Chapter 11 - Project Management
Chapter 11 - Project Management
1) PERT and CPM are quantitative analysis tools designed to schedule and control large projects.
Answer: TRUE
Diff: Easy
Topic: INTRODUCTION
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
2) PERT is a deterministic analysis tool allowing for precise times of activities within a project.
Answer: FALSE
Diff: Moderate
Topic: INTRODUCTION
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
4) The first step in planning and scheduling a project is to develop the work breakdown structure.
Answer: TRUE
Diff: Moderate
Topic: INTRODUCTION
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
6) The optimistic time is the greatest amount of time that could be required to complete an
activity.
Answer: FALSE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
7) CPM was developed for use in managing projects about which we have good information
about activity or task completion times.
Answer: TRUE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
8) With PERT, we are able to calculate the probability of finishing the project within a specified
time.
Answer: TRUE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
9) The identification of the project activities and their time, cost, resource requirements,
predecessors, and person(s) responsible is called PERT planning.
Answer: FALSE
Diff: Moderate
Topic: INTRODUCTION
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
2
Copyright © 2018 Pearson Education, Inc.
10) Before drawing a PERT or CPM network, we must identify all activities and their
predecessors.
Answer: TRUE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
11) The three time estimates employed in PERT are optimistic time, average time, and
pessimistic time.
Answer: FALSE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
12) Given the variability of the activity completion times, the original critical path we identify in
our PERT analysis may not always be the actual critical path as the project takes place.
Answer: TRUE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
13) In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times
of all of its immediate predecessors.
Answer: TRUE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
3
Copyright © 2018 Pearson Education, Inc.
15) One of the most significant benefits of PERT is that it forces the project manager to sit down
and plan the project in great detail—and thus come to an understanding of relationships between
the activities.
Answer: TRUE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
16) The longest time path through a PERT/CPM network is called the critical path.
Answer: TRUE
Diff: Moderate
Topic: INTRODUCTION
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
17) In CPM, crashing an activity that is not on the critical path increases the cost of the project.
Answer: TRUE
Diff: Moderate
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Concept
4
Copyright © 2018 Pearson Education, Inc.
18) Through the use of PERT/CPM, astute managers can derive flexibility by identifying
noncritical activities and replanning, rescheduling, and reallocating resources such as personnel
and finances.
Answer: TRUE
Diff: Moderate
Topic: INTRODUCTION
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
19) One PERT/COST assumption is that money is spent at a constant rate over the time taken to
complete an activity.
Answer: TRUE
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Concept
20) Given the assumptions in PERT, the probability that a project will be completed in less time
than required by the activities on the critical path is approximately 50%.
Answer: TRUE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
21) Gantt charts and PERT diagrams provide the same information, just in different formats.
Answer: FALSE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
5
Copyright © 2018 Pearson Education, Inc.
22) Gantt charts contain information about the time taken by each activity, but not about the
sequential dependencies of the activities.
Answer: TRUE
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
24) The value of work completed is computed by multiplying budgeted cost by the percent
completion.
Answer: TRUE
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Concept
25) For projects that have a daily fixed cost, it is not possible to reduce the overall duration once
the cost of crashing exceeds the daily fixed cost.
Answer: FALSE
Diff: Moderate
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Concept
26) The activity crash cost is equal to the incremental cost of shortening the project.
Answer: FALSE
Diff: Moderate
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Concept
6
Copyright © 2018 Pearson Education, Inc.
27) Once the crash cost per time period value is negative, no additional crashing should be
performed.
Answer: FALSE
Diff: Moderate
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Concept
28) When crashing a project, all critical paths must be shortened by the same amount for activity
duration reductions to be cost-effective.
Answer: TRUE
Diff: Moderate
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Concept
29) The activity difference is the actual duration of an activity less the planned duration of that
same activity.
Answer: FALSE
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Concept
7
Copyright © 2018 Pearson Education, Inc.
33) The first step in planning and scheduling a project is to develop the
A) employee scheduling plan.
B) PERT/CPM network diagram.
C) critical path.
D) work breakdown structure.
Answer: D
Diff: Moderate
Topic: INTRODUCTION
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
8
Copyright © 2018 Pearson Education, Inc.
35) PERT
A) assumes that we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a network technique that uses three time estimates for each activity in a project.
D) is a deterministic network technique that allows for project crashing.
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
36) CPM
A) assumes we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a deterministic network technique that allows for project crashing.
D) is a network technique that allows three time estimates for each activity in a project.
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
9
Copyright © 2018 Pearson Education, Inc.
38) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days
respectively, compute the PERT expected activity time for this activity.
A) 8
B) 6
C) 7
D) 9
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
39) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days
respectively, compute the PERT expected activity time for this activity.
A) 6
B) 7
C) 9
D) 5
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
10
Copyright © 2018 Pearson Education, Inc.
40) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18
days respectively, compute the PERT expected activity time for this activity.
A) 14
B) 12
C) 11
D) 13
Answer: D
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
41) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20
days respectively, compute the PERT variance for this activity.
A) 3
B) 6
C) 9
D) 18
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
42) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18
days respectively, compute the PERT variance for this activity.
A) 2.33
B) 5.44
C) 8.00
D) 64.00
Answer: B
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
11
Copyright © 2018 Pearson Education, Inc.
43) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15
days, respectively, compute the PERT standard deviation for this activity.
A) 2
B) 4
C) 5
D) 15
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
44) Given the following small project, the critical path is ________ days.
Immediate Time
Activity Predecessor (days)
A - 10
B - 4
C A, B 6
A) 10
B) 14
C) 16
D) 20
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
12
Copyright © 2018 Pearson Education, Inc.
45) Given the following small project, the critical path is ________ days.
Immediate Time
Activity Predecessor (days)
A - 8
B A 4
C - 10
A) 4
B) 10
C) 12
D) 22
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
Table 11-1
The following represents a project with known activity times. All times are in weeks.
Immediate
Activity Predecessor Time
A - 4
B - 3
C A 2
D B 7
E C, D 4
F B 5
46) Using the data in Table 11-1, what is the minimum possible time required for completing the
project?
A) 8
B) 14
C) 25
D) 10
Answer: B
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
13
Copyright © 2018 Pearson Education, Inc.
47) Using the data in Table 11-1, what is the latest possible time that C may be started without
delaying completion of the project?
A) 0
B) 4
C) 8
D) 10
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
48) According to Table 11-1, compute the slack time for activity D.
A) 0
B) 5
C) 3
D) 6
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
49) Using the data in Table 11-1, compute the latest finish time for activity E.
A) 4
B) 10
C) 14
D) 25
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
14
Copyright © 2018 Pearson Education, Inc.
Table 11-2
The following represents a project with four activities. All times are in weeks.
50) According to the data in Table 11-2, what is the critical path?
A) A-B
B) A-C
C) B-D
D) A-B-C-D
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
51) According to the data in Table 11-2, what is the minimum expected completion time for the
project?
A) 18
B) 19
C) 37
D) 11
Answer: B
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
15
Copyright © 2018 Pearson Education, Inc.
52) According to Table 11-2, there are four activities in the project. Assume the normal
distribution is appropriate to use to determine the probability of finishing by a particular time. If
you wished to find the probability of finishing the project in 20 weeks or fewer, it would be
necessary to find the variance and then the standard deviation to be used with the normal
distribution. What variance would be used?
A) 2
B) 4
C) 8
D) 12
Answer: B
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
53) According to Table 11-2, there are four activities in the project. Assume the normal
distribution is appropriate to use to determine the probability of finishing by a particular time.
What is the probability that the project is finished in 16 weeks or fewer? (Round to two
decimals.)
A) 0.07
B) 0.93
C) 0.43
D) 0.77
Answer: A
Diff: Difficult
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
54) Consider a project that has an expected completion time of 60 weeks and a standard
deviation of five weeks. What is the probability that the project is finished in 70 weeks or fewer?
(Round to two decimals.)
A) 0.98
B) 0.48
C) 0.50
D) 0.02
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
16
Copyright © 2018 Pearson Education, Inc.
55) Your company is considering submitting a bid on a major project. You determine that the
expected completion time is 100 weeks and the standard deviation is 10 weeks. It is assumed that
the normal distribution applies. You wish to set the due date for the project such that there is an
85 percent chance that the project will be finished by this time. What due date should be set?
A) 108.0
B) 110.4
C) 89.6
D) 85.0
Answer: B
Diff: Difficult
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
Table 11-3
56) According to Table 11-3, there are five activities in a PERT project. Which activities are on
the critical path?
A) A-C-E
B) B-D
C) A-B-C-D
D) B-E
Answer: D
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
17
Copyright © 2018 Pearson Education, Inc.
57) According to Table 11-3, there are five activities in a PERT project. What is the variance of
the critical path?
A) 5.222
B) 4.222
C) 1.222
D) 1.111
Answer: D
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
58) According to Table 11-3, there are five activities in a PERT project. If the normal distribution
were used to find the probability of finishing this project in 24 weeks or fewer, what mean and
variance would be used?
A) 30 and 5.222
B) 20 and 5.222
C) 30 and 4.222
D) 22.667 and 1.111
Answer: D
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
18
Copyright © 2018 Pearson Education, Inc.
19
Copyright © 2018 Pearson Education, Inc.
64) The two common techniques for drawing PERT networks are
A) NOA and NRA.
B) AON and AOA.
C) GANTT and NOA.
D) ONA and OAO.
Answer: B
Diff: Difficult
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
65) In PERT analysis, the probability of the optimistic time occurring should be on the order of
A) 1/3.
B) 1/6.
C) 1/10.
D) 1/100.
Answer: D
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
20
Copyright © 2018 Pearson Education, Inc.
66) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days
respectively, compute the expected time for this activity.
A) 5
B) 6
C) 7
D) 12
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
67) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days
respectively, compute the expected time for this activity.
A) 3
B) 4
C) 5
D) 6
Answer: D
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
68) Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days
respectively, compute the PERT expected activity time for this activity.
A) 10
B) 12
C) 9
D) 11
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
21
Copyright © 2018 Pearson Education, Inc.
69) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days
respectively, compute the PERT variance for this activity.
A) 3
B) 1
C) 9
D) 6
Answer: B
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
22
Copyright © 2018 Pearson Education, Inc.
Immediate Time
Activity Predecessor (days)
A -- 10
B A 4
C A 6
D B 7
E C 5
A)
B)
C)
23
Copyright © 2018 Pearson Education, Inc.
D)
Answer: A
Diff: Easy
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
Immediate Time
Activity Predecessor (days)
A -- 10
B A 4
C A 6
D B, C 7
E C 5
24
Copyright © 2018 Pearson Education, Inc.
Immediate Time
Activity Predecessor (days)
A -- 6
B A 2
C -- 8
D B, C 5
E D 7
25
Copyright © 2018 Pearson Education, Inc.
Table 11-4
The following represents a project with known activity times. All times are in weeks.
Immediate
Activity Predecessor Time
A -- 4
B -- 3
C A 2
D B 7
E C, D 4
F B 5
G E, F 4
73) Using the data in Table 11-4, what is the minimum possible time required for completing the
project?
A) 8
B) 12
C) 18
D) 10
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
74) Using the data in Table 11-4, what is the latest possible time that C may be started without
delaying completion of the project?
A) 0
B) 4
C) 8
D) 10
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
26
Copyright © 2018 Pearson Education, Inc.
75) Using the data in Table 11-4, compute the slack time for activity D.
A) 0
B) 5
C) 3
D) 6
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
76) Using the data in Table 11-4, compute the latest finish time for activity E.
A) 4
B) 10
C) 14
D) 25
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
77) Using the data in Table 11-4, determine the latest time activity A can be started without
delaying the project completion.
A) 4
B) 3
C) 8
D) 6
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
27
Copyright © 2018 Pearson Education, Inc.
78) Using the data in Table 11-4, determine the latest time activity A can be finished and not
delay any activity?
A) 4
B) 0
C) 8
D) 5
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
79) Consider a project that has an expected completion time of 50 weeks and a standard
deviation of 9 weeks. What is the probability that the project is finished in 57 weeks or fewer?
(Round to two decimals.)
A) 0.68
B) 0.78
C) 0.22
D) 0.32
Answer: B
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
80) Your company is considering submitting a bid on a major project. You determine that the
expected completion time is 150 weeks and the standard deviation is 10 weeks. It is assumed that
the normal distribution applies. You wish to set the due date for the project such that there is a 95
percent chance that the project will be finished by this time. What due date should be set?
A) 108.0
B) 160.4
C) 166.5
D) 135.0
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
28
Copyright © 2018 Pearson Education, Inc.
Table 11-5
Immediate
Activity Predecessor Time ES EF LS LF
A -- 4 0 4 6 10
B -- 5 0 5 0 5
C A 3 4 7 10 13
D B 8 5 13 5 13
E B 2 5 7 16 18
F C, D 3 13 16 15 18
G C, D 7 13 20 13 20
H E, F 2 16 18 18 20
81) How long could Table 11-5's activity E be delayed without delaying the completion of the
project?
A) 7
B) 16
C) 11
D) 18
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
82) How long could Table 11-5's activity F be delayed without delaying the project?
A) 2
B) 3
C) 14
D) 16
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
29
Copyright © 2018 Pearson Education, Inc.
83) What is the minimum possible time required for completing the Table 11-5 project?
A) 14
B) 18
C) 17
D) 20
Answer: D
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
Table 11-6
Immediate Most
Activity Optimistic Pessimistic σ σ2
Predecessor Likely
A -- 2 3 4 0.333 0.111
B -- 2 5 8 1.000 1.000
C A 1 2 9 1.330 1.780
D A 5 5 5 0.000 0.000
E B, C 6 7 8 0.333 0.111
F B 14 14 14 0.000 0.000
G D, E 1 5 9 1.333 1.780
H G, F 1 4 8 1.167 1.362
30
Copyright © 2018 Pearson Education, Inc.
Figure 11-1
31
Copyright © 2018 Pearson Education, Inc.
87) Given the network in Figure 11-1, the time to complete those activities on the critical path is
expected to be
A) 20.
B) 22.
C) 25.
D) 26.
Answer: C
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
88) Given the network shown in Figure 11-1, assume that completion of A is delayed by two
days. What other activities are impacted?
A) B
B) D
C) E
D) C
Answer: D
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
32
Copyright © 2018 Pearson Education, Inc.
89) Given the network shown in Figure 11-1 and the following information, what is the variance
of the critical path?
A) 16
B) 7
C) 9
D) 8
Answer: C
Diff: Difficult
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
90) PERT assumes that the total completion time of a project follows which of the following
probability distributions?
A) normal
B) exponential
C) binomial
D) Poisson
Answer: A
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Concept
33
Copyright © 2018 Pearson Education, Inc.
91) Activity D of a project has a budgeted cost of $45,000 and is 20% complete. What is the
value of work completed?
A) 450
B) 4500
C) 900
D) 9000
Answer: D
Diff: Easy
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
92) Activity B of a project has a budgeted cost of $50,000 and is 30% complete. The actual cost
of the activity is $12,000. What is the activity difference?
A) -15,000
B) -3,000
C) 0
D) 3,000
Answer: B
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
93) The value of work completed for an activity is determined by which of the following?
A) budgeted cost - actual cost
B) actual cost divided by budgeted cost
C) percentage of work completed multiplied by actual activity cost
D) percentage of work completed multiplied by budgeted activity cost
Answer: D
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Concept
34
Copyright © 2018 Pearson Education, Inc.
95) Reducing the overall activity time is based on which of the following steps?
A) crashing activities with the lowest overall crash cost
B) crashing activities with the lowest overall normal cost
C) crashing activities on the critical path based on lowest overall cost
D) crashing activities on the critical path based on lowest cost/week
Answer: D
Diff: Moderate
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Concept
96) An alternative approach to project crashing is to use which of the following techniques?
A) linear programming
B) nonlinear programming
C) Markov analysis
D) queuing theory
Answer: A
Diff: Moderate
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Concept
35
Copyright © 2018 Pearson Education, Inc.
97) Which of the following is not a decision variable when formulating the project crashing
problem as a linear program?
A) the early finish times of critical activities
B) the early finish times of noncritical activities
C) the finish time of the project
D) the early start times of all activities
Answer: D
Diff: Moderate
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Concept
99) The process of smoothing out the utilization of resources in a project is called
A) CPM.
B) PERT.
C) project crashing.
D) resource leveling.
Answer: D
Diff: Easy
Topic: OTHER TOPICS IN PROJECT MANAGEMENT
LO: 11.4: Understand the important role of software in project management.
AACSB: Analytical thinking
Classification: Concept
36
Copyright © 2018 Pearson Education, Inc.
37
Copyright © 2018 Pearson Education, Inc.
Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-
activity project but spilled her energy drink on the paper and the acid in the beverage wiped out
some of the table entries. The remaining legible entries are correct.
102) Consider the project summarized in Table 11-7. What is the slack for Activity C?
A) 0
B) 1
C) 5
D) 7
Answer: A
Diff: Difficult
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
103) Consider the project summarized in Table 11-7. What is the early finish time for Activity D?
A) 19
B) 20
C) 21
D) 22
Answer: B
Diff: Difficult
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
38
Copyright © 2018 Pearson Education, Inc.
104) Consider the project summarized in Table 11-7. What is the early finish time for Activity E?
A) 25
B) 26
C) 27
D) 28
Answer: C
Diff: Difficult
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
105) Consider the project summarized in Table 11-7. What is the critical path?
A) ABDGH
B) ACEGH
C) ABDFH
D) ACEFH
Answer: D
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
106) Consider the project summarized in Table 11-7. What is the slack for Activity D?
A) 7
B) 5
C) 1
D) 0
Answer: A
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
39
Copyright © 2018 Pearson Education, Inc.
107) Consider the project summarized in Table 11-7. What is the late start time for Activity G?
A) 27
B) 28
C) 29
D) 30
Answer: B
Diff: Difficult
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to
complete his plans for world conquest. The estimated time in weeks and cost in US dollars
appear in the table along with the shortest possible duration for each activity and cost of those
expedited activities. Activities are designated generically as A, B, and so on in order to avoid any
copycat projects of this nature.
108) Consider the project summarized in Table 11-8. What is the minimum cost project in order
to finish in a year?
A) $58,500
B) $53,500
C) $51,750
D) 55,250
Answer: A
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
40
Copyright © 2018 Pearson Education, Inc.
109) Consider the project summarized in Table 11-8. What activities should be expedited in order
to complete the project within a year at minimum cost?
A) F, B
B) A, I, J
C) F, B, E
D) B, E, A
Answer: B
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
110) Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in
the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of
the world. Determine the minimum cost project factoring in both the costs of expediting and the
opportunity cost. What is the overall minimum cost?
A) $171,500
B) $166,250
C) $159,850
D) $152,700
Answer: C
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
111) Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in
the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of
the world. Determine the minimum cost project factoring in both the costs of expediting and the
opportunity cost. What is the duration of the overall minimum cost project?
A) 49 weeks
B) 48 weeks
C) 47 weeks
D) 46 weeks
Answer: D
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
41
Copyright © 2018 Pearson Education, Inc.
112) Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in
the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of
the world. Which of these activities should not be reduced in an effort to deliver a minimum cost
(both project and opportunity cost) project?
A) F
B) H
C) G
D) E
Answer: A
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
113) Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in
the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of
the world. Which of these activities should be crashed in an effort to deliver a minimum cost
(both project and opportunity cost) project?
A) F
B) H
C) D
D) C
Answer: B
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
42
Copyright © 2018 Pearson Education, Inc.
114) Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in
the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of
the world. These costs are easy to quantify, but it's difficult to stomach not controlling the world
when it's just a matter of a few extra dollars. What's the earliest this project can be completed and
what would the overall project cost be?
A) 38 weeks
B) 40 weeks
C) 44 weeks
D) 46 weeks
Answer: C
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
115) Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in
the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of
the world. These costs are easy to quantify, but it's difficult to stomach not controlling the world
when it's just a matter of a few extra dollars. What's the cost of the minimum duration project?
A) $158,550
B) $163,850
C) $156,350
D) $161,550
Answer: D
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
43
Copyright © 2018 Pearson Education, Inc.
Immediate
Activity Time ES EF LS LF
Predecessor
A -- 4 0 4 6 10
B -- 5 0 5 0 5
C A 3 4 7 10 13
D B 8 5 13 5 13
E B 2 5 7 16 18
F C, D 3 13 16 15 18
G C, D 7 13 20 13 20
H E, F 2 16 18 18 20
44
Copyright © 2018 Pearson Education, Inc.
117) Consider the project with the following estimates for activity times and precedence
relationships:
45
Copyright © 2018 Pearson Education, Inc.
118) Consider the tasks, durations, and predecessor relationships in the following network. Draw
the network and answer the questions that follow.
(a) 40
(b) 8079
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
46
Copyright © 2018 Pearson Education, Inc.
119) Given:
Determine:
(a) the critical path.
(b) the probability that the project will be completed in 22 weeks.
Answer:
(a) Critical path is A-C-F. Expected time is 19.
(b) Variance for critical path is 2.889, so standard deviation is 1.70. P(X ≤ 22) = 0.9608.
Diff: Difficult
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
47
Copyright © 2018 Pearson Education, Inc.
120) A small software development project has five major activities. The times are estimated and
provided in the table below.
Immediate
Activity a m b
Predecessor
A -- 2 5 8
B -- 10 10 10
C A 4 7 10
D B 2 5 14
E C 3 3 3
Diff: Difficult
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
48
Copyright © 2018 Pearson Education, Inc.
121) Development of a new deluxe version of a particular software product is being considered.
The activities necessary for the completion of this are listed in the table below (Time in weeks).
Diff: Difficult
Topic: PERT/CPM and PROJECT CRASHING
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
49
Copyright © 2018 Pearson Education, Inc.
122) Draw the PERT network associated with the following activities.
Immediate
Activity
Predecessor
A --
B A
C A
D B
E B
F C, E
G A, D
H F
I F
J G, H, I
Answer:
Diff: Moderate
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
50
Copyright © 2018 Pearson Education, Inc.
Determine:
(a) the critical path.
(b) the probability that the project will be completed in 22 weeks.
Answer:
(a) Critical path is B-E-G-I.
(b) Variance for critical path is 6.33; standard deviation is 2.51. The probability that the project
will be completed in 22 weeks = 0.65.
Diff: Difficult
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
51
Copyright © 2018 Pearson Education, Inc.
124) A small software development project has four major activities. The times are estimated and
provided in the table below.
Immediate
Activity a m b
Predecessor
A -- 2 5 8
B A 3 6 9
C A 4 7 10
D B 2 5 14
E D 3 3 3
F C 6 8 10
G E, F 1 1 1
H C 6 10 14
I G, H 3 4 5
Diff: Difficult
Topic: PERT/CPM
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
52
Copyright © 2018 Pearson Education, Inc.
125) An IT project requires 6 activities. The table below displays the expected time and budgeted
cost for each activity.
53
Copyright © 2018 Pearson Education, Inc.
A
B
C
D 1800 1800
E 1000
F 1333.33 1333.33 1333.33 1333.33 1333.33 1333.33
Total in
Period 2800 1800 1333.33 1333.33 1333.33 1333.33 1333.33 1333.33
Cumu-
lative
from start25200 27000 28333.33 29666.67 31000 32333.34 33666.67 35000
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
54
Copyright © 2018 Pearson Education, Inc.
126) An IT project requires 6 activities. The table below displays the expected time and budgeted
cost for each activity.
Expected Immediate
Activity Budgeted Cost
time (weeks) Predecessors
A 3 $2,000 None
B 4 $6,000 None
C 2 $7,000 A
D 5 $9,000 B
E 3 $3,000 C
F 6 $8,000 B,D
A
B 1500 1500 1500 1500
C
D 1800 1800 1800
E
F
Total in
Period 1500 1500 1500 1500 1800 1800 1800
Cumu-
lative
from start1500 3000 4500 6000 7800 9600 11400
55
Copyright © 2018 Pearson Education, Inc.
56
Copyright © 2018 Pearson Education, Inc.
127) An IT project requires 6 activities. The table below displays the expected time and budgeted
cost for each activity.
Expected Immediate
Activity Budgeted Cost
time (weeks) Predecessors
A 3 $2,000 None
B 4 $6,000 None
C 2 $7,000 A
D 5 $9,000 B
E 3 $3,000 C
F 6 $8,000 B,D
Diff: Moderate
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
128) Activity C of a project has a budgeted cost of $40,000 and is 20% complete. The actual cost
is $10,000.
57
Copyright © 2018 Pearson Education, Inc.
129) Development of a new deluxe version of a particular software product is being considered.
The activities necessary for the completion of this are listed in the table below (Time in weeks).
Immediate
Activity a m b
Predecessor
A -- 2 5 8
B A 3 6 9
C A 4 7 10
D B 2 5 14
E D 3 3 3
F C 6 8 10
G E, F 1 1 1
H C 6 10 14
I G, H 3 4 5
(a) If you wish to reduce the time required to complete this project by two weeks, which
activity(ies) should be crashed, and how much will this increase the total cost?
(b) What would be the added cost if you wanted to complete the project in the minimum time
possible?
Answer:
(a) Crash D, two weeks at an additional cost of $100
(b) Crash D 4 weeks, G 2 weeks, E 3 weeks, A 1 week, and B 1 week, for a total additional cost
of $1,700
Diff: Difficult
Topic: PERT/CPM and PROJECT CRASHING
LO: 11.1: Understand how to plan, monitor, and control projects with the use of PERT and
CPM.
AACSB: Analytical thinking
Classification: Application
58
Copyright © 2018 Pearson Education, Inc.
59
Copyright © 2018 Pearson Education, Inc.
Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-
activity project but spilled her energy drink on the paper and the acid in the beverage wiped out
some of the table entries. The remaining legible entries are correct.
135) Consider the project summarized in Table 11-7. Provide all missing information.
Answer:
Activity Predecessor Duration ES EF LS LF Slack
A -- 0 5 0 5 0
B A 7 5 12 12 19 7
C A 13 5 18 5 18 0
D B 8 12 20 19 27 7
E C 9 18 27 18 27 0
F D,E 7 27 34 27 34 0
G E 6 27 33 28 34 1
H F,G 5 34 40 34 40 0
Diff: Difficult
Topic: PERT/COST
LO: 11.2: Determine earliest start, earliest finish, latest start, latest finish, and slack times for
each activity, along with the total project completion time and total project cost.
AACSB: Analytical thinking
Classification: Application
60
Copyright © 2018 Pearson Education, Inc.
Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to
complete his plans for world conquest. The estimated time in weeks and cost in US dollars
appear in the table along with the shortest possible duration for each activity and cost of those
expedited activities. Activities are designated generically as A, B, and so on in order to avoid any
copycat projects of this nature.
136) Consider the project summarized in Table 11-8. What is the minimum cost project in order
to finish in a year? List the activities crashed and the total cost? What is the difference in the total
project cost before and after crashing?
Answer: The minimum cost 52-week project costs $58,500, which is $5,000 more than the
original project cost of $53,500.
Activity A should be reduced by 5 weeks at $700 per week
Activity I should be reduced by 1 week at $750
Activity J should be reduced by 1 week at $750
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
61
Copyright © 2018 Pearson Education, Inc.
137) Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in
the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of
the world. Determine the minimum cost project factoring in both the costs of expediting and the
opportunity cost. What is the overall minimum cost and duration of the project?
Answer: The original project cost is $53,500 plus $2,000/week times the 59-week duration for a
total cost of $171,500. Activities should be shortened as long as the cost of expediting does not
exceed $2000/week.
Activity A should be reduced by 5 weeks at $700 per week
Activity I should be reduced by 1 week at $750
Activity J should be reduced by 2 weeks at $750 per week
Activity B should be reduced by 1 week at $600
Activity E should be reduced by 2 weeks at $650 per week
Activity G should be reduced by 5 weeks at $1000 per week
Activity H should be reduced by 2 weeks at $850 per week
The crash cost of the 46-week project is $67,850 plus the fixed cost of $2,000/week for 46 weeks
of $92,000 for a total project cost of $159,850.
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
138) Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in
the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of
the world. These costs are easy to quantify, but it's difficult to stomach not controlling the world
when it's just a matter of a few extra dollars. What's the earliest this project can be completed and
what would the overall project cost be?
Answer: The original project cost is $53,500 plus $2,000/week times the 59-week duration for a
total cost of $171,500.
Activity A should be reduced by 5 weeks at $700 per week
Activity I should be reduced by 1 week at $750
Activity J should be reduced by 2 weeks at $750 per week
Activity B should be reduced by 1 week at $600
Activity E should be reduced by 2 weeks at $650 per week
Activity G should be reduced by 5 weeks at $1000 per week
Activity H should be reduced by 4 weeks at $850 per week
Activity E should be reduced by 2 weeks at $2000 per week
The crash cost of the 44-week project is $73,550 plus the fixed cost of $2,000/week for 44 weeks
of $88,000 for a total project cost of $161,550.
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
62
Copyright © 2018 Pearson Education, Inc.
Table 11-9
A mad scientist has identified the twelve steps required to complete his "take over the world"
rehabilitation. The estimated time in weeks and cost in US dollars appear in the table along with
the shortest possible duration for each activity and cost of those expedited activities.
139) Consider the project summarized in Table 11-9. What is the duration of the normal
completion time and project cost at that time? What activities should be crashed to reduce
completion time by ten weeks as inexpensively as possible? What is the new project duration and
cost?
Answer: The normal completion time is 80 weeks at a cost of $93,575. To reduce the project ten
weeks these activities should be crashed:
Activity M should be reduced by 5 weeks at $290 per week
Activity L should be reduced by 4 weeks at $405 per week
Activity J should be reduced by 1 week at $500
A 70-week project will cost $97,145
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
63
Copyright © 2018 Pearson Education, Inc.
140) Consider the project summarized in Table 11-9. In addition to the cost of the activities, the
mad scientist must rent a menagerie of comfort animals during his program. The menagerie
includes a number of animals, plus the feed, along with the services of a shepherd at a cost of
$700 per week. What is the duration of the normal completion time and total project cost at that
time? What activities should be crashed to minimize the total project cost? What is the new
project duration and cost?
Answer: The normal completion time is 80 weeks at a cost of $93,575 for the activities and
another $56,000 menagerie cost, for a total of $149,575.
To minimize the project cost these activities should be crashed:
Activity M should be reduced by 5 weeks at $290 per week
Activity L should be reduced by 4 weeks at $405 per week
Activity J should be reduced by 1 week at $500
Activity A should be crashed by 3 weeks at $600 per week
A 67-week project will cost $5370 in crash costs, $46,900 in menagerie costs plus the activity
costs of $93,575 for a total cost of $145,845.
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
64
Copyright © 2018 Pearson Education, Inc.
141) Consider the project summarized in Table 11-9. In addition to the cost of the activities, the
mad scientist must rent a menagerie of comfort animals during his program. The menagerie
includes a number of animals, plus the feed, along with the services of a shepherd at a cost of
$700 per week. What is the duration of the normal completion time and total project cost at that
time? The mad scientist discovers he is allergic to llamas and decides to finish the project as
quickly as possible in order to get the animals out of his studio apartment in Greenwich Village.
What activities should be crashed to minimize the project duration? What is the new project
duration and cost?
Answer: The normal completion time is 80 weeks at a cost of $93,575 for the activities and
another $56,000 menagerie cost, for a total of $149,575.
To minimize the project cost these activities should be crashed:
Activity M should be reduced by 5 weeks at $290 per week
Activity L should be reduced by 4 weeks at $405 per week
Activity J should be reduced by 5 weeks at $500 per week
Activity A should be crashed by 3 weeks at $600 per week
Activity K should be crashed by 3 weeks at $750 per week
Activity H should be crashed by 4 weeks at $437.50 per week
Activity F should be crashed by 3 weeks at $516.67 per week
Activity B should be crashed by 4 weeks at $512.50 per week
Activity C should be crashed by 4 weeks at $600 per week
Activity D should be crashed by 3 weeks at $600 per week
A 53-week project will cost $19,170 in crash costs, $37,100 in menagerie costs plus the activity
costs of $93,575 for a total cost of $149,845.
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
65
Copyright © 2018 Pearson Education, Inc.
142) Consider the project summarized in Table 11-9. In addition to the cost of the activities, the
mad scientist must rent a menagerie of comfort animals during his program. The menagerie
includes a number of animals, plus the feed, along with the services of a shepherd at a cost of
$700 per week. There is also a $500/week penalty imposed by the League of Justice for any
project lasting longer that 52 weeks. What is the duration of the normal completion time and total
project cost at that time? What activities should be crashed to minimize the total project cost?
What is the new project duration and cost?
Answer: The normal completion time is 80 weeks at a cost of $93,575 for the activities, another
$56,000 menagerie cost, plus $14,000 in penalty costs for a total of $163,575.
To minimize the project cost these activities should be crashed:
Activity M should be reduced by 5 weeks at $290 per week
Activity L should be reduced by 4 weeks at $405 per week
Activity J should be reduced by 5 weeks at $500 per week
Activity A should be crashed by 3 weeks at $600 per week
Activity K should be crashed by 3 weeks at $750 per week
Activity H should be crashed by 4 weeks at $437.50 per week
Activity F should be crashed by 3 weeks at $516.67 per week
Activity B should be crashed by 4 weeks at $512.50 per week
Activity C should be crashed by 1 week at $600 per week
A 56-week project will cost $15,570 in crash costs, $39,200 in menagerie costs, $2000 in penalty
costs plus the activity costs of $93,575 for a total cost of $150,345.
Diff: Difficult
Topic: PROJECT CRASHING
LO: 11.3: Reduce total project time at the least total cost by crashing the network using manual
and linear programming techniques.
AACSB: Analytical thinking
Classification: Application
66
Copyright © 2018 Pearson Education, Inc.