Final FSR Cum DPR - Chhabra - 4x250 MW RRVUN - B
Final FSR Cum DPR - Chhabra - 4x250 MW RRVUN - B
FINAL FEASIBILITY
REPOR REPOR
INDEX
Page :2
6.3 Basis and Assumptions..................................................................................................57
6.4 Specific Water Consumption of the plant.......................................................................57
6.5 Water Requirement for FGD System and Source.........................................................58
6.6 Assessment of plant water consumption.......................................................................58
6.7 FGD Waste water treatment Plant.................................................................................62
12.0 Conclusions...................................................................................................88
13.1 Financial.........................................................................................................91
13.2 General..........................................................................................................................91
Page :3
13.4 Cost of Land...................................................................................................................91
13.5 Cost of other items.........................................................................................................91
13.6 Project cost Summary....................................................................................................91
13.7 Fixed and variable Cost.................................................................................................92
13.8 Assumptions...................................................................................................................92
13.9 Impact on Generation Cost............................................................................................93
List of Annexures
List of Exhibit
for EADS
Page :4
1
Executive Summary
1.1 EXECUTIVE SUMMARY
1.2 Introduction
Rajasthan Rajya Vidyut Utpadan Nigam Ltd (XXXXXXX) has a Coal based Thermal
Power Plant with capacity of 4x250 MW in Tehsil Xxxxxxx, Rajasthan. The plant
uses Indian Coal sourced from mines in SECL, Korba (C.G) through washery circuit
and Parsa east & KanteBasan Coal Block, Ambikapur (C.G).
XXXXXXX has appointed Fichtner Consulting Engineers (India) Private Limited (FI)
for carrying out the Evaluation and Assessment of existing power plants of
XXXXXXX and prepare Feasibility Report for meeting revised environmental norms
by the existing units.
The scope of this report is to establish the Feasibility Study for the following units of
Xxxxxxx Thermal Power Project(CTPP).
Unit-I 30.10.2009
FI team visited the power plant site to study the plant details. FI team collected the
plant design data, specifically with regard to coal analysis, Plant water consumption,
designed emissions levels of SO2, NOx. Site walkthrough was also conducted to
study the plant equipment layout and to ascertain the space provision and its
availability for installation of pollution control equipment. Annexure-1 lists the data
collected from XXXXXXX during the site visit.
For the purpose of arriving baseline emission data, a blend of 70% Indian coal with
0.6% Sulphur, and 30% Imported coal with 0.7% Sulphur and 35% ash content as
per the input from XXXXXXX, and water consumption as per design water balance
diagram provided by XXXXXXX are considered.
The Unit-I to Unit-IV falls under the category “ TPPs (units) installed after 1st
January, 2004, up to 31 st December,2016” and “Units smaller than 500MW capacity
units”, as mentioned in the MOEF & CC gazette notification.
PM mg/Nm³ 50
Continuous emission monitoring system is installed for the Units – 1,2,3 & 4 of the
plant. Further to that, the emission data measured at site by FI appointed agency for
seven days will also form baseline emission data for the study. However, expected
worst case emission values are calculated based on coal analysis provided by the
XXXXXXX. Field Tests were carried out on Units-1,2 &3. Unit-4 was under annual
shutdown and hence the historical data is considered for PM and highest data from
identical units are considered for SO 2 and NOx.
Present emission level is assessed and compared with the limiting emission values
mandated by December 2015 MOEF&CC norms.
Emission
(Base Line
Line Data)
data XXXXXXX
Site measurem ent
Data)
250 MW
1900 600 (157.15) NA 50 543.79 300 0.078 0.03
(Unit 1)
250 MW
1900 600 (438.66) NA 50 590.83 300 0.19 0.03
(Unit 2)
3.18 3.5
250 MW
1900 600 (93.7) NA 50 615.29 300 0.13 0.03
(Unit 3)
250 MW
1900 600 - 105# 50 615.2 300 - 0.03
(Unit 4)
For the purpose of arriving baseline emission data, a blend of 70% Indian
coal with 0.6% Sulphur, and 30% Imported coal with 0.7% Sulphur and
35% ash content as per the input from XXXXXXX, and water
consumption as per design water balance diagram provided by
XXXXXXX are considered. The estimated SO2 emission value is
exceeding the stipulated limit by around 69%. Hence suitable
SO2emission control system is recommended.
The NOx emission data measured is higher than the MOEF stipulated
limit of 300 mg/Nm 3. Hence suitable NOx control measures are
recommended for implementation with efficiency of around 34%.
PM emission is above the MOEF stipulated limit of 50 mg/Nm3.
Therefore, suitable modification to the ESP is recommended to limit the
particulate emission within MOEF&CC stipulation.
Unit 4 was under shutdown during the site emission measurement
activity performed by FI. The historic emission data of PM, SO 2 & NOx
provided by XXXXXXX for Unit 4 is more than MOEF&CC norms, but the
maximum of the PM, SOx & NOx data recorded during site emission
measurement for 1 to 3 unit is higher than historic emission data so it is
considered as baseline for unit 4.Suitable modification in the ESP is
recommended to meet the MOEF&CC limit.
The mercury emission measured by FI at site is higher than the MOEF
stipulated limit. Therefore, the plant requires suitable mercury control
measures..
There are many technologies available and these technologies are used in many
plants which are in operation worldwide for SO2 control in flue gas from power
plants. The selection of appropriate technology and equipment will depend on many
factors such as type of boiler, coal analysis, SO 2 removal efficiency required,
operational requirement, environmental regulation, layout feasibility, land
availability, proven technology, auxiliary power and utility requirement and capital &
operating cost.
Based on the detailed study presented in this report, FI concluded the following
measures and system for further review and implementation.
For Unit #1,2,3 & 4 the estimated SO 2 emission level is around 69 % above the Dec
2015 MOEF&CC norms, for which wet lime stone based FGD is recommended to
limit the SO2 emission level within Dec 2015 MOEF&CC norms.
Scheme, layout and equipment details for the selected technology for SO 2 emission
control are covered in Section 4.
The highest measured NOx emission for Unit 1,2 & 3 is 543.79 mg/Nm 3,
590.83mg/Nm3and 615.29mg/Nm3respectivily, which forms the baseline data. Unit
4 was under shutdown during the site emission measurement activity performed by
FI. The historic emission data of PM, SOx & NOx provided by XXXXXXX for Unit 4
is more than MOEF&CC norms, but the maximum of the PM, SOx & NOx data
recorded during site emission measurement for 1 to 3 unit is higher than historic
emission data so it is considered as baseline for unit 4.
For all units Combustion control methods along with Selective Non-Catalytic
Reduction (SNCR) technology is the proposed to control NOx emission level as per
Dec 2015 MOEF norms.
NOx control system as applicable for the subject plant is presented in Section – 4 of
this Report.
In Unit 1,2,3 & 4 the PM level in flue gas is exceeding the MOEF&CC stipulated limit,
Hence, suitable abatement methods are to be implemented considering the PM
reduction due to WFGD. In Unit 1,2,3 & 4 the mercury level in flue gas is 0.19
mg/Nm3. which is exceeding the MOEF&CC stipulated limit by around
84.5%. Powdered Activated Carbon (PAC) injection system is recommended
for mercury capture.
Page :
10
Details of Mercury and PM emission control methods are described in Section – 5
of the report.
The plant design specific water consumption without considering FGD requirement
is within the MOEF&CC stipulated limit. Under design conditions, with the additional
water requirement for FGD, the consumptive water requirement increases by
160 m³/h and the specific water consumption to 3.34 m³/MWh.
a. The total Auxiliary power consumption for FGD is estimated as 2668kW, which
is about 1.07% of gross unit power output. Major power consumers are Booster
Fan, Slurry recirculation pumps. The spare capacity of existing Unit transformers
(UT) shall be utilized to provide power supply to FGD system.
b. The flue gas temperature at FGD outlet after installation of wet limestone FGD is
around 54.5°C.Hence, each unit is recommended to be provided with separate
RCC wet stack of minimum 100m height, with steel flue with suitable corrosion
and acid resistant lining. Hot flue gas during FGD bypass operation shall be
dispersed through the existing stack.
d. With the additional water requirement for FGD from the clarified water system,
the consumptive water requirement increases by 84 m³/h for each phase. The
specific water consumption for Phase 1 will be 3.38 m 3/MWh and for phase 2 will
be 3.53 m3/MWh, when including FGD water requirement. When considering the
actual historic plant water consumption of 3.18 m 3/MWh, the specific water
consumption including FGD requirement is around 3.35 m 3/MWh, which is within
MOEF&CC stipulation.
e. FGD waste water treatment plant (UF-RO based) is proposed to treat the FGD
waste water.
f. Lime stone is the sorbent used in FGD. The estimated lime stone requirement
for each unit is around 2.1 TPH based on minimum 85 % purity of limestone.
h. The aqueous Reagent (aqueous Ammonia) consumption shall be 0.6 TPH for
each boiler
i. Dedicated PLC based control system shall be provided for the FGD system of
Unit #1, 2, 3 & 4. This PLC shall be interfaced with the respective existing plant
DCS for monitoring from CCR through soft link and hardwiring is also envisaged
with Plant DCS for the control & interlock signals with main plant.
The EPC project completion time period implementation of FGD, SNCR and ESP
retrofit shall be around 24 months. The project shall be executed in separate
package.
The estimated project cost for the installation of FGD, Combustion modification,
SNCR, PAC, ESP retrofit and WWTP plant for the 4x250 MW units is
Rs.1093 Crores
The estimated total project cost for the installation of FGD is Rs.148.21 Crores
(0.59 Cr/MW), Combustion modification is Rs. 38.18 Crores (0.15 Cr/MW), SNCR is
Rs. 79.34 Crores (0.32 Cr/MW), PAC system is 5.09 Crores (0.02 Cr/MW), ESP
retrofit is Rs.2.19 Cr (0.009 Cr/MW) for each 250 MW unit.
The common FGD waste water treatment plant for all the four units is estimated to
cost Rs.0.90 Cr (0.004 Cr/MW)
2
Basis of Study
2.1 BASIS OF STUDY
MOEF&CC:
Clause No 33A of the Gazette
notification on Amendment
dated 28th June 2018:
Power generation capacity:
The 250 MW units of CTPP are commissioned between the year 2010 and 2014.
Hence the units falls under the category “TPPs (units) installed after 1st January
2004 up to 31st December 2016”, and “Units having capacity of less than 500MW”
as mentioned in the MOEF&CC gazette notification.
PM mg/Nm³ 50
FI team visited the power plant site and studied the existing plant design features
and discussed with XXXXXXX officials. FI team collected the plant design data and
related particulars with regard to coal analysis, emissions levels of SO 2, NOx, and
Particulate emission. The emission data were measured at 4x250 MW units by the
agency engaged by FI, which forms the baseline value for this report.
4Pass x 7Fields
Electrostatic precipitator Designed for 100 mg/Nm3 emission
220m high Twin brick flue RCC chimney for unit 1 & 2
Chimney
220m high Twin brick flue RCC chimney for unit 3 & 4
Space for FGD is available and marked on the Plot
Space for FGD Plan attached as annexure.
Annexure 1: Lists the data collected from CTPP during site visit which is used as
basis for this study.
3
Technology Overview for
SO2 and NOx Control
3.1 TECHNOLOGY OVERVIEW FOR SO2 AND NOX CONTROL
This section describes the emission control technologies available to control the
most common pollutants such as Oxides of Sulphur (SO2) and Oxides of Nitrogen
(NOx) in flue gas. These technologies include the Flue Gas Desulphurisation (FGD)
and Selective Catalytic & Selective Non-Catalytic Reduction (SCR/SNCR).
Technologies with higher removal efficiency are required to meet the applicable
emission norms in India, issued by MOEF&CC in December 2015.
Coal is used as primary fuel in thermal power plants. In India, thermal power plants
use both low sulphur Indian coal and high sulphur containing imported coal. Coal
contains elements like Carbon, Nitrogen, Sulphur, Ash and other elements. Coal
combustion process with air results in formation of pollutants such as NOx, SO 2 and
SO3.
When Sulphur containing fuel undergoes combustion, the sulphur in the fuel
combines with oxygen and forms gaseous SO 2.
S + O2 → SO2
Wet limestone based FGD (Wet FGD) is a proven technology used worldwide for
the control of SO2 from utility power plant.
The SO2 removal process occurs as hot flue gas enters the absorber where it is
cooled and saturated by the limestone slurry. The flue gas then flows upward
through the absorber spray zone, where lime stone slurry is sprayed counter current
to the flue gas flow, completing the SO 2 removal process. The process includes
forced oxidation system to convert Calcium Sulphite (CaSO3.½H2O) formed by SO2
removal process to Calcium Sulphate (CaSO 4.½H2O) or gypsum.
The limestone forced oxidation system could achieve efficiency in the range of
90 - 98% in power plants firing variety of coal.
The major systems/equipment of Wet limestone based FGD system are slurry
recirculation pumps, oxidation blowers, Flue gas handling system including Booster
fan and Gas to Gas Heat Exchanger (if opted), Lime slurry preparation, gypsum
handling system, waste water recovery system and related duct work, isolation and
bypass dampers.
Flow diagram for Wet limestone based FGD system is presented in Exhibit No. 1,
Schematic Diagram for Wet Lime stone based FGD system.
Circulating Dry Scrubber FGD technology is semi-dry type SO2 control technology
used for utility power plants where higher SO 2 capture efficiency is required. Each
CFBS system consists of a Circulating Fluidized Bed Scrubber and one no. 100%
capacity pulse jet fabric filter (PJFF) as major equipments.
Hydrated Lime (CaO) is used as the reagent in the system. Dry lime will be
pulverized and stored in lime storage silos. The lime will be conveyed to hydrator
system where it is hydrated and further stored in hydrated lime storage silos.
Flue gas from the ID Fans will enter the CFBS near the bottom of the scrubber
vessel. The gas will move in turbulent flow upward through the scrubber. The flue
gas, boiler ash, un-reacted lime and FGD byproducts emerge from the top of the
CFBS as a dust / gas mixture that proceeds to the fabric filter. Byproduct material is
re-circulated from the PJFF to the CFBS to maximize reagent utilization.
The flue gas is cooled by evaporation of finely sprayed water injected into the
CFBS. The water is sprayed through return-flow nozzles and is finely dispersed by
hydraulic atomization through the use of high-pressure water pumps. The water flow
is automatically adjusted according to the set process temperature and is
continuously controlled by a control valve in the return-flow line, leading excess
water from the injection nozzles back to the water storage tank.
The cooling of the flue gas reduces its effective volume and also enhances the
reactivity of the pollutants to allow for optimized removal.
The mixture of reagent & ash in flue gas are separated in the fabric filter, and a
large portion of the solids collected are recirculated through a control valve back into
the CFBS. After sufficient retention time in the scrubber the byproduct is discharged
out of the fabric filter to a storage silo by an external conveying system. The pulse
jet fabric filters are designed for online cleaning of filter bags.
Flow diagram for Semi Dry FGD system is given in the enclosed flow diagram
Exhibit No. 2 Schematic Diagram for Semi Dry FGD system.
Sea water based FGD is a type of Wet FGD, where the sea water is used as reagent.
The alkalinity in sea water is used for scrubbing the SO 2 from the flue gas. This
system is adopted for power plants installed in coastal area based on alkalinity level
in sea water and where SO2 capture efficiency of maximum 90% is required. This
system is not elaborated in this report as it’s not applicable for this power plant.
Dry sorbent injection systems involve the injection of a dry sorbent (typically sodium
bicarbonate or lime) into the ductwork following the boiler. SO2 reacts directly with
the
dry sorbent, and the dry product is collected in a downstream particulate control
device. Because a separate absorber vessel is not needed, capital costs are
minimized. Dry injection systems are generally applied when lower removal
efficiencies are required, or in small plants where the capital cost for other absorber
types may not be justified. Dry injection systems can typically achieve removal
efficiencies ranging from 50 to 70% depending on the specific conditions of the
application.
The EADS process is based on reaction between Ammonia and SO2 in the
Absorber tower to form the intermediate product Ammonium Sulphite /bisulphate.
Air will be fed into the absorber to oxidise this product into Ammonium Sulphate.
a. Flue gas system: Flue gas enters the absorber. After cooling, scrubbing, and
demisting steps, clean flue gas is discharged from the stack.
c. Ammonium Sulphate system (AS): The AS slurry is further refined through solid-
liquid separation, drying and packaging to produce AS fertilizer.
d. Very high efficiency (99.9%), lower SO2 emission (<35 mg/Nm 3), no waste water
treatment and solid waste disposal cost, zero CO 2 emission, 50% lower auxiliary
power consumption compared to limestone based plants and high value fertiliser
as by-product are the features of this system.
Electron Beam Flue Gas Treatment system
The sulphur oxides (SOx) and nitrogen oxides (NOx) present in the flue gas react
with these radicals and are thereby converted first into sulfuric acid and nitric acid
and subsequently into aerosols, (fine powdered matter) of ammonium sulphate and
ammonium nitrate.
These aerosols are then extracted by means of an electrostatic precipitator and the
cleaned flue gas is emitted via the stack.
The advantage of this system being, Desulphurisation and Denitration take place in
one process. The Desulphurisation efficiency is over 95% and Denitration efficiency
is over 80%.
Very few references of Industrial coal burning plants are available in the world and,
maximum size of the plant being 200 MW TPP.
ReACT Technology
Contact between flue gas and slow moving bed of activate carbon /coke, provides
mechanisms for efficient adsorption of SO2 and acid gases of Hg,flyash capture, and
surface promoted catalytic and non-catalytic NOx reduction. Ammonia injected into
the flue gas upstream of the moving bed of coke, helps in NOx reduction on the
surface of activated coke which helps in low temperature SCR reactions. NOx and
NH3 are reduced to N2.Ammonia added will help in SOx reduction also. The design
provided for 95% of SOx control generally yields 20-40% NOx reduction. The
Ammonia injection is in the range of 0.5 mol:mol of SO2.
The salient features of Wet limestone, Semi-Dry FGD and Ammonia based systems
are summarized in comparative form below for the following reasons:
a. These systems are with proven technologies with high efficiency of SO2 removal.
b. Other systems enumerated above are having fewer references around the globe.
c. Reagents are easily available in India.
Efficient
Wet limestone Dry/Semi Dry Ammonia De-
Parameter REACTTM
based FGD based FGD sulphurisation
(EADS)
Technology Proven Proven Emerging New Multi
technology for technology for technology for pollutant control
variety of coal for plants upto 300 variety of coal and technology
higher capacity MW. For units for higher capacity (SO2/NOx/Hg
Power plants. above 300 MW, Power Plants. control) for
multiple modules variety of coal
are required. and for higher
capacity Power
Plants.
SO2 Removal Higher> 90 % Maximum 94 %. Upto 99.9% Upto 99.9%
Efficiency and up to 98 %
Reagent type Lime stone Quick lime Anhydrous Activated coke
Ammonia and Ammonia
/ Aqueous
Ammonia / Urea
By product Gypsum Unreacted lime Ammonium Sulfuric acid
generated is of along with Sulphate which is
commercial gypsum, calcium generated is marketable.
grade sulphite are widely used as
recovered in the fertilizer
fabric filter, which
are disposed as
land fill.
Requirement No Yes No No
of Fabric filter
Operational Responsive to Lower part load High Turndown Responsive to
Flexibility variation in boiler efficiency. ratio 30-110% variation in
load. boiler load.
Power 1-2% of the 0.5 -1 % of the 0.5-1.0% of the 1.5 – 1.6 % of
consumption Installed Plant Installed plant installed plant the Installed
capacity. capacity. Power capacity. Plant capacity.
consumption is
less due to the
Efficient
Wet limestone Dry/Semi Dry Ammonia De-
Parameter REACTTM
based FGD based FGD sulphurisation
(EADS)
less number of
equipments and
lower pressure
drop.
Water Water Water Water Water
requirement requirement is requirement is requirement is requirement is
comparatively less in similar to Wet very minimal.
higher due to comparison to Limestone
slurry the wet system. process
preparation.
SO3 capture SO3 capture is High removal SO3 capture is High removal
around 25 - 40 % efficiency for SO3. about 98 %. efficiency for
SO3.
Pressure drop Higher Lower Similar to Wet Higher
across the Limestone FGD.
system
Raw material Cost of Costlier Very Costly. But, Very Costly as,
cost Limestone is less the requirement it needs to be
in comparison to would be 1/3rd of imported.
Lime powder. Limestone per MT
of SO2 removal.
Area Higher Lower Equal to Wet Less compared
Requirement Limestone based to Wet
plant Limestone plant
Suppliers Many suppliers Many suppliers Limited suppliers Limited
available world available world suppliers
wide wide
NOx refers to the cumulative emissions of nitric oxide (NO), nitrogen dioxide (NO 2)
and trace quantities of other nitrogen species generated during combustion.
Combustion of any fossil fuel generates NOx due to high temperatures and the
availability of oxygen and nitrogen from both the air and fuel. N 2 and O2 present in
the air combine to form NO and NO 2 at high temperatures. The quantity of NOx
formed during combustion depends on the quantity of nitrogen and oxygen
available, the temperature, the intensity of mixing and the time for reaction.
The most detrimental effect comes from NO 2 which forms from the reaction of NO
and oxygen. Once in the atmosphere, the NO2 is involved in a series of reactions
that form secondary pollutants. The NO2 can react with sunlight and hydrocarbon
radicals to produce ground level ozone/photochemical (urban) smog, acid rain
constituents,
and particulate matter. NO2 also absorbs the full spectrum of light and can reduce
visibility. NOx is associated with respiratory disorders, corrosion of materials and
damage to vegetation. Excess NOx concentrations in the air result in a brownish
color.
NOx in flue gas is the result of Oxidizing either Nitrogen in the combustion air or
Nitrogen in fuel or both.
Over Fire Air (OFA) is also used in conjunction with low-NOx burners to complete
the combustion process at a lower temperature. Air is injected above the normal
combustion zone when over fire air is used, the burners function at a lower than
normal air to fuel ratio, which reduces NOx formations. OFA system reduces the
NOx formation by creating fuel rich combustion zone.
Design ammonia slip values range from 2 to 10 ppm. SCR system can be installed
on new plants or retrofitted onto existing Pulverized coal boiler.
An exothermic reaction occurs as ammonia and NOx flow over catalyst forming
Nitrogen and Water vapour. Following are main process reactions:
Catalyst
4NO + 4NH3 + O2 → 4N2 + 6H2O
Catalyst
2NO2 + 4NH3 + O2 → 3N2 + 6H2O
Selective Catalytic Reduction (SCR) uses a catalyst and requires a system to meter
and inject ammonia into the flue gas such that it mixes before passing through the
catalyst. The necessary spacing between the ammonia injection grid and the
catalyst, and the space needed by each, require lengthening the boiler duct work.
In High Dust SCR configuration, the catalyst is located at the outlet of the
economizer and upstream of air preheater.
Vertical SCR reactor will be used for coal fired boilers, where the flue gas flows
downward through the catalyst. The reactor contains multiple layers of catalyst. The
volume of catalyst required varies with each installation. Soot blowers are installed
to remove particulates from the catalyst surfaces. For designs with honeycomb
catalyst, the catalyst pitch is typically about 7 to 9 mm to allow easy passage of
particulates and to facilitate cleaning with soot blowers. To obtain uniform gas flow
and remove particulates, high-dust SCR designs usually include turning vanes and
a flow- rectifying grid in the ductwork upstream of the reactor. A hopper may be
installed at the bottom of the SCR to collect ash and other particulates separated
from the flue gas stream. The flue gas exiting the SCR is ducted to the air heater
inlet.
NOx reduction is effective in a limited temperature range. For the majority of
commercial catalysts, the optimum temperatures range from 250˚C to 425˚C,
depending on gas composition and catalyst type. Catalyst effectiveness is reduced
as the gas temperature falls below or rises above the optimum.
The cost of a catalyst is typically a major portion (about 25 to 30%) of total SCR
system cost. Type of catalyst and the volume required are dependent on various
parameters such as inlet NOx level, NOx emission limits, flue gas temperature,
allowable ammonia slip, Oxygen content in flue gas, inlet dust loading, allowable
pressure drop across catalyst, flue gas catalyst poison concentration etc.
The commonly applied catalysts are all based on a porous titanium-dioxide carrier
material on which the catalytically active components like vanadium pentoxide and
tungsten trioxide are dispersed. To provide a large gas contact area with a minimum
pressure loss, the catalysts are provided as elements containing a large number of
parallel channels (corrugated and extruded honeycomb types) or a number of
parallel, spaced plates (plate-type catalysts).
In Low Dust SCR (Clean gas SCR) configuration, the catalyst is located at the outlet
of the ESP and upstream of ID fan OR downstream of FGD.
The arrangement is similar to High dust SCR. Due to lower temperature of the flue
gas to be cleaned, additional heat source (high temperature steam / Liquid fuel
firing) needs to be considered to raise the temperature of flue gas to around 350
Deg.C for effective NOx control.
The NOx reduction is effective only within a given temperature range. For the
majority of SNCR systems, the optimum temperatures can range from 760˚C to
1100˚C. With SNCR, as the flue gas temperature approaches the optimum, the
reaction rate increases and fewer injection nozzles are required to achieve a given
NOx removal efficiency.
Optimum temperature, required NOx removal efficiency, flue gas flow and inlet NOx
concentration are used to size the SNCR.
SNCR De-NOx efficiency for large coal-fired units is 25-50% with no by-products.
The salient features of SNCR and SCR system are discussed below.
XXXXXXX has installed continuous emission monitoring system for Unit #1,2,3& 4
of the plant. The units are under operation and the emission levels measured at site
by FI engaged agency, estimated value based on design worst coal analysis and
historical data are assessed and compared with the limiting emission values
mandated by December 2015 MOEF&CC norms.
a) The SO2 emission data estimated by FI based on blended coal anlysis provided
by XXXXXXX is considered as the base emission value.
b) As per the MOEF&CC norms, for power plants of capacity less than 500 MW
and installed after 1st January,2004, up to 31 st December, 2016” as
mentioned in the MOEF & CC gazette notification. The permitted SO 2
emission is 600 mg/Nm³.
Based on the above the FGD SO2 removal efficiency works out to minimum of
69%.
Dry / Semi dry type of Desulphurisation system is not suitable for the
reqiredSO2removal efficiency and unit capacity. The dry/semidry system requires
replacement of boiler auxiliaries – ESP (with bag filter)and ID fans. Also, the by-
product is suitable only for landfilling.
The other technologies like Ammonia based FGD system and React are not widely
installed worldwide and has no reference installation in India. Considering limited
suppliers for these technologies and higher reagent cost, these technologies are not
recommended for this plant.
Wet limestone based Flue Gas Desulphurization (FGD) technology is considered for
SO2 emission control for these units with SO 2 removal efficiency 95% to meet the
December 2015 MOEF&CC norms stipulation.
Wet limestone based FGD with insitu forced oxidation is proven technology
implemented Worldwide for utility power plants.
This system will be Add-on to the unit at downstream of ID fan with a tap off and
bypass arrangement. Hence no modification required in ESP
The Layout of Wet FGD system / equipment and facility is worked out and
feasible to accommodate in the available space optimally.
Gypsum will be the by product which is marketable.
Provides higher SO2 removal efficiency (90 to 98%) for range of coal analysis .
Limestone mines are located close (300 to 400 KM radius) to the plant for
sourcing.
Wet FGD System and Equipment
In Wet FGD system, SO 2 removal process occurs as the hot flue gas enter the
absorber tower where it is cooled and saturated by limestone slurry. The flue gas
flows upwards through the absorber spray zone, where limestone slurry is sprayed
counter current to the flue gas flow, completing the SO 2 removal process.
The flue gas is tapped from the flue gas duct at downstream of ID fan discharge
damper. A booster fan is provided to develop the head required to overcome the
pressure drop across the FGD system. The pressurised untreated flue gas from the
booster fan enters the absorber. The flue gas will be dispersed to atmosphere
through the existing stack during FGD bypass condition.
The treated gas from absorber released to the atmosphere through the proposed wet
stack at about 53°C.
FGD system to be installed at this plant shall have inlet, outlet and bypass dampers
to be provided on the ducting. Necessary modifications for the installation of the
bypass damper in the flue gas duct and utilization of the existing duct supports shall
be evaluated during implementation.
The major systems / equipment of the Wet limestone FGD system are listed and
their design & functional details are discussed below.
Booster Fan
Lime Handling and Slurry preparation system.
Absorber and Slurry re-circulation system
Gypsum dewatering system
Waste water treatment system
Emergency Slurry tanks
Emergency water tanks
Process water tanks
a) Booster Fan for FGD System
Booster fan shall be required to feed the flue gas to FGD system to address the
following:
Pressure drop across the FGD system from the unclean flue gas take off
point till the clean flue gas join back to the existing ducting.
The flue gas temperature drop in FGD system will reduce the draft available
at the proposed wet stack.
In order to develop the head required for the above, Booster fans shall be
provided for the FGD system. The head to be developed by booster fan is
calculated based on thermoflow data.
Ball mills, mill permeate tanks, Hydro cyclones, Lime slurry tanks shall have
redundancy.
The Limestone handling system shall be sized for 25.5TPH to cater the
4 x 250 MW units, considering 8hour operation per day.
c) Absorber and Slurry re-circulation system
Absorber is a spray type absorber where the flue gas and the limestone slurry
flow in the counter current direction. The limestone slurry is sprayed at different
levels in the Absorber through spray nozzle grids. Each elevation spray nozzle
grid is supplied by a dedicated slurry recirculation pump and a common standby
for all the recirculation pumps will be provided. The sprayed lime slurry is
collected in the reaction chamber located in the bottom of the Absorber. The
slurry is re-circulated in the absorber.
The Absorbers to be installed in CTPP shall be designed for optimum Flue gas
velocity. The Slurry pump capacity and the numbers shall be decided based on
the optimum Liquid / Gas (L/G) ratio.
Absorber type and design shall be specific to the FGD supplier, and hence shall
be finalised during implementation.
The slurry density and pH in the absorber reaction chamber shall be monitored
and portion of the slurry shall be bled to maintain the solids concentration in the
slurry.
The slurry shall be pumped to the 2x100% hydro cyclones where the over flow is
taken back to the absorber and the underflow is taken to the vacuum belt filter.
The gypsum from the vacuum belt filter shall have moisture < 10 %, chlorides
< 100 ppm and shall be stored in the ground floor of the gypsum dehydration
building.
The wallboard gypsum generation from the system is about 3.9 TPH and this
depends on the quality of the limestone fed to the system. The generated
gypsum shall be stored in the ground floor of gypsum dewatering building, which
shall be sized to store for minimum 3 days. Additional space for gypsum storage
shall be decided during implementation phase based on gypsum utilization
program.
Using pay loader gypsum shall be loading to the truck and it shall be transported
to the cement /gypsum board manufacturer’s location.
The Emergency slurry tank shall be of MS with inside glass flake lining/ ceramic
acid resistant tile lining. The capacity of the tank shall be suitable for holding the
volume of one absorber reaction tank. The Slurry tanks shall be provided with
Agitator and pump re-circulation facility to avoid settling of slurry in the tank. The
system is common system and is used only during emergency or planned shut
down for the transfer of slurry from the absorber to take up maintenance work in
the Absorber/ Reaction tank.
The water required for the FGD system shall be tapped from the Makeup water
line to the CW system. The Process water tanks shall be MS with Inside Epoxy
coating. The tank shall be sized for holding 12 hours storage requirement. One
tank shall be used for equipment cooling and the other tank shall be used for
process and mist cleaning requirement. The hot water after the equipment
cooling shall be used for the process and the mist cleaning purpose.
g) Waste water
The waste water from the FGD system has high Suspended and dissolved
solids of about 30,000 ppm. This shall be treated in clarifier which is part of the
FGD system to remove suspended solids, neutralized and transferred to the UF-
RO based FGD waste water treatment plant. Around 1.5 m 3/hr of waste water is
generated from the FGD system. This value is based on similar project
experience.
The auxiliary power consumption for the FGD equipment of each unit shall be
around 2668 KW. The major power consumers are the Booster fan and Slurry
recirculation pumps.
The makeup water quantity for the FGD system including HVAC is estimated to
be around 56 m3/hr. This is as per FI in house data.
Instrument air requirement for the system shall be1 Nm 3/min, based on FI in
house data.
DM water for make-up of the closed cooling water system, if required shall be
sourced from the existing DM water system header. The requirement will be for
initial filling of the system, and for makeup intermittently.
The temperature of flue gas at FGD outlet after installation of wet limestone FGD
shall be around 54.50C. This is in wet saturated condition, hence installation of
separate wet stack of 115m height with suitable internal lining is recommended for
each unit. The wet stack shall be designed as per EPRI wet stack design guide.
The wet stack, ducts handling wet flue gas shall be provided with Stack Liquid
Discharge, corrosion resistant lining, Condensate collection system and drainage.
The stack drain shall be neutralised and send to the existing effluent treatment plant.
The proposed wet stack shall be of RCC shell with steel flue.Since, the flue gas is
wet saturated and with acid condensate the steel flue need to be provided with
suitable corrosion/acid resistant liner.
However the various types of chimney lining and the details are presented below.
Titanium lining
The flue can is lined internally with Titanium plates of 1 to 2 mm thickness. This
lining process is adopted only for newly constructed chimney.
Borosilicate lining
Borosilicate lining in the form of tile fixing inside the chimney, which can be done
as retrofit in the already constructed chimney.
High temperature Glass flake lining
Based on feedback from Liner suppliers, around 3 to 4 months are required for
the applying this lining and the application has to be carried out during
shutdowns in phases.
Use of acid resistant bricks similar to the existing chimney can be done for the
wet stack. However flue gas velocity required to be maintained in such flues
need to be limited to 13 to 14 m/sec unlike the other liners where the velocity
shall be maintained around 16 to 17 m/sec.
Refer to Table 1.3, the design NOx levels at the stack of these units are exceeding
the MOEF&CC stipulated limit.
Emission level as derived from the coal used in the plant is assessed and compared
with the limiting emission values mandated by December 2015 MOEF&CC norms.
a) OEM guaranteed value for NOx emission is 615.29 mg/Nm 3.The details of boiler
provided with Low NOx burners, and presence of Over Fire Air (OFA/SOFA) are
not available.
In view of the above Base line data for NOx for the purpose of NOx control
technology selection is considered as 615.29 mg/Nm³
NOx Control Technology Selection
Based on December 2015 MOEF norms Unit #1,2,3&4 were installed after 1st
January 2004. Hence, the permissible maximum NOx emission is 300 mg/Nm³ for
all the 4 units. The units are already provided with upper OFA ports as informed by
XXXXXXX.
The NOx control method proposed to be adopted shall ensure reduction of NOx
from 615.29mg/Nm³ to 300 mg/Nm³. Based on feedback from various boiler
suppliers the combustion control like low NOx burners, Over fire air shall and Low
NOx burners shall contain the NOx emission to 450 mg/Nm3 at the furnace outlet.
Considering that first step NOX control will be achieved by implementing the
combustion control in consultation with boiler supplier, the further NOx control is
required to meet MOEF &CC norms.
The required NOx removal efficiency for reducing NOx from 450 mg/Nm 3 to
300 Nm3 is around 34%. Selective Non-Catalytic Reduction (SNCR) method is the
proposed as suitable technology.
The SNCR system need to be adopted for NOx control, as the NOx control
efficiency required is around 34%, in the absence of primary NOx control system in
the boiler.
The major equipment of the suggested SNCR system would comprise of the
following.
The equipment design data is arrived based on the inputs and assumptions
discussed in the report.
a) Ammonia unloading & Storage system
Three numbers Ammonia bulk storage tanks (for 7 days storage) for both the
units will be provided to store the required aqueous ammonia solution.
Ammonia received in road tankers will be unloaded to the bulk storage tank
by the two nos. (1W+1S) common ammonia unloading pumps.
Ammonia from the bulk storage tank will be transferred to the ammonia
mixing and injection system of each boiler by means of two nos. (1W+1S)
metering pumps supplied for each boiler NOx reactor.
For proper dispersion of ammonia in the boiler flue gas path mixing of
ammonia with air is required. Two (2) nos. (1W+1S) dilution air blowers for
each boiler will supply the required dilution air to the mixing unit where the
ammonia is vaporized and mixed in the required proportion.
The ammonia solution after mixing with air will be transferred to the injection
lancers of the reactor.
Reagent Selection
Urea injection requires DM water for forming urea solution whereas liquid
ammonia solution does not require dilution. Thus, additional cost of DM
water generation and corresponding increase in specific plant water
consumption are avoided with the use of aqueous ammonia.
The NOx and Ammonia measurement will be made at the inlet and outlet
of the NOx reactor.
The generated SO3 will lead to acid corrosion and ash clogging due to
production of ammonium hydrogen sulphate and ammonium sulphate
The auxiliary power consumption for the SNCR equipment & systems will
be around 51 kW. The major power consumers will be the Ammonia
injection pumps and dilution blowers.
Based on the input data collected from CTPP for250 MW and estimated values, the
design data and performance parameters are presented below.
1. Booster Fans
Plant configuration MW 250
- Quantity Nos. 2x100%
- Capacity m3/s 501
- Total developed Head mmWC 290
2. Absorber
Wet spray tower type
- Type
absorber
- Numbers 1x100%
Carbon steel with internal
- Material of Construction
Glass Flake lining
- Absorber removal efficiency % 68.4% (min)
- FGD removal efficiency % 68.4% (min)
- Absorber gas velocity m/s 3.0
3. Limestone Crusher
Mercury is present in coal in trace amount and is released during coal combustion
process and can appear in the flue gas as particulate mercury (solid phase) and as
vapour phase mercury (gaseous phase). Vapour phase mercury, appearing in flue
gas, shall be present as either elemental mercury or oxidized mercury depending on
the type of coal. The mercury in solid phase are collected in bottom ash, in the ESP
along with flyash, in FGD effluent in the form of scrubbed slurry.
Mercury in some chemical form is very toxic. Mercury, when in filters in soil and
water sources, can be converted to methyl-mercury by microorganisms and
accumulate in the fatty tissues of fish that live in the mercury contaminated water.
Consumption of contaminated fish is the main identified risk to humans.
Powdered Activated Carbon Injection in flue gas path has the potential to achieve
95% Hg control. The performance of activated carbon is related to its physical
properties like surface area, pore size distribution, and particle size distribution and
chemical characteristics. The capacity for Hg capture generally increases with
increasing surface area and pore volume.
PAC is carbon that is treated with high temperature steam to create large surface
area.
The pores of the carbon sorbent must be large enough to provide free access to
internal surface area by mercury ions while avoiding excessive blockage by
previously adsorbed reactants. As particle sizes decrease, access to the internal
surface area of particle increases along with potential adsorption rates.
The PAC system comprises Two no. Bulk silo for storing activated carbon required
for 7 days consumption. One no. screw feeder below each silo shall feed the carbon
at required rate to the supply pipe. One no. transport air blower for each silo will
supply the transportation air to the supply pipe which will carry the carbon to the
injection point at the ESP inlet duct.
250 MW
438 50 0.19 0.03
(Unit 2)
250 MW
93 50 0.13 0.03
(Unit 3)
250 MW
105# 50 0.19 0.03
(Unit 4)
(#) Historic maximum data
5.5 Requirement of Mercury Capture
The coal analysis received from CTPP, does not indicate any Mercury (Hg)
presence. However Mercury presence is identified in the flue gas as per FI
measured emission data.
In Unit 1,2,3 & 4 the mercury level in flue gas is 0.19 mg/Nm 3. Which is exceeding
the MOEF&CC stipulated limit by around 84.5%. Powdered Activated Carbon (PAC)
injection system is recommended for achieving mercury control.
However based on the mercury capture efficiency provided by the FGD/Nox control,
the requirement of separate Hg control like PAC or chemical additives for improving
Hg capture efficiency in the FGD-Nox control systems shall be concluded.
Indian coal with max.34.8% ash content is fired as primary fuel in this power plant.
As the boilers are Pulverized fired design, 90% of the ash in the form of fly ash is
captured in the ESP.
The Electrostatic precipitator works on the technique that employs the application of
an electric field to separate out the suspended particles from the flue gas by ionizing
the ash particle and collecting in collecting electrode.
An ESP of 4 pass x 7 fields is provided for the unit for controlling the particulate
emission.
The ESP has been designed for an inlet dust burden of maximum 87.9gm/Nm 3 with
an average operating particulate removal efficiency of 99.88% (all fields in
operation).
In Unit 1,2,3 & 4 the PM level in flue gas is exceeding the MOEF&CC stipulated limit
hence modification of existing ESP is recommended to limit the Particulate Matter
within 50 mg/Nm³.
The ESP has been designed for the guaranteed performance of 100 mg/Nm 3 of
Particulate emission with worst coal firing @ BMCR load, which is exceeding the
December-2015 MOEF Norms- 50 mg/Nm3. It is observed that no additional space
is provided at site for installation of additional ESP fields in future.
Hence, abatement methods for the PM emission control is required to increase the
ESP efficiency to 99.95%, considering the design inlet dust loading. It is
recommended that the particulate emission reduction due to wet lime stone FGD
need to be considered prior to implementing the retrofit work in ESP. The ammonia
injection in SNCR will contribute for reduction in ash resistivity, and hence increase
in ESP efficiency. This shall also be considered for the extent of ESP retrofit.
The following are the various retrofit methods to improve ESP collection efficiency.
One of the following measures or combination of them shall be implemented for
achieving the required PM at ESP outlet, considering techno economic aspects, site
conditions, available area, etc.
The advantages of High frequency TR sets over conventional TR sets are mentioned
below:
a) Decreases the ESP dust emission up to 60% without the need of expanding the
ESP
b) Improved power factor in the range of 0.9 ensuring reduced input current and
losses. The power factor of the conventional TR set measures about 0.6
c) Reduced arc shutdown time in the range of 10 micro seconds ensuring quick
voltage restoration.
d) Reduced arc energy results in lesser wear & tear of electrodes
e) Less power consumption based on the above advantages
f) Smaller and lighter than the conventional TR sets.
g) Overall reduction in electrode surface area and weight.
Unit-3 93 50 99.89
Parameter
Description Unit
250 MW
This chapter covers the evaluation of design plant water consumption, and impact of
the additional water consumption due to installation of FGD system, on the existing
plant water system to meet the MOEF&CC stipulated limit. Also the mitigation
measures to limit the plant water consumption within the stipulated MOEF norms is
covered in this chapter.
Specific Water Consumption standards for Thermal Power Plants as per Ministry of
Environment, Forest and Climate Change are given below:
The maximum of the monthly plant actual specific water consumption data provided
by XXXXXXX for the period between April 2016 to January 2018 is 3.18 m3/MWh.
This forms the baseline data for analysing specific water consumption.
The plant consumptive water requirement for the 4x250 MW unit as per the design
water balance diagram areas are as below:
For unit 1 & 2 it is about 1638 m 3/hr (when ash water recovery is available). The
specific plant water consumption is 3.22 m3/MWh.
For unit 3 & 4 it is about 1685 m3/hr (when ash water recovery is available). The
specific plant water consumption is 3.37 m3/MWh.
The Specific water consumption as per the actual plant consumption data and
design water balance is within the MOEF & CC stipulated limit.
The FI measured raw water consumption data when 3 units (except Unit 2) in
operation, and plant load at 600 MW is 880 to 920 m3/hr supplied from phase 2 raw
water pump house. This works out to 1.46 m3/MWh to 1.53 m3/MWh.
Since the plant was not in full load operation, and the consumption pattern was
changed due to rainfall that caused reduction in CHP dust suppression etc., the
design water consumption data is considered as baseline for evaluating methods to
optimise water consumption.
6.5 Water Requirement for FGD System and Source
Make up water requirement for each Wet FGD system works out to 56 m³/hr. This
water requirement will be tapped from clarified water storage tank of phase 1 & 2
(168.1 m3/hr) and balance 53.5 m³/hr is suggested to be tapped from the Phase 2
CMB which is supplied for horticulture purpose in design WBD. The 2.4 m3/hr
recovery water from the proposed FGD WWTP shall also be used for the FGD
makeup.
With the additional water requirement for FGD from the clarified water system, the
consumptive water requirement increases by 84 m³/h for each phase.The specific
water consumption for Phase 1 will be 3.38 m 3/MWh and for phase 2 will be 3.53
m3/MWh, when including FGD water requirement.
When considering the actual historic plant water consumption of 3.18 m 3/MWh, the
specific water consumption including FGD requirement is around 3.35 m 3/MWh.
From the above it is concluded that the plant specific water consumption including
FGD requirement is within the MOEF&CC stipulated limit.
There would be reject from each FGD plant, which is estimated at around 1.5 m3/h.
This water contains very high suspended solids and dissolved solids. The reject
water shall be treated in a clarifier to remove suspended matter. This water will be
treated in the proposed UF-RO based waste water treatment plant for achieving
zero waste discharge. The R.O reject shall be used in ash slurry system, and solid
waste will be handled by agencies authorized by XXXXXXX.
The table provided below provides the assessment of the design consumptive water
requirement, areas of optimization/suggestions to reduce plant water consumption.
Table 6.2 Plant Water Consumption
Assumptions/
Suggested/
SI No Parameter Unit Value as per WBD Reference/ Basis
optimized Value
details
PHASE - I
Evaporation + drift
1. loss of each Cooling m3/hr 564
tower
Blow down of each
2. m3/hr 162
Cooling tower
Make up for each
3. m3/hr 726
Cooling tower
Total clarified water
4. required for CT m3/hr 1452
Make up
Clarified water
5. required for Service m3/hr 61
water application.
Clarified water
6. required for DM m3/hr 51
plant inlet.
Total clarified water =1452+51+61
7. m3/hr
required for Phase- I =1564
Raw water inlet to Considering 97.5%
8. m3/hr 1604
clarifier recovery
Clarified water
18. required for Service m3/hr 55
water application.
Clarified water
19. required for DM m3/hr 84.8
plant inlet.
Page :
60
Assumptions/
Suggested/
SI No Parameter Unit Value as per WBD Reference/
optimized Value
Basis
details
Total clarified water
20. m3/hr =1621.8
required for Phase- I
Raw water inlet to
21. m3/hr 1651.3
clarifier
22. Evaporation loss m3/hr 33.75
Total Raw water =1651.3+33.75
23. m3/hr
Required for Phase-I =1685.05
Specific Water
=1685/2X250
24. Consumption for m3/mw
=3.37
Phase-I
This additional water
requirement for FGD
shall be taken from
Clarified water storage
tank.
Water Required for
FGD for one unit is 56
Water required for m3/hr ,
= 112-28
25. FGD plant. for m3/hr 2x56 = 112 m3/hr
=84
phase. Is required totally for
phase 2 ,of which 28
m3/hr will be met by
the CMB water from
phase 2 and recovery
water from the
proposed FGD
WWTP.
Total Raw water
requirement and =1685+84
specific water =1797/(2X250)
26. m3/hr
consumption =3.53 m3/mw
,including FGD
(For phase II)
This is disposed in
3
31. Reject water from m /hr 3.6 Ash slurry sump.
Table 6.2 Design Data for FGD waste water treatment plant
A.
FGD Waste collection pit
1) Quantity 1 No.
B. MEDIA FILTER
1) Quantity 2 x 100 %
5) MOC GRP/FRP
C. ULTRAFILTRATION SKID
1) Quantity 2 x 100 %
Sl.No. Description Data
5) Min recovery 90 %
D. SWRO SKID
The System and equipment Layout requirement for the Wet FGD and SNCR
systems is studied to ascertain the feasibility of locating the equipment and facilities
to meet the functional requirements.
Equipment space for FGD, SNCR and FGD waste water treatment plant is
presented in the Plot Plan.
From the site walkthrough survey it is observed that around 15m x 50m space is
available in front of the ID fans.
However for Unit-1 it is observed that, a cooling water pit located in the same area
requires relocation and for Unit-3 it is observed that, 2 nos. existing condensate
storage tanks in that area requires relocation.
The major FGD system equipment namely booster fan, Absorber for each unit are
proposed to be located near the chimney. The Slurry re-circulation pumps,
Oxidation blowers, Gypsum bleed pumps and standby Absorber slurry re-circulation
pump are proposed to be located near the absorber.
2 x 100 % booster fans for the unit is suggested for the FGD system.
The limestone storage, preparation and handling system, and other auxiliary
buildings for FGD is proposed to be located on the east side of chimney which is
allocated for future FGD. One no.115m high wet stack for each unit shall be located
in the space available adjacent to the fly ash silo.
The lime slurry building shall house the wet ball mills, mill permeate tank,
Compressors and DG sets in the Ground floor. The lime slurry tanks and transfer
pumps, Limestone silo, air receivers shall be located outside the Lime slurry
preparation building.
The Electrical and Control rooms, cable vaults shall be located above the lime slurry
preparation building.
The Process water tanks, Emergency slurry tanks and pump sheds shall be located
near the lime slurry building.
The Gypsum dewatering building shall be located near the emergency slurry tanks.
Gypsum dewatering building shall house the vacuum belt filters and waste water
treatment system. Gypsum generated shall be stored in the ground floor of the
gypsum dehydration building and three days storage capacity of gypsum is
envisaged.
The reagent- Aqueous Ammonia receipt, storage and distribution to the respective
units will be located in the FGD Reagent preparation plant area. This area will be
properly fenced for protecting any trespassing into this area.
The space for the proposed FGD waste water treatment plant shall be around 15m
x 15m near the existing fuel oil facility, as identified in the plot plan.The clarifier, UF-
RO treatment plant, chemical dosing system etc, are recommended to be located in
this space.
The reagent storage and distribution to the respective units will be located in the
FGD Reagent preparation plant area.
The installation of FGD system in the plant warrants for additional buildings and
facilities along with foundation works for the equipments & support structures.
The following list summarizes the major buildings & structures envisaged for
installing the FGD. The facilities are arrived at based on similar installation and
considering scope of optimizing and finalization during implementation.
Table 7.1 List of Buildings and foundation
Type of
Type of Building Roofing /
Description foundation Side cladding
/ Structure Flooring
expected
Booster Fan Vendor Supply Open / Raft - -
Equipment Foundations
Flue Gas Duct Steel ducts Open / Raft - -
supported on Foundations
Structural steel
frame (for FGD
&SNCR)
Absorber Structural Steel Open / Raft - -
tank Foundations
Elevator - Open / Raft - -
Foundations
Oxidation Vendor Supply Open / Raft - -
Blower Equipment Foundations
Slurry Vendor Supply Open / Raft - -
Recirculation Equipment Foundations
Pump located
below FGD
Limestone RCC Building Open / Raft Brick Wall RCC slab
Slurry Foundations
Preparation
building
Limestone Steel Tank Open / Raft - -
Slurry Tank Foundations
Limestone Steel silo Open / Raft - -
storage Silo Foundations
Gypsum RCC Building Open / Raft Brick Wall RCC slab
Dewatering Foundations
Building
Emergency Steel Tank Open / Raft - -
Slurry Tank Foundations
Process Water Steel Tank Open / Raft - -
Tank Foundations
Process Water Steel Structure Open / Raft Permanent Permanent
pump shed Foundations colour coated colour coated
metal cladding galvanized MS
troughed metal
deck sheet
Limestone Structural Steel Open / Raft Permanent Permanent
unloading & Foundations colour coated colour coated
Storage shed sandwiched galvanized MS
insulated metal troughed metal
Type of
Type of Building Roofing /
Description foundation Side cladding
/ Structure Flooring
expected
cladding above deck sheet
3m high brick
wall.
Pipe & Cable Steel Structure Open / Raft - -
Racks Foundations
Ammonia Steel structures & Open / Raft - -
Storage tanks Tank Foundations
Activated Steel structure, Open / Raft
carbon silo supported on Foundations
steel columns.
FGD waste RCC Building Open / Raft Brick Wall RCC slab
water treatment Foundations
plant
8
Auxiliary Power Consumption &
Utility Requirements
8.1 AUXILIARY POWER CONSUMPTION & UTILITY REQUIREMENTS
The auxiliary power required for operation of Wet Lime stone based FGD and
SNCR systems for the Unit #1,2,3 &4 are discussed in this section.
The major equipments in FGD and SNCR systems along with the power
consumption are provided below. The sizing of equipment is based on BMCR
condition.
Table 8.1: Major Equipment in FGD,SNCR & PAC system with Power
Consumption
Page :
70
The total Auxiliary power requirement of FGD, SNCR, FGD WWTP and PAC
systems is estimated to be around 2749 kW for each unit. This will work out to
around 1.10% of installed capacity.
The following are the process utility requirement for the proposed FGD, SNCR and
PAC system.
a) Make Up water
The FGD make up water requirement for each unit shall be around 56 m 3/hr
(maximum), based on FI experience on similar capacity projects .Clarified raw
water from the clarified water storage tank (phase 1 & phase 2) shall be used as
FGD make up water.
b) FGD Reagent requirement
Lime stone is the Reagent used in FGD. The estimated lime stone requirement is
around 2.1 TPH per unit. The quantity of limestone is arrived based on minimum
purity of 85%.
c) Reagent requirement for SNCR
Aqueous Ammonia (of 29% concentration) is used in SNCR. The estimated
Aqueous Ammonia is around 0.6 TPH per unit.
d) Reagent requirement for PAC system
Powdered activated carbon is used in PAC system. The estimated activated
carbon powder requirement is around 0.23 T/hr for each unit.
The Gypsum generated from the wet limestone FGD is a by-product which can be
sold to industries and agricultural farms. The various usage of gypsum is listed
below.
It is suggested that XXXXXXX shall sell the gypsum to Cement industries similar to
fly ash. Also the gypsum shall be utilized for agriculture purpose and in fly ash brick
manufacturing purpose.
Limestone of 85% purity is considered for FGD system. Accordingly, the limestone
requirement for each 250MW unit works out to 50.4 T/Day.
Limestone handling and storage system is one of the major facilities required for
FGD Plant. Limestone requirement for the FGD system may be sourced from
nearby limestone mines. As, limestone is hygroscopic in nature, a closed shed is
required to store raw limestone. Limestone is proposed to be transported to the
plant by dumpers. The expected size of raw limestone is (-) 150mm which will be
crushed and used in the ball mill.
The plant will have 7days storage of raw Limestone storage in closed area. The
limestone from the storage area will be unloaded into the dump hoppers by
dumpers and further transferred into lime stone day silo via limestone crusher,
bucket elevator, and feeders. The complete facility from hopper, part of bucket
elevators will be underground.
Two nos. limestone storage silos each having 24 hours storage capacity will be
provided. Limestone will be discharged from the day silo onto the weigh belt feeder
and forwarded to the wet ball mill inlet.
Miscellaneous systems like ventilation system for the facilities, Dust extraction
system for containing the dust at the limestone handling and gypsum handling area,
conveying and transfer facilities, Dust suppression system at the unloading area,
level switches and indicators, Air blaster system and Gates below hopper and silo
as required shall be envisaged.
The limestone handling system will be designed for eight hour operation catering to
a day’s requirement of both the unit with an operating capacity of 25.5 TPH.
Two wet ball mills are envisaged below the silo (1W+1S) catering to both the units.
Regulated quantity of limestone will be fed to the wet horizontal type ball mill. The
limestone milling system would generally consist of wet ball mill, mill oil unit, mill
product tank with an agitator, mill product pump, and mill hydro-cyclone and 2-way
distributor.
The water of required quality will be supplied to wet ball mill and mill slurry tank.
Slurry from the wet ball mill will flow by gravity to the mill product tank and then
pumped up to the mill hydro-cyclone. The mill hydro-cyclone underflow containing
the oversized material will be recirculated to the wet ball mill inlet directly, while the
overflow will be discharged to the limestone slurry feed tank via 2-way distributor as
a product of wet ball mill system. The limestone slurry will be pumped from the
limestone slurry feed tank to the absorber.
Activated Carbon requirement for each 250 MW unit works out to 5.52 T/Day.
Two no. Powdered Activated Carbon storage silos both having 7 days storage
capacity will be provided.
9
Interface Requirement
with Existing Plant
9.1 INTERFACE REQUIREMENT WITH EXISTING PLANT
The FGD installation for the 4x250 MW unit is to be done as retrofit to the existing
power plant. This would require many interfaces for process, utility, electrical and
control system.
This section covers the interface details with the operating plant.
Fire Fighting system Extension of existing fire hydrant system to FGD area
Power requirement of FGD system will be 2668 kW for each unit and for SNCR
system it will 51 kW for each unit as detailed in chapter 08.
SNCR power, PAC and FGD WWTP power is required at 415 V level which can be
derived from 415 V FGD PCC.
FGD power need to be drawn at 6.6 kV level from the power plant.
As per the transformer loading details received during input data collection, loading
of ST-1 , ST-2 and ST-4 was 21 MW , 21.7 MW and 3.71 MW respectively. Hence
the Station transformer will have the adequate spare capacity to feed the FGD
system. During site visit, Unit Transformers of Unit-1 & Unit-2 were under
maintenance.
As per the data collected during site visit no spare feeders are available in station
switchboards of Units 1,2,3 & 4.Hence, following is proposed to cater the FGD
loads. For Units 1,2,3 & 4 new additional feeder panel need to be provided by
extending the sides of station switchboards, necessary and required modification for
expansion of bus bars shall be carried during detailed engineering.
For the FGD system, Power supply is envisaged at two levels viz., 6.6 kV & 415 V,
to provide power for all the drives and equipment. For FGD system, one 6.6 kV
Switchboard with two incomers and bus coupler will be provided. Motors rated
>200 kW will be fed from 6.6 kV Switchboard. Motors rated up to 200 kW will be fed
from 415 V supply. 415 V supply will be derived from 6.6 kV FGD switchboard
through LT service transformers.
Dedicated 220V DC battery system is envisaged for control supply and critical DC
power requirement.
Dedicated 415 V AC emergency DG set is envisaged for the FGD system to feed
critical 415 V drives and panels.
Dedicated 230 V AC UPS supply system is envisaged to feed PLC panels and
workstations.
The retrofitting measures for augmentation of ESP efficiency may require facilities
such as addition of 415V power feeders and control panels. The number of
additional
power feeders, additional control panels and the power requirement can be
ascertained based on the extend of the modification to be performed in the ESP in
consultation with ESP vendor.
The usage of existing spare feeders in the ESP MCC and or addition of new feeders
will be decided during detail engineering. The additional power if required will be
marginal and can be fed from the existing LT board. The layout and location of new
control panels and the extension of ESP MCC if emerges will be decided during
detail engineering.
Dedicated PLC based control system shall be provided for the FGD system and
separate dedicated PLC based control system is envisaged for the control and
operation of SNCR system. These PLCs shall be interfaced with the respective
existing plant DCS for monitoring from CCR through softlink and hardwiring is also
envisaged with Plant DCS for the control & interlock signals with Main plant.
Spare I/O channels (to be added if required in future) and spare soft link ports in
plant DCS shall be utilized for these softlink and hardwired interface.
The minimum target reliability of the control system hardware like each electronic
module/card, power supply, peripheral devices etc. considering its failure rate/mean
time between failures (MTBF), meantime to repair (MTTR), should be designed in
such a way that the availability of the complete C&I system is assured for
99.7%.Redundancy of components and system shall be dictated by availability
criteria as mentioned above to ensure that the system availability target as well as
safety considerations in critical applications are fully met.
The design of the control systems and related equipments shall adhere to the
principle of 'Fail Safe' operation wherever safety of personnel / plant equipment is
involved. 'Fail Safe' operation signifies that the loss of signal, loss of excitation or
failure of any component shall not cause a hazardous condition.
The programmable logic controller (PLC ) based control system shall fully achieve
the various functions of modulating controls, open loop controls including sequence
interlock and equipment protection, monitoring, alarming etc. for Flue gas
desulphurization system & SNCR system. PLC based control systems of the FGD &
SNCR systems shall be interfaced to Plant DCS through redundant soft link
interface and hardwiring is also envisaged with Plant DCS for the control & interlock
signals with Main plant. Control, operation & monitoring will be done from the local
control room located in the FGD Area. However a remote operating station of FGD
PLC& SNCR PLC shall be located in the existing Central control Room (CCR).
All the C&I devices and equipments shall be provided to achieve these functions
and to make the system complete and operable. The control system shall be latest
with State of the Art technology. All equipment, system and accessories of this
project shall be from the latest proven product range of a reputed experienced
manufacturer whose successful performance has been established by a
considerable period of satisfactory operation in similar FGD & SNCR operations of
coal fired and utility power stations and shall be based on the best modern
engineering practice. All equipment / systems located in air conditioned areas shall
also be designed and constructed to operate for short periods of plant operation
when air-conditioning equipment malfunctions (without loss of function, departure
from specifications requirements or damage) at the maximum ambient temperature
of 50°C and relative humidity of 95% RH).
Local control room shall accommodate the control and monitoring equipments of the
Flue gas desulphurization & SNCR for the Unit #1,2,3&4, 4x 250 MW CTPP plant.
The local control room shall house the operator stations, engineering station,
printers and control panels of the FGD, WWTP, SNCR and PAC systems and in
addition remote operating stations of FGD, WWTP, SNCR and PAC system PLCs
shall be located in the existing unit CCR.
10
Project Cost Estimate
10.1 PROJECT COST ESTIMATE
The project cost estimates for FGD, combustion modification, SNCR, ESP retrofit,
WWTP and PAC systems proposed have been worked out on the following basis:
Mechanical 60 60 60 60
Civil works 32 32 32 32
Equipment cost 99 99 99 99
Taxes & duties (Mechanical, Civil
18.81 18.81 18.81 18.81
works, Electrical and C&I)
Erection, Testing and
Commissioning (including tax & 9.41 9.41 9.41 9.41
duties)
Overheads &Contingency 7.95 7.95 7.95 7.95
Page :
80
Table 10.2 Project Cost Estimate –-SNCR [Rs in Crores]
Mechanical 50 50 50 50
Civil works 1 1 1 1
Equipment cost 53 53 53 53
Taxes & duties (Mechanical, Civil
10.07 10.07 10.07 10.07
works, Electrical and C&I)
Erection, Testing and
Commissioning (including tax & 5.04 5.04 5.04 5.04
duties)
Overheads &Contingency 4.26 4.26 4.26 4.26
Mechanical 25 25 25 25
Civil works 0 0 0 0
Description 4x250 MW
Contractor’s EPC scope shall include the submission of required design inputs/
drawings for execution of civil and electrical works.
The EPC Contractor will be assisted in formulating the concepts, systems, basic
and detailed engineering, procurement, interface engineering, construction
management services, Erection and testing management services, Inspection,
quality control, expediting and Project management by Engineering Consultants /
competent professionals.
FI interaction with various OEMs and experience on similar capacity FGD project,
the following project implementation schedule is arrived for the project.
The overall EPC project schedule for implementation of FGD work will be 24
months. Interfacing of Flue gas duct for FGD will be the major activity that
requires unit shutdown.
Project Schedule for SCR systems shall be 15 months.
Project schedule for PAC system, ESP retrofit & WWTP plant shall be 6
months.
The proposed project being a brown field project, construction facilities will have to
be developed, around the available infrastructure and the requirement to implement
the project within scheduled time frame.
Owner will have to carry out project preparatory works such as identification of
storage and fabrication yard, approach roads for the material gate, arranging of
construction power, construction water etc.
It is recommended that owner to arrange for the space for the FGD in phases
without affecting plant operation.
12
Conclusions
12.1 CONCLUSIONS
To restrict the SO2 emission levels below the stipulated value of 600 mg/Nm3,
wet lime stone based FGD with efficiency of around 69% is recommended.
The FI measured value of NOx emission is 615.29 mg/Nm 3. To restrict the NOx
emission levels below the stipulated value of 300 mg/Nm 3, Combustion control
methods along with Selective Non-Catalytic Reduction (SNCR) technology is
recommended.
Adequate space is available in the plant for accommodating wet limestone FGD
and SNCR system for all the 4 units.
In Unit 1,2,3 & 4 the PM level in flue gas is exceeding the MOEF&CC stipulated
limit, Hence, suitable abatement methods are to be implemented considering the
PM reduction due to WFGD.
Mercury level in Unit 1,2,3& 4 flue gas is 0.19 mg/Nm3. which is exceeding the
MOEF&CC stipulated limit by around 84.5%. PAC system is recommended to
control mercury to the stipulated limit.
The total Auxiliary power consumption for FGD, SNCR, PAC and WWTP
systems of each 250MW units is estimated as 2749 kW, which is about 1.1% of
gross unit power output.
The flue gas temperature at FGD outlet after installation of wet limestone FGD is
around 54.5°C.Hence, each unit is recommended to be provided with separate
RCC wet stack of minimum 100m height, with steel flue with suitable corrosion
and acid resistant lining. Hot flue gas during FGD bypass operation shall be
dispersed through the existing stack.
The design specific plant water consumption is within the MOEF&CC stipulated
limit. The FGD make up water requirement shall be around 56 m 3/hr, on
continuous basis. The make-up water shall be clarified water.
With the additional water requirement for FGD from the clarified water system,
the consumptive water requirement increases by 84 m³/h for each phase.The
specific water consumption for Phase 1 will be 3.38 m 3/MWh and for phase 2 will
be 3.53 m3/MWh, when including FGD water requirement. When considering the
actual historic plant water consumption of 3.18 m 3/MWh, the specific water
consumption including FGD requirement is around 3.35 m 3/MWh, which is within
MOEF&CC stipulation.
FGD waste water treatment plant (UF-RO based) is proposed to treat the FGD
waste water.
Control System:
Dedicated PLC based control system shall be provided for the FGD system and
separate dedicated PLC based control system shall be provided for the SNCR
system. These PLCs shall be interfaced with the existing plant DCS for
monitoring from CCR through softlink. Hardwiring is also envisaged with Plant
DCS for control & interlock signals with main plant. Spare I/O channels (to be
added if required in future) and spare soft link ports shall be utilized for these
softlink and hardwired interface.
Project Cost:
The estimated project cost for the installation of FGD, Combustion modification,
SNCR, PAC, ESP retrofit and WWTP plant for the 4x250 MW units is Rs.1093
Crores
The estimated total project cost for the installation of FGD is Rs.148.21 Crores
(0.59 Cr/MW), Combustion modification is Rs. 38.18 Crores (0.15 Cr/MW),
SNCR is Rs. 79.34 Crores (0.32 Cr/MW), PAC system is 5.09 Crores (0.02
Cr/MW), ESP retrofit is Rs.2.19 Cr (0.009 Cr/MW) for each 250 MW unit.
The common FGD waste water treatment plant for all the four units is estimated
to cost Rs.0.90 Cr (0.004 Cr/MW)
Project Schedule:
The EPC project completion time period implementation of FGD, Combustion
modification, SNCR, PAC system and ESP retrofit shall be around 24 months.
The project shall be executed in separate EPC package for each system.
13
Financial
Page :
90
13.1 FINANCIAL
13.2 General
The project cost estimates have been worked out on the following basis.
The landed cost per ton of limestone and Ammonia has been taken as Rs. 2500 and
Rs.49000 respectively.
The landed cost per ton of Powdered Activated Carbon is considered as Rs.45000.
Cost of various other items has been estimated based on prevailing market price.
GST has been considered as 18% wherever applicable ( i.e., supplies, civil
works and erection, testing and commissioning.
The following fixed and variable costs are considered along with appropriate
escalations.
a. Interest on Loan
b. Return on Equity
c. Depreciation
d. O&M Expenses
e. Interest on Working Capital-Loan
13.8 Assumptions
Depreciation for Plant & Machinery : Straight line method, As per CERC
norms.
Based on the above assumptions, fixed and variable cost is listed below:
a) Andritz Technologies
b) K C Cottrell India Pvt Ltd
c) GE-Alstom
d) China Datang Technologies & Engineering Co, Ltd
e) BHEL (licensee of MHPS, Japan)
f) Babcock Power Engineering
g) Thermax Limited (licensee of Marsulex Environmental Technologies Inc., USA)
h) Hitachi, Japan
i) Jiangnan Environmental Technology – China
j) Hamon Group
k) ISGEC
SCR/SNCR System
a) ISGEC
b) Andritz Technologies
c) K C Cottrell India Pvt Ltd
d) GE-Alstom
e) China Datang Technologies & Engineering Co, Ltd
f) ERC Chemtrol Pvt. Ltd.
g) Jiangnan Environmental Technology – China
h) Hammon group
Annexure-1
List of Inputs
Annexure - 1
List of
Inputs
The following key inputs received from XXXXXXX CTPP are used for preparing the
report:
FICHTNER
List of Exhibit
1 2 3 4
1. Unit 1 FGD Area
2. Unit 2 FGD Area
3. Unit 3 FGD Area
4. Unit 4 FGD Area
5. FGD ,SNCR
Auxiliaries
6. FGD- Waste
water treatment
plant(15mx15m)
7. Space for Wet
7 7 stack dia 12m each
(unit wise)
6
Consulting Engineers
(India) Private Limited
Chennai, Bangaluru
Exhibit No. 13A
FGD
makeup
FGD makeup
FGD makeup
FICHTNER
EXHIBIT No. 14
Note: Plant load at 600 MW, Unit 2 under shutdown- During measurement
EXHIBIT - 15 Schematic Diagram- Typical PAC injection
System