Jobs Safety Analysis (JSA) : JOB/ACTIVITY NAME: Scaffolding Erection, Dismantling Work, Work at Height, Welding Work

This document provides a jobs safety analysis for various activities including scaffolding erection, dismantling, work at heights, and welding. It identifies potential hazards for each task and lists control measures to mitigate risks. Required personal protective equipment is specified for all jobs. Proper handling, barricading, fall protection, permits, training, and supervision are emphasized for high risk activities like scaffolding work and welding to prevent injuries from falls, electrocution, burns, and other dangers.

Uploaded by

uttam mishra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
466 views

Jobs Safety Analysis (JSA) : JOB/ACTIVITY NAME: Scaffolding Erection, Dismantling Work, Work at Height, Welding Work

This document provides a jobs safety analysis for various activities including scaffolding erection, dismantling, work at heights, and welding. It identifies potential hazards for each task and lists control measures to mitigate risks. Required personal protective equipment is specified for all jobs. Proper handling, barricading, fall protection, permits, training, and supervision are emphasized for high risk activities like scaffolding work and welding to prevent injuries from falls, electrocution, burns, and other dangers.

Uploaded by

uttam mishra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4

Jobs Safety Analysis

(JSA)

JOB/ACTIVITY NAME: Scaffolding Erection , Dismantling work , Work at height, Welding Work. Date:

JSA #: HTG-JSA- ESEPPL-


DEPARTMENT/AGENCY NAME AREA LOCATION(s): Duct Fabrication Yard OTHER INFORMATION:

Department:

Agency: M/s.ESE POWERCON PVT LTD

REQUIRED PERSONAL PROTECTIVE EQUIPMENT FOR ENTIRE JOB

Safety Helmet Safety Goggles Hearing Protection Dust Masks Others


Safety Shoes Full body harness Face Shield Gum Boots
Reflective vest Welding Gloves Welding Goggles
Hand Gloves Chemical Resistant Gloves Leather Gloves

Sl.no Description of task Potential Hazards Control measures Action By


1. Shifting of 1. Physical Injury due 1.Use appropriate trolley/Trailer for shifting of Scaffolding Safety Officer
Scaffolding to improper materials
Materials Handling 2.Dont do Manual lifting if the materials is too heavy to lift.
2.Egronomical 3.For Shifting of Scaffolding materials to height use rope &
Hazard due to Pulley arrangement & tie the scaffolding materials properly to
improper lifting of avoids slips.
material 4.Ensure no access block during Shifting of scaffolding
3. Slippage of materials.
materials during 5.Wear all required PPE & follow all safety signage’s at
lifting work-site.
6.Prior to work conduct TBT at Site.
533405805.doc Page 1 of 3
2. Erection of 1.Fall of materials due 1.Always ensure Proper installation of guard rails & fall Safety Officer
Scaffolding to improper stacking arrestor system to avoid of fall of persons
2.Check the area & ensure no live wire should located near to
2.Fall of Persons.
scaffolding.
3.Electrocution 3.Use Standard ladder for erection work & use three-point
4.Scaffolding collapse contact during climbing.
5.Unauthorized entry 4.Only competent & experienced manpower to be engaged for
scaffolding work.
5.Whole area to be barricaded prior to work.
6.Maintain Housekeeping & 5s system at work area.
7.Wear all required PPE .
8.Ladder should be provided for proper access.
9.Standard scaffolding must be erected as per the load
requirement (Light /Heavy/Medium)
10.Scaffolding should be erected under the supervision of
authorized scaffolder and site engineer.
11.All the hand (Hammers, spanners) tools must be provided
with fall protection rope and tie rope.
12.Only aluminum ladder with sufficient length should be
provided
13.All the height working platform must be fully covered
with gratings or planks.
14.All the manhole openings should be protected with either
standard hard barricading or mesh or cover to prevent
accidental fall of person and material
15.Follow Permit to work system.
3. Work on Collapse of 1.All the height work must be started with having valid work
scaffolding or Structure permit
man basket, Fall of Person 2.Trained and medically fit (i.e. All the height workforce
man lift, scissor should be gone through Vertigo Test)workforce to be
Fall of
lift, suspended deployed.
Material
platform. Other
height work 3.All the scaffolding must be erected under the supervision of
platform. site engineer and qualified scaffold only. Only good condition
and scaffolding components should be used for all type of
scaffolding
Page 2 of 4
4.Standard platform gratings should be used, and the height
work platform should have a minimum of350mm to 400mm
or a minimum of double grating working platform must be
arranged Double railing (mid rail, and top tailing) must be
arranged for all the height work platform.
5.Scaffolding tags must be arranged to identification
Standard ladder with vertical fall arrester for each person must
be provided

6.Scaffolding or ladder component must be avoid for direct


welding to the structural column or other structure.

7.Only beam clamp or grating clamp should be used for


scaffolding tube fixing to the column or beam structure
component.
8.Double lanyard safety harness with shock absorber of
approved brand must be provided to the workforce.

9.Without HTG HSE dept. alternation of any type of


scaffolding or safety protective facility must not be changed

4. Dismantling of Fall of 1.Ensure proper lifting & lowering management. Standard


Scaffolding material, Bag should be used for lowering of clamps.
clamp, spanner 2.Safety Net to be tied & barricading to be provided below to
from height dismantling work.
Injury to 3.On the Job Training & Safety Training to be provided on
Person continuous basis.
Property 4.Sequence of dismantling followed, all the bracing are in
Page 3 of 4
Damage place, scaffold in vertical.
5.Double lanyard safety harness with shock absorber of
approved brand must be provided to the workforce

5. Welding ,Cutting & Burn Injury, Fire, 1.Always make sure that all electrical connections are
Grinding activity Electrocution, Flying securely made.
Chips 2.All Cables must be maintained in good conditions & laying
above the ground.
3.ELCB/RCCB/MCCB should be checked before the job.
4.Wheel guard is must for grinding & cutting activity.
5.Area shall be free from any combustible material during
cutting , welding & grinding.
6.Fire Extinguisher shall be placed near the hot work area.
7.Welders should use Welding Helmets, Sleeves, Apron,
Leather hand Gloves.
8.

Kindly specify If any other measures to be implemented:

I will affirm that the aforesaid precautions shall be communicated to all of the workmen and ensured the compliance during the execution
of the job.

JSA Approved by
JSA Reviewed By:
JSA prepared by: (Agency) (HTG & Adani if
(HTG Site Engineer)
need)

Signature: Signature Signature

Page 4 of 4