 1 min