FinalReport - Bridge Project
FinalReport - Bridge Project
Engineering
Assignments 1, 2, 3, & 4
Group 3
TABLE OF CONTENTS
11
2. Assignment 2: Preliminary and Final Project Analysis for Live and Dead Loads
21
2
24
29
Recommendations
67
69
6. Appendices
296
4
5
The bridge design project consists of the planning and design for two proposals for a
prestressed concrete girder bridge and the second is a continuous, composite, steel girder
bridge. Both proposals are designed with the same site conditions. The elevation of the site and
the typical roadway section is shown in Figure 1.1. The total length of the proposed bridges is
350 feet which is divided between three spans. Both proposals contain five traffic lanes. The
bridges will be designed for the HL-93 loading which contains vehicle HS20 or Tandem and the
lane load.
The purpose of the first assignment is to develop preliminary bridge elevations, plans, and
dimensions for both proposals. First, the elevation of the bridge is checked to ensure there is
adequate area beneath the bridge for the safe passage of a design flood. Second, preliminary
6
span lengths, girder spacings, deck depths, and layouts are found and detailed using pertinent
AASHTO Articles. Finally, a comparison between the prestressed concrete girder bridge and the
In order to complete the goals described in the problem statement, this assignment meets the
following objectives:
1. Determine the required free area under the bridge superstructure using Talbot’s formula,
and compare this to the approximate available area beneath the bridge superstructure of
both bridge designs and suggest possible road elevation, abutment location, or pier location
revisions.
2. Estimate the dead load of the superstructure for the prestressed concrete girder design and
the steel girder design including a 2.5” asphalt wearing surface, concrete deck, parapet,
3. Submit scaled plan, elevation, and cross-section drawings for the prestressed concrete
girder and the steel girder superstructures. Preliminarily size members for drawings based
4. Provide a comparison of the two alternate structures. Based on this initial analysis, suggest
which superstructure material could be preferred for the project and why.
The 100-year extreme flood requires a cross-sectional area (Areq) below the bridge that is large
enough for the safe passage of floodwaters. The required cross-sectional area (Areq) is
Where ‘C = 0.307’ is a coefficient related to the character of the area drained, and ‘M = 400,000
With the provided bottom bed elevation of 1315.10 feet, finish elevation of 1340.08 feet, and
embankment slopes of 2H:1V, the available cross-sectional area (Aav) is 5331 square feet and
5626 square feet for the prestressed concrete girder bridge and steel girder bridge respectively.
See Appendix 1 for calculations. Since the available area is greater than the required area, the
provided bridge elevation is adequate for extreme flood passage beneath the bridge and is not
AASHTO specifications divide dead loads into DC1, DC2 and DW. The self-weight of concrete
deck, steel girders, and stay-in-place forms are included in DC1 . While any dead loads acting on
the bridge after the concrete cures, is defined as DC2. Finally, the wearing surface weight is
defined as DW.
The estimated exterior girder dead loads are around 2.13, 0.10 and 0.23 kips per foot per girder,
for DC1, DC2 and DW, respectively. See Appendix 1 for the calculations.
8
AASHTO specifications divide dead loads into DC1, DC2 and DW. The self-weight of concrete
deck, steel girders, and stay-in-place forms are included in DC1 . While any dead loads acting on
the bridge after the concrete cures, is defined as DC2. Finally, the wearing surface weight is
defined as DW.
The estimated exterior girder dead loads are around 1.72, 0.14 and 0.30 kips per foot per girder,
for DC1, DC2 and DW, respectively. See Appendix 1 for calculations.
.
Table 1.2 - Steel Girder Bridge Dead Load Summary
This section details the preliminary plans, elevations and cross-sections of the proposed
prestressed concrete and steel bridges. AASHTO Table 2.5.2.6.3-1 below shows the minimum
depths required for the different types of bridge superstructures. The bridges designed in this
The proposed bridge is a highway bridge with five traffic lanes. The total length of the proposed
bridge is 349’ divided between three spans with lengths of 109’, 131’, and 109’. The bridge
consists of three precast AASHTO Type V girders which are assumed to be simply supported
for non-composite action and continuously supported for composite action. The bridge
elevation is shown in Figure 1.2. The bridge will be designed for HL-93 loading which considers
The superstructure of these bridges consists of eight I-shaped precast prestressed concrete
girders, a concrete deck, and internal cast-in-place diaphragms. The internal cast-in-place
diaphragms are provided in order to ensure that any applied load will be distributed to all eight
girders. These internal cast-in-place diaphragms are spaced at equally with 3 per span.
The precast concrete girders are transversely spaced at 8’-2”. The total deck width is 63’-0”
which contains five 12’-0” wide traffic lanes in addition to two edge barriers with a width of 1’-6”,
AASHTO Type V is chosen as the bridge section for this proposal. The AASHTO Type V section
has a total depth of 63”, and a web thickness of 8”. The upper flange is 42” wide, and the
thickness varies from 5” to 12”. The lower flange is 28” wide and has a variable thickness from
11
8” to 18”. Finally, the concrete deck is assumed to be 8” thick. The calculations showing the
Appendix 6.
The proposed bridge is a highway bridge with five traffic lanes. The total length of the proposed
bridge is 349’ divided between three spans with lengths of 113’, 123’, and 113’. The bridge
consists of three spans of continuous steel composite plate girders. The bridge elevation is
shown in Figure 1.4. The bridge will be designed for HL-93 loading which considers the vehicle
The superstructure of this bridge consists of six built-up plate girders, a concrete deck, and
internal cross frames. Due to transportation concerns, field splices are proposed to divide the
total bridge length into five segments. The lengths of these segments are as follows: two
exterior segments of 79’-6”, one interior segment of 70’-0”, and two segments above the interior
supports of 60’-0”. Internal cross frames are provided in order to stabilize the plate girders
during construction, and they are spaced between 17’-9” and 19’-6”.
12
The steel plate girders are transversely spaced at 11’-2”. The total deck width is 63’-0” which
contains five 12’-0” wide traffic lanes in addition to two edge barriers with a width of 1’-6”, as
The total depth of the plate girders is 50” with a web depth of 48” and a web thickness of 0.5”.
The upper flange is 15” wide and 0.75” thick, while the lower flange is 25” wide and 1.25” thick.
Finally, the concrete deck is assumed to be 10” thick. The calculations showing the procedure
The objectives and results of the preceding discussion are summarized below.
1. The cross sectional area beneath the superstructures of both the prestressed
concrete girder bridge and the steel girder bridge were found to be adequate for the
passage of an extreme flood with no major revisions from the given site conditions
required.
2. The dead loads for the prestressed concrete girder bridge and steel girder bridge
were found based on assumptions of the girder sizes, deck thickness, wearing surface
thickness, and barrier sizes. The summaries of the findings are shown above in their
respective sections.
13
3. Drawings of the plans, elevations, and sections of the prestressed concrete girder
bridge and steel girder bridge including the topography with the required fill and
4. A comparison between the prestressed concrete girder bridge and steel girder bridge
is shown below.
To compare the two specific types of bridges, factors such as service life, cost, and load
capacity are essential to determine the best option. According to the study of Brandon Boatman
Comparing the two estimated dead loads, the steel girder bridge has a smaller dead load for
structural components and nonstructural attachments (DC1) which is equal to 1.72 kips per foot.
For the prestressed concrete girder bridge, this value is equal to 2.14 kips per foot.
Through class discussion and subsequent research, it was found that prestressed concrete
girder bridges in Nebraska tend to be the most economical and widely used design for highway
After the comparison between the two designs, the design team would recommend the
prestressed concrete girder bridge design because of the longer service life and the lower
2. Assignment 2: Preliminary and Final Project for Live and Dead Loads
The following design project report proposes two bridge design options (a continuous composite
prestressed concrete girder bridge and a continuous composite steel girder bridge) for a given
site elevation and roadway section. From the Assignment 1, the general layout and estimated
dead loads for both bridges were determined. These values were used for Assignment 2 and
Assignment 3.
For Assignment 2, both the Dead and Live Loads will be estimated for a three-span bridge with
total length of 349’ ft to determine the interior girder moment and shear envelopes for the
prestressed concrete and for the steel superstructures using the following load cases:
● HS20 truck girder moment envelope and girder shear envelope, including
impact.
including impact.
● HS20 design lane load girder moment envelope and girder shear
envelope with the lane loading strategically placed for continuous spans.
16
● Dead load girder moment envelope and girder shear envelope. This will
be preliminary until the final superstructure has been designed and the
2) Total, factored design girder moment envelope and girder shear envelope (for
STR I, SVC I, SVC II, SVC III combinations only). This will be preliminary until
the final superstructure has been designed and the exact dead load is
c) 1.25 DC + 1.5 DW + 1.75 (90% of two HS20 trucks + 90% Lane load full)
c) 1.0 DC + 1.0 DW + 1.0 (90% of two HS20 trucks + 90% Lane load full)
c) 1.0 DC + 1.0 DW + 1.3 (90% of two HS20 trucks + 90% Lane load full)
c) 1.0 DC + 1.0 DW + 0.8 (90% of two HS20 trucks + 90% Lane load full)
17
The objective is to tabulate and plot the interior girder moment envelopes and shear envelopes
for both prestressed concrete girder bridge and a steel girder bridge. To obtain the analysis
results for shear and moment envelopes, the following objectives are required for this
assignment.
● Influence lines for shear and moment at any point in the three continuous span
beam structure.
● HL 93 design load (HS20 Truck, design Tandem and lane load) are to be moved
across shear and moment IL´s in both directions with axle load placements at the
● The extreme force effects obtained at least at 1/10th span points are to be
forces.
● Shear and moment envelopes of dead load of structural components and dead
● Extreme effect envelopes for individual loads (HS20 truck, tandem, lane load and
dead loads) are to be combined using load combinations for Strength I, Service II
This project will be performed using previously estimated loads as well as the previously
determined locations for piers and abutments. First, a series of unfactored trucks loads and self
weight loads will be used to develop various moment and shear envelopes. Combining these
component envelopes, a single factored envelope will be developed for preliminary use until the
Assumptions:
● It will be assumed that the interior girder shear and moment distribution factor is
1.0, this distribution factor will be applied to both the negative and positive
Considerations:
● Trucks as being able to travel both from left to right and from right to left across
the superstructure.
Dead Loads: Three load cases are defined as DC1, DC2 and DW which presents dead loads.
These cases refers to the Dead Load of structural components and nonstructural attachments
(DC) and Dead Load of wearing surfaces and utilities (DW), where both are analyzed using
static load strategy, and they are loaded so that they occupy the three spans.
19
Assuming a normal weight concrete as 145 pcf for Fc<5 Ksi (Table 3.5.1.1 of AASHTO LFRD
2012) and the cross area according the previous drawings the three components of Dead Load
(permanent load acting on the noncomposite section, permanent load acting on the long-term
It was assumed that no loads provenient from earth, water are acting over the structure as dead
loads.
Moving Loads: Using the computer software SAP to calculate all internal forces, then using
Excel to formulate a worksheet and calculate the maximum/minimum values for Moment/Shear.
A uniform lane load of 0.64 kip/ft is distributed along the bridge in different cases to achieve the
Two moving load cases are defined as HS20-L and HS20-R which presents the design load
truck HS20 travelling to the right and to the left of the bridge. The image below represents the
Using the generalized excel sheet created, the shear and moment envelopes are calculated and
plotted for a three-span (109ft, 131ft and 109ft) continuous girders. The tabulated values of the
20
moment and shear envelopes are given in the tables below. The corresponding moment and
shear envelopes plots, as well as the calculations, are in Appendix 2. The influence lines plots
at 1/10th span points and the corresponding load positions are shown in Appendix.
Using the generalized excel sheet created, the shear and moment envelopes are calculated and
plotted for a three-span (109ft, 131ft and 109ft) continuous girders. The tabulated values of the
moment and shear envelopes are given in the tables below. The corresponding moment and
shear envelopes plots, as well as the calculations, are in Appendix 2. The influence lines plots
at 1/10th span points and the corresponding load positions are shown in Appendix.
The moment and shear envelopes were plotted for both structures (prestressed concrete and
steel bridges), as seen in Appendix 2, using the values for dead and live (moving) load.
Calculations were done with unfactored HS20 truck girder moment envelope and girder shear
envelope, including impact. Based on 90% of two HS20 trucks at a 50’ headway, the unfactored
moment and shear envelopes were calculated between points of dead load contraflexure. For
23
the girder moment and shear envelope was used unfactored HS20 design lane load. Finally it
were found the factored design girder moment and shear envelopes for STR I, SVC I, SVC II
It is important to notice that the maximum moment, maximum shear and minimum shear
are found for the prestressed concrete load combination (10.659,20 k-ft ; 494,10 k ; -494,0 k) as
shown on table 2.5A.2, and the minimum moment is found for the steel girder load combination
In this assignment, the reinforced concrete deck for both the prestressed concrete bridge and
steel girder bridge will be analyzed and designed using an optimized girder spacing. The final
thickness of the concrete deck for the prestressed concrete girder bridge is 8”, while the final
thickness of the concrete deck for the steel girder bridge is 10”. The concrete compressive
strength for both bridges is 4,000 psi ,and the steel reinforcement yield strength is 60,000 psi.
For Assignment 3, the objective is to propose the girders’ sizes and spacings as well as the
thickness and reinforcement for the overlaying deck for both the prestressed concrete girder
and the steel girder bridges. The reinforced concrete decks are designed for AASHTO HS20
loadings and detailing requirements. Finally, a refined size and shape of the girders for both
Using the bridge dimensions determined in Assignment 1 and preliminary analysis information
1. Determine the preliminary girder number and spacing that will result in the most efficient
prestressed concrete and steel superstructures. This will include consideration of the
25
influence girder spacing has on the magnitude of the AASHTO approximate girder
distribution factors, concrete deck thickness required, and volume of steel reinforcing.
2. Execute the concrete deck final design using AASHTO HS20 loading and provide scaled plan
3. Provide a refined size and shape estimate of the main concrete and steel members for the
The reinforced concrete deck for both the prestressed concrete bridge and steel girder bridge
will be analyzed using the method outlined in AASHTO Article 4.6.2.1 and designed using the
Traditional Method outlined in AASHTO Article 9.7.3. The dead and live load moment
envelopes are found using SAP2000, summed and graphed in Excel, and the final design was
The original prestressed concrete and steel girder designs called for 8 and 6 girders
respectively. The overhangs were originally sized with the intent to match the exterior moment
distribution factors with the interior moment distribution factors. However, it is an objective of
this assignment to optimize the girder spacing and deck thickness through consideration of
approximate girder distribution factors, concrete deck thickness, and steel reinforcement. The
procedure for both bridge designs was similar. It is important to note that all calculations are
approximate and are repeated with refined numbers for the final design calculations The
original design was compared to designs with one more and one less girder, but still spaced
26
evenly across the bridge width. The reinforced concrete deck thickness did not change as it
was above the minimum required value of 6.5” per AASHTO Table 2.5.2.6.3-1. The interior
moment distribution factor was calculated for the maximum positive interior condition and used
the constant values specified in AASHTO Table 4.6.2.2.1-2 for simplicity. The factored negative
moment includes the estimated dead loads specified later in this assignment and live loads from
AASHTO Appendix A4 and were combined with the Strength I load combination factors. Since
the negative moment typically requires the more reinforcement than the positive moment
because of the different reinforcement clear depths, it is only condition that is investigated. The
summaries for the findings of the girder spacing optimization studies are shown below for both
bridges. Hand calculations for the tables below are shown in Appendix 3.
Table 3.1 - Prestressed Concrete Girder Bridge - Girder Spacing Optimization Summary
There were very small differences between all prestressed concrete girder designs. Typically
the most efficient design would utilize the fewest number of girders, however the design team
was already directed to use a design with eight girders in feedback from Assignment 1. The
The steel girder spacing optimization study showed more significant differences. Due to the
large moments that are generated and to the subsequently large amounts of steel reinforcement
in the deck in the design with five girders, the design with six girders is selected for further
design.
The moment envelopes for the reinforced concrete deck for both bridges are created using the
previously estimated dead loads and HS20 truck configurations for the live loads. The
envelopes are calculated using SAP2000 and verified by hand calculation methods at various
locations. The sections below discuss the calculation of the moment envelopes in more detail.
Both the steel and prestressed deck is designed as a continuous reinforced concrete member
with a width of 1’ and subjected to the dead load cases of DC1, DC2, and DW and the live load
case of HS20. The DC1 load case is the weight of the structure before the concrete in the deck
cures and acts compositely with the girders. The load is applied to the deck as a uniform load
across the deck, and the deck is assumed to act continuously over the supports. The DC2 load
case is the additional weight of the structure that is added after the concrete in the deck cures,
and in this case is just the weight of barriers. The weight of the barriers is applied as a point
load at the edges of the deck. The DW load case is the weight of the wearing surface, 2.5” of
asphalt, and is applied as a uniform load in a similar manner as DC1. See Appendix 3 for
calculations. The dead loads applied to both bridges are shown below.
28
Table 3.3 - Prestressed Bridge Dead Loads Table 3.4 - Steel Bridge Dead
Loads
Envelopes were created for each of these load cases using SAP2000, and the results are
shown in Appendix 3.
The calculation of the of live load moment envelopes for the prestressed concrete girder bridge
and the steel girder bridge is a similar process with the only differences being the number of
girders and the thickness of the concrete deck. The live load moment envelopes were
calculated using SAP2000 with five variations of HS20 loadings in order to find the maximum
positive and negative moments experienced by the reinforced concrete bridge deck. The five
variations transversely move across the deck and include a single HS20 truck, two HS20 trucks
spaced at 4’ and at the spacing of the prestressed concrete girders or steel girders, and three
trucks spaced at 4’ and at the spacing of the prestressed concrete girder or steel girders. The 4’
spacing is intended to produce maximum negative moments over the supports, while the girder
spacing between trucks is intended to produce maximum positive moments in the center of the
spans. The five HS20 variations are also multiplied by multiple presence factors depending on
the number of trucks. It was found through design checks that up to three HS20 trucks would
produce the maximum load effects because of the influence lines and multiple presence factors,
29
so only the five HS20 load cases were created. For an example, the variation utilizing two
HS20 trucks spaced at 4’ on the prestressed concrete bridge is shown below. Other diagrams
With these five variations of HS20 loading, the total live load moment envelopes are found and
are multiplied by a dynamic allowance of 1.33. The live load moment envelope for the
prestressed concrete bridge is shown below. The calculations are shown in Appendix 3.
The reinforced concrete deck is designed with the Service I load combination for crack control
and the Strength I load combination for flexural strength utilizing the previously calculated load
cases. The reinforcement across the deck is sized for the single maximum negative and
positive moments experienced by the deck as recommended by AASHTO Article 4.6.2.1.1. The
design for both the prestressed concrete bridge and the steel girder is similar except that the
prestressed concrete bridge has an 8” thick concrete deck while the steel girder bridge has a
30
10” thick concrete deck due to the larger girder spacings. In order to convert the HS20 loading
into an equivalent 1’ strip, the applicable equations from AASHTO Table 4.3.2.1.3-1 were used.
The reinforcement was sized and spaced per detailing requirements from AASHTO Article 5.10.
For both bridges, calculations are shown in Appendix 3, and the final reinforcement designs are
shown in Appendix 6.
1. The girder spacings for both bridges were optimized by calculating the deck thickness,
negative moment, and the required negative moment reinforcement for several girder
spacings. There were minimal differences between the prestressed concrete girder
designs with the seven and eight girders, but the design with eight girders was
selected to proceed with design from feedback in Assignment 1. The steel girder
spacing optimization summary showed more significant differences. The design with
six girders was selected because it generated a more reasonable maximum negative
moment in the reinforced concrete deck than the design with five girders, and it
clearly had fewer girders than the design with seven girders for a more optimal
design.
2. The concrete deck was analyzed with the previous estimated dead loads and five variations
of the AASHTO HS20 loading and using SAP2000 to create the load case envelopes.
These load case envelopes were combined for the Strength I load combination in
order to find the maximum negative and positive moments experienced by the deck
31
and were combined for the Service I load combination to check the reinforcement
design for crack control. The final designs of the reinforcement are located with the
drawings in Appendix 6.
3. The prestressed concrete bridge utilizes (8) AASHTO Type V concrete girder lines in a
three span condition with spans of 109’, 131’, and 109’ respectively. The reinforced
concrete deck is 8”. At this point in the project, these preliminary sizes appear to be
adequate.
4. The steel girder bridge utilizes (6) steel plate girders in a three span condition with spans of
113’, 123’, and 113’, and plate girder depths of approximately 50”. The reinforced
concrete deck is 10”. At this point in the project, these preliminary sizes appear to be
adequate.
32
In this section of the design project, the final superstructure design for the prestressed concrete
girder bridge is shown. First, the preliminary deck and girder depth is checked to ensure that
there is adequate area beneath the superstructure for a design flood. The final moment and
shear girder distribution factors are calculated utilizing methods and assumptions from
Assignment 2, and with the final deck thickness and girder size, the final girder moment and
shear envelopes are recreated. With the moment envelopes, the final size and spacing of
interior girder reinforcement and prestressing strands can be calculated including the steel
reinforcement in the deck over the support to ensure continuous composite action. Finally, the
interior girder can be checked for its shear capacity and the #4 stirrups can be spaced as
required.
The first objective for this assignment is met by checking the cross sectional area beneath the
superstructure for a 100 year design flood to confirm the final design layout. The prestressed
interior girder moment distribution factors are recalculated with the final design, and the moment
and shear envelopes are reconstructed according to the provisions in the AASHTO 2012
specification for Strength I, Service I, and Service III. With these envelopes, a final design of a
prestressed concrete girder is calculated utilizing a Mathcad Worksheet and checked with hand
calculations. The concrete used for the design of the prestressed concrete girder has an initial
compressive strength of 6,000 pounds per square inch and a final compressive strength of
8,000 pounds per square inch. The concrete used for the design of the reinforced concrete
33
deck has a compressive strength of 4,000 pounds per square inch. The steel reinforcement
used in the deck is ASTM A615 Grade 60 steel bars with a yield strength of 60,000 pounds per
square inch. The prestressing tendons are 0.6ӯ Grade 270 low relaxation strands with an
In order to complete the goals described in the problem statement, this assignment meets the
following objectives:
1. Based on the final deck thickness and preliminary girder design of the superstructure, confirm
that the pier and abutment locations are adequate to pass the extreme flood calculated in
Assignment 1.
2. Determine the final moment and shear girder distribution factors, revise the deck and girder
dead loads, and reconstruct the girder moment and shear envelopes.
3. Compute the size and spacing of all interior girder reinforcement and prestressing strands
through the calculation of losses, stress limitations for service and strength limit states, and
4. Determine the amount of reinforcement required to transfer tensile forces through the deck
The force effect envelopes are calculated using AASHTO 2012 specifications. The final
prestressed girder design discussed below will loosely follow the procedure listed in AASHTO
34
Appendix A5. The final design of the prestressed girder was aided by the development of a
The final substructure elevation has not changed since the preliminary design, so the previous
calculation is adequate. However to summarize the previous findings, the 100-year extreme
flood requires a cross-sectional area (Areq) below the bridge that is large enough for the safe
passage of floodwaters. The required cross-sectional area (Areq) is calculated using Talbot’s
formula:
Where ‘C = 0.307’ is a coefficient related to the character of the area drained, and ‘M =
With the provided bottom bed elevation of 1315.10 feet, finish elevation of 1340.08 feet, and
embankment slopes of 2H:1V, the available cross-sectional area (Aav) is 5331 square feet. See
Appendix 1 for calculations. Since the available area is greater than the required area, the
provided bridge elevation is adequate for extreme flood passage beneath the bridge.
The final girder moment and shear envelopes are dependent on the final design of the bridge. If
the final design of the bridge calls for a thicker deck or a larger girder, the live load distribution
factors, the dead load, and the load effect envelopes must be recalculated with the higher dead
35
load. If the new load effect envelopes require further redesign, the process iterates again. The
The live load distribution factors are calculated for the moment and shear forces. The full written
calculations and hand calculations are shown in the appropriate appendix. The moment
distribution factors are calculated three times for different conditions: positive moment in the
exterior spans, positive moment in the interior spans, and negative moment over the support
using equations from AASHTO Table 4.6.2.2.2b-1. The longitudinal stiffness parameter is
The span length, deck thickness, girder spacing, girder number, and longitudinal stiffness
parameter are within the “Range of Applicability”, so the moment distribution factors for the
The final values for the three conditions are shown below.
The shear distribution factor is calculated as the maximum of the equations from AASHTO
Table 4.6.2.2.3a-1.
The live load moment envelopes found from the HL93 with the dynamic load allowance in
Assignment 2 are multiplied by the distribution factors corresponding to their location along the
beam span. The exterior span positive moments are multiplied by a distribution factor of (g =
0.707 lanes), while the interior span positive moments are multiplied by a distribution factor of (g
= 0.673 lanes). The support region negative moments are multiplied by (g = 0.689 lanes). The
support region is defined as the distance between points of contra-flexure under a uniform load
37
on all spans. The shear distribution factor used for all spans is (g = 0.826). The figure below
illustrates the locations where the load distribution factors were used for the bending moments
The final girder size, deck thickness, wearing surface, and estimate of the other structural
components and nonstructural attachments have not changed since Assignment 2, however a
DC1 is the weight of the structural components acting on the girder before the deck cures. The
load effects are calculated assuming that the girders are simply supported on the piers. DC2 is
the weight of the structural components and nonstructural attachments acting on the girder after
the deck cures, and the load effects are calculated assuming that the girders act continuously
over the entire span. DW is the weight of the wearing surface, and the load effects are
The shear and moment envelopes for the load combinations Strength I, Service I, and Service
III are calculated per AASHTO 2012 for use in the design of the prestressed concrete girder.
The shear and moment envelopes are the sum of the dead and live load effects multiplied by
the applicable load effect factor. The envelopes are calculated using Microsoft Excel, and the
Strength I envelopes are shown below for an example. The other envelopes are located in
Appendix 4A.
The design of prestressed concrete girders is a highly iterative process dependent on the shape
of the girder, placement and area of prestressing strands, and placement and area of mild
reinforcement. This process lends itself well to computer software design methods, and as a
result, the team created a Mathcad Worksheet to help with the iterative design calculations. The
design utilizes an AASHTO Type V Girder with both straight and harped 0.6ӯ Grade 270 low
relaxation tendons prestressed to a value of 75% of their maximum tensile strength. The
concrete has an initial compressive strength of 6,000 psi and a final compressive strength of
8,000 psi. Two sections of the final design of interior prestressed girder are shown below for
reference. The more detailed prestressed concrete girder plans and elevations are shown in
40
the drawings in Appendix 6. The prestressed concrete girders will be designed for the service
The estimation of prestress losses is a complex process that is dependent on several factors
including the mix design, curing procedure, concrete strength, and strand relaxation properties.
AASHTO Article 5.9.5 provides a reasonable method to approximate these losses. The total
prestress loss in a pretensioned member is a sum of the losses due to elastic shortening at the
time of transfer and the losses due to long-term shrinkage and creep of concrete, and relaxation
of the steel.
41
The aforementioned Mathcad Worksheet takes these losses into effect by first directly
calculating the prestress loss due to elastic shortening using AASHTO Equation C5.9.5.2.3a-1.
The time dependent losses are calculated using the method detailed in AASHTO Article 5.9.5.3
Approximate Estimate of Time-Dependent Losses since the prestressed girder used in this
relaxation properties, and exposed to average temperatures and conditions. Sample hand
Prestress loss due to creep of concrete, shrinkage of concrete, and relaxation of steel:
The section properties are calculated for the AASHTO Type V beam section with the selected
slab thickness and slab effective width to find the section modulus at the bottom of the girder,
the top of the girder, and the top of the deck. Since the behavior is elastic, the applied moments
are divided by the section moduli to calculate the stresses experienced by the prestressed
The maximum compressive and tensile stresses that can be experienced by the concrete in the
prestressed concrete girder at prestress transfer and at service limit states are given in
AASHTO Article 5.9.4, and the values used for this project are shown below. The girder self
weight and prestressing forces are used to find the temporary stresses before losses. Load
combination Service I is used to check the compressive stresses experienced by the concrete
after losses, and load combination Service III is used to check the tensile stresses because it
applies a load factor of 0.8 instead of 1.0 onto the live load effects. The term “before losses”
indicates that the long-term losses are not yet applied to reduce the prestressing force.
The maximum tensile stresses that can be experienced by the prestressing tendons is given by
AASHTO article 5.9.3, and the values used for this project are shown below.
The Mathcad Worksheet calculates the top and bottom stresses experienced by the prestressed
girder at every tenth location (and on both sides of supports) along the beam span and graphs
the results for the stresses at transfer before losses, at permanent loads after losses, and at
Service I and III load combinations. The stresses are then checked to ensure they are below
43
the appropriate limit. An example graph showing the stresses at transfer is shown below. More
Figure 4A.5 - Mathcad Output Graph - Transfer Stresses at Top and Bottom of Prestressed Concrete
Girder
Equation 5.7.3.2.2-1 shown below. The prestressed concrete girder designed in this project
compositely act with the girder to improve the flexural resistance of the member. For both the
109’ and 131’ girders, the depth of the compression block remains in the deck. The strength
The positive flexural capacity is going to change over the length of the member because the
draped strands move the center of gravity of the prestressing strands, and this effect is
The positive flexural capacity is compared to the maximum positive moment envelopes for load
The negative flexural resistance is going to be calculated assuming the additional steel in the
reinforced concrete deck will carry the tensile stresses, and this will be discussed in the next
section.
The reinforced concrete deck forces the non-continuous prestressed girders to act continuously
over the supports. This continuous action causes negative moments to develop over the
supports that is resisted by the Grade 60 steel bar reinforcement located in the deck. The
flexural capacity is calculated using the AASHTO Equation 5.7.3.2.2-1 shown above and is
checked for adequacy with the maximum negative moment envelope from the Strength I load
combination. The continuity steel reinforcement will replace the previously designed deck
reinforcement over the supports. The reinforcing steel is designed to meet minimum
45
plans are shown in Appendix 6. Hand calculations are shown in Appendix 4A.
4A.5.5. Design the Shear Reinforcement for the Interior Prestressed Girder
The shear resistance of the prestressed girder will follow the simplified procedure outlined
AASHTO Article 5.8.3.4.3. The total shear capacity of the section is the sum of the concrete
shear capacity, reinforcing steel shear capacity, and the prestressing shear capacity. The
prestressing shear capacity is equal to zero when the procedure in Article 5.8.3.4.3 is used as it
is considered in the concrete shear capacity equations. The concrete capacity is equal to the
Both strengths were calculated using Mathcad, and the capacities were graphed at every tenth
Figure 4A.7 - Mathcad Output Graph - Flexural-Shear and Web-Shear Cracking Strengths
47
The required shear capacity of the steel reinforcement is found as the difference between the
factored shear and the concrete capacity. The steel reinforcement shear capacity is calculated
Depending on whether the flexural-shear strength or the web-shear strength controls, the value
The strength reduction factor for shear design is equal to 0.9 per AASHTO Article 5.5.4.2.
The prestressed girder design will utilize #4 stirrups spaced as shown in the drawings in
Appendix 6. The design was checked to be in accordance of AASHTO Articles 5.8.2.5 and
reinforcement.
48
1. The cross sectional area beneath the superstructure was checked to confirm that it is
of a size to allow the passage of an extreme flood. The base elevation of 1315.10 and
the finish elevation of 1340.08 will provide enough cross sectional area. No changes
were needed.
2. The dead loads were unchanged from the previous assignments, however the
summary was provided. The moment and shear girder distribution factors were
recalculated based on the final design of the prestressed concrete girder and were
applied to the previously calculated HL93 loading with the dynamic allowance. Final
shear and moment envelopes were created in Excel for the Strength I, Service I, and
Service III load combinations for use in the design of the prestressed concrete girder.
3. The design of the prestressed concrete girder was aided by a Mathcad Worksheet,
and sample calculations were confirmed by hand. The final design for an interior
prestressed girder line utilized 3 AASHTO Type V girders. The two exterior beams are
both 109’ long, and the interior span is 131’. Both designs use straight and harped
pretensioned strands. The exterior girders use 24 straight strands, and 8 harped. The
interior girder uses 34 straight strands and 10 harped. The elevations and sections of
both girders are shown in Appendix 6. The girder designs pass allowable stress checks
for both at transfer before losses and at service limit states after losses. The girder
designs also exceed the required flexural capacity required by Strength I load
combination.
4. In order for the girders to act continuously over the supports, the steel reinforcement
in the deck is needed to transfer the tensile forces. The reinforcement in the deck for
49
continuity replaces the typical deck steel at those locations and is design as (14) #7 bars
spaced at 4” on center each face (28 total), parallel to the flow of traffic, and extending
for 35’ each side of the support. This design was found to be adequate for to resist the
maximum negative moment produced by the Strength I load combination and meets the
5. The design of the prestressed girder was aided by a Mathcad Worksheet and sample
calculations were confirmed by hand. The method used to calculate the shear capacity of the
girder is outlined in AASHTO Article 5.8.3.4.3. The final design utilizes #4 stirrups spaced as
required from 14” to 24” along the girder span. This design was found to be adequate to resist
the maximum shear found from the Strength I load combination and meets all detailing
In this section, the final design of the interior steel girders for the strength limit state in flexure is
detailed. This includes the recalculation of the moment envelopes using refined dead loads and
distribution factors for the live loads. The steel girder bridge consists of 6 steel plate girders of a
constant depth with a composite concrete deck spanning continuously over 3 spans of 113’,
123’, and 113’. The girders are braced by cross frames spaced at a maximum of 25’ to
discretely brace the top flange during construction and the bottom flange throughout the life of
the bridge. In order to aid in the constructability and transportation of the girders, the girders are
spliced into 5 members with a maximum length of 88’. The design of the interior girders is
The final design of the steel girder bridge is checked for adequacy in the event of an extreme
flood. The moment and shear envelopes are recalculated using refined dead loads and
distribution factors. The final design of the interior girders utilizes plate steel with a yield
strength of 50,000 pounds per square inch. The concrete for the deck has a compressive
strength of 4,000 pounds per square inch and is designed to compositely act with the steel
girders, through the use of shear studs, to increase the positive moment capacity of the
members. The steel girder has two different cross sections: the heavier cross section is used
over the supports, where the composite action of the deck is ignored, to resist the large negative
In order to complete the goals described in the problem statement, this assignment meets the
following objectives:
1. Based on the final deck thickness and preliminary girder design of the superstructure, confirm
that the pier and abutment locations are adequate to pass the extreme flood calculated in
Assignment 1.
2. Determine the final moment and shear girder distribution factors, revise the deck and girder
dead loads, and reconstruct the girder moment and shear envelopes.
3. Use the factored moment envelopes to determine the steel plate girder sizes and dimensions
for the strength limit state for both negative and positive flexure and locate the cross-frames.
4. Locate splices for the superstructure interior girders by limiting the girder length based on
The force effect envelopes are calculated using AASHTO 2012 specifications and follows a
similar process that was described in Assignment 4A. The final steel girder design discussed
below will loosely follow the flowcharts in AASHTO Appendix C6.4. The final design of the steel
girder was aided by the development of a Mathcad Worksheet that is shown with hand
calculations in Appendix 4B. The interior girder is only designed for flexure in constructability
The final substructure elevation has generally not changed since the preliminary design, so the
previous calculation is adequate. However to summarize the previous findings, the 100-year
extreme flood requires a cross-sectional area (Areq) below the bridge that is large enough for
the safe passage of floodwaters. The required cross-sectional area (Areq) is calculated using
Talbot’s formula:
Where ‘C = 0.307’ is a coefficient related to the character of the area drained, and ‘M =
With the provided bottom bed elevation of 1315.10 feet, finish elevation of 1340.08 feet, and
embankment slopes of 2H:1V, the available cross-sectional area (Aav) is 5626 square feet. See
Appendix 1 for calculations. Since the available area is greater than the required area, the
provided bridge elevation is adequate for extreme flood passage beneath the bridge.
The final girder moment and shear envelopes are dependent on the final design of the bridge. If
the final design of the bridge calls for a thicker deck or a larger girder, the live load distribution
factors, the dead load, and the load effect envelopes must be recalculated with the higher dead
load. If the new load effect envelopes require further redesign, the process iterates again. The
The live load distribution factors are calculated for the moment and shear forces. The full written
calculations and hand calculations are shown in the appropriate appendix. The moment
distribution factors are calculated three times for different conditions: positive moment in the
exterior spans, positive moment in the interior spans, and negative moment over the support
using equations from AASHTO Table 4.6.2.2.2b-1. The longitudinal stiffness parameter is
recalculated using the final design by finding the average stiffness of the two girder sections
The span length, deck thickness, girder spacing, girder number, and longitudinal stiffness
parameter are within the “Range of Applicability”, so the moment distribution factors for the
The final values for the three conditions are shown below.
The shear distribution factor is calculated as the maximum of the equations from AASHTO
Table 4.6.2.2.3a-1.
The live load moment envelopes found from the HL93 with the dynamic load allowance in
Assignment 2 are multiplied by the distribution factors corresponding to their location along the
beam span. The exterior span positive moments are multiplied by a distribution factor of (g =
0.759 lanes), while the interior span positive moments are multiplied by a distribution factor of (g
= 0.741 lanes). The support region negative moments are multiplied by (g = 0.750 lanes). The
support region is defined as the distance between points of contra-flexure under a uniform load
on all spans. The shear distribution factor used for all spans is (g = 1.029). The figure below
illustrates the locations where the load distribution factors were used for the bending moments
The final girder size, deck thickness, wearing surface, and estimate of the other structural
components and nonstructural attachments have not significantly changed since Assignment 2,
DC1 is the weight of the structural components acting on the girder before the deck cures. DC2
is the weight of the structural components and nonstructural attachments acting on the girder
after the deck cures. DW is the weight of the wearing surface. For all three load cases, the
The shear and moment envelopes for the load combinations Strength I and Service II are
calculated per AASHTO 2012 for use in the design of the steel girder. The load combinations
The shear and moment envelopes are the sum of the dead and live load effects multiplied by
the applicable load effect factor. The envelopes are calculated using Microsoft Excel, and the
Strength I envelopes are shown below for an example. The other envelopes are located in
Appendix 4B.
The flexural design of the interior steel girder is accordance with AASHTO Article 6.10 and
utilizes the previously calculated shear and moment envelopes for both Strength I and Service II
load combinations. The flexural design is limited to the constructability and strength limit states
per class requirements. The interior steel girder is not designed for shear. The iterative design
calculations were aided by the creation of a Mathcad Worksheet which was confirmed by the
hand calculations in Appendix 4B. The Mathcad Worksheet allowed for quick design iterations
to find plate girder sizes that would produce the required capacity.
The two interior plate girder sections meet the proportional limits outlined in AASHTO Article
6.10.2, and the cross sections and their usage locations are shown below. The proportional
58
limits also helped to preliminarily size the plate girder web and flanges. Due to the large
negative moments and lack of composite action over the supports, the plates for the girder
sections over the supports are increased in size to increase the moment capacity.
4B.5.3.2. constructability
The interior plate girder was designed to provide adequate strength for construction loads using
factors defined in AASHTO 3.4.2. The girder was checked using equations from AASHTO
6.10.3.2 as a noncomposite section to ensure that stresses in the steel girders did not exceed
the compression or tension limits for flexure provided below along the length of the girders
59
The stresses in the flanges are found by dividing the moments induced by the construction load
combination by the appropriate non composite section modulus. All three compressive stress
limits are calculated and plotted along the length of the beam to check for adequacy and is
shown below. A similar plot is created for the tensile stress limits and is shown in Appendix 4B
The interior steel girder is designed to resist the moments induced by the Strength I load
noncomposite section at the supports to resist negative flexure. AASHTO Appendix A6 is not
The steel girder as a composite section in positive flexure is designed using the equations
outlined in AASHTO Article 6.10.7.1 because the cross section meets the requirements to be
The depth of the plastic neutral axis is found to be in the deck, therefore the web of the steel
To be adequate for positive flexure, the section must satisfy AASHTO Equation 6.10.7.1.1-1:
With the nominal moment capacity found using equations from AASHTO Article 6.10.7.1.2:
62
And limited by AASHTO Equation 6.10.7.1.2-3 when the girders are continuous:
The plastic moment capacity is found using the applicable equations from AASHTO Table D6.1-
1, and the yield moment capacity is found as the minimum applied moment required to force
either the top or bottom flange of the composite steel section to yield. The process to calculate
The final moment capacity is compared to the positive moment produced by the Strength I load
The noncomposite sections in negative flexure for the steel girder over the supports are
designed utilizing the equations from AASHTO Article 6.10.8. The compressive flange is
discretely braced at a maximum of 24.5’ from cross frames while the tension flange is
To be adequate for negative flexure, the discretely braced compression flange must satisfy
To be adequate for negative flexure, the continuously braced tension flange must satisfy
The nominal flexural resistance of the compression flange is found using the equations from
AASHTO Article 6.10.8.2. The equations utilize slenderness ratios to check for flange local
buckling and utilize beam unbraced limits to check for lateral torsional buckling of the cross
section. The minimum of the local buckling and lateral torsional buckling capacities is the
Since the tension flange is continuously braced, the nominal flexural resistance is the yield
strength of the tension flange multiplied by the hybrid factor and applicable resistance factor
The compressive or tensile flange stress in both flanges is calculated as the summation of the
factored moments divided by their applicable section modulus. The precomposite dead load
moment is divided by a noncomposite section modulus, the post composite dead load moment
is divided by a long term composite section modulus considering a modular ratio of “3n”, and the
live load moment is divided by a short term composite section modulus considering the typical
It is important to note that AASHTO Appendix A6 was not utilized for this design, so the section
was not required to be checked for compactness over the supports. However to meet the
requirements of the class project, the noncomposite cross section was checked for
compactness using AASHTO 6.10.6.2.3, and the web was found to be nonslender.
The Mathcad Worksheet and the sample hand calculations are shown in Appendix 4B.
1. The cross sectional area beneath the superstructure was checked to confirm that it is
of a size to allow the passage of an extreme flood. The base elevation of 1315.10 and
the finish elevation of 1340.08 will provide enough cross sectional area. No changes
were needed.
2. The dead loads were unchanged from the previous assignments, however the
summary was provided. The moment and shear girder distribution factors were
recalculated based on the final design of the steel girder and were applied to the
previously calculated HL93 loading with the dynamic allowance. Final shear and
65
moment envelopes were created in Excel for the Strength I and Service II load
3. The design of the steel girder was aided by a Mathcad Worksheet, and sample
calculations were confirmed by hand. The final design for an interior steel girder line
utilized five plate girder sections spliced together with two different plate girder cross
sections. The detailed plate girder dimensions, lengths, and section locations are shown
in the drawings in Appendix 6. See Figures 4B.4 and 4B.5 for a summary located in this
section. The steel plate girder cross section utilized over the support was designed to
neglect the composite action from the deck and to fully resist the negative moment. The
height and thickness of the plates used for the web for both cross sections is the same
to aid in the constructability of the splices. The cross frames have been located at a
maximum spacing of 25’ and at the supports. The plan view of the steel girder bridge in
4. The splices for the steel girders have been located with the intent to limit lengths
based on transportation requirements and to allow for a heavier steel plate girder cross
section to be spliced over the supports. The heavier cross sections extend for 25’ past
5. Both steel girder cross sections have been checked for compactness for their
respective conditions. It was found that the composite midspan cross section in positive
flexure is compact per AASHTO Article 6.10.6.2.2, and the noncomposite support cross
section in negative flexure has a noncompact web per AASHTO Article 6.10.6.2.3.
66
Recommendations
The final aspect of this project compares the two bridge superstructure design options and
makes a final recommendation. Both bridges have the same overall span length, but have
different interior span lengths, numbers of girders, and, clearly, different superstructure designs.
The comparison includes quantity and cost estimates and an overall option comparison
between the prestressed concrete girder design and the steel girder design. With the steel
girder design being simplistic due to time constraints, it is difficult to make an accurate
The goal of Assignment 5 is to estimate the costs for the superstructures for both bridge designs
using the given costs from the assignment sheet. The final cost estimates, in conjunction with
other design criteria, is to be used to compare the designs and make a final recommendation on
In order to complete the goals described in the problem statement, this assignment meets the
following objectives:
1. Present quantity and cost estimates for the superstructures of both bridge designs using the
provided unit costs. Exclude the costs of the substructure for the preliminary cost estimate.
2. Compare the the two bridge designs using the quantity and cost estimates and other design
criteria.
67
3. Make a recommendation for the final bridge design to be used at the described location.
The estimated quantities and costs are tabulated using Microsoft Excel. The unit costs are
provided in the given assignment requirements. The supporting substructure is excluded from
the cost estimates, however, an estimated weight is calculated to be used in the comparison
between the bridge designs. It can be reasonably assumed that a higher estimated weight will
5.5.1. Quantity and Cost Estimate of the Prestressed Concrete Girder Bridge
The quantity and cost estimate for the prestressed concrete girder bridge superstructure is
The quantity and cost estimate for the steel girder bridge superstructure is shown in the table
below. It is important to note that the steel girders have only been designed for constructability
and the strength limit state in flexure and may not accurately reflect the final steel girder bridge
design.
69
Using the previously calculated quantities, a total weight for both superstructures can be
calculated and compared. The table below shows the estimated weights of both
superstructures.
70
1. The estimated costs of the superstructures for the prestressed concrete girder bridge and
steel girder bridge were calculated using the given unit costs. The prestressed concrete
girder bridge superstructure has an estimated cost of $85 per square foot while the steel
girder bridge has a similar cost of $87 per square foot of bridge surface area. The overall
span length and bridge width are equal for both bridge designs.
2. Some important things to note about the bridge designs before a comparison between the
using seven girders would likely be more efficient than a design using eight
could reduce the cost and weight of the prestressed concrete bridge by a
significant amount.
b. The steel girder design is not fully complete. This could increase the cost and
In comparing the current cost and weight estimates of the two bridge designs, the
prestressed concrete girder bridge has a slightly lower estimated cost per square foot of
superstructure even without the likely reduction in cost from using fewer girders. But due to
the larger weight of the prestressed concrete superstructure, it can be speculated that the
overall cost of the structure is slightly lower using the steel girder bridge design.
steel girder bridge would likely have the lowest overall initial cost due to the 40% reduction
in weight since the costs of the superstructures are very similar. The reduction in weight
Both bridge designs have the same overall span lengths, finish elevation, number of spans,
and bridge width, so there is minimal difference in cost or performance from the overall
bridge conditions.
In looking at ease of maintenance, concrete structures are typically easier and less
expensive to maintain over the lifespan of the bridge as steel structures require
maintenance painting.
3. In consideration of the previous discussion, the team would recommend the prestressed
concrete girder bridge design due to the slightly lower estimated superstructure cost per
square foot and the lower costs associated with maintenance over the lifespan of the bridge.
Additionally, it is speculated that with the previously discussed redesign of the prestressed
concrete girder bridge and a more complete design of the steel girder bridge, the
72
prestressed concrete girder bridge design would become the significantly lower cost design
option.
73
6. Appendices
- Because of the girder symmetry about point (D), Cy and Ey influence line values are the
same.
- The different point’s deflections will be calculated for the half of the girder only.
- Supports (C) and (E) will be removed to evaluate the force method equations.
1
- Using the previous figures gives the following equations
∗ ∗ 0.0 → 1
∗ ∗ 0.0 → 2
. ∗ ∗ .
.
∗ ∗
. ∗ ∗
2 2 ∗ 349 ∗ 236 236 113
∗ ∗
.
.
. .
∗ ∗
679257.1385
∗ ∗ → 3
587002.0282 587002.0282
. .
∗ ∗ 0.0 → 5
. . .
∗ ∗ ∗ 0.0
. . ∗
. .
∗ ∗ 0.0
.
679257.1385
∗ ∗ → 6
199009.3279 587002.0282
2
1.2. Calculating deflections at (C) due to load at (X):
∗ ∗ . .
2 ∗ 349 ∗ 174.5 174.5 113 .
∗ ∗
∗ ∗ . .
2 ∗ 349 ∗ 292.5 292.5 113 .
∗ ∗
.
.
.
.
. . . ∗ .
. @ ∗ ∗
. . .
. @ 0.708 /
. . . ∗ .
. @ ∗ ∗
. . .
3
. @ 0.584 /
. . . ∗ .
. @ ∗ ∗
. . .
. @ 0.137 /
. @ 0.137 /
. . . ∗ .
. @ ∗ ∗
. . .
. @ 0.584 /
. . . ∗ .
. @ ∗ ∗
. . .
. @ 0.708 /
∗ ∗
4
. . ∗ . ∗
. @ 0.404 /
. . ∗ . ∗
. @ 0.084 /
. . ∗ . ∗
. @ 0.025 /
1.0 0.0
1.0
0.0
5
Example Calculations
. @ 0.404 /
. @ 0.084 /
. @ 0.025 /
56.5 ∗ 56.5 x
∗ 56.5 0.0
56.5 ∗
Example Calculations
6
. @ 56.5 ∗ 0.084 ∗ 56.5 4.746 /
1.0 0.0
1.0
0.0
Example Calculations
7
. @ 0.084 0.584 0.50 /
∗ 174.5 ∗ 61.5
Example Calculations
8
Deflections/EI Joint Reactions Influence Lines Influence Lines Areas
Point Loc.
fC fE Cy Ey AY VB MB VD MD Cy VB MB VD MD
A=1.0 0 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.1 11.3 -84024.97 -66408.75 0.15 -0.04 0.87 -0.13 4.21 0.03 -1.06 0.88 -0.71 23.81 0.17 -6.00
1.2 22.6 -167074.23 -132350.31 0.31 -0.07 0.75 -0.25 8.51 0.06 -2.06 2.61 -2.12 71.91 0.49 -17.64
1.3 33.9 -248172.06 -197357.50 0.45 -0.10 0.63 -0.37 12.99 0.08 -2.93 4.28 -3.50 121.49 0.78 -28.19
1.4 45.2 -326342.76 -260963.14 0.59 -0.12 0.51 -0.49 17.72 0.10 -3.61 5.86 -4.84 173.52 1.02 -36.92
B=1.5 56.5 -400610.61 -322700.04 0.71 -0.14 0.40 -0.60 22.81 0.11 -4.02 7.31 -6.12 229.01 1.19 -43.11
B'=1.5001 56.501 -400616.98 -322705.41 0.71 -0.14 0.40 0.40 22.81 0.11 -4.02 0.00 0.00 0.02 0.00 0.00
1.6 67.8 -469999.89 -382101.02 0.81 -0.14 0.30 0.30 17.03 0.11 -4.12 8.59 3.98 225.05 1.28 -46.01
1.7 79.1 -533534.90 -438698.89 0.90 -0.13 0.21 0.21 11.77 0.11 -3.83 9.67 2.88 162.70 1.25 -44.92
1.8 90.4 -590239.91 -492026.47 0.96 -0.10 0.13 0.13 7.12 0.09 -3.09 10.50 1.89 106.73 1.08 -39.10
1.9 101.7 -639139.23 -541616.58 0.99 -0.06 0.06 0.06 3.17 0.05 -1.83 11.04 1.03 58.13 0.77 -27.83
C=2.0 113 -679257.14 -587002.03 1.00 0.00 0.00 0.00 0.00 0.00 0.00 11.27 0.32 17.90 0.29 -10.37
2.1 125.3 -712112.20 -631077.93 0.97 0.09 -0.04 -0.04 -2.50 -0.07 2.72 12.11 -0.27 -15.35 -0.46 16.71
2.2 137.6 -734009.32 -669016.00 0.91 0.20 -0.07 -0.07 -4.09 -0.17 6.20 11.54 -0.72 -40.52 -1.48 54.83
2.3 149.9 -745551.01 -700213.74 0.82 0.33 -0.09 -0.09 -4.92 -0.27 10.44 10.60 -0.98 -55.39 -2.68 102.32
2.4 162.2 -747339.78 -724068.63 0.71 0.45 -0.09 -0.09 -5.10 -0.38 15.45 9.37 -1.09 -61.57 -4.02 159.20
D = 2.5 174.5 -739978.15 -739978.15 0.58 0.58 -0.08 -0.08 -4.77 -0.50 21.21 7.94 -1.07 -60.67 -5.43 225.47
1.9. Influence lines full calculations using Excel:
9
D'=2.5001 174.501 -739977.19 -739979.10 0.58 0.58 -0.08 -0.08 -4.77 0.50 21.21 0.00 0.00 0.00 0.00 0.02
2.6 186.8 -724068.63 -747339.78 0.45 0.71 -0.07 -0.07 -4.06 0.38 15.45 6.39 -0.96 -54.26 5.43 225.45
2.7 199.1 -700213.74 -745551.01 0.33 0.82 -0.05 -0.05 -3.09 0.27 10.44 4.80 -0.78 -43.98 4.02 159.20
2.8 211.4 -669016.00 -734009.32 0.20 0.91 -0.04 -0.04 -2.01 0.17 6.20 3.24 -0.56 -31.40 2.68 102.32
2.9 223.7 -631077.93 -712112.20 0.09 0.97 -0.02 -0.02 -0.94 0.07 2.72 1.80 -0.32 -18.12 1.48 54.83
E=3.0 236 -587002.03 -679257.14 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.56 -0.10 -5.76 0.46 16.71
3.1 247.3 -541616.58 -639139.23 -0.06 0.99 0.01 0.01 0.65 -0.05 -1.83 -0.35 0.06 3.65 -0.29 -10.37
3.2 258.6 -492026.47 -590239.91 -0.10 0.96 0.02 0.02 1.09 -0.09 -3.09 -0.94 0.17 9.81 -0.77 -27.83
3.3 269.9 -438698.89 -533534.90 -0.13 0.90 0.02 0.02 1.35 -0.11 -3.83 -1.33 0.24 13.78 -1.08 -39.10
3.4 281.2 -382101.02 -469999.89 -0.14 0.81 0.03 0.03 1.45 -0.11 -4.12 -1.53 0.28 15.83 -1.25 -44.92
F=3.5 292.5 -322700.04 -400610.61 -0.14 0.71 0.03 0.03 1.42 -0.11 -4.02 -1.56 0.29 16.22 -1.28 -46.02
3.6 303.8 -260963.14 -326342.76 -0.12 0.59 0.02 0.02 1.27 -0.10 -3.61 -1.46 0.27 15.19 -1.19 -43.11
3.7 315.1 -197357.50 -248172.06 -0.10 0.45 0.02 0.02 1.03 -0.08 -2.93 -1.25 0.23 13.01 -1.02 -36.92
3.8 326.4 -132350.31 -167074.23 -0.07 0.31 0.01 0.01 0.73 -0.06 -2.06 -0.96 0.18 9.94 -0.78 -28.19
3.9 337.7 -66408.75 -84024.97 -0.04 0.15 0.01 0.01 0.37 -0.03 -1.06 -0.60 0.11 6.22 -0.49 -17.64
G=4.0 349 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.20 0.04 2.12 -0.17 -6.00
Influence Line (+Ve) Area A(+) = 140.35 11.97 1296.03 22.39 1117.07
Influence Line (-Ve) Area A(-) = -10.19 -24.13 -387.03 -22.39 -600.20
Influence Line total Area A total = 130.16 -12.16 909.00 0.00 516.87
Reaction (Cy) Influence Line
1.00
0.80
0.60
0.40
0.20
0.00
0 30 60 90 120 150 180 210 240 270 300 330 360
-0.20
0.80
0.60
0.40
0.20
0.00
0 30 60 90 120 150 180 210 240 270 300 330 360
-0.20
10
Shear (VB) Influence Line
0.60
0.40
0.20
0.00
0 30 60 90 120 150 180 210 240 270 300 330 360
-0.20
-0.40
-0.60
-0.80
20.00
16.00
12.00
8.00
4.00
0.00
0 30 60 90 120 150 180 210 240 270 300 330 360
-4.00
-8.00
11
Shear (VD) Influence Line
0.60
0.40
0.20
0.00
0 30 60 90 120 150 180 210 240 270 300 330 360
-0.20
-0.40
-0.60
20.00
16.00
12.00
8.00
4.00
0.00
0 30 60 90 120 150 180 210 240 270 300 330 360
-4.00
-8.00
12
2. Hand calculations Reaction, Moment and Shear Envelops:
- Dead load reaction Cy, moments and shear at points (B and D) are manually calculated.
- Influence lines total areas, calculated previously in excel, are used for dead loads.
Reaction Cy
13
Point (D) Shear and Moments
- For live loads maximum positive reaction (Cy), the influence line positive area is used with
the lane load and the HS-20 is positioned so that it produces the highest effect as follows:
- For live loads maximum negative reaction (Cy), the influence line negative area is used with
the lane load and the HS-20 is positioned so that it produces the highest effect as follows:
14
0.64 ∗ I. L. negative area 1.33 ∗ 32 ∗ y y 8∗y
2.3. Live Loads Maximum and Minimum Moment and Shear at point (B):
- For live loads maximum positive Moment (MB), the influence line positive area is used with
the lane load and the HS-20 is positioned so that it produces the highest effect as follows:
- For live loads maximum negative Moment (MB), the influence line negative area is used
with the lane load and the HS-20 is positioned so that it produces the highest effect as
follows:
15
- For live loads maximum positive shear (VB), the influence line positive area is used with the
lane load and the HS-20 is positioned so that it produces the highest effect as follows:
- For live loads maximum negative shear (VB), the influence line negative area is used with
the lane load and the HS-20 is positioned so that it produces the highest effect as follows:
2.4. Live Loads Maximum and Minimum Moment and Shear at point (D):
- For live loads maximum positive Moment (MD), the influence line positive area is used with
the lane load and the HS-20 is positioned so that it produces the highest effect as follows:
16
0.64 ∗ I. L. positive area 1.33 ∗ 32 ∗ y y 8∗y
- For live loads maximum negative Moment (MD), the influence line negative area is used
with the lane load and the HS-20 is positioned so that it produces the highest effect as
follows:
- For live loads maximum positive shear (VD), the influence line positive area is used with the
lane load and the HS-20 is positioned so that it produces the highest effect as follows:
17
- For live loads maximum negative shear (VD), the influence line negative area is used with
the lane load and the HS-20 is positioned so that it produces the highest effect as follows:
The calculated reactions, shear forces and bending moments are tabulated using Excel, and
the required load combinations (STR I, SVC I, SVC II and SCV III) are calculates in the next
table
LIVE (IM) 182.90 -19.10 40.80 -67.50 2657.00 -715.90 53.60 -53.60 2375.60 -762.00
STR I 673.26 319.76 104.39 -85.14 7115.58 1213.00 93.80 -93.80 5559.35 68.55
SVC I 458.94 256.94 66.58 -41.72 4584.20 1211.30 53.60 -53.60 3471.40 333.80
SVC II 513.81 251.21 78.82 -61.97 5381.30 996.53 69.68 -69.68 4184.08 105.20
SVC III 422.36 260.76 58.42 -28.22 4052.80 1354.48 42.88 -42.88 2996.28 486.20
18
3. Analysis cases:
A 2-D frame element analysis using SAP program generated for both bridges in order to consider
as much design sections as possible, and to reduce time consumption. In these analyses, dead loads
(DC1, DC2 and DW) and the design load are computed using static load analysis while truck loads
A description of different load and analysis cases defined in the analysis program is stated
below.
Three load cases are defined as DC1, DC2 and DW which presents dead loads. These
cases are analyzed using static load strategy, and they are loaded so that they occupy the
Two moving load cases are defined as HS20-L and HS20-R which presents the design
load truck HS20 travelling to the right and to the left of the bridge. Both of these cases are
19
HS20 Travelling
to the right of the
bridge (HS20-R)
HS20 Travelling
to the left of the
bridge (HS20-L)
Two moving load cases are defined as 2-HS20-L and 2-HS20-R which presents the two
design load truck HS20 travelling to the right and to the left of the bridge. Both of these
20
3.1.4. Tandem moving load:
One moving load cases are defined as TML which presents the tandem design load
Four static analysis cases are defined to model lane load critical positions. The cases are
- LL-SPAN(2) case of loading produces the highest positive bending moments along SPAN-2
- LL-SPAN(1+3) case of loading produces the highest positive bending moments along
SPAN-1 and SPAN-3, the highest joint vertical reactions Cy and Gy and the highest shear
21
- LL-SPAN(1+2) case of loading produces the highest negative bending moments, vertical
- LL-SPAN(2+3) case of loading produces the highest negative bending moments, vertical
22
3.1.6. Load cases summary:
Four static analysis cases are defined to model lane load critical positions. The cases are
HS20-R Moving Load HS20 truck moving to the right of the bridge
HS20-L Moving Load HS20 truck moving to the left of the bridge
2-HS20-R Moving Load Two HS20 truck moving to the right of the bridge
2-HS20-L Moving Load Two HS20 truck moving to the left of the bridge
23
4. Steel Bridge analysis cases results, internal forces envelopes and load combinations:
SAP structural analysis results are exported to excel so that moment and shear diagrams will be
clearer.
The tabulated values shows positive and negative extreme shear and bending moments at
each section. The figure plotted for the HS20 shear and moments multiplied by
(1+IM=1.33).
800
Moment (kip-ft)
400
0
0 35 70 105 140 175 210 245 280 315 350
-400
-800
-1030.90 -1030.90
-1200
Span Distances (ft)
24
Shear Envelopes (HS20) - kip
100
90.90 89.97 85.89
75
50
25
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-25
-50
-75
-85.89 -89.97 -90.90
-100
Span Distances (ft)
Unfactored Shear and Moments (HS20) Shear and Moments (HS20) * (1+IM=1.33)
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 6.29 0.00 -64.58 0.00 8.37 0.00 -85.89 0.00
1.1 11.3 6.29 629.50 -55.68 -71.13 8.37 837.24 -74.05 -94.61
1.2 22.6 11.04 1061.90 -46.98 -142.21 14.68 1412.33 -62.48 -189.14
1.3 33.9 19.40 1311.76 -38.59 -213.29 25.80 1744.64 -51.33 -283.68
1.4 45.2 28.00 1417.83 -30.63 -284.37 37.24 1885.71 -40.74 -378.22
B=1.5 56.5 36.25 1387.09 -23.20 -355.46 48.22 1844.83 -30.86 -472.76
1.6 67.8 44.04 1241.20 -16.42 -426.54 58.57 1650.80 -21.84 -567.29
1.7 79.1 51.25 973.39 -10.40 -497.62 68.17 1294.60 -13.83 -661.83
1.8 90.4 57.78 614.67 -5.40 -568.70 76.85 817.51 -7.18 -756.37
1.9 101.7 63.52 208.97 -1.80 -639.78 84.48 277.93 -2.39 -850.90
C=2.0 113 68.34 201.87 -1.79 -775.12 90.90 268.49 -2.38 -1030.90
C'=2.0 113.0001 7.94 201.87 -67.64 -775.12 10.56 268.49 -89.97 -1030.90
2.1 125.3 7.94 258.12 -61.42 -677.36 10.56 343.29 -81.68 -900.89
2.2 137.6 7.94 678.39 -54.20 -579.68 10.56 902.26 -72.09 -770.97
2.3 149.9 14.00 1009.12 -46.31 -481.99 18.62 1342.13 -61.59 -641.05
2.4 162.2 21.58 1212.09 -38.04 -384.31 28.70 1612.08 -50.59 -511.13
D = 2.5 174.5 29.69 1269.11 -29.69 -286.62 39.49 1687.92 -39.49 -381.21
2.6 186.8 38.04 1212.09 -21.58 -384.31 50.59 1612.08 -28.70 -511.13
2.7 199.1 46.31 1009.12 -14.00 -481.99 61.59 1342.13 -18.62 -641.05
2.8 211.4 54.20 678.39 -7.94 -579.68 72.09 902.26 -10.56 -770.97
2.9 223.7 61.42 258.12 -7.94 -677.36 81.68 343.29 -10.56 -900.89
E=3.0 236 67.64 201.87 -7.94 -775.12 89.97 268.49 -10.56 -1030.90
E'=3.0 236.0001 1.79 201.87 -68.34 -775.12 2.38 268.49 -90.90 -1030.90
3.1 247.3 1.80 208.97 -63.52 -639.78 2.39 277.93 -84.48 -850.90
3.2 258.6 5.40 614.67 -57.78 -568.70 7.18 817.51 -76.85 -756.37
3.3 269.9 10.40 973.39 -51.25 -497.62 13.83 1294.60 -68.17 -661.83
3.4 281.2 16.42 1241.20 -44.04 -426.54 21.84 1650.80 -58.57 -567.29
F=3.5 292.5 23.20 1387.09 -36.25 -355.46 30.86 1844.83 -48.22 -472.76
3.6 303.8 30.63 1417.83 -28.00 -284.37 40.74 1885.71 -37.24 -378.22
3.7 315.1 38.59 1311.76 -19.40 -213.29 51.33 1744.64 -25.80 -283.68
3.8 326.4 46.98 1061.90 -11.04 -142.21 62.48 1412.33 -14.68 -189.14
3.9 337.7 55.68 629.50 -6.29 -71.13 74.05 837.24 -8.37 -94.61
G=4.0 349 64.58 0.00 -6.29 0.00 85.89 0.00 -8.37 0.00
25
4.1.2. Truck moving load (2HS20):
The tabulated values shows positive and negative extreme shear forces and bending
moments at each section. The figure plotted for the 2-HS20 spaced at 50’-0” headway,
400
0
0 35 70 105 140 175 210 245 280 315 350
-400
-800
-1200
-1600
-1714.57 -1714.57
-2000
Span Distances (ft)
20
0
-20 0 35 70 105 140 175 210 245 280 315 350
-40
-60
-80
-90.40
-100 -103.66 -106.03
-120
Span Distances (ft)
26
Unfactored Shear and Moments (2-HS20) Shear and Moments (2-HS20) * (1.33) * (0.90)
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 7.06 0.00 -75.52 0.00 8.45 0.00 -90.40 0.00
1.1 11.3 7.06 695.39 -61.50 -79.79 8.45 832.39 -73.62 -95.51
1.2 22.6 11.08 1107.38 -48.99 -159.48 13.27 1325.53 -58.64 -190.89
1.3 33.9 19.40 1339.22 -38.76 -239.19 23.22 1603.04 -46.40 -286.31
1.4 45.2 29.18 1424.64 -30.63 -318.90 34.92 1705.29 -36.66 -381.72
B=1.5 56.5 39.20 1387.09 -23.20 -398.60 46.93 1660.35 -27.78 -477.13
1.6 67.8 48.70 1248.72 -16.42 -478.31 58.29 1494.72 -19.66 -572.54
1.7 79.1 57.05 992.72 -10.40 -558.02 68.28 1188.28 -12.45 -667.95
1.8 90.4 64.00 616.21 -5.40 -637.73 76.61 737.60 -6.46 -763.36
1.9 101.7 75.31 208.97 -1.83 -790.40 90.15 250.14 -2.19 -946.11
C=2.0 113 88.58 206.64 -1.83 -1432.39 106.03 247.35 -2.19 -1714.57
C'=2.0 113.0001 8.13 206.64 -86.60 -1432.39 9.73 247.35 -103.66 -1714.57
2.1 125.3 8.13 258.12 -73.07 -749.78 9.73 308.96 -87.46 -897.49
2.2 137.6 8.13 682.47 -62.04 -593.36 9.73 816.92 -74.27 -710.26
2.3 149.9 14.00 1042.57 -53.32 -493.37 16.76 1247.96 -63.83 -590.57
2.4 162.2 22.18 1223.56 -43.14 -393.38 26.55 1464.60 -51.64 -470.88
D = 2.5 174.5 32.19 1269.11 -32.19 -293.39 38.53 1519.13 -38.53 -351.19
2.6 186.8 43.14 1223.56 -22.18 -393.38 51.64 1464.60 -26.55 -470.88
2.7 199.1 53.32 1042.57 -14.00 -493.37 63.83 1247.96 -16.76 -590.57
2.8 211.4 62.04 682.47 -8.13 -593.36 74.27 816.92 -9.73 -710.26
2.9 223.7 73.07 258.12 -8.13 -749.78 87.46 308.96 -9.73 -897.49
E=3.0 236 86.60 206.64 -8.13 -1432.39 103.66 247.35 -9.73 -1714.57
E'=3.0 236.0001 1.83 206.64 -88.58 -1432.39 2.19 247.35 -106.03 -1714.57
3.1 247.3 1.83 208.97 -75.31 -790.40 2.19 250.14 -90.15 -946.11
3.2 258.6 5.40 616.21 -64.00 -637.73 6.46 737.60 -76.61 -763.36
3.3 269.9 10.40 992.72 -57.05 -558.02 12.45 1188.28 -68.28 -667.95
3.4 281.2 16.42 1248.72 -48.70 -478.31 19.66 1494.72 -58.29 -572.54
F=3.5 292.5 23.20 1387.09 -39.20 -398.60 27.78 1660.35 -46.93 -477.13
3.6 303.8 30.63 1424.64 -29.18 -318.90 36.66 1705.29 -34.92 -381.72
3.7 315.1 38.76 1339.22 -19.40 -239.19 46.40 1603.04 -23.22 -286.31
3.8 326.4 48.99 1107.38 -11.08 -159.48 58.64 1325.53 -13.27 -190.89
3.9 337.7 61.50 695.39 -7.06 -79.79 73.62 832.39 -8.45 -95.51
G=4.0 349 75.52 0.00 -7.06 0.00 90.40 0.00 -8.45 0.00
27
4.1.3. Tandem moving load (TML):
The tabulated values shows positive and negative extreme shear and bending moments at
each section. The figure plotted for the TML shear and moments multiplied by
(1+IM=1.33).
1200
800
Moments (kip-ft)
400
0
0 35 70 105 140 175 210 245 280 315 350
-400
-1200
Span Distances (ft)
25
Shear Forces (kip)
0
0 35 70 105 140 175 210 245 280 315 350
-25
-50
-65.69 -65.84
-65.02
-75
Span Distances (ft)
28
Unfactored Shear and Moments (TML) Shear and Moments (TML) * (1+IM=1.33)
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 4.48 0.00 -48.89 0.00 5.96 0.00 -65.02 0.00
1.1 11.3 5.17 481.99 -42.63 -50.70 6.87 641.05 -56.70 -67.43
1.2 22.6 11.37 824.25 -36.46 -101.36 15.12 1096.25 -48.50 -134.81
1.3 33.9 17.44 1032.87 -30.47 -152.02 23.19 1373.72 -40.52 -202.19
1.4 45.2 23.29 1117.01 -24.71 -202.68 30.97 1485.63 -32.87 -269.57
B=1.5 56.5 28.84 1095.49 -19.28 -253.34 38.36 1457.00 -25.64 -336.94
1.6 67.8 34.02 983.15 -14.25 -304.00 45.25 1307.59 -18.95 -404.32
1.7 79.1 38.76 789.16 -9.69 -354.66 51.55 1049.59 -12.89 -471.70
1.8 90.4 42.97 535.69 -5.69 -405.32 57.15 712.47 -7.56 -539.08
1.9 101.7 46.57 248.36 -2.31 -455.99 61.94 330.32 -3.07 -606.46
C=2.0 113 49.50 144.49 -1.28 -554.79 65.84 192.17 -1.70 -737.87
C'=2.0 113.0001 5.69 144.49 -49.39 -554.79 7.56 192.17 -65.69 -737.87
2.1 125.3 5.69 284.57 -45.52 -484.82 7.56 378.48 -60.54 -644.81
2.2 137.6 7.57 582.38 -40.84 -414.90 10.06 774.57 -54.32 -551.82
2.3 149.9 12.67 817.95 -35.56 -344.99 16.86 1087.87 -47.30 -458.83
2.4 162.2 18.24 966.56 -29.89 -275.07 24.26 1285.52 -39.76 -365.84
D = 2.5 174.5 24.05 1013.89 -24.05 -205.15 31.99 1348.47 -31.99 -272.85
2.6 186.8 29.89 966.56 -18.24 -275.07 39.76 1285.52 -24.26 -365.84
2.7 199.1 35.56 817.95 -12.67 -344.99 47.30 1087.87 -16.86 -458.83
2.8 211.4 40.84 582.38 -7.57 -414.90 54.32 774.57 -10.06 -551.82
2.9 223.7 45.52 284.57 -5.69 -484.82 60.54 378.48 -7.56 -644.81
E=3.0 236 49.39 144.49 -5.69 -554.79 65.69 192.17 -7.56 -737.87
E'=3.0 236.0001 1.28 144.49 -49.50 -554.79 1.70 192.17 -65.84 -737.87
3.1 247.3 2.31 248.36 -46.57 -455.99 3.07 330.32 -61.94 -606.46
3.2 258.6 5.69 535.69 -42.97 -405.32 7.56 712.47 -57.15 -539.08
3.3 269.9 9.69 789.16 -38.76 -354.66 12.89 1049.59 -51.55 -471.70
3.4 281.2 14.25 983.15 -34.02 -304.00 18.95 1307.59 -45.25 -404.32
F=3.5 292.5 19.28 1095.49 -28.84 -253.34 25.64 1457.00 -38.36 -336.94
3.6 303.8 24.71 1117.01 -23.29 -202.68 32.87 1485.63 -30.97 -269.57
3.7 315.1 30.47 1032.87 -17.44 -152.02 40.52 1373.72 -23.19 -202.19
3.8 326.4 36.46 824.25 -11.37 -101.36 48.50 1096.25 -15.12 -134.81
3.9 337.7 42.63 481.99 -5.17 -50.70 56.70 641.05 -6.87 -67.43
G=4.0 349 48.89 0.00 -4.48 0.00 65.02 0.00 -5.96 0.00
29
4.1.4. Lane moving load (LL):
In this section, moments and shear forces are plotted for each case of loading, then the
1000
800
600
400
200
Moment (kip-ft)
0
-200 0 35 70 105 140 175 210 245 280 315 350
-400
-600
-800
-1000
-1200
Span Distances (ft)
60
45
30
15
Shear (kip)
0
0 35 70 105 140 175 210 245 280 315 350
-15
-30
-45
-60
Span Distances (ft)
30
Moment Envelopes (Lane Load-LL)
1000
827.53 827.53
800 709.96
600
400
200
Moment (kip-ft)
0
0 35 70 105 140 175 210 245 280 315 350
-200
-400
-600
-800
-1000 -1024.96 -1024.96
-1200
Span Distances (ft)
0
0 35 70 105 140 175 210 245 280 315 350
-10
-20
-30
-40
-50
Span Distances (ft)
31
LL-SPAN(1+2) LL-SPAN(1+3) LL-SPAN(2) LL-SPAN(2+3) Shear and Moment Envelopes
Point Loc.
V M V M V M V M V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -27.09 0.00 -32.73 0.00 4.43 0.00 3.22 0.00 4.43 0.00 -32.73 0.00
1.1 11.3 -19.85 265.38 -25.49 329.12 4.43 -50.07 3.22 -36.39 4.43 329.12 -25.49 -50.07
1.2 22.6 -12.62 448.84 -18.26 576.27 4.43 -100.09 3.22 -72.76 4.43 576.27 -18.26 -100.09
1.3 33.9 -5.39 550.61 -11.03 741.72 4.43 -150.12 3.22 -109.13 4.43 741.72 -11.03 -150.12
1.4 45.2 1.84 570.67 -3.80 825.48 4.43 -200.15 3.22 -145.50 4.43 825.48 -3.80 -200.15
B=1.5 56.5 9.07 509.04 3.43 827.53 4.43 -250.18 3.22 -181.87 9.07 827.53 3.22 -250.18
1.6 67.8 16.30 365.71 10.66 747.89 4.43 -300.21 3.22 -218.23 16.30 747.89 3.22 -300.21
1.7 79.1 23.53 140.68 17.90 586.56 4.43 -350.24 3.22 -254.60 23.53 586.56 3.22 -350.24
1.8 90.4 30.76 -166.04 25.13 343.52 4.43 -400.26 3.22 -290.97 30.76 343.52 3.22 -400.26
1.9 101.7 37.99 -554.46 32.36 18.79 4.43 -450.29 3.22 -327.34 37.99 18.79 3.22 -554.46
C=2.0 113 45.23 -1024.96 39.59 -387.97 4.43 -500.36 3.22 -363.73 45.23 -363.73 3.22 -1024.96
C'=2.0 113.0001 -44.74 -1024.96 0.00 -387.97 -39.36 -500.36 -33.98 -363.73 0.00 -363.73 -44.74 -1024.96
2.1 125.3 -36.86 -522.88 0.00 -387.97 -31.48 -64.43 -26.11 6.04 0.00 6.04 -36.86 -522.88
2.2 137.6 -28.99 -117.96 0.00 -387.97 -23.61 274.36 -18.24 278.72 0.00 278.72 -28.99 -387.97
2.3 149.9 -21.12 190.15 0.00 -387.97 -15.74 516.36 -10.37 454.60 0.00 516.36 -21.12 -387.97
2.4 162.2 -13.25 401.46 0.00 -387.97 -7.87 661.56 -2.50 533.69 0.00 661.56 -13.25 -387.97
32
D = 2.5 174.5 -5.38 515.97 0.00 -387.97 0.00 709.96 5.38 515.97 5.38 709.96 -5.38 -387.97
2.6 186.8 2.50 533.69 0.00 -387.97 7.87 661.56 13.25 401.46 13.25 661.56 0.00 -387.97
2.7 199.1 10.37 454.60 0.00 -387.97 15.74 516.36 21.12 190.15 21.12 516.36 0.00 -387.97
2.8 211.4 18.24 278.72 0.00 -387.97 23.61 274.36 28.99 -117.96 28.99 278.72 0.00 -387.97
2.9 223.7 26.11 6.04 0.00 -387.97 31.48 -64.43 36.86 -522.88 36.86 6.04 0.00 -522.88
E=3.0 236 33.98 -363.73 0.00 -387.97 39.36 -500.36 44.74 -1024.96 44.74 -363.73 0.00 -1024.96
E'=3.0 236.0001 -3.22 -363.73 -39.59 -387.97 -4.43 -500.36 -45.23 -1024.96 -3.22 -363.73 -45.23 -1024.96
3.1 247.3 -3.22 -327.34 -32.36 18.79 -4.43 -450.29 -37.99 -554.46 -3.22 18.79 -37.99 -554.46
3.2 258.6 -3.22 -290.97 -25.13 343.52 -4.43 -400.26 -30.76 -166.04 -3.22 343.52 -30.76 -400.26
3.3 269.9 -3.22 -254.60 -17.90 586.56 -4.43 -350.24 -23.53 140.68 -3.22 586.56 -23.53 -350.24
3.4 281.2 -3.22 -218.23 -10.66 747.89 -4.43 -300.21 -16.30 365.71 -3.22 747.89 -16.30 -300.21
F=3.5 292.5 -3.22 -181.87 -3.43 827.53 -4.43 -250.18 -9.07 509.04 -3.22 827.53 -9.07 -250.18
3.6 303.8 -3.22 -145.50 3.80 825.48 -4.43 -200.15 -1.84 570.67 3.80 825.48 -4.43 -200.15
3.7 315.1 -3.22 -109.13 11.03 741.72 -4.43 -150.12 5.39 550.61 11.03 741.72 -4.43 -150.12
3.8 326.4 -3.22 -72.76 18.26 576.27 -4.43 -100.09 12.62 448.84 18.26 576.27 -4.43 -100.09
3.9 337.7 -3.22 -36.39 25.49 329.12 -4.43 -50.07 19.85 265.38 25.49 329.12 -4.43 -50.07
G=4.0 349 -3.22 0.00 32.73 0.00 -4.43 0.00 27.09 0.00 32.73 0.00 -4.43 0.00
4.1.5. Dead loads (DC1, DC2 and DW):
In this section, moments and shear forces are plotted for each dead load case, and no
2000
1690.33 1690.33
1600
1200 870.37
800
244.27
400 244.27 125.78
Moment (kip-ft)
0
-400 0 35 70 105 140 175 210 245 280 315 350
-800 -347.00
-1200
-1600
-2000
-2401.27 -2401.27
-2400
-2800
Span Distances (ft)
125
119.00 106.40
100
76.50
75
50
25
Shear (kip)
15.38 11.05
0
0 35 70 105 140 175 210 245 280 315 350
-25
-17.20
-50
-75 -76.50
-100 -106.40 -119.00
-125
Span Distances (ft)
33
DC1 DC2 DW
Point Loc.
V M V M V M
A=1.0 0 -76.50 0.00 -6.19 0.00 -11.05 0.00
1.1 11.3 -56.93 754.32 -4.61 61.04 -8.23 109.01
1.2 22.6 -37.39 1287.16 -3.03 104.16 -5.40 186.01
1.3 33.9 -17.84 1599.17 -1.44 129.41 -2.58 231.09
1.4 45.2 1.70 1690.33 0.14 136.79 0.25 244.27
B=1.5 56.5 21.25 1560.66 1.72 126.30 3.07 225.53
1.6 67.8 40.80 1210.15 3.30 97.93 5.90 174.88
1.7 79.1 60.34 638.80 4.88 51.69 8.72 92.31
1.8 90.4 79.89 -153.39 6.47 -12.41 11.55 -22.17
1.9 101.7 99.44 -1166.42 8.05 -94.39 14.37 -168.56
C=2.0 113 119.00 -2401.27 9.63 -194.32 17.20 -347.00
C'=2.0 113.0001 -106.40 -2401.27 -8.61 -194.32 -15.38 -347.00
2.1 125.3 -85.10 -1222.91 -6.89 -98.96 -12.30 -176.72
2.2 137.6 -63.83 -307.10 -5.17 -24.85 -9.22 -44.38
2.3 149.9 -42.55 347.05 -3.44 28.09 -6.15 50.15
2.4 162.2 -21.28 739.54 -1.72 59.85 -3.08 106.87
D = 2.5 174.5 0.00 870.37 0.00 70.43 0.00 125.78
2.6 186.8 21.28 739.54 1.72 59.85 3.08 106.87
2.7 199.1 42.55 347.05 3.44 28.09 6.15 50.15
2.8 211.4 63.83 -307.10 5.17 -24.85 9.22 -44.38
2.9 223.7 85.10 -1222.91 6.89 -98.96 12.30 -176.72
E=3.0 236 106.40 -2401.27 8.61 -194.32 15.38 -347.00
E'=3.0 236.0001 -119.00 -2401.27 -9.63 -194.32 -17.20 -347.00
3.1 247.3 -99.44 -1166.42 -8.05 -94.39 -14.37 -168.56
3.2 258.6 -79.89 -153.39 -6.47 -12.41 -11.55 -22.17
3.3 269.9 -60.34 638.80 -4.88 51.69 -8.72 92.31
3.4 281.2 -40.80 1210.15 -3.30 97.93 -5.90 174.88
F=3.5 292.5 -21.25 1560.66 -1.72 126.30 -3.07 225.53
3.6 303.8 -1.70 1690.33 -0.14 136.79 -0.25 244.27
3.7 315.1 17.84 1599.17 1.44 129.41 2.58 231.09
3.8 326.4 37.39 1287.16 3.03 104.16 5.40 186.01
3.9 337.7 56.93 754.32 4.61 61.04 8.23 109.01
G=4.0 349 76.50 0.00 6.19 0.00 11.05 0.00
34
4.2. Steel Bridge live loads envelopes:
Bending moments and shear forces envelopes for (HS-20 * 1.33 + Lane Load), (0.90
*1.33* 2-HS20 + 0.90 * Lane Load) and (TML*1.33 + Lane Load) are generated in excel. The
live load internal forces envelopes at each section are plotted from theses tabulated values.
For example, the positive envelope at each section is the maximum of (HS-20 * 1.33 + Lane
Load), (0.90 * 1.33 * 2-HS20 + 0.90 * Lane Load) or (TML*1.33 + Lane Load) at this section.
-80.01 -80.01
400
0
-400 0 35 70 105 140 175 210 245 280 315 350
-800
-1200
-769.18
-1600
-2000
-2637.03
-2400 -2637.03
-2800
Span Distances (ft)
25
0
-25 0 35 70 105 140 175 210 245 280 315 350
-50
-75
-100
-125 -119.86 -146.74
-143.92
-150
-175
Span Distances (ft)
35
Shear and Moments (HS20) * (1+IM=1.33) Shear and Moments (0.90)*(2-HS20) *(1.33) Shear and Moments (TML) * (1+IM=1.33) Shear and Moments (Lane Loads) Moving Loads Envelopes
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 8.37 0.00 -85.89 0.00 8.45 0.00 -90.40 0.00 5.96 0.00 -65.02 0.00 4.43 0.00 -32.73 0.00 12.80 0.00 -119.86 0.00
1.1 11.3 8.37 837.24 -74.05 -94.61 8.45 832.39 -73.62 -95.51 6.87 641.05 -56.70 -67.43 4.43 329.12 -25.49 -50.07 12.80 1166.36 -99.54 -144.67
1.2 22.6 14.68 1412.33 -62.48 -189.14 13.27 1325.53 -58.64 -190.89 15.12 1096.25 -48.50 -134.81 4.43 576.27 -18.26 -100.09 19.55 1988.60 -80.74 -289.24
1.3 33.9 25.80 1744.64 -51.33 -283.68 23.22 1603.04 -46.40 -286.31 23.19 1373.72 -40.52 -202.19 4.43 741.72 -11.03 -150.12 30.23 2486.36 -62.35 -433.80
1.4 45.2 37.24 1885.71 -40.74 -378.22 34.92 1705.29 -36.66 -381.72 30.97 1485.63 -32.87 -269.57 4.43 825.48 -3.80 -200.15 41.67 2711.19 -44.54 -578.37
B=1.5 56.5 48.22 1844.83 -30.86 -472.76 46.93 1660.35 -27.78 -477.13 38.36 1457.00 -25.64 -336.94 9.07 827.53 3.22 -250.18 57.29 2672.36 -27.64 -722.93
1.6 67.8 58.57 1650.80 -21.84 -567.29 58.29 1494.72 -19.66 -572.54 45.25 1307.59 -18.95 -404.32 16.30 747.89 3.22 -300.21 74.87 2398.69 -18.62 -867.50
1.7 79.1 68.17 1294.60 -13.83 -661.83 68.28 1188.28 -12.45 -667.95 51.55 1049.59 -12.89 -471.70 23.53 586.56 3.22 -350.24 91.70 1881.16 -10.61 -1012.07
1.8 90.4 76.85 817.51 -7.18 -756.37 76.61 737.60 -6.46 -763.36 57.15 712.47 -7.56 -539.08 30.76 343.52 3.22 -400.26 107.61 1161.03 -4.34 -1156.63
1.9 101.7 84.48 277.93 -2.39 -850.90 90.15 250.14 -2.19 -946.11 61.94 330.32 -3.07 -606.46 37.99 18.79 3.22 -554.46 124.34 349.11 0.15 -1445.12
C=2.0 113 90.90 268.49 -2.38 -1030.90 106.03 247.35 -2.19 -1714.57 65.84 192.17 -1.70 -737.87 45.23 -363.73 3.22 -1024.96 146.74 -80.01 0.71 -2637.03
C'=2.0 113.0001 10.56 268.49 -89.97 -1030.90 9.73 247.35 -103.66 -1714.57 7.56 192.17 -65.69 -737.87 0.00 -363.73 -44.74 -1024.96 10.56 -80.01 -143.92 -2637.03
2.1 125.3 10.56 343.29 -81.68 -900.89 9.73 308.96 -87.46 -897.49 7.56 378.48 -60.54 -644.81 0.00 6.04 -36.86 -522.88 10.56 384.51 -120.64 -1423.77
2.2 137.6 10.56 902.26 -72.09 -770.97 9.73 816.92 -74.27 -710.26 10.06 774.57 -54.32 -551.82 0.00 278.72 -28.99 -387.97 10.56 1180.98 -101.08 -1158.95
2.3 149.9 18.62 1342.13 -61.59 -641.05 16.76 1247.96 -63.83 -590.57 16.86 1087.87 -47.30 -458.83 0.00 516.36 -21.12 -387.97 18.62 1858.49 -82.83 -1029.02
2.4 162.2 28.70 1612.08 -50.59 -511.13 26.55 1464.60 -51.64 -470.88 24.26 1285.52 -39.76 -365.84 0.00 661.56 -13.25 -387.97 28.70 2273.64 -63.84 -899.10
36
D = 2.5 174.5 39.49 1687.92 -39.49 -381.21 38.53 1519.13 -38.53 -351.19 31.99 1348.47 -31.99 -272.85 5.38 709.96 -5.38 -387.97 44.87 2397.88 -44.87 -769.18
2.6 186.8 50.59 1612.08 -28.70 -511.13 51.64 1464.60 -26.55 -470.88 39.76 1285.52 -24.26 -365.84 13.25 661.56 0.00 -387.97 63.84 2273.64 -28.70 -899.10
2.7 199.1 61.59 1342.13 -18.62 -641.05 63.83 1247.96 -16.76 -590.57 47.30 1087.87 -16.86 -458.83 21.12 516.36 0.00 -387.97 82.83 1858.49 -18.62 -1029.02
2.8 211.4 72.09 902.26 -10.56 -770.97 74.27 816.92 -9.73 -710.26 54.32 774.57 -10.06 -551.82 28.99 278.72 0.00 -387.97 101.08 1180.98 -10.56 -1158.95
2.9 223.7 81.68 343.29 -10.56 -900.89 87.46 308.96 -9.73 -897.49 60.54 378.48 -7.56 -644.81 36.86 6.04 0.00 -522.88 120.64 384.51 -10.56 -1423.77
E=3.0 236 89.97 268.49 -10.56 -1030.90 103.66 247.35 -9.73 -1714.57 65.69 192.17 -7.56 -737.87 44.74 -363.73 0.00 -1024.96 143.92 -80.01 -10.56 -2637.03
E'=3.0 236.0001 2.38 268.49 -90.90 -1030.90 2.19 247.35 -106.03 -1714.57 1.70 192.17 -65.84 -737.87 -3.22 -363.73 -45.23 -1024.96 -0.71 -80.01 -146.74 -2637.03
3.1 247.3 2.39 277.93 -84.48 -850.90 2.19 250.14 -90.15 -946.11 3.07 330.32 -61.94 -606.46 -3.22 18.79 -37.99 -554.46 -0.15 349.11 -124.34 -1445.12
3.2 258.6 7.18 817.51 -76.85 -756.37 6.46 737.60 -76.61 -763.36 7.56 712.47 -57.15 -539.08 -3.22 343.52 -30.76 -400.26 4.34 1161.03 -107.61 -1156.63
3.3 269.9 13.83 1294.60 -68.17 -661.83 12.45 1188.28 -68.28 -667.95 12.89 1049.59 -51.55 -471.70 -3.22 586.56 -23.53 -350.24 10.61 1881.16 -91.70 -1012.07
3.4 281.2 21.84 1650.80 -58.57 -567.29 19.66 1494.72 -58.29 -572.54 18.95 1307.59 -45.25 -404.32 -3.22 747.89 -16.30 -300.21 18.62 2398.69 -74.87 -867.50
F=3.5 292.5 30.86 1844.83 -48.22 -472.76 27.78 1660.35 -46.93 -477.13 25.64 1457.00 -38.36 -336.94 -3.22 827.53 -9.07 -250.18 27.64 2672.36 -57.29 -722.93
3.6 303.8 40.74 1885.71 -37.24 -378.22 36.66 1705.29 -34.92 -381.72 32.87 1485.63 -30.97 -269.57 3.80 825.48 -4.43 -200.15 44.54 2711.19 -41.67 -578.37
3.7 315.1 51.33 1744.64 -25.80 -283.68 46.40 1603.04 -23.22 -286.31 40.52 1373.72 -23.19 -202.19 11.03 741.72 -4.43 -150.12 62.35 2486.36 -30.23 -433.80
3.8 326.4 62.48 1412.33 -14.68 -189.14 58.64 1325.53 -13.27 -190.89 48.50 1096.25 -15.12 -134.81 18.26 576.27 -4.43 -100.09 80.74 1988.60 -19.55 -289.24
3.9 337.7 74.05 837.24 -8.37 -94.61 73.62 832.39 -8.45 -95.51 56.70 641.05 -6.87 -67.43 25.49 329.12 -4.43 -50.07 99.54 1166.36 -12.80 -144.67
G=4.0 349 85.89 0.00 -8.37 0.00 90.40 0.00 -8.45 0.00 65.02 0.00 -5.96 0.00 32.73 0.00 -4.43 0.00 119.86 0.00 -12.80 0.00
4.3. Steel Bridge factored design envelopes:
In this section, the dead loads (DC1, DC2 and DW) internal forces calculated in section
- Using these load combinations with the tabulated values in Excel gives the following
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000
-4000
-5000
-6000
-7000 -8379.80 -8379.80
-8000
-9000
Span Distances (ft)
37
Shear Envelopes Load Combination (STR I-a)
500
443.37
400 418.67
329.68
300
200
100
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-100
-200
-300
-329.68
-400 -418.67
-443.37
-500
Span Distances (ft)
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination STR I-a
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -76.50 0.00 -6.19 0.00 -11.05 0.00 12.80 0.00 -119.86 0.00 -97.55 0.00 -329.68 0.00
1.1 11.3 -56.93 754.32 -4.61 61.04 -8.23 109.01 12.80 1166.36 -99.54 -144.67 -66.88 3223.83 -263.46 929.53
1.2 22.6 -37.39 1287.16 -3.03 104.16 -5.40 186.01 19.55 1988.60 -80.74 -289.24 -24.41 5498.21 -199.91 1512.00
1.3 33.9 -17.84 1599.17 -1.44 129.41 -2.58 231.09 30.23 2486.36 -62.35 -433.80 24.93 6858.50 -137.09 1748.21
1.4 45.2 1.70 1690.33 0.14 136.79 0.25 244.27 41.67 2711.19 -44.54 -578.37 75.60 7394.89 -75.27 1638.16
B=1.5 56.5 21.25 1560.66 1.72 126.30 3.07 225.53 57.29 2672.36 -27.64 -722.93 133.57 7123.62 -15.06 1181.85
1.6 67.8 40.80 1210.15 3.30 97.93 5.90 174.88 74.87 2398.69 -18.62 -867.50 194.99 6095.12 31.37 379.29
1.7 79.1 60.34 638.80 4.88 51.69 8.72 92.31 91.70 1881.16 -10.61 -1012.07 255.09 4293.62 76.04 -769.53
1.8 90.4 79.89 -153.39 6.47 -12.41 11.55 -22.17 107.61 1161.03 -4.34 -1156.63 313.59 1791.31 117.66 -2264.61
1.9 101.7 99.44 -1166.42 8.05 -94.39 14.37 -168.56 124.34 349.11 0.15 -1445.12 373.50 -1217.91 156.16 -4357.81
C=2.0 113 119.00 -2401.27 9.63 -194.32 17.20 -347.00 146.74 -80.01 0.71 -2637.03 443.37 -3905.02 187.81 -8379.80
C'=2.0 113.0001 -106.40 -2401.27 -8.61 -194.32 -15.38 -347.00 10.56 -80.01 -143.92 -2637.03 -148.33 -3905.02 -418.67 -8379.80
2.1 125.3 -85.10 -1222.91 -6.89 -98.96 -12.30 -176.72 10.56 384.51 -120.64 -1423.77 -114.95 -1244.53 -344.55 -4409.03
2.2 137.6 -63.83 -307.10 -5.17 -24.85 -9.22 -44.38 10.56 1180.98 -101.08 -1158.95 -81.59 1585.21 -276.97 -2509.66
2.3 149.9 -42.55 347.05 -3.44 28.09 -6.15 50.15 18.62 1858.49 -82.83 -1029.02 -34.13 3796.51 -211.68 -1256.64
2.4 162.2 -21.28 739.54 -1.72 59.85 -3.08 106.87 28.70 2273.64 -63.84 -899.10 16.87 5138.41 -145.08 -413.88
D = 2.5 174.5 0.00 870.37 0.00 70.43 0.00 125.78 44.87 2397.88 -44.87 -769.18 78.52 5560.97 -78.52 18.61
2.6 186.8 21.28 739.54 1.72 59.85 3.08 106.87 63.84 2273.64 -28.70 -899.10 145.08 5138.41 -16.87 -413.88
2.7 199.1 42.55 347.05 3.44 28.09 6.15 50.15 82.83 1858.49 -18.62 -1029.02 211.68 3796.51 34.13 -1256.64
2.8 211.4 63.83 -307.10 5.17 -24.85 9.22 -44.38 101.08 1180.98 -10.56 -1158.95 276.97 1585.21 81.59 -2509.66
2.9 223.7 85.10 -1222.91 6.89 -98.96 12.30 -176.72 120.64 384.51 -10.56 -1423.77 344.55 -1244.53 114.95 -4409.03
E=3.0 236 106.40 -2401.27 8.61 -194.32 15.38 -347.00 143.92 -80.01 -10.56 -2637.03 418.67 -3905.02 148.33 -8379.80
E'=3.0 236.0001 -119.00 -2401.27 -9.63 -194.32 -17.20 -347.00 -0.71 -80.01 -146.74 -2637.03 -187.81 -3905.02 -443.37 -8379.80
3.1 247.3 -99.44 -1166.42 -8.05 -94.39 -14.37 -168.56 -0.15 349.11 -124.34 -1445.12 -156.16 -1217.91 -373.50 -4357.81
3.2 258.6 -79.89 -153.39 -6.47 -12.41 -11.55 -22.17 4.34 1161.03 -107.61 -1156.63 -117.66 1791.31 -313.59 -2264.61
3.3 269.9 -60.34 638.80 -4.88 51.69 -8.72 92.31 10.61 1881.16 -91.70 -1012.07 -76.04 4293.62 -255.09 -769.53
3.4 281.2 -40.80 1210.15 -3.30 97.93 -5.90 174.88 18.62 2398.69 -74.87 -867.50 -31.37 6095.12 -194.99 379.29
F=3.5 292.5 -21.25 1560.66 -1.72 126.30 -3.07 225.53 27.64 2672.36 -57.29 -722.93 15.06 7123.62 -133.57 1181.85
3.6 303.8 -1.70 1690.33 -0.14 136.79 -0.25 244.27 44.54 2711.19 -41.67 -578.37 75.27 7394.89 -75.60 1638.16
3.7 315.1 17.84 1599.17 1.44 129.41 2.58 231.09 62.35 2486.36 -30.23 -433.80 137.09 6858.50 -24.93 1748.21
3.8 326.4 37.39 1287.16 3.03 104.16 5.40 186.01 80.74 1988.60 -19.55 -289.24 199.91 5498.21 24.41 1512.00
3.9 337.7 56.93 754.32 4.61 61.04 8.23 109.01 99.54 1166.36 -12.80 -144.67 263.46 3223.83 66.88 929.53
G=4.0 349 76.50 0.00 6.19 0.00 11.05 0.00 119.86 0.00 -12.80 0.00 329.68 0.00 97.55 0.00
38
4.3.2. Load combination (STR I-b) results:
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000
-4000
-5000
-6000 -7176.39 -7176.39
-7000
-8000
-9000
Span Distances (ft)
0
0 35 70 105 140 175 210 245 280 315 350
-100
-200
-300 -291.35
-365.35 -383.73
-400
-500
Span Distances (ft)
39
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination STR I-b
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -76.50 0.00 -6.19 0.00 -11.05 0.00 12.80 0.00 -119.86 0.00 -59.21 0.00 -291.35 0.00
1.1 11.3 -56.93 754.32 -4.61 61.04 -8.23 109.01 12.80 1166.36 -99.54 -144.67 -38.34 2845.80 -234.93 551.50
1.2 22.6 -37.39 1287.16 -3.03 104.16 -5.40 186.01 19.55 1988.60 -80.74 -289.24 -5.67 4853.14 -181.17 866.93
1.3 33.9 -17.84 1599.17 -1.44 129.41 -2.58 231.09 30.23 2486.36 -62.35 -433.80 33.87 6057.07 -128.15 946.78
1.4 45.2 1.70 1690.33 0.14 136.79 0.25 244.27 41.67 2711.19 -44.54 -578.37 74.74 6547.77 -76.12 791.04
B=1.5 56.5 21.25 1560.66 1.72 126.30 3.07 225.53 57.29 2672.36 -27.64 -722.93 122.92 6341.49 -25.70 399.72
1.6 67.8 40.80 1210.15 3.30 97.93 5.90 174.88 74.87 2398.69 -18.62 -867.50 174.55 5488.65 10.93 -227.18
1.7 79.1 60.34 638.80 4.88 51.69 8.72 92.31 91.70 1881.16 -10.61 -1012.07 224.85 3973.48 45.80 -1089.67
1.8 90.4 79.89 -153.39 6.47 -12.41 11.55 -22.17 107.61 1161.03 -4.34 -1156.63 273.55 1868.18 77.62 -2187.74
1.9 101.7 99.44 -1166.42 8.05 -94.39 14.37 -168.56 124.34 349.11 0.15 -1445.12 323.67 -633.35 106.33 -3773.25
C=2.0 113 119.00 -2401.27 9.63 -194.32 17.20 -347.00 146.74 -80.01 0.71 -2637.03 383.73 -2701.61 128.18 -7176.39
C'=2.0 113.0001 -106.40 -2401.27 -8.61 -194.32 -15.38 -347.00 10.56 -80.01 -143.92 -2637.03 -95.01 -2701.61 -365.35 -7176.39
2.1 125.3 -85.10 -1222.91 -6.89 -98.96 -12.30 -176.72 10.56 384.51 -120.64 -1423.77 -72.30 -631.66 -301.90 -3796.16
2.2 137.6 -63.83 -307.10 -5.17 -24.85 -9.22 -44.38 10.56 1180.98 -101.08 -1158.95 -49.60 1739.11 -244.98 -2355.76
2.3 149.9 -42.55 347.05 -3.44 28.09 -6.15 50.15 18.62 1858.49 -82.83 -1029.02 -12.81 3622.58 -190.35 -1430.57
2.4 162.2 -21.28 739.54 -1.72 59.85 -3.08 106.87 28.70 2273.64 -63.84 -899.10 27.53 4767.79 -134.41 -784.51
40
D = 2.5 174.5 0.00 870.37 0.00 70.43 0.00 125.78 44.87 2397.88 -44.87 -769.18 78.52 5124.78 -78.52 -417.58
2.6 186.8 21.28 739.54 1.72 59.85 3.08 106.87 63.84 2273.64 -28.70 -899.10 134.41 4767.79 -27.53 -784.51
2.7 199.1 42.55 347.05 3.44 28.09 6.15 50.15 82.83 1858.49 -18.62 -1029.02 190.35 3622.58 12.81 -1430.57
2.8 211.4 63.83 -307.10 5.17 -24.85 9.22 -44.38 101.08 1180.98 -10.56 -1158.95 244.98 1739.11 49.60 -2355.76
2.9 223.7 85.10 -1222.91 6.89 -98.96 12.30 -176.72 120.64 384.51 -10.56 -1423.77 301.90 -631.66 72.30 -3796.16
E=3.0 236 106.40 -2401.27 8.61 -194.32 15.38 -347.00 143.92 -80.01 -10.56 -2637.03 365.35 -2701.61 95.01 -7176.39
E'=3.0 236.0001 -119.00 -2401.27 -9.63 -194.32 -17.20 -347.00 -0.71 -80.01 -146.74 -2637.03 -128.18 -2701.61 -383.73 -7176.39
3.1 247.3 -99.44 -1166.42 -8.05 -94.39 -14.37 -168.56 -0.15 349.11 -124.34 -1445.12 -106.33 -633.35 -323.67 -3773.25
3.2 258.6 -79.89 -153.39 -6.47 -12.41 -11.55 -22.17 4.34 1161.03 -107.61 -1156.63 -77.62 1868.18 -273.55 -2187.74
3.3 269.9 -60.34 638.80 -4.88 51.69 -8.72 92.31 10.61 1881.16 -91.70 -1012.07 -45.80 3973.48 -224.85 -1089.67
3.4 281.2 -40.80 1210.15 -3.30 97.93 -5.90 174.88 18.62 2398.69 -74.87 -867.50 -10.93 5488.65 -174.55 -227.18
F=3.5 292.5 -21.25 1560.66 -1.72 126.30 -3.07 225.53 27.64 2672.36 -57.29 -722.93 25.70 6341.49 -122.92 399.72
3.6 303.8 -1.70 1690.33 -0.14 136.79 -0.25 244.27 44.54 2711.19 -41.67 -578.37 76.12 6547.77 -74.74 791.04
3.7 315.1 17.84 1599.17 1.44 129.41 2.58 231.09 62.35 2486.36 -30.23 -433.80 128.15 6057.07 -33.87 946.78
3.8 326.4 37.39 1287.16 3.03 104.16 5.40 186.01 80.74 1988.60 -19.55 -289.24 181.17 4853.14 5.67 866.93
3.9 337.7 56.93 754.32 4.61 61.04 8.23 109.01 99.54 1166.36 -12.80 -144.67 234.93 2845.80 38.34 551.50
G=4.0 349 76.50 0.00 6.19 0.00 11.05 0.00 119.86 0.00 -12.80 0.00 291.35 0.00 59.21 0.00
4.3.3. Load combination (SVC I) results:
0
0 35 70 105 140 175 210 245 280 315 350
-1000
-2000
-3000
-4000
-5000 -5579.63 -5579.63
-6000
Span Distances (ft)
0
0 35 70 105 140 175 210 245 280 315 350
-70
-140
-210 -213.59
-280 -274.30
-292.56
-350
Span Distances (ft)
41
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination SVC I
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -76.50 0.00 -6.19 0.00 -11.05 0.00 12.80 0.00 -119.86 0.00 -80.94 0.00 -213.59 0.00
1.1 11.3 -56.93 754.32 -4.61 61.04 -8.23 109.01 12.80 1166.36 -99.54 -144.67 -56.97 2090.72 -169.31 779.70
1.2 22.6 -37.39 1287.16 -3.03 104.16 -5.40 186.01 19.55 1988.60 -80.74 -289.24 -26.27 3565.93 -126.55 1288.09
1.3 33.9 -17.84 1599.17 -1.44 129.41 -2.58 231.09 30.23 2486.36 -62.35 -433.80 8.37 4446.04 -84.22 1525.87
1.4 45.2 1.70 1690.33 0.14 136.79 0.25 244.27 41.67 2711.19 -44.54 -578.37 43.76 4782.58 -42.45 1493.02
B=1.5 56.5 21.25 1560.66 1.72 126.30 3.07 225.53 57.29 2672.36 -27.64 -722.93 83.33 4584.85 -1.60 1189.55
1.6 67.8 40.80 1210.15 3.30 97.93 5.90 174.88 74.87 2398.69 -18.62 -867.50 124.87 3881.65 31.37 615.46
1.7 79.1 60.34 638.80 4.88 51.69 8.72 92.31 91.70 1881.16 -10.61 -1012.07 165.64 2663.97 63.33 -229.26
1.8 90.4 79.89 -153.39 6.47 -12.41 11.55 -22.17 107.61 1161.03 -4.34 -1156.63 205.51 973.07 93.56 -1344.60
1.9 101.7 99.44 -1166.42 8.05 -94.39 14.37 -168.56 124.34 349.11 0.15 -1445.12 246.19 -1080.26 122.00 -2874.49
C=2.0 113 119.00 -2401.27 9.63 -194.32 17.20 -347.00 146.74 -80.01 0.71 -2637.03 292.56 -3022.61 146.53 -5579.63
C'=2.0 113.0001 -106.40 -2401.27 -8.61 -194.32 -15.38 -347.00 10.56 -80.01 -143.92 -2637.03 -119.82 -3022.61 -274.30 -5579.63
2.1 125.3 -85.10 -1222.91 -6.89 -98.96 -12.30 -176.72 10.56 384.51 -120.64 -1423.77 -93.72 -1114.08 -224.93 -2922.37
2.2 137.6 -63.83 -307.10 -5.17 -24.85 -9.22 -44.38 10.56 1180.98 -101.08 -1158.95 -67.65 804.65 -179.30 -1535.28
2.3 149.9 -42.55 347.05 -3.44 28.09 -6.15 50.15 18.62 1858.49 -82.83 -1029.02 -33.53 2283.78 -134.98 -603.73
2.4 162.2 -21.28 739.54 -1.72 59.85 -3.08 106.87 28.70 2273.64 -63.84 -899.10 2.63 3179.90 -89.91 7.16
42
D = 2.5 174.5 0.00 870.37 0.00 70.43 0.00 125.78 44.87 2397.88 -44.87 -769.18 44.87 3464.47 -44.87 297.41
2.6 186.8 21.28 739.54 1.72 59.85 3.08 106.87 63.84 2273.64 -28.70 -899.10 89.91 3179.90 -2.63 7.16
2.7 199.1 42.55 347.05 3.44 28.09 6.15 50.15 82.83 1858.49 -18.62 -1029.02 134.98 2283.78 33.53 -603.73
2.8 211.4 63.83 -307.10 5.17 -24.85 9.22 -44.38 101.08 1180.98 -10.56 -1158.95 179.30 804.65 67.65 -1535.28
2.9 223.7 85.10 -1222.91 6.89 -98.96 12.30 -176.72 120.64 384.51 -10.56 -1423.77 224.93 -1114.08 93.72 -2922.37
E=3.0 236 106.40 -2401.27 8.61 -194.32 15.38 -347.00 143.92 -80.01 -10.56 -2637.03 274.30 -3022.61 119.82 -5579.63
E'=3.0 236.0001 -119.00 -2401.27 -9.63 -194.32 -17.20 -347.00 -0.71 -80.01 -146.74 -2637.03 -146.53 -3022.61 -292.56 -5579.63
3.1 247.3 -99.44 -1166.42 -8.05 -94.39 -14.37 -168.56 -0.15 349.11 -124.34 -1445.12 -122.00 -1080.26 -246.19 -2874.49
3.2 258.6 -79.89 -153.39 -6.47 -12.41 -11.55 -22.17 4.34 1161.03 -107.61 -1156.63 -93.56 973.07 -205.51 -1344.60
3.3 269.9 -60.34 638.80 -4.88 51.69 -8.72 92.31 10.61 1881.16 -91.70 -1012.07 -63.33 2663.97 -165.64 -229.26
3.4 281.2 -40.80 1210.15 -3.30 97.93 -5.90 174.88 18.62 2398.69 -74.87 -867.50 -31.37 3881.65 -124.87 615.46
F=3.5 292.5 -21.25 1560.66 -1.72 126.30 -3.07 225.53 27.64 2672.36 -57.29 -722.93 1.60 4584.85 -83.33 1189.55
3.6 303.8 -1.70 1690.33 -0.14 136.79 -0.25 244.27 44.54 2711.19 -41.67 -578.37 42.45 4782.58 -43.76 1493.02
3.7 315.1 17.84 1599.17 1.44 129.41 2.58 231.09 62.35 2486.36 -30.23 -433.80 84.22 4446.04 -8.37 1525.87
3.8 326.4 37.39 1287.16 3.03 104.16 5.40 186.01 80.74 1988.60 -19.55 -289.24 126.55 3565.93 26.27 1288.09
3.9 337.7 56.93 754.32 4.61 61.04 8.23 109.01 99.54 1166.36 -12.80 -144.67 169.31 2090.72 56.97 779.70
G=4.0 349 76.50 0.00 6.19 0.00 11.05 0.00 119.86 0.00 -12.80 0.00 213.59 0.00 80.94 0.00
4.3.4. Load combination (SVC II) results:
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000
-4000
-5000
-6370.74 -6370.74
-6000
-7000
Span Distances (ft)
210
140
70
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-70
-140
-210
-249.55
-280
-317.47 -336.58
-350
Span Distances (ft)
43
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination SVC II
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -76.50 0.00 -6.19 0.00 -11.05 0.00 12.80 0.00 -119.86 0.00 -77.11 0.00 -249.55 0.00
1.1 11.3 -56.93 754.32 -4.61 61.04 -8.23 109.01 12.80 1166.36 -99.54 -144.67 -53.13 2440.63 -199.17 736.29
1.2 22.6 -37.39 1287.16 -3.03 104.16 -5.40 186.01 19.55 1988.60 -80.74 -289.24 -20.40 4162.51 -150.78 1201.32
1.3 33.9 -17.84 1599.17 -1.44 129.41 -2.58 231.09 30.23 2486.36 -62.35 -433.80 17.44 5191.95 -102.92 1395.73
1.4 45.2 1.70 1690.33 0.14 136.79 0.25 244.27 41.67 2711.19 -44.54 -578.37 56.26 5595.94 -55.81 1319.51
B=1.5 56.5 21.25 1560.66 1.72 126.30 3.07 225.53 57.29 2672.36 -27.64 -722.93 100.51 5386.56 -9.89 972.67
1.6 67.8 40.80 1210.15 3.30 97.93 5.90 174.88 74.87 2398.69 -18.62 -867.50 147.33 4601.25 25.78 355.21
1.7 79.1 60.34 638.80 4.88 51.69 8.72 92.31 91.70 1881.16 -10.61 -1012.07 193.15 3228.31 60.15 -532.88
1.8 90.4 79.89 -153.39 6.47 -12.41 11.55 -22.17 107.61 1161.03 -4.34 -1156.63 237.80 1321.38 92.25 -1691.59
1.9 101.7 99.44 -1166.42 8.05 -94.39 14.37 -168.56 124.34 349.11 0.15 -1445.12 283.50 -975.53 122.04 -3308.02
C=2.0 113 119.00 -2401.27 9.63 -194.32 17.20 -347.00 146.74 -80.01 0.71 -2637.03 336.58 -3046.61 146.74 -6370.74
C'=2.0 113.0001 -106.40 -2401.27 -8.61 -194.32 -15.38 -347.00 10.56 -80.01 -143.92 -2637.03 -116.65 -3046.61 -317.47 -6370.74
2.1 125.3 -85.10 -1222.91 -6.89 -98.96 -12.30 -176.72 10.56 384.51 -120.64 -1423.77 -90.56 -998.73 -261.12 -3349.50
2.2 137.6 -63.83 -307.10 -5.17 -24.85 -9.22 -44.38 10.56 1180.98 -101.08 -1158.95 -64.48 1158.94 -209.62 -1882.96
2.3 149.9 -42.55 347.05 -3.44 28.09 -6.15 50.15 18.62 1858.49 -82.83 -1029.02 -27.94 2841.33 -159.83 -912.44
2.4 162.2 -21.28 739.54 -1.72 59.85 -3.08 106.87 28.70 2273.64 -63.84 -899.10 11.24 3861.99 -109.06 -262.57
44
D = 2.5 174.5 0.00 870.37 0.00 70.43 0.00 125.78 44.87 2397.88 -44.87 -769.18 58.33 4183.83 -58.33 66.65
2.6 186.8 21.28 739.54 1.72 59.85 3.08 106.87 63.84 2273.64 -28.70 -899.10 109.06 3861.99 -11.24 -262.57
2.7 199.1 42.55 347.05 3.44 28.09 6.15 50.15 82.83 1858.49 -18.62 -1029.02 159.83 2841.33 27.94 -912.44
2.8 211.4 63.83 -307.10 5.17 -24.85 9.22 -44.38 101.08 1180.98 -10.56 -1158.95 209.62 1158.94 64.48 -1882.96
2.9 223.7 85.10 -1222.91 6.89 -98.96 12.30 -176.72 120.64 384.51 -10.56 -1423.77 261.12 -998.73 90.56 -3349.50
E=3.0 236 106.40 -2401.27 8.61 -194.32 15.38 -347.00 143.92 -80.01 -10.56 -2637.03 317.47 -3046.61 116.65 -6370.74
E'=3.0 236.0001 -119.00 -2401.27 -9.63 -194.32 -17.20 -347.00 -0.71 -80.01 -146.74 -2637.03 -146.74 -3046.61 -336.58 -6370.74
3.1 247.3 -99.44 -1166.42 -8.05 -94.39 -14.37 -168.56 -0.15 349.11 -124.34 -1445.12 -122.04 -975.53 -283.50 -3308.02
3.2 258.6 -79.89 -153.39 -6.47 -12.41 -11.55 -22.17 4.34 1161.03 -107.61 -1156.63 -92.25 1321.38 -237.80 -1691.59
3.3 269.9 -60.34 638.80 -4.88 51.69 -8.72 92.31 10.61 1881.16 -91.70 -1012.07 -60.15 3228.31 -193.15 -532.88
3.4 281.2 -40.80 1210.15 -3.30 97.93 -5.90 174.88 18.62 2398.69 -74.87 -867.50 -25.78 4601.25 -147.33 355.21
F=3.5 292.5 -21.25 1560.66 -1.72 126.30 -3.07 225.53 27.64 2672.36 -57.29 -722.93 9.89 5386.56 -100.51 972.67
3.6 303.8 -1.70 1690.33 -0.14 136.79 -0.25 244.27 44.54 2711.19 -41.67 -578.37 55.81 5595.94 -56.26 1319.51
3.7 315.1 17.84 1599.17 1.44 129.41 2.58 231.09 62.35 2486.36 -30.23 -433.80 102.92 5191.95 -17.44 1395.73
3.8 326.4 37.39 1287.16 3.03 104.16 5.40 186.01 80.74 1988.60 -19.55 -289.24 150.78 4162.51 20.40 1201.32
3.9 337.7 56.93 754.32 4.61 61.04 8.23 109.01 99.54 1166.36 -12.80 -144.67 199.17 2440.63 53.13 736.29
G=4.0 349 76.50 0.00 6.19 0.00 11.05 0.00 119.86 0.00 -12.80 0.00 249.55 0.00 77.11 0.00
4.3.5. Load combination (SVC III) results:
2000
1000
Moment (kip-ft)
0
0 35 70 105 140 175 210 245 280 315 350
-1000
-2000
-3000
-4000
-5052.22 -5052.22
-5000
-6000
Span Distances (ft)
0
0 35 70 105 140 175 210 245 280 315 350
-60
-120
-180 -189.62
-240 -245.51 -263.21
-300
Span Distances (ft)
45
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination SVC III
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -76.50 0.00 -6.19 0.00 -11.05 0.00 12.80 0.00 -119.86 0.00 -83.50 0.00 -189.62 0.00
1.1 11.3 -56.93 754.32 -4.61 61.04 -8.23 109.01 12.80 1166.36 -99.54 -144.67 -59.53 1857.45 -149.40 808.63
1.2 22.6 -37.39 1287.16 -3.03 104.16 -5.40 186.01 19.55 1988.60 -80.74 -289.24 -30.18 3168.21 -110.41 1345.94
1.3 33.9 -17.84 1599.17 -1.44 129.41 -2.58 231.09 30.23 2486.36 -62.35 -433.80 2.32 3948.76 -71.75 1612.63
1.4 45.2 1.70 1690.33 0.14 136.79 0.25 244.27 41.67 2711.19 -44.54 -578.37 35.42 4240.34 -33.54 1608.69
B=1.5 56.5 21.25 1560.66 1.72 126.30 3.07 225.53 57.29 2672.36 -27.64 -722.93 71.87 4050.37 3.93 1334.14
1.6 67.8 40.80 1210.15 3.30 97.93 5.90 174.88 74.87 2398.69 -18.62 -867.50 109.89 3401.91 35.09 788.96
1.7 79.1 60.34 638.80 4.88 51.69 8.72 92.31 91.70 1881.16 -10.61 -1012.07 147.30 2287.73 65.45 -26.85
1.8 90.4 79.89 -153.39 6.47 -12.41 11.55 -22.17 107.61 1161.03 -4.34 -1156.63 183.99 740.86 94.43 -1113.27
1.9 101.7 99.44 -1166.42 8.05 -94.39 14.37 -168.56 124.34 349.11 0.15 -1445.12 221.32 -1150.08 121.97 -2585.46
C=2.0 113 119.00 -2401.27 9.63 -194.32 17.20 -347.00 146.74 -80.01 0.71 -2637.03 263.21 -3006.61 146.39 -5052.22
C'=2.0 113.0001 -106.40 -2401.27 -8.61 -194.32 -15.38 -347.00 10.56 -80.01 -143.92 -2637.03 -121.93 -3006.61 -245.51 -5052.22
2.1 125.3 -85.10 -1222.91 -6.89 -98.96 -12.30 -176.72 10.56 384.51 -120.64 -1423.77 -95.84 -1190.99 -200.80 -2637.61
2.2 137.6 -63.83 -307.10 -5.17 -24.85 -9.22 -44.38 10.56 1180.98 -101.08 -1158.95 -69.77 568.45 -159.08 -1303.49
2.3 149.9 -42.55 347.05 -3.44 28.09 -6.15 50.15 18.62 1858.49 -82.83 -1029.02 -37.25 1912.08 -118.41 -397.93
2.4 162.2 -21.28 739.54 -1.72 59.85 -3.08 106.87 28.70 2273.64 -63.84 -899.10 -3.11 2725.17 -77.14 186.98
46
D = 2.5 174.5 0.00 870.37 0.00 70.43 0.00 125.78 44.87 2397.88 -44.87 -769.18 35.89 2984.89 -35.89 451.24
2.6 186.8 21.28 739.54 1.72 59.85 3.08 106.87 63.84 2273.64 -28.70 -899.10 77.14 2725.17 3.11 186.98
2.7 199.1 42.55 347.05 3.44 28.09 6.15 50.15 82.83 1858.49 -18.62 -1029.02 118.41 1912.08 37.25 -397.93
2.8 211.4 63.83 -307.10 5.17 -24.85 9.22 -44.38 101.08 1180.98 -10.56 -1158.95 159.08 568.45 69.77 -1303.49
2.9 223.7 85.10 -1222.91 6.89 -98.96 12.30 -176.72 120.64 384.51 -10.56 -1423.77 200.80 -1190.99 95.84 -2637.61
E=3.0 236 106.40 -2401.27 8.61 -194.32 15.38 -347.00 143.92 -80.01 -10.56 -2637.03 245.51 -3006.61 121.93 -5052.22
E'=3.0 236.0001 -119.00 -2401.27 -9.63 -194.32 -17.20 -347.00 -0.71 -80.01 -146.74 -2637.03 -146.39 -3006.61 -263.21 -5052.22
3.1 247.3 -99.44 -1166.42 -8.05 -94.39 -14.37 -168.56 -0.15 349.11 -124.34 -1445.12 -121.97 -1150.08 -221.32 -2585.46
3.2 258.6 -79.89 -153.39 -6.47 -12.41 -11.55 -22.17 4.34 1161.03 -107.61 -1156.63 -94.43 740.86 -183.99 -1113.27
3.3 269.9 -60.34 638.80 -4.88 51.69 -8.72 92.31 10.61 1881.16 -91.70 -1012.07 -65.45 2287.73 -147.30 -26.85
3.4 281.2 -40.80 1210.15 -3.30 97.93 -5.90 174.88 18.62 2398.69 -74.87 -867.50 -35.09 3401.91 -109.89 788.96
F=3.5 292.5 -21.25 1560.66 -1.72 126.30 -3.07 225.53 27.64 2672.36 -57.29 -722.93 -3.93 4050.37 -71.87 1334.14
3.6 303.8 -1.70 1690.33 -0.14 136.79 -0.25 244.27 44.54 2711.19 -41.67 -578.37 33.54 4240.34 -35.42 1608.69
3.7 315.1 17.84 1599.17 1.44 129.41 2.58 231.09 62.35 2486.36 -30.23 -433.80 71.75 3948.76 -2.32 1612.63
3.8 326.4 37.39 1287.16 3.03 104.16 5.40 186.01 80.74 1988.60 -19.55 -289.24 110.41 3168.21 30.18 1345.94
3.9 337.7 56.93 754.32 4.61 61.04 8.23 109.01 99.54 1166.36 -12.80 -144.67 149.40 1857.45 59.53 808.63
G=4.0 349 76.50 0.00 6.19 0.00 11.05 0.00 119.86 0.00 -12.80 0.00 189.62 0.00 83.50 0.00
5. Pre-Stressed Bridge analysis cases results, internal forces envelopes and load combinations:
SAP structural analysis results are exported to excel so that moment and shear diagrams will be
clearer.
The tabulated values shows positive and negative extreme shear and bending moments at
each section. The figure plotted for the HS20 shear and moments multiplied by
(1+IM=1.33).
500
Moment (kip-ft)
0
0 35 70 105 140 175 210 245 280 315 350
-500
-1000 -688.70
-1500
-2500
Span Distances (ft)
47
Shear Envelopes (HS20)
125
100 100.20 99.69
87.99
75
50
25
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-25
-50
-75
-87.99
-100 -99.69 -100.20
-125
Span Distances (ft)
Unfactored Shear and Moments (HS20) Shear and Moments (HS20) * (1+IM=1.33)
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 7.26 0.00 -66.16 0.00 9.65 0.00 -87.99 0.00
1.1 10.9 11.24 625.39 -57.34 -79.17 14.95 831.77 -76.26 -105.30
1.2 21.8 18.02 1062.33 -48.72 -158.29 23.96 1412.90 -64.80 -210.52
1.3 32.7 26.22 1323.83 -40.40 -237.40 34.88 1760.69 -53.73 -315.74
1.4 43.6 34.77 1449.23 -32.49 -316.52 46.24 1927.48 -43.21 -420.97
B=1.5 54.5 42.98 1442.38 -25.10 -395.63 57.16 1918.36 -33.38 -526.19
1.6 65.4 50.75 1326.46 -18.32 -474.74 67.50 1764.19 -24.37 -631.41
1.7 76.3 57.98 1090.94 -12.27 -553.86 77.11 1450.95 -16.32 -736.63
1.8 87.2 64.56 765.27 -7.25 -632.97 85.86 1017.81 -9.65 -841.85
1.9 98.1 70.38 389.52 -3.64 -964.01 93.60 518.06 -4.84 -1282.13
C=2.0 109 75.34 194.36 -1.78 -1503.30 100.20 258.50 -2.37 -1999.39
C'=2.0 109.0001 6.92 194.36 -74.95 -1503.30 9.20 258.49 -99.69 -1999.39
2.1 122.1 9.26 366.72 -68.83 -898.05 12.31 487.73 -91.54 -1194.41
2.2 135.2 14.34 721.53 -61.64 -536.70 19.08 959.64 -81.98 -713.81
2.3 148.3 21.06 1060.24 -53.71 -517.82 28.01 1410.12 -71.44 -688.70
2.4 161.4 28.72 1277.70 -45.37 -517.82 38.19 1699.34 -60.34 -688.70
D = 2.5 174.5 36.93 1340.05 -36.93 -517.82 49.11 1782.26 -49.11 -688.70
2.6 187.6 45.37 1277.70 -28.72 -517.82 60.34 1699.34 -38.19 -688.70
2.7 200.7 53.71 1060.24 -21.06 -517.82 71.44 1410.12 -28.01 -688.70
2.8 213.8 61.64 721.53 -14.34 -536.70 81.98 959.64 -19.08 -713.81
2.9 226.9 68.83 366.72 -9.26 -898.05 91.54 487.73 -12.31 -1194.41
E=3.0 240 74.95 194.36 -6.92 -1503.30 99.69 258.49 -9.20 -1999.39
E'=3.0 240.0001 1.78 194.36 -75.34 -1503.30 2.37 258.50 -100.20 -1999.39
3.1 250.9 3.64 389.52 -70.38 -964.01 4.84 518.06 -93.60 -1282.13
3.2 261.8 7.25 765.27 -64.56 -632.97 9.65 1017.81 -85.86 -841.85
3.3 272.7 12.27 1090.94 -57.98 -553.86 16.32 1450.95 -77.11 -736.63
3.4 283.6 18.32 1326.46 -50.75 -474.74 24.37 1764.19 -67.50 -631.41
F=3.5 294.5 25.10 1442.38 -42.98 -395.63 33.38 1918.36 -57.16 -526.19
3.6 305.4 32.49 1449.23 -34.77 -316.52 43.21 1927.48 -46.24 -420.97
3.7 316.3 40.40 1323.83 -26.22 -237.40 53.73 1760.69 -34.88 -315.74
3.8 327.2 48.72 1062.33 -18.02 -158.29 64.80 1412.90 -23.96 -210.52
3.9 338.1 57.34 625.39 -11.24 -79.17 76.26 831.77 -14.95 -105.30
G=4.0 349 66.16 0.00 -7.26 0.00 87.99 0.00 -9.65 0.00
48
5.1.2. Truck moving load (2HS20):
The tabulated values shows positive and negative extreme shear forces and bending
moments at each section. The figure plotted for the 2-HS20 spaced at 50’-0” headway,
0
0 35 70 105 140 175 210 245 280 315 350
-400
-800 -626.33
-1200
-1600
-2000 -1993.32 -1993.32
-2400
Span Distances (ft)
20
0
-20 0 35 70 105 140 175 210 245 280 315 350
-40
-60
-80
-90.75
-100 -112.93
-116.32
-120
Span Distances (ft)
49
Unfactored Shear and Moments (2-HS20) Shear and Moments (2-HS20) * (1.33) * (0.90)
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 8.68 0.00 -75.82 0.00 10.39 0.00 -90.75 0.00
1.1 10.9 12.66 678.17 -62.18 -94.63 15.15 811.77 -74.43 -113.28
1.2 21.8 19.43 1096.91 -50.31 -189.19 23.26 1313.00 -60.22 -226.46
1.3 32.7 27.64 1342.02 -40.42 -283.75 33.09 1606.40 -48.38 -339.65
1.4 43.6 36.19 1452.63 -32.51 -378.32 43.31 1738.80 -38.91 -452.84
B=1.5 54.5 44.40 1443.40 -25.12 -472.88 53.14 1727.75 -30.06 -566.03
1.6 65.4 52.17 1330.52 -18.34 -567.44 62.45 1592.63 -21.95 -679.22
1.7 76.3 59.40 1105.27 -12.29 -662.00 71.10 1323.01 -14.71 -792.41
1.8 87.2 69.33 770.19 -7.27 -756.56 82.99 921.91 -8.70 -905.60
1.9 98.1 81.31 391.35 -3.66 -1103.04 97.33 468.45 -4.38 -1320.34
C=2.0 109 94.34 196.40 -1.80 -1665.26 112.93 235.09 -2.16 -1993.32
C'=2.0 109.0001 6.99 196.39 -97.18 -1665.26 8.37 235.08 -116.32 -1993.32
2.1 122.1 9.33 367.80 -83.37 -904.78 11.17 440.26 -99.79 -1083.02
2.2 135.2 14.42 724.45 -69.39 -542.26 17.25 867.17 -83.06 -649.09
2.3 148.3 21.14 1107.18 -56.25 -523.25 25.30 1325.29 -67.33 -626.33
2.4 161.4 28.79 1312.43 -45.54 -523.25 34.46 1570.98 -54.51 -626.33
D = 2.5 174.5 37.00 1350.11 -37.00 -523.25 44.29 1616.08 -44.29 -626.33
2.6 187.6 45.54 1312.43 -28.79 -523.25 54.51 1570.98 -34.46 -626.33
2.7 200.7 56.25 1107.18 -21.14 -523.25 67.33 1325.29 -25.30 -626.33
2.8 213.8 69.39 724.45 -14.42 -542.26 83.06 867.17 -17.25 -649.09
2.9 226.9 83.37 367.80 -9.33 -904.78 99.79 440.26 -11.17 -1083.02
E=3.0 240 97.18 196.39 -6.99 -1665.26 116.32 235.08 -8.37 -1993.32
E'=3.0 240.0001 1.80 196.40 -94.34 -1665.26 2.16 235.09 -112.93 -1993.32
3.1 250.9 3.66 391.35 -81.31 -1103.04 4.38 468.45 -97.33 -1320.34
3.2 261.8 7.27 770.19 -69.33 -756.56 8.70 921.91 -82.99 -905.60
3.3 272.7 12.29 1105.27 -59.40 -662.00 14.71 1323.01 -71.10 -792.41
3.4 283.6 18.34 1330.52 -52.17 -567.44 21.95 1592.63 -62.45 -679.22
F=3.5 294.5 25.12 1443.40 -44.40 -472.88 30.06 1727.75 -53.14 -566.03
3.6 305.4 32.51 1452.63 -36.19 -378.32 38.91 1738.80 -43.31 -452.84
3.7 316.3 40.42 1342.02 -27.64 -283.75 48.38 1606.40 -33.09 -339.65
3.8 327.2 50.31 1096.91 -19.43 -189.19 60.22 1313.00 -23.26 -226.46
3.9 338.1 62.18 678.17 -12.66 -94.63 74.43 811.77 -15.15 -113.28
G=4.0 349 75.82 0.00 -8.68 0.00 90.75 0.00 -10.39 0.00
50
5.1.3. Tandem moving load (TML):
The tabulated values shows positive and negative extreme shear and bending moments at
each section. The figure plotted for the TML shear and moments multiplied by
(1+IM=1.33).
1200
800
Moments (kip-ft)
400
0
0 35 70 105 140 175 210 245 280 315 350
-400
-800 -494.38
-1200
-1426.75 -1426.75
-1600
Span Distances (ft)
40
Shear Forces (kip)
20
0
0 35 70 105 140 175 210 245 280 315 350
-20
-40
-60
-66.68 -72.36 -72.64
-80
Span Distances (ft)
51
Unfactored Shear and Moments (TML) Shear and Moments (TML) * (1+IM=1.33)
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 5.15 0.00 -50.13 0.00 6.85 0.00 -66.68 0.00
1.1 10.9 10.23 479.18 -43.93 -56.20 13.61 637.31 -58.43 -74.74
1.2 21.8 16.38 824.71 -37.82 -112.35 21.79 1096.86 -50.30 -149.42
1.3 32.7 22.40 1042.25 -31.87 -168.50 29.80 1386.20 -42.39 -224.10
1.4 43.6 28.22 1140.28 -26.15 -224.65 37.53 1516.57 -34.78 -298.79
B=1.5 54.5 33.75 1136.34 -20.74 -280.80 44.88 1511.33 -27.59 -373.47
1.6 65.4 38.92 1044.99 -15.71 -336.96 51.77 1389.84 -20.90 -448.15
1.7 76.3 43.67 873.45 -11.14 -393.11 58.09 1161.69 -14.82 -522.83
1.8 87.2 47.92 642.11 -7.10 -449.26 63.73 854.01 -9.44 -597.52
1.9 98.1 51.59 374.58 -3.65 -690.11 68.62 498.20 -4.86 -917.85
C=2.0 109 54.62 139.53 -1.28 -1072.74 72.64 185.57 -1.70 -1426.75
C'=2.0 109.0001 4.97 139.52 -54.41 -1072.74 6.60 185.57 -72.36 -1426.75
2.1 122.1 8.06 367.54 -50.62 -644.55 10.72 488.83 -67.32 -857.25
2.2 135.2 12.47 614.88 -45.97 -386.27 16.59 817.78 -61.14 -513.74
2.3 148.3 17.59 854.99 -40.67 -371.71 23.40 1137.14 -54.10 -494.38
2.4 161.4 23.20 1013.28 -34.97 -371.71 30.86 1347.67 -46.50 -494.38
D = 2.5 174.5 29.07 1064.13 -29.07 -371.71 38.66 1415.30 -38.66 -494.38
2.6 187.6 34.97 1013.28 -23.20 -371.71 46.50 1347.67 -30.86 -494.38
2.7 200.7 40.67 854.99 -17.59 -371.71 54.10 1137.14 -23.40 -494.38
2.8 213.8 45.97 614.88 -12.47 -386.27 61.14 817.78 -16.59 -513.74
2.9 226.9 50.62 367.54 -8.06 -644.55 67.32 488.83 -10.72 -857.25
E=3.0 240 54.41 139.52 -4.97 -1072.74 72.36 185.57 -6.60 -1426.75
E'=3.0 240.0001 1.28 139.53 -54.62 -1072.74 1.70 185.57 -72.64 -1426.75
3.1 250.9 3.65 374.58 -51.59 -690.11 4.86 498.20 -68.62 -917.85
3.2 261.8 7.10 642.11 -47.92 -449.26 9.44 854.01 -63.73 -597.52
3.3 272.7 11.14 873.45 -43.67 -393.11 14.82 1161.69 -58.09 -522.83
3.4 283.6 15.71 1044.99 -38.92 -336.96 20.90 1389.84 -51.77 -448.15
F=3.5 294.5 20.74 1136.34 -33.75 -280.80 27.59 1511.33 -44.88 -373.47
3.6 305.4 26.15 1140.28 -28.22 -224.65 34.78 1516.57 -37.53 -298.79
3.7 316.3 31.87 1042.25 -22.40 -168.50 42.39 1386.20 -29.80 -224.10
3.8 327.2 37.82 824.71 -16.38 -112.35 50.30 1096.86 -21.79 -149.42
3.9 338.1 43.93 479.18 -10.23 -56.20 58.43 637.31 -13.61 -74.74
G=4.0 349 50.13 0.00 -5.15 0.00 66.68 0.00 -6.85 0.00
52
5.1.4. Lane moving load (LL):
In this section, moments and shear forces are plotted for each case of loading, then the
1000
800
600
400
200
Moment (kip-ft)
0
-200 0 35 70 105 140 175 210 245 280 315 350
-400
-600
-800
-1000
-1200
Span Distances (ft)
60
45
30
15
Shear (kip)
0
0 35 70 105 140 175 210 245 280 315 350
-15
-30
-45
-60
Span Distances (ft)
53
Moment Envelopes (Lane Load-LL)
1000
784.23
800 780.93 780.93
600
400
200
Moment (kip-ft)
0
0 35 70 105 140 175 210 245 280 315 350
-200
-400
-600
-800
-1000 -1054.93 -1054.93
-1200
Span Distances (ft)
0
0 35 70 105 140 175 210 245 280 315 350
-10
-20
-30 -31.77
-40
-46.45 -44.56
-50
Span Distances (ft)
54
LL-SPAN(1+2) LL-SPAN(1+3) LL-SPAN(2) LL-SPAN(2+3) Shear and Moment Envelopes
Point Loc.
V M V M V M V M V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -25.20 0.00 -31.77 0.00 5.40 0.00 4.23 0.00 5.40 0.00 -31.77 0.00
1.1 10.9 -18.23 236.68 -24.79 308.26 5.40 -58.86 4.23 -46.15 5.40 308.26 -24.79 -58.86
1.2 21.8 -11.25 397.32 -17.82 540.49 5.40 -117.73 4.23 -92.29 5.40 540.49 -17.82 -117.73
1.3 32.7 -4.27 481.92 -10.84 696.67 5.40 -176.59 4.23 -138.44 5.40 696.67 -10.84 -176.59
1.4 43.6 2.70 490.49 -3.87 776.82 5.40 -235.46 4.23 -184.58 5.40 776.82 -3.87 -235.46
B=1.5 54.5 9.68 423.01 3.11 780.93 5.40 -294.32 4.23 -230.73 9.68 780.93 3.11 -294.32
1.6 65.4 16.65 279.50 10.09 709.00 5.40 -353.19 4.23 -276.88 16.65 709.00 4.23 -353.19
1.7 76.3 23.63 59.95 17.06 561.04 5.40 -412.05 4.23 -323.02 23.63 561.04 4.23 -412.05
1.8 87.2 30.61 -235.64 24.04 337.03 5.40 -470.92 4.23 -369.17 30.61 337.03 4.23 -470.92
1.9 98.1 37.58 -607.27 31.02 36.99 5.40 -529.78 4.23 -415.31 37.58 36.99 4.23 -607.27
C=2.0 109 44.56 -1054.93 37.99 -339.09 5.40 -588.65 4.23 -461.46 44.56 -339.09 4.23 -1054.93
C'=2.0 109.0001 -46.45 -1054.93 0.00 -339.09 -41.92 -588.65 -37.39 -461.46 0.00 -339.09 -46.45 -1054.93
2.1 122.1 -38.07 -501.35 0.00 -339.09 -33.54 -94.41 -29.01 -26.57 0.00 -26.57 -38.07 -501.35
2.2 135.2 -29.68 -57.59 0.00 -339.09 -25.15 290.00 -20.62 298.49 0.00 298.49 -29.68 -339.09
2.3 148.3 -21.30 276.33 0.00 -339.09 -16.77 564.57 -12.24 513.72 0.00 564.57 -21.30 -339.09
2.4 161.4 -12.91 500.42 0.00 -339.09 -8.38 729.32 -3.85 619.12 0.00 729.32 -12.91 -339.09
55
D = 2.5 174.5 -4.53 614.68 0.00 -339.09 0.00 784.23 4.53 614.68 4.53 784.23 -4.53 -339.09
2.6 187.6 3.85 619.12 0.00 -339.09 8.38 729.32 12.91 500.42 12.91 729.32 0.00 -339.09
2.7 200.7 12.24 513.72 0.00 -339.09 16.77 564.57 21.30 276.33 21.30 564.57 0.00 -339.09
2.8 213.8 20.62 298.49 0.00 -339.09 25.15 290.00 29.68 -57.59 29.68 298.49 0.00 -339.09
2.9 226.9 29.01 -26.57 0.00 -339.09 33.54 -94.41 38.07 -501.35 38.07 -26.57 0.00 -501.35
E=3.0 240 37.39 -461.46 0.00 -339.09 41.92 -588.65 46.45 -1054.93 46.45 -339.09 0.00 -1054.93
E'=3.0 240.0001 -4.23 -461.46 -37.99 -339.09 -5.40 -588.65 -44.56 -1054.93 -4.23 -339.09 -44.56 -1054.93
3.1 250.9 -4.23 -415.31 -31.02 36.99 -5.40 -529.78 -37.58 -607.27 -4.23 36.99 -37.58 -607.27
3.2 261.8 -4.23 -369.17 -24.04 337.03 -5.40 -470.92 -30.61 -235.64 -4.23 337.03 -30.61 -470.92
3.3 272.7 -4.23 -323.02 -17.06 561.04 -5.40 -412.05 -23.63 59.95 -4.23 561.04 -23.63 -412.05
3.4 283.6 -4.23 -276.88 -10.09 709.00 -5.40 -353.19 -16.65 279.50 -4.23 709.00 -16.65 -353.19
F=3.5 294.5 -4.23 -230.73 -3.11 780.93 -5.40 -294.32 -9.68 423.01 -3.11 780.93 -9.68 -294.32
3.6 305.4 -4.23 -184.58 3.87 776.82 -5.40 -235.46 -2.70 490.49 3.87 776.82 -5.40 -235.46
3.7 316.3 -4.23 -138.44 10.84 696.67 -5.40 -176.59 4.27 481.92 10.84 696.67 -5.40 -176.59
3.8 327.2 -4.23 -92.29 17.82 540.49 -5.40 -117.73 11.25 397.32 17.82 540.49 -5.40 -117.73
3.9 338.1 -4.23 -46.15 24.79 308.26 -5.40 -58.86 18.23 236.68 24.79 308.26 -5.40 -58.86
G=4.0 349 -4.23 0.00 31.77 0.00 -5.40 0.00 25.20 0.00 31.77 0.00 -5.40 0.00
5.1.5. Dead loads (DC1, DC2 and DW):
In this section, moments and shear forces are plotted for each dead load case, and no
envelopes are generate because dead loads are permanent loads. It is important to note that
pre-stressed bridge acts as three simply supported spans under load DC1 while it acts as
4800
4200
4569.12
3600
3000
Moment (kip-ft)
1800
1200
600 211.47 173.88 211.47
0
0 35 70 105 140 175 210 245 280 315 350
-600
Span Distances (ft) -362.40
150
139.52
125 116.09
100 116.09
75
50
25
Shear (kip)
16.38 10.30
0
-25 0 35 70 105 140 175 210 245 280 315 350
-16.95
-50
-75
-100 -116.09
-116.09
-125
-139.52
-150
Span Distances (ft)
56
DC1 DC2 DW
Point Loc.
V M V M V M
A=1.0 0 -116.09 0.00 -9.27 0.00 -10.30 0.00
1.1 10.9 -92.87 1138.79 -6.82 87.68 -7.58 97.42
1.2 21.8 -69.65 2024.52 -4.37 148.63 -4.85 165.14
1.3 32.7 -46.43 2657.19 -1.91 182.84 -2.13 203.16
1.4 43.6 -23.22 3036.78 0.54 190.32 0.60 211.47
B=1.5 54.5 0.00 3163.32 2.99 171.07 3.33 190.08
1.6 65.4 23.22 3036.78 5.45 125.09 6.05 138.99
1.7 76.3 46.43 2657.19 7.90 52.38 8.78 58.20
1.8 87.2 69.65 2024.52 10.35 -47.07 11.50 -52.30
1.9 98.1 92.87 1138.79 12.80 -173.25 14.23 -192.50
C=2.0 109 116.09 0.00 15.26 -326.16 16.95 -362.40
C'=2.0 109.0001 -139.52 0.00 -14.74 -326.16 -16.38 -362.40
2.1 122.1 -111.61 1644.88 -11.79 -152.40 -13.10 -169.34
2.2 135.2 -83.71 2924.23 -8.84 -17.26 -9.83 -19.18
2.3 148.3 -55.81 3838.06 -5.90 79.27 -6.55 88.08
2.4 161.4 -27.90 4386.35 -2.95 137.19 -3.28 152.43
D = 2.5 174.5 0.00 4569.12 0.00 156.49 0.00 173.88
2.6 187.6 27.90 4386.35 2.95 137.19 3.28 152.43
2.7 200.7 55.81 3838.06 5.90 79.27 6.55 88.08
2.8 213.8 83.71 2924.23 8.84 -17.26 9.83 -19.18
2.9 226.9 111.61 1644.88 11.79 -152.40 13.10 -169.34
E=3.0 240 139.52 0.00 14.74 -326.16 16.38 -362.40
E'=3.0 240.0001 -116.09 0.00 -15.26 -326.16 -16.95 -362.40
3.1 250.9 -92.87 1138.79 -12.80 -173.25 -14.23 -192.50
3.2 261.8 -69.65 2024.52 -10.35 -47.07 -11.50 -52.30
3.3 272.7 -46.43 2657.19 -7.90 52.38 -8.78 58.20
3.4 283.6 -23.22 3036.78 -5.45 125.09 -6.05 138.99
F=3.5 294.5 0.00 3163.32 -2.99 171.07 -3.33 190.08
3.6 305.4 23.22 3036.78 -0.54 190.32 -0.60 211.47
3.7 316.3 46.43 2657.19 1.91 182.84 2.13 203.16
3.8 327.2 69.65 2024.52 4.37 148.63 4.85 165.14
3.9 338.1 92.87 1138.79 6.82 87.68 7.58 97.42
G=4.0 349 116.09 0.00 9.27 0.00 10.30 0.00
57
5.2. Pre-Stressed Bridge live loads envelopes:
Bending moments and shear forces envelopes for (HS-20 * 1.33 + Lane Load), (0.90
*1.33* 2-HS20 + 0.90 * Lane Load) and (TML*1.33 + Lane Load) are generated in excel. The
live load internal forces envelopes at each section are plotted from theses tabulated values.
For example, the positive envelope at each section is the maximum of (HS-20 * 1.33 + Lane
Load), (0.90 * 1.33 * 2-HS20 + 0.90 * Lane Load) or (TML*1.33 + Lane Load) at this section.
0
-500 0 35 70 105 140 175 210 245 280 315 350
-1000
-1500
-1027.80
-2000
-2500
-3054.33 -3054.33
-3000
-3500
Span Distances (ft)
25
0
-25 0 35 70 105 140 175 210 245 280 315 350
-50
-75
-100
-125 -119.76
-153.03
-150 -158.13
-175
Span Distances (ft)
58
Shear and Moments (HS20) * (1+IM=1.33) Shear and Moments (0.90)*(2-HS20) *(1.33) Shear and Moments (TML) * (1+IM=1.33) Shear and Moments (Lane Loads) Moving Loads Envelopes
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 9.65 0.00 -87.99 0.00 10.39 0.00 -90.75 0.00 6.85 0.00 -66.68 0.00 5.40 0.00 -31.77 0.00 15.25 0.00 -119.76 0.00
1.1 10.9 14.95 831.77 -76.26 -105.30 15.15 811.77 -74.43 -113.28 13.61 637.31 -58.43 -74.74 5.40 308.26 -24.79 -58.86 20.35 1140.04 -101.06 -166.25
1.2 21.8 23.96 1412.90 -64.80 -210.52 23.26 1313.00 -60.22 -226.46 21.79 1096.86 -50.30 -149.42 5.40 540.49 -17.82 -117.73 29.36 1953.38 -82.61 -332.42
1.3 32.7 34.88 1760.69 -53.73 -315.74 33.09 1606.40 -48.38 -339.65 29.80 1386.20 -42.39 -224.10 5.40 696.67 -10.84 -176.59 40.28 2457.37 -64.57 -498.59
1.4 43.6 46.24 1927.48 -43.21 -420.97 43.31 1738.80 -38.91 -452.84 37.53 1516.57 -34.78 -298.79 5.40 776.82 -3.87 -235.46 51.64 2704.30 -47.08 -664.76
B=1.5 54.5 57.16 1918.36 -33.38 -526.19 53.14 1727.75 -30.06 -566.03 44.88 1511.33 -27.59 -373.47 9.68 780.93 3.11 -294.32 66.84 2699.30 -30.27 -830.92
1.6 65.4 67.50 1764.19 -24.37 -631.41 62.45 1592.63 -21.95 -679.22 51.77 1389.84 -20.90 -448.15 16.65 709.00 4.23 -353.19 84.15 2473.19 -20.13 -997.09
1.7 76.3 77.11 1450.95 -16.32 -736.63 71.10 1323.01 -14.71 -792.41 58.09 1161.69 -14.82 -522.83 23.63 561.04 4.23 -412.05 100.74 2011.98 -12.09 -1163.26
1.8 87.2 85.86 1017.81 -9.65 -841.85 82.99 921.91 -8.70 -905.60 63.73 854.01 -9.44 -597.52 30.61 337.03 4.23 -470.92 116.47 1354.84 -5.41 -1329.43
1.9 98.1 93.60 518.06 -4.84 -1282.13 97.33 468.45 -4.38 -1320.34 68.62 498.20 -4.86 -917.85 37.58 36.99 4.23 -607.27 131.18 555.05 -0.62 -1889.40
C=2.0 109 100.20 258.50 -2.37 -1999.39 112.93 235.09 -2.16 -1993.32 72.64 185.57 -1.70 -1426.75 44.56 -339.09 4.23 -1054.93 153.03 -70.10 1.65 -3054.33
C'=2.0 109.0001 9.20 258.49 -99.69 -1999.39 8.37 235.08 -116.32 -1993.32 6.60 185.57 -72.36 -1426.75 0.00 -339.09 -46.45 -1054.93 9.20 -70.10 -158.13 -3054.33
2.1 122.1 12.31 487.73 -91.54 -1194.41 11.17 440.26 -99.79 -1083.02 10.72 488.83 -67.32 -857.25 0.00 -26.57 -38.07 -501.35 12.31 462.26 -134.05 -1695.76
2.2 135.2 19.08 959.64 -81.98 -713.81 17.25 867.17 -83.06 -649.09 16.59 817.78 -61.14 -513.74 0.00 298.49 -29.68 -339.09 19.08 1258.13 -111.66 -1052.90
2.3 148.3 28.01 1410.12 -71.44 -688.70 25.30 1325.29 -67.33 -626.33 23.40 1137.14 -54.10 -494.38 0.00 564.57 -21.30 -339.09 28.01 1974.69 -92.73 -1027.80
2.4 161.4 38.19 1699.34 -60.34 -688.70 34.46 1570.98 -54.51 -626.33 30.86 1347.67 -46.50 -494.38 0.00 729.32 -12.91 -339.09 38.19 2428.66 -73.25 -1027.80
59
D = 2.5 174.5 49.11 1782.26 -49.11 -688.70 44.29 1616.08 -44.29 -626.33 38.66 1415.30 -38.66 -494.38 4.53 784.23 -4.53 -339.09 53.64 2566.50 -53.64 -1027.80
2.6 187.6 60.34 1699.34 -38.19 -688.70 54.51 1570.98 -34.46 -626.33 46.50 1347.67 -30.86 -494.38 12.91 729.32 0.00 -339.09 73.25 2428.66 -38.19 -1027.80
2.7 200.7 71.44 1410.12 -28.01 -688.70 67.33 1325.29 -25.30 -626.33 54.10 1137.14 -23.40 -494.38 21.30 564.57 0.00 -339.09 92.73 1974.69 -28.01 -1027.80
2.8 213.8 81.98 959.64 -19.08 -713.81 83.06 867.17 -17.25 -649.09 61.14 817.78 -16.59 -513.74 29.68 298.49 0.00 -339.09 111.66 1258.13 -19.08 -1052.90
2.9 226.9 91.54 487.73 -12.31 -1194.41 99.79 440.26 -11.17 -1083.02 67.32 488.83 -10.72 -857.25 38.07 -26.57 0.00 -501.35 134.05 462.26 -12.31 -1695.76
E=3.0 240 99.69 258.49 -9.20 -1999.39 116.32 235.08 -8.37 -1993.32 72.36 185.57 -6.60 -1426.75 46.45 -339.09 0.00 -1054.93 158.13 -70.10 -9.20 -3054.33
E'=3.0 240.0001 2.37 258.50 -100.20 -1999.39 2.16 235.09 -112.93 -1993.32 1.70 185.57 -72.64 -1426.75 -4.23 -339.09 -44.56 -1054.93 -1.65 -70.10 -153.03 -3054.33
3.1 250.9 4.84 518.06 -93.60 -1282.13 4.38 468.45 -97.33 -1320.34 4.86 498.20 -68.62 -917.85 -4.23 36.99 -37.58 -607.27 0.62 555.05 -131.18 -1889.40
3.2 261.8 9.65 1017.81 -85.86 -841.85 8.70 921.91 -82.99 -905.60 9.44 854.01 -63.73 -597.52 -4.23 337.03 -30.61 -470.92 5.41 1354.84 -116.47 -1329.43
3.3 272.7 16.32 1450.95 -77.11 -736.63 14.71 1323.01 -71.10 -792.41 14.82 1161.69 -58.09 -522.83 -4.23 561.04 -23.63 -412.05 12.09 2011.98 -100.74 -1163.26
3.4 283.6 24.37 1764.19 -67.50 -631.41 21.95 1592.63 -62.45 -679.22 20.90 1389.84 -51.77 -448.15 -4.23 709.00 -16.65 -353.19 20.13 2473.19 -84.15 -997.09
F=3.5 294.5 33.38 1918.36 -57.16 -526.19 30.06 1727.75 -53.14 -566.03 27.59 1511.33 -44.88 -373.47 -3.11 780.93 -9.68 -294.32 30.27 2699.30 -66.84 -830.92
3.6 305.4 43.21 1927.48 -46.24 -420.97 38.91 1738.80 -43.31 -452.84 34.78 1516.57 -37.53 -298.79 3.87 776.82 -5.40 -235.46 47.08 2704.30 -51.64 -664.76
3.7 316.3 53.73 1760.69 -34.88 -315.74 48.38 1606.40 -33.09 -339.65 42.39 1386.20 -29.80 -224.10 10.84 696.67 -5.40 -176.59 64.57 2457.37 -40.28 -498.59
3.8 327.2 64.80 1412.90 -23.96 -210.52 60.22 1313.00 -23.26 -226.46 50.30 1096.86 -21.79 -149.42 17.82 540.49 -5.40 -117.73 82.61 1953.38 -29.36 -332.42
3.9 338.1 76.26 831.77 -14.95 -105.30 74.43 811.77 -15.15 -113.28 58.43 637.31 -13.61 -74.74 24.79 308.26 -5.40 -58.86 101.06 1140.04 -20.35 -166.25
G=4.0 349 87.99 0.00 -9.65 0.00 90.75 0.00 -10.39 0.00 66.68 0.00 -6.85 0.00 31.77 0.00 -5.40 0.00 119.76 0.00 -15.25 0.00
5.3. Pre-Stressed Bridge factored design envelopes:
In this section, the dead loads (DC1, DC2 and DW) internal forces calculated in section
- Using these load combinations with the tabulated values in Excel gives the following
4000
3000
2000
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000
-4000
-5000 -6296.37 -6296.37
-6000
-7000
Span Distances (ft)
60
Shear Envelopes Load Combination (STR I-a)
500
457.40 494.10
381.72
400
300
200
100
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-100
-200
-300
-400 -381.72
-494.10 -457.40
-500
Span Distances (ft)
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination STR I-a
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -116.09 0.00 -9.27 0.00 -10.30 0.00 15.25 0.00 -119.76 0.00 -145.46 0.00 -381.72 0.00
1.1 10.9 -92.87 1138.79 -6.82 87.68 -7.58 97.42 20.35 1140.04 -101.06 -166.25 -100.36 3674.29 -312.82 1388.28
1.2 21.8 -69.65 2024.52 -4.37 148.63 -4.85 165.14 29.36 1953.38 -82.61 -332.42 -48.41 6382.57 -244.37 2382.41
1.3 32.7 -46.43 2657.19 -1.91 182.84 -2.13 203.16 40.28 2457.37 -64.57 -498.59 6.86 8155.16 -176.63 2982.24
1.4 43.6 -23.22 3036.78 0.54 190.32 0.60 211.47 51.64 2704.30 -47.08 -664.76 62.93 9083.62 -109.83 3187.77
B=1.5 54.5 0.00 3163.32 2.99 171.07 3.33 190.08 66.84 2699.30 -30.27 -830.92 125.70 9176.88 -44.24 2998.99
1.6 65.4 23.22 3036.78 5.45 125.09 6.05 138.99 84.15 2473.19 -20.13 -997.09 192.17 8488.91 9.67 2415.92
1.7 76.3 46.43 2657.19 7.90 52.38 8.78 58.20 100.74 2011.98 -12.09 -1163.26 257.38 6995.22 59.92 1438.55
1.8 87.2 69.65 2024.52 10.35 -47.07 11.50 -52.30 116.47 1354.84 -5.41 -1329.43 321.07 4764.33 107.78 66.87
1.9 98.1 92.87 1138.79 12.80 -173.25 14.23 -192.50 131.18 555.05 -0.62 -1889.40 383.00 1889.52 152.34 -2388.26
C=2.0 109 116.09 0.00 15.26 -326.16 16.95 -362.40 153.03 -70.10 1.65 -3054.33 457.40 -1073.97 192.50 -6296.37
C'=2.0 109.0001 -139.52 0.00 -14.74 -326.16 -16.38 -362.40 9.20 -70.10 -158.13 -3054.33 -201.28 -1073.98 -494.10 -6296.37
2.1 122.1 -111.61 1644.88 -11.79 -152.40 -13.10 -169.34 12.31 462.26 -134.05 -1695.76 -152.36 2420.54 -408.49 -1355.99
2.2 135.2 -83.71 2924.23 -8.84 -17.26 -9.83 -19.18 19.08 1258.13 -111.66 -1052.90 -97.04 5806.67 -325.84 1762.37
2.3 148.3 -55.81 3838.06 -5.90 79.27 -6.55 88.08 28.01 1974.69 -92.73 -1027.80 -37.93 8484.48 -249.24 3230.13
2.4 161.4 -27.90 4386.35 -2.95 137.19 -3.28 152.43 38.19 2428.66 -73.25 -1027.80 23.36 10133.22 -171.66 4084.43
D = 2.5 174.5 0.00 4569.12 0.00 156.49 0.00 173.88 53.64 2566.50 -53.64 -1027.80 93.87 10659.20 -93.87 4369.19
2.6 187.6 27.90 4386.35 2.95 137.19 3.28 152.43 73.25 2428.66 -38.19 -1027.80 171.66 10133.22 -23.36 4084.43
2.7 200.7 55.81 3838.06 5.90 79.27 6.55 88.08 92.73 1974.69 -28.01 -1027.80 249.24 8484.48 37.93 3230.13
2.8 213.8 83.71 2924.23 8.84 -17.26 9.83 -19.18 111.66 1258.13 -19.08 -1052.90 325.84 5806.67 97.04 1762.37
2.9 226.9 111.61 1644.88 11.79 -152.40 13.10 -169.34 134.05 462.26 -12.31 -1695.76 408.49 2420.54 152.36 -1355.99
E=3.0 240 139.52 0.00 14.74 -326.16 16.38 -362.40 158.13 -70.10 -9.20 -3054.33 494.10 -1073.98 201.28 -6296.37
E'=3.0 240.0001 -116.09 0.00 -15.26 -326.16 -16.95 -362.40 -1.65 -70.10 -153.03 -3054.33 -192.50 -1073.97 -457.40 -6296.37
3.1 250.9 -92.87 1138.79 -12.80 -173.25 -14.23 -192.50 0.62 555.05 -131.18 -1889.40 -152.34 1889.52 -383.00 -2388.26
3.2 261.8 -69.65 2024.52 -10.35 -47.07 -11.50 -52.30 5.41 1354.84 -116.47 -1329.43 -107.78 4764.33 -321.07 66.87
3.3 272.7 -46.43 2657.19 -7.90 52.38 -8.78 58.20 12.09 2011.98 -100.74 -1163.26 -59.92 6995.22 -257.38 1438.55
3.4 283.6 -23.22 3036.78 -5.45 125.09 -6.05 138.99 20.13 2473.19 -84.15 -997.09 -9.67 8488.91 -192.17 2415.92
F=3.5 294.5 0.00 3163.32 -2.99 171.07 -3.33 190.08 30.27 2699.30 -66.84 -830.92 44.24 9176.88 -125.70 2998.99
3.6 305.4 23.22 3036.78 -0.54 190.32 -0.60 211.47 47.08 2704.30 -51.64 -664.76 109.83 9083.62 -62.93 3187.77
3.7 316.3 46.43 2657.19 1.91 182.84 2.13 203.16 64.57 2457.37 -40.28 -498.59 176.63 8155.16 -6.86 2982.24
3.8 327.2 69.65 2024.52 4.37 148.63 4.85 165.14 82.61 1953.38 -29.36 -332.42 244.37 6382.57 48.41 2382.41
3.9 338.1 92.87 1138.79 6.82 87.68 7.58 97.42 101.06 1140.04 -20.35 -166.25 312.82 3674.29 100.36 1388.28
G=4.0 349 116.09 0.00 9.27 0.00 10.30 0.00 119.76 0.00 -15.25 0.00 381.72 0.00 145.46 0.00
61
5.3.2. Load combination (STR I-b) results:
2000
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000
-4000
-5000 -5874.17 -5874.17
-6000
-7000
Span Distances (ft)
0
0 35 70 105 140 175 210 245 280 315 350
-100
-200
-300
-329.09
-400 -426.19
-397.02
-500
Span Distances (ft)
62
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination STR I-b
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -116.09 0.00 -9.27 0.00 -10.30 0.00 15.25 0.00 -119.76 0.00 -92.83 0.00 -329.09 0.00
1.1 10.9 -92.87 1138.79 -6.82 87.68 -7.58 97.42 20.35 1140.04 -101.06 -166.25 -59.03 3162.21 -271.49 876.21
1.2 21.8 -69.65 2024.52 -4.37 148.63 -4.85 165.14 29.36 1953.38 -82.61 -332.42 -18.38 5481.60 -214.34 1481.44
1.3 32.7 -46.43 2657.19 -1.91 182.84 -2.13 203.16 40.28 2457.37 -64.57 -498.59 25.59 6988.47 -157.90 1815.54
1.4 43.6 -23.22 3036.78 0.54 190.32 0.60 211.47 51.64 2704.30 -47.08 -664.76 70.35 7774.38 -102.41 1878.53
B=1.5 54.5 0.00 3163.32 2.99 171.07 3.33 190.08 66.84 2699.30 -30.27 -830.92 121.83 7848.27 -48.11 1670.39
1.6 65.4 23.22 3036.78 5.45 125.09 6.05 138.99 84.15 2473.19 -20.13 -997.09 177.00 7264.11 -5.50 1191.12
1.7 76.3 46.43 2657.19 7.90 52.38 8.78 58.20 100.74 2011.98 -12.09 -1163.26 230.90 5997.41 33.45 440.73
1.8 87.2 69.65 2024.52 10.35 -47.07 11.50 -52.30 116.47 1354.84 -5.41 -1329.43 283.30 4116.68 70.01 -580.78
1.9 98.1 92.87 1138.79 12.80 -173.25 14.23 -192.50 131.18 555.05 -0.62 -1889.40 333.92 1715.21 103.26 -2562.58
C=2.0 109 116.09 0.00 15.26 -326.16 16.95 -362.40 153.03 -70.10 1.65 -3054.33 397.02 -651.77 132.12 -5874.17
C'=2.0 109.0001 -139.52 0.00 -14.74 -326.16 -16.38 -362.40 9.20 -70.10 -158.13 -3054.33 -133.37 -651.78 -426.19 -5874.17
2.1 122.1 -111.61 1644.88 -11.79 -152.40 -13.10 -169.34 12.31 462.26 -134.05 -1695.76 -98.04 2042.12 -354.16 -1734.42
2.2 135.2 -83.71 2924.23 -8.84 -17.26 -9.83 -19.18 19.08 1258.13 -111.66 -1052.90 -56.30 4805.54 -285.10 761.23
2.3 148.3 -55.81 3838.06 -5.90 79.27 -6.55 88.08 28.01 1974.69 -92.73 -1027.80 -10.77 7038.55 -222.07 1784.20
2.4 161.4 -27.90 4386.35 -2.95 137.19 -3.28 152.43 38.19 2428.66 -73.25 -1027.80 36.94 8420.42 -158.08 2371.62
63
D = 2.5 174.5 0.00 4569.12 0.00 156.49 0.00 173.88 53.64 2566.50 -53.64 -1027.80 93.87 8857.44 -93.87 2567.43
2.6 187.6 27.90 4386.35 2.95 137.19 3.28 152.43 73.25 2428.66 -38.19 -1027.80 158.08 8420.42 -36.94 2371.62
2.7 200.7 55.81 3838.06 5.90 79.27 6.55 88.08 92.73 1974.69 -28.01 -1027.80 222.07 7038.55 10.77 1784.20
2.8 213.8 83.71 2924.23 8.84 -17.26 9.83 -19.18 111.66 1258.13 -19.08 -1052.90 285.10 4805.54 56.30 761.23
2.9 226.9 111.61 1644.88 11.79 -152.40 13.10 -169.34 134.05 462.26 -12.31 -1695.76 354.16 2042.12 98.04 -1734.42
E=3.0 240 139.52 0.00 14.74 -326.16 16.38 -362.40 158.13 -70.10 -9.20 -3054.33 426.19 -651.78 133.37 -5874.17
E'=3.0 240.0001 -116.09 0.00 -15.26 -326.16 -16.95 -362.40 -1.65 -70.10 -153.03 -3054.33 -132.12 -651.77 -397.02 -5874.17
3.1 250.9 -92.87 1138.79 -12.80 -173.25 -14.23 -192.50 0.62 555.05 -131.18 -1889.40 -103.26 1715.21 -333.92 -2562.58
3.2 261.8 -69.65 2024.52 -10.35 -47.07 -11.50 -52.30 5.41 1354.84 -116.47 -1329.43 -70.01 4116.68 -283.30 -580.78
3.3 272.7 -46.43 2657.19 -7.90 52.38 -8.78 58.20 12.09 2011.98 -100.74 -1163.26 -33.45 5997.41 -230.90 440.73
3.4 283.6 -23.22 3036.78 -5.45 125.09 -6.05 138.99 20.13 2473.19 -84.15 -997.09 5.50 7264.11 -177.00 1191.12
F=3.5 294.5 0.00 3163.32 -2.99 171.07 -3.33 190.08 30.27 2699.30 -66.84 -830.92 48.11 7848.27 -121.83 1670.39
3.6 305.4 23.22 3036.78 -0.54 190.32 -0.60 211.47 47.08 2704.30 -51.64 -664.76 102.41 7774.38 -70.35 1878.53
3.7 316.3 46.43 2657.19 1.91 182.84 2.13 203.16 64.57 2457.37 -40.28 -498.59 157.90 6988.47 -25.59 1815.54
3.8 327.2 69.65 2024.52 4.37 148.63 4.85 165.14 82.61 1953.38 -29.36 -332.42 214.34 5481.60 18.38 1481.44
3.9 338.1 92.87 1138.79 6.82 87.68 7.58 97.42 101.06 1140.04 -20.35 -166.25 271.49 3162.21 59.03 876.21
G=4.0 349 116.09 0.00 9.27 0.00 10.30 0.00 119.76 0.00 -15.25 0.00 329.09 0.00 92.83 0.00
5.3.3. Load combination (SVC I) results:
6000 7465.99
5000
4000
Moment (kip-ft)
3000
2000
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000 -3742.88 -3742.88
-4000
Span Distances (ft)
210
140
70
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-70
-140
-210
-255.41
-280
-301.32
-328.75
-350
Span Distances (ft)
64
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination SVC I
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -116.09 0.00 -9.27 0.00 -10.30 0.00 15.25 0.00 -119.76 0.00 -120.41 0.00 -255.41 0.00
1.1 10.9 -92.87 1138.79 -6.82 87.68 -7.58 97.42 20.35 1140.04 -101.06 -166.25 -86.91 2463.93 -208.32 1157.64
1.2 21.8 -69.65 2024.52 -4.37 148.63 -4.85 165.14 29.36 1953.38 -82.61 -332.42 -49.50 4291.67 -161.48 2005.87
1.3 32.7 -46.43 2657.19 -1.91 182.84 -2.13 203.16 40.28 2457.37 -64.57 -498.59 -10.20 5500.55 -115.05 2544.59
1.4 43.6 -23.22 3036.78 0.54 190.32 0.60 211.47 51.64 2704.30 -47.08 -664.76 29.56 6142.88 -69.16 2773.82
B=1.5 54.5 0.00 3163.32 2.99 171.07 3.33 190.08 66.84 2699.30 -30.27 -830.92 73.16 6223.77 -23.95 2693.55
1.6 65.4 23.22 3036.78 5.45 125.09 6.05 138.99 84.15 2473.19 -20.13 -997.09 118.87 5774.05 14.58 2303.77
1.7 76.3 46.43 2657.19 7.90 52.38 8.78 58.20 100.74 2011.98 -12.09 -1163.26 163.85 4779.74 51.02 1604.50
1.8 87.2 69.65 2024.52 10.35 -47.07 11.50 -52.30 116.47 1354.84 -5.41 -1329.43 207.97 3279.99 86.09 595.73
1.9 98.1 92.87 1138.79 12.80 -173.25 14.23 -192.50 131.18 555.05 -0.62 -1889.40 251.08 1328.10 119.27 -1116.35
C=2.0 109 116.09 0.00 15.26 -326.16 16.95 -362.40 153.03 -70.10 1.65 -3054.33 301.32 -758.66 149.94 -3742.88
C'=2.0 109.0001 -139.52 0.00 -14.74 -326.16 -16.38 -362.40 9.20 -70.10 -158.13 -3054.33 -161.43 -758.66 -328.75 -3742.88
2.1 122.1 -111.61 1644.88 -11.79 -152.40 -13.10 -169.34 12.31 462.26 -134.05 -1695.76 -124.19 1785.40 -270.55 -372.62
2.2 135.2 -83.71 2924.23 -8.84 -17.26 -9.83 -19.18 19.08 1258.13 -111.66 -1052.90 -83.30 4145.92 -214.04 1834.89
2.3 148.3 -55.81 3838.06 -5.90 79.27 -6.55 88.08 28.01 1974.69 -92.73 -1027.80 -40.24 5980.09 -160.99 2977.61
2.4 161.4 -27.90 4386.35 -2.95 137.19 -3.28 152.43 38.19 2428.66 -73.25 -1027.80 4.07 7104.63 -107.38 3648.17
65
D = 2.5 174.5 0.00 4569.12 0.00 156.49 0.00 173.88 53.64 2566.50 -53.64 -1027.80 53.64 7465.99 -53.64 3871.70
2.6 187.6 27.90 4386.35 2.95 137.19 3.28 152.43 73.25 2428.66 -38.19 -1027.80 107.38 7104.63 -4.07 3648.17
2.7 200.7 55.81 3838.06 5.90 79.27 6.55 88.08 92.73 1974.69 -28.01 -1027.80 160.99 5980.09 40.24 2977.61
2.8 213.8 83.71 2924.23 8.84 -17.26 9.83 -19.18 111.66 1258.13 -19.08 -1052.90 214.04 4145.92 83.30 1834.89
2.9 226.9 111.61 1644.88 11.79 -152.40 13.10 -169.34 134.05 462.26 -12.31 -1695.76 270.55 1785.40 124.19 -372.62
E=3.0 240 139.52 0.00 14.74 -326.16 16.38 -362.40 158.13 -70.10 -9.20 -3054.33 328.75 -758.66 161.43 -3742.88
E'=3.0 240.0001 -116.09 0.00 -15.26 -326.16 -16.95 -362.40 -1.65 -70.10 -153.03 -3054.33 -149.94 -758.66 -301.32 -3742.88
3.1 250.9 -92.87 1138.79 -12.80 -173.25 -14.23 -192.50 0.62 555.05 -131.18 -1889.40 -119.27 1328.10 -251.08 -1116.35
3.2 261.8 -69.65 2024.52 -10.35 -47.07 -11.50 -52.30 5.41 1354.84 -116.47 -1329.43 -86.09 3279.99 -207.97 595.73
3.3 272.7 -46.43 2657.19 -7.90 52.38 -8.78 58.20 12.09 2011.98 -100.74 -1163.26 -51.02 4779.74 -163.85 1604.50
3.4 283.6 -23.22 3036.78 -5.45 125.09 -6.05 138.99 20.13 2473.19 -84.15 -997.09 -14.58 5774.05 -118.87 2303.77
F=3.5 294.5 0.00 3163.32 -2.99 171.07 -3.33 190.08 30.27 2699.30 -66.84 -830.92 23.95 6223.77 -73.16 2693.55
3.6 305.4 23.22 3036.78 -0.54 190.32 -0.60 211.47 47.08 2704.30 -51.64 -664.76 69.16 6142.88 -29.56 2773.82
3.7 316.3 46.43 2657.19 1.91 182.84 2.13 203.16 64.57 2457.37 -40.28 -498.59 115.05 5500.55 10.20 2544.59
3.8 327.2 69.65 2024.52 4.37 148.63 4.85 165.14 82.61 1953.38 -29.36 -332.42 161.48 4291.67 49.50 2005.87
3.9 338.1 92.87 1138.79 6.82 87.68 7.58 97.42 101.06 1140.04 -20.35 -166.25 208.32 2463.93 86.91 1157.64
G=4.0 349 116.09 0.00 9.27 0.00 10.30 0.00 119.76 0.00 -15.25 0.00 255.41 0.00 120.41 0.00
5.3.4. Load combination (SVC II) results:
3000
2000
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000
-4000 -4659.18 -4659.18
-5000
Span Distances (ft)
3000
2000
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000
-4000 -4659.18 -4659.18
-5000
Span Distances (ft)
66
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination SVC II
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -116.09 0.00 -9.27 0.00 -10.30 0.00 15.25 0.00 -119.76 0.00 -115.83 0.00 -291.34 0.00
1.1 10.9 -92.87 1138.79 -6.82 87.68 -7.58 97.42 20.35 1140.04 -101.06 -166.25 -80.81 2805.94 -238.63 1107.76
1.2 21.8 -69.65 2024.52 -4.37 148.63 -4.85 165.14 29.36 1953.38 -82.61 -332.42 -40.70 4877.69 -186.26 1906.14
1.3 32.7 -46.43 2657.19 -1.91 182.84 -2.13 203.16 40.28 2457.37 -64.57 -498.59 1.89 6237.76 -134.42 2395.02
1.4 43.6 -23.22 3036.78 0.54 190.32 0.60 211.47 51.64 2704.30 -47.08 -664.76 45.06 6954.17 -83.28 2574.39
B=1.5 54.5 0.00 3163.32 2.99 171.07 3.33 190.08 66.84 2699.30 -30.27 -830.92 93.21 7033.56 -33.03 2444.27
1.6 65.4 23.22 3036.78 5.45 125.09 6.05 138.99 84.15 2473.19 -20.13 -997.09 144.11 6516.01 8.54 2004.65
1.7 76.3 46.43 2657.19 7.90 52.38 8.78 58.20 100.74 2011.98 -12.09 -1163.26 194.07 5383.34 47.39 1255.52
1.8 87.2 69.65 2024.52 10.35 -47.07 11.50 -52.30 116.47 1354.84 -5.41 -1329.43 242.91 3686.44 84.47 196.90
1.9 98.1 92.87 1138.79 12.80 -173.25 14.23 -192.50 131.18 555.05 -0.62 -1889.40 290.44 1494.61 119.09 -1683.17
C=2.0 109 116.09 0.00 15.26 -326.16 16.95 -362.40 153.03 -70.10 1.65 -3054.33 347.23 -779.68 150.44 -4659.18
C'=2.0 109.0001 -139.52 0.00 -14.74 -326.16 -16.38 -362.40 9.20 -70.10 -158.13 -3054.33 -158.67 -779.69 -376.19 -4659.18
2.1 122.1 -111.61 1644.88 -11.79 -152.40 -13.10 -169.34 12.31 462.26 -134.05 -1695.76 -120.50 1924.08 -310.77 -881.35
2.2 135.2 -83.71 2924.23 -8.84 -17.26 -9.83 -19.18 19.08 1258.13 -111.66 -1052.90 -77.58 4523.36 -247.54 1519.02
2.3 148.3 -55.81 3838.06 -5.90 79.27 -6.55 88.08 28.01 1974.69 -92.73 -1027.80 -31.83 6572.50 -188.81 2669.27
2.4 161.4 -27.90 4386.35 -2.95 137.19 -3.28 152.43 38.19 2428.66 -73.25 -1027.80 15.52 7833.23 -129.35 3339.84
67
D = 2.5 174.5 0.00 4569.12 0.00 156.49 0.00 173.88 53.64 2566.50 -53.64 -1027.80 69.73 8235.94 -69.73 3563.36
2.6 187.6 27.90 4386.35 2.95 137.19 3.28 152.43 73.25 2428.66 -38.19 -1027.80 129.35 7833.23 -15.52 3339.84
2.7 200.7 55.81 3838.06 5.90 79.27 6.55 88.08 92.73 1974.69 -28.01 -1027.80 188.81 6572.50 31.83 2669.27
2.8 213.8 83.71 2924.23 8.84 -17.26 9.83 -19.18 111.66 1258.13 -19.08 -1052.90 247.54 4523.36 77.58 1519.02
2.9 226.9 111.61 1644.88 11.79 -152.40 13.10 -169.34 134.05 462.26 -12.31 -1695.76 310.77 1924.08 120.50 -881.35
E=3.0 240 139.52 0.00 14.74 -326.16 16.38 -362.40 158.13 -70.10 -9.20 -3054.33 376.19 -779.69 158.67 -4659.18
E'=3.0 240.0001 -116.09 0.00 -15.26 -326.16 -16.95 -362.40 -1.65 -70.10 -153.03 -3054.33 -150.44 -779.68 -347.23 -4659.18
3.1 250.9 -92.87 1138.79 -12.80 -173.25 -14.23 -192.50 0.62 555.05 -131.18 -1889.40 -119.09 1494.61 -290.44 -1683.17
3.2 261.8 -69.65 2024.52 -10.35 -47.07 -11.50 -52.30 5.41 1354.84 -116.47 -1329.43 -84.47 3686.44 -242.91 196.90
3.3 272.7 -46.43 2657.19 -7.90 52.38 -8.78 58.20 12.09 2011.98 -100.74 -1163.26 -47.39 5383.34 -194.07 1255.52
3.4 283.6 -23.22 3036.78 -5.45 125.09 -6.05 138.99 20.13 2473.19 -84.15 -997.09 -8.54 6516.01 -144.11 2004.65
F=3.5 294.5 0.00 3163.32 -2.99 171.07 -3.33 190.08 30.27 2699.30 -66.84 -830.92 33.03 7033.56 -93.21 2444.27
3.6 305.4 23.22 3036.78 -0.54 190.32 -0.60 211.47 47.08 2704.30 -51.64 -664.76 83.28 6954.17 -45.06 2574.39
3.7 316.3 46.43 2657.19 1.91 182.84 2.13 203.16 64.57 2457.37 -40.28 -498.59 134.42 6237.76 -1.89 2395.02
3.8 327.2 69.65 2024.52 4.37 148.63 4.85 165.14 82.61 1953.38 -29.36 -332.42 186.26 4877.69 40.70 1906.14
3.9 338.1 92.87 1138.79 6.82 87.68 7.58 97.42 101.06 1140.04 -20.35 -166.25 238.63 2805.94 80.81 1107.76
G=4.0 349 116.09 0.00 9.27 0.00 10.30 0.00 119.76 0.00 -15.25 0.00 291.34 0.00 115.83 0.00
5.3.5. Load combination (SVC III) results:
3000
2000
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3132.02 -3132.02
-3000
-4000
Span Distances (ft)
0
0 35 70 105 140 175 210 245 280 315 350
-70
-140
-210
-231.46 -270.71
-280 -297.13
-350
Span Distances (ft)
68
DC1 DC2 DW Live Load Envelopes (Truck + Lane Load) Load Combination SVC III
Point Loc.
V M V M V M V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -116.09 0.00 -9.27 0.00 -10.30 0.00 15.25 0.00 -119.76 0.00 -123.46 0.00 -231.46 0.00
1.1 10.9 -92.87 1138.79 -6.82 87.68 -7.58 97.42 20.35 1140.04 -101.06 -166.25 -90.98 2235.92 -188.11 1190.89
1.2 21.8 -69.65 2024.52 -4.37 148.63 -4.85 165.14 29.36 1953.38 -82.61 -332.42 -55.38 3901.00 -144.96 2072.35
1.3 32.7 -46.43 2657.19 -1.91 182.84 -2.13 203.16 40.28 2457.37 -64.57 -498.59 -18.25 5009.08 -102.13 2644.31
1.4 43.6 -23.22 3036.78 0.54 190.32 0.60 211.47 51.64 2704.30 -47.08 -664.76 19.24 5602.02 -59.74 2906.77
B=1.5 54.5 0.00 3163.32 2.99 171.07 3.33 190.08 66.84 2699.30 -30.27 -830.92 59.79 5683.91 -17.90 2859.73
1.6 65.4 23.22 3036.78 5.45 125.09 6.05 138.99 84.15 2473.19 -20.13 -997.09 102.04 5279.42 18.61 2503.19
1.7 76.3 46.43 2657.19 7.90 52.38 8.78 58.20 100.74 2011.98 -12.09 -1163.26 143.70 4377.35 53.44 1837.15
1.8 87.2 69.65 2024.52 10.35 -47.07 11.50 -52.30 116.47 1354.84 -5.41 -1329.43 184.68 3009.02 87.17 861.61
1.9 98.1 92.87 1138.79 12.80 -173.25 14.23 -192.50 131.18 555.05 -0.62 -1889.40 224.84 1217.09 119.40 -738.47
C=2.0 109 116.09 0.00 15.26 -326.16 16.95 -362.40 153.03 -70.10 1.65 -3054.33 270.71 -744.64 149.61 -3132.02
C'=2.0 109.0001 -139.52 0.00 -14.74 -326.16 -16.38 -362.40 9.20 -70.10 -158.13 -3054.33 -163.27 -744.64 -297.13 -3132.02
2.1 122.1 -111.61 1644.88 -11.79 -152.40 -13.10 -169.34 12.31 462.26 -134.05 -1695.76 -126.65 1692.95 -243.74 -33.47
2.2 135.2 -83.71 2924.23 -8.84 -17.26 -9.83 -19.18 19.08 1258.13 -111.66 -1052.90 -87.12 3894.30 -191.71 2045.47
2.3 148.3 -55.81 3838.06 -5.90 79.27 -6.55 88.08 28.01 1974.69 -92.73 -1027.80 -45.84 5585.16 -142.44 3183.17
2.4 161.4 -27.90 4386.35 -2.95 137.19 -3.28 152.43 38.19 2428.66 -73.25 -1027.80 -3.57 6618.90 -92.73 3853.73
69
D = 2.5 174.5 0.00 4569.12 0.00 156.49 0.00 173.88 53.64 2566.50 -53.64 -1027.80 42.91 6952.69 -42.91 4077.26
2.6 187.6 27.90 4386.35 2.95 137.19 3.28 152.43 73.25 2428.66 -38.19 -1027.80 92.73 6618.90 3.57 3853.73
2.7 200.7 55.81 3838.06 5.90 79.27 6.55 88.08 92.73 1974.69 -28.01 -1027.80 142.44 5585.16 45.84 3183.17
2.8 213.8 83.71 2924.23 8.84 -17.26 9.83 -19.18 111.66 1258.13 -19.08 -1052.90 191.71 3894.30 87.12 2045.47
2.9 226.9 111.61 1644.88 11.79 -152.40 13.10 -169.34 134.05 462.26 -12.31 -1695.76 243.74 1692.95 126.65 -33.47
E=3.0 240 139.52 0.00 14.74 -326.16 16.38 -362.40 158.13 -70.10 -9.20 -3054.33 297.13 -744.64 163.27 -3132.02
E'=3.0 240.0001 -116.09 0.00 -15.26 -326.16 -16.95 -362.40 -1.65 -70.10 -153.03 -3054.33 -149.61 -744.64 -270.71 -3132.02
3.1 250.9 -92.87 1138.79 -12.80 -173.25 -14.23 -192.50 0.62 555.05 -131.18 -1889.40 -119.40 1217.09 -224.84 -738.47
3.2 261.8 -69.65 2024.52 -10.35 -47.07 -11.50 -52.30 5.41 1354.84 -116.47 -1329.43 -87.17 3009.02 -184.68 861.61
3.3 272.7 -46.43 2657.19 -7.90 52.38 -8.78 58.20 12.09 2011.98 -100.74 -1163.26 -53.44 4377.35 -143.70 1837.15
3.4 283.6 -23.22 3036.78 -5.45 125.09 -6.05 138.99 20.13 2473.19 -84.15 -997.09 -18.61 5279.42 -102.04 2503.19
F=3.5 294.5 0.00 3163.32 -2.99 171.07 -3.33 190.08 30.27 2699.30 -66.84 -830.92 17.90 5683.91 -59.79 2859.73
3.6 305.4 23.22 3036.78 -0.54 190.32 -0.60 211.47 47.08 2704.30 -51.64 -664.76 59.74 5602.02 -19.24 2906.77
3.7 316.3 46.43 2657.19 1.91 182.84 2.13 203.16 64.57 2457.37 -40.28 -498.59 102.13 5009.08 18.25 2644.31
3.8 327.2 69.65 2024.52 4.37 148.63 4.85 165.14 82.61 1953.38 -29.36 -332.42 144.96 3901.00 55.38 2072.35
3.9 338.1 92.87 1138.79 6.82 87.68 7.58 97.42 101.06 1140.04 -20.35 -166.25 188.11 2235.92 90.98 1190.89
G=4.0 349 116.09 0.00 9.27 0.00 10.30 0.00 119.76 0.00 -15.25 0.00 231.46 0.00 123.46 0.00
75
A 2-D frame element analysis using SAP program generated the deck in order to consider
as much case of loading as possible, and to reduce time consumption. In these analyses, dead
loads (DC1, DC2 and DW) and the design load are computed using static load analysis while
A description of different load and analysis cases defined in the analysis program is
stated below.
A strip of width 1.00 foot, and the three load cases are defined as DC1, DC2 and
DW which presents dead loads. These cases are analyzed using static load strategy.
In these loads, DC1 occupying the whole deck width, DC2 modelled as concentrated
load at barrier C.G, while DW occupying the clear distance between the two
. .
Wearing: DW ∗ 0.15 ∗ 0.145 ∗ 1.0 0.0365 /
Five moving load cases are defined as 1-HS20, 2-HS20-4’, 2-HS20-16’, 3-HS20-
according to the shape of influence lines. The first case 1-HS20 presents one truck
The two cases 2-HS20-4’ and 2-HS20-16’ present two trucks with different
spacing, the first case is where the two trucks spaced at 4’ while in the second case
the two trucks spaced at 16’. The spacing 4’ is believed to produce the maximum
negative moment generated from two trucks, while the spacing 16’ aimed to
spacing as previously described for the two cases 2-HS20-4’ and 2-HS20-16’.
The following SAP out is the bending moment envelopes due to moving load
factors. Theses multiple presence factors are 1.20, 1.00 and 0.85 for one truck
Moments envelopes for these moving load cases are plotted below twice. In the first
plot, the dynamic allowance in not included, while the second plot includes an dynamic
allowance of 1.33.
The following SAP out is the dead loads bending moment per 1.00 foot strip width.
A description of different load and analysis cases defined in the analysis program is
stated below.
A strip of width 1.00 foot, and the three load cases are defined as DC1, DC2 and
DW which presents dead loads. These cases are analyzed using static load strategy.
In these loads, DC1 occupying the whole deck width, DC2 modelled as concentrated
load at barrier C.G, while DW occupying the clear distance between the two
. .
Wearing: DW ∗ 0.15 ∗ 0.145 ∗ 1.0 0.0365 /
1.2.2. Pre-stressed bridge deck moving loads (HS20):
Five moving load cases are defined as 1-HS20, 2-HS20-4’, 2-HS20-10’, 3-HS20-
according to the shape of influence lines. The first case 1-HS20 presents one truck
The two cases 2-HS20-4’ and 2-HS20-10’ present two trucks with different
spacing, the first case is where the two trucks spaced at 4’ while in the second case
the two trucks spaced at 10’. The spacing 4’ is believed to produce the maximum
negative moment generated from two trucks, while the spacing 10’ aimed to
The two cases 3-HS20-4’ and 3-HS20-10’ present three trucks with different
spacing as previously described for the two cases 2-HS20-4’ and 2-HS20-16’.
The following SAP out is the bending moment envelopes due to moving load
factors. Theses multiple presence factors are 1.20, 1.00 and 0.85 for one truck
Moments envelopes for these moving load cases are plotted below twice. In the first
plot, the dynamic allowance in not included, while the second plot includes a dynamic
allowance of 1.33.
The following SAP out is the dead loads bending moment per 1.00 foot strip width.
In this section, the design of both bridges deck is outlined. The top and bottom
reinforcement layers are calculated using moment envelopes generated in the previous
section.
In order to convert the moments found from the HS20 moving load analysis into a
per foot linear strip, the moments must be divided by the equivalent width. The
The equivalent width for negative bending is found by the following equation.
2.1.2.1.Main reinforcement:
The concrete for the deck has a compressive strength of 4,000 psi. The depth
of the slab less the sacrificial layer is 9.5”. Assuming the use of #5 bars and
using the required 1” clear dimension, the depth of the reinforcement is 8.19”.
equation.
16.4 ∗
2 ∗ .85 ∗
16.4 ∗ 14.1 ∗
1.30
0.465 0.059
2
1.5"
Finally, the spacing of the reinforcement should not exceed the limits imposed
700γe
8" ‐ 2dc 18.1"
βs fss
The provided steel reinforcement is adequate for both strength and detailing
requirements.
2.1.2.2.Distribution Steel:
The area of the distribution steel per AASHTO 9.7.3 is required to be greater
than:
220
min , 67 ∗ 0.306
100
2.1.3.1.Main reinforcement:
The depth of the slab less the sacrificial layer is 9.5”. Assuming the use of #5
bars and using the required 2.5” clear dimension, the depth of the
reinforcement is 6.69”.
equation.
20.6 ∗
2 ∗ .85 ∗
20.6 ∗ 17.8 ∗
The reinforcement per AASHTO 5.7.3.3.2 is required to develop a bending
1.30
0.744 0.059
2
1.5"
700γe
5" ‐ 2dc 6.14"
βs fss
The provided steel reinforcement is adequate for both strength and detailing
requirements.
2.1.3.2.Distribution steel:
The area of the distribution steel per AASHTO 9.7.3 is required to be greater
than:
220
min , 67 ∗ 0.489
100
In order to convert the moments found from the HS20 moving load analysis into a
per foot linear strip, the moments must be divided by the equivalent width. The
The equivalent width for negative bending is found by the following equation.
2.2.2.1.Main reinforcement:
The concrete for the deck has a compressive strength of 4,000 psi. The depth
of the slab less the sacrificial layer is 8”. Assuming the use of #5 bars and
using the required 1” clear dimension, the depth of the reinforcement is 6.69”.
equation.
13.3 ∗
2 ∗ .85 ∗
12.8 ∗ 11.5 ∗
The reinforcement per AASHTO 5.7.3.3.2 is required to develop a bending
1.30
0.40 0.054
2
1.5"
700γe
4" ‐ 2dc 17.3"
βs fss
The provided steel reinforcement is adequate for both strength and detailing
requirements.
2.2.2.2.Distribution Steel:
The area of the distribution steel per AASHTO 9.7.3 is required to be greater
than:
220
min , 67 ∗ 0.311
100
2.2.3.1.Main reinforcement:
The depth of the slab less the sacrificial layer is 8”. Assuming the use of #5
bars and using the required 2.5” clear dimension, the depth of the
reinforcement is 5.19”.
Use #5 ASTM A615 Grade 60 steel bars at 5” on center.
equation.
15.5 ∗
2 ∗ .85 ∗
15.5 ∗ 11.8 ∗
1.30
0.744 0.054
2
1.5"
Finally, the spacing of the reinforcement should not exceed the limits imposed
700γe
5" ‐ 2dc 6.89"
βs fss
The provided steel reinforcement is adequate for both strength and detailing
requirements.
2.2.3.2.Distribution Steel:
The area of the distribution steel per AASHTO 9.7.3 is required to be greater
than:
220
min , 67 ∗ 0.498
100
- The bridge consists of three spans having lengths of 109’, 131’ and 109’, respectively.
- Girder type is AASHTO girder type VI, having the following dimensions:
Girder depth, d = 63 in
- Deck slab thickness, ts, is 8.0 in (includes ½ in integral wearing surface which is not
- Haunch assumed to be 2.0 in depth, but not included in the composite section properties, and
1
1.2. Materials:
- Concrete strength:
.
33000 ∗ ∗ ′
- Reinforcing steel:
- Pre-stressing strands:
2
2. Cross section properties:
Effective span length is the actual span length for simply supported beams or the distance
between points of permanent dead load inflection for continuous spans. This length is nearly
equals 75% of the span length for a span continuous from one side, or 56% of the span for a
span continuous from both sides. These lengths are calculated from the bridge analysis
, 8 ∗ 12 2 98
3
2.2. Concrete girder properties of section:
∗ ∗ .
- Deck slab area, 519.80
.
∗ ∗ .
- Deck slab moment of inertia, 2436.57
∗ . ∗
∗ ∗ ∗ . . ∗ . ∗ .
- C.G to girder bottom, 43.75
.
939624
4
5
3. Live load distribution factors:
Live load distribution factors will be calculated for bending moments and shear forces. The bending
moment distribution factors will be calculated three times. The first time considers the positive
bending moments for exterior spans, the second one considers the positive moments affecting the
interior span, and the last one for the support negative moments.
- Girder C.G. to Deck C.G distance, 0.50 ∗ 31.05 0.5 ∗ 7.5 34.80
- Number of girders, 8 4 →
6
3.1.3. Positive moment distribution factor, exterior span:
. . . . . .
0.06 ∗ ∗
∗ ∗ .
0.490
. . .
- For two or more lanes loaded, 0.075 ∗ ∗
. ∗ ∗
. . . . . .
0.075 ∗ ∗
. ∗ ∗ .
0.707
. . . . . .
0.06 ∗ ∗
∗ ∗ .
0.460
. . .
- For two or more lanes loaded, 0.075 ∗ ∗
. ∗ ∗
. . . . . .
0.075 ∗ ∗
. ∗ ∗ .
0.673
7
3.1.5. Negative moment at support distribution factor:
. . .
- For one lane loaded, 0.06 ∗ ∗
∗ ∗
. . . . . .
0.06 ∗ ∗
∗ ∗ .
0.474
. . .
- For two or more lanes loaded, 0.075 ∗ ∗
. ∗ ∗
. . . . . .
0.075 ∗ ∗
. ∗ ∗ .
0.689
.
- For one lane loaded, 0.36 0.36
0.687
. .
- For two or more lanes loaded, 0.20 0.20
0.826
8
4. Design internal forces:
In this section, the previously calculated load distribution factors are applied to the live load
Live load distribution factors are applied to the bending moments and shear forces envelopes in
The exterior span positive bending moments are multiplied by a distribution factor of (g = 0.707
lanes), while the interior span positive bending moments are multiplied by a distribution factor
of (g = 0.673 lanes). The support region negative moments are multiplied by (g = 0.689 lanes).
The support region is defined as the distance between points of contra-flexure under a uniform
load on all spans, and this distance found from the SAP analysis file. The support region length
is 55.5 ft. which presents 27.0 ft. from the exterior span and 28.50 ft. from the interior span.
The figure below illustrates the used load distribution factors for bending moments and shear
forces, respectively.
9
Live loads bending moments and shear forces envelopes including the load distribution factors
are shown in the figures below. The generated tables are also presented below the internal forces
envelopes.
400
0
-400 0 35 70 105 140 175 210 245 280 315 350
-800
-1200 -691.71
-1600
-2104.43 -2104.43
-2000
-2400
Span Distances (ft)
100 98.92
75
50
25
Shear (kips)
0
-25 0 35 70 105 140 175 210 245 280 315 350
-50
-75
-100 -98.92 -126.40
-125 -130.61
-150
Span Distances (ft)
10
Distribution Factors Moving Loads Envelopes (Without DF) Moving Loads Envelopes * g (With DF)
Point Loc.
M(+ve) M(-ve) V V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 0.71 0.71 0.83 15.25 0.00 -119.76 0.00 12.59 0.00 -98.92 0.00
1.1 10.9 0.71 0.71 0.83 20.35 1140.04 -101.06 -166.25 16.81 806.01 -83.47 -117.54
1.2 21.8 0.71 0.71 0.83 29.36 1953.38 -82.61 -332.42 24.25 1381.04 -68.24 -235.02
1.3 32.7 0.71 0.71 0.83 40.28 2457.37 -64.57 -498.59 33.27 1737.36 -53.34 -352.50
1.4 43.6 0.71 0.71 0.83 51.64 2704.30 -47.08 -664.76 42.66 1911.94 -38.89 -469.98
B=1.5 54.5 0.71 0.71 0.83 66.84 2699.30 -30.27 -830.92 55.21 1908.40 -25.00 -587.46
1.6 65.4 0.71 0.71 0.83 84.15 2473.19 -20.13 -997.09 69.51 1748.54 -16.63 -704.94
1.7 76.3 0.71 0.71 0.83 100.74 2011.98 -12.09 -1163.26 83.22 1422.47 -9.98 -822.42
1.8 87.2 0.71 0.71 0.83 116.47 1354.84 -5.41 -1329.43 96.20 957.87 -4.47 -939.90
1.9 98.1 0.71 0.69 0.83 131.18 555.05 -0.62 -1889.40 108.36 392.42 -0.51 -1301.80
C=2.0 109 0.71 0.69 0.83 153.03 -70.10 1.65 -3054.33 126.40 -49.56 1.37 -2104.43
C'=2.0 109.0001 0.67 0.69 0.83 9.20 -70.10 -158.13 -3054.33 7.60 -47.18 -130.61 -2104.43
2.1 122.1 0.67 0.69 0.83 12.31 462.26 -134.05 -1695.76 10.17 311.10 -110.73 -1168.38
2.2 135.2 0.67 0.69 0.83 19.08 1258.13 -111.66 -1052.90 15.76 846.72 -92.23 -725.45
2.3 148.3 0.67 0.67 0.83 28.01 1974.69 -92.73 -1027.80 23.14 1328.97 -76.60 -691.71
2.4 161.4 0.67 0.67 0.83 38.19 2428.66 -73.25 -1027.80 31.55 1634.49 -60.50 -691.71
D = 2.5 174.5 0.67 0.67 0.83 53.64 2566.50 -53.64 -1027.80 44.31 1727.25 -44.31 -691.71
2.6 187.6 0.67 0.67 0.83 73.25 2428.66 -38.19 -1027.80 60.50 1634.49 -31.55 -691.71
2.7 200.7 0.67 0.67 0.83 92.73 1974.69 -28.01 -1027.80 76.60 1328.97 -23.14 -691.71
2.8 213.8 0.67 0.69 0.83 111.66 1258.13 -19.08 -1052.90 92.23 846.72 -15.76 -725.45
2.9 226.9 0.67 0.69 0.83 134.05 462.26 -12.31 -1695.76 110.73 311.10 -10.17 -1168.38
E=3.0 240 0.67 0.69 0.83 158.13 -70.10 -9.20 -3054.33 130.61 -47.18 -7.60 -2104.43
E'=3.0 240.0001 0.71 0.69 0.83 -1.65 -70.10 -153.03 -3054.33 -1.37 -49.56 -126.40 -2104.43
3.1 250.9 0.71 0.69 0.83 0.62 555.05 -131.18 -1889.40 0.51 392.42 -108.36 -1301.80
3.2 261.8 0.71 0.71 0.83 5.41 1354.84 -116.47 -1329.43 4.47 957.87 -96.20 -939.90
3.3 272.7 0.71 0.71 0.83 12.09 2011.98 -100.74 -1163.26 9.98 1422.47 -83.22 -822.42
3.4 283.6 0.71 0.71 0.83 20.13 2473.19 -84.15 -997.09 16.63 1748.54 -69.51 -704.94
F=3.5 294.5 0.71 0.71 0.83 30.27 2699.30 -66.84 -830.92 25.00 1908.40 -55.21 -587.46
3.6 305.4 0.71 0.71 0.83 47.08 2704.30 -51.64 -664.76 38.89 1911.94 -42.66 -469.98
3.7 316.3 0.71 0.71 0.83 64.57 2457.37 -40.28 -498.59 53.34 1737.36 -33.27 -352.50
3.8 327.2 0.71 0.71 0.83 82.61 1953.38 -29.36 -332.42 68.24 1381.04 -24.25 -235.02
3.9 338.1 0.71 0.71 0.83 101.06 1140.04 -20.35 -166.25 83.47 806.01 -16.81 -117.54
G=4.0 349 0.71 0.71 0.83 119.76 0.00 -15.25 0.00 98.92 0.00 -12.59 0.00
11
4.2. Dead loads Internal forces (DC1, DC2 and DW):
Dead loads bending moments and shear forces plotted here are the same values previously
4800
4200
4569.12
3600
3000
Moment (kip-ft)
1800
1200
600 211.47 173.88 211.47
0
0 35 70 105 140 175 210 245 280 315 350
-600
Span Distances (ft) -362.40
150
139.52
125 116.09
100 116.09
75
50
25
Shear (kip)
16.38 10.30
0
-25 0 35 70 105 140 175 210 245 280 315 350
-16.95
-50
-75
-100 -116.09
-116.09
-125
-139.52
-150
Span Distances (ft)
12
DC1 DC2 DW
Point Loc.
V M V M V M
A=1.0 0 -116.09 0.00 -9.27 0.00 -10.30 0.00
1.1 10.9 -92.87 1138.79 -6.82 87.68 -7.58 97.42
1.2 21.8 -69.65 2024.52 -4.37 148.63 -4.85 165.14
1.3 32.7 -46.43 2657.19 -1.91 182.84 -2.13 203.16
1.4 43.6 -23.22 3036.78 0.54 190.32 0.60 211.47
B=1.5 54.5 0.00 3163.32 2.99 171.07 3.33 190.08
1.6 65.4 23.22 3036.78 5.45 125.09 6.05 138.99
1.7 76.3 46.43 2657.19 7.90 52.38 8.78 58.20
1.8 87.2 69.65 2024.52 10.35 -47.07 11.50 -52.30
1.9 98.1 92.87 1138.79 12.80 -173.25 14.23 -192.50
C=2.0 109 116.09 0.00 15.26 -326.16 16.95 -362.40
C'=2.0 109.0001 -139.52 0.00 -14.74 -326.16 -16.38 -362.40
2.1 122.1 -111.61 1644.88 -11.79 -152.40 -13.10 -169.34
2.2 135.2 -83.71 2924.23 -8.84 -17.26 -9.83 -19.18
2.3 148.3 -55.81 3838.06 -5.90 79.27 -6.55 88.08
2.4 161.4 -27.90 4386.35 -2.95 137.19 -3.28 152.43
D = 2.5 174.5 0.00 4569.12 0.00 156.49 0.00 173.88
2.6 187.6 27.90 4386.35 2.95 137.19 3.28 152.43
2.7 200.7 55.81 3838.06 5.90 79.27 6.55 88.08
2.8 213.8 83.71 2924.23 8.84 -17.26 9.83 -19.18
2.9 226.9 111.61 1644.88 11.79 -152.40 13.10 -169.34
E=3.0 240 139.52 0.00 14.74 -326.16 16.38 -362.40
E'=3.0 240.0001 -116.09 0.00 -15.26 -326.16 -16.95 -362.40
3.1 250.9 -92.87 1138.79 -12.80 -173.25 -14.23 -192.50
3.2 261.8 -69.65 2024.52 -10.35 -47.07 -11.50 -52.30
3.3 272.7 -46.43 2657.19 -7.90 52.38 -8.78 58.20
3.4 283.6 -23.22 3036.78 -5.45 125.09 -6.05 138.99
F=3.5 294.5 0.00 3163.32 -2.99 171.07 -3.33 190.08
3.6 305.4 23.22 3036.78 -0.54 190.32 -0.60 211.47
3.7 316.3 46.43 2657.19 1.91 182.84 2.13 203.16
3.8 327.2 69.65 2024.52 4.37 148.63 4.85 165.14
3.9 338.1 92.87 1138.79 6.82 87.68 7.58 97.42
G=4.0 349 116.09 0.00 9.27 0.00 10.30 0.00
13
4.3. Pre-stressed Bridge factored design envelopes:
In this section, the dead loads (DC1, DC2 and DW) internal forces presented in section (4.2) are
- Using these load combinations with the tabulated values in Excel gives the following
7500 9190.53
6250
5000
Moment (kip-ft)
3750
2500
1250
0
-1250 0 35 70 105 140 175 210 245 280 315 350
-2500
-3750 -4634.05 -4634.05
-5000
Span Distances (ft)
14
Shear Envelopes Load Combination (STR I)
500
400 410.80 445.95 345.26
300
200
100
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-100
-200
-300
-345.26
-400 -445.95 -410.80
-500
Span Distances (ft)
15
4.3.2. Load Combination (SVC III) results:
3000
2000
1000
0
0 35 70 105 140 175 210 245 280 315 350
-1000
-2372.10 -2372.10
-2000
-3000
Span Distances (ft)
0
0 35 70 105 140 175 210 245 280 315 350
-70
-140
-210 -214.79 -249.41
-280 -275.12
-350
Span Distances (ft)
16
Load Combination SVC III
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -125.58 0.00 -214.79 0.00
1.1 10.9 -93.82 1968.70 -174.04 1229.86
1.2 21.8 -59.46 3443.12 -133.46 2150.27
1.3 32.7 -23.86 4433.07 -93.14 2761.18
1.4 43.6 12.05 4968.13 -53.19 3062.59
B=1.5 54.5 50.49 5051.19 -13.68 3054.50
1.6 65.4 90.32 4699.70 21.41 2736.91
1.7 76.3 129.68 3905.74 55.12 2109.82
1.8 87.2 168.46 2691.45 87.93 1173.23
1.9 98.1 206.58 1086.98 119.48 -268.39
C=2.0 109 249.41 -728.21 149.38 -2372.10
C'=2.0 109.0001 -164.55 -726.30 -275.12 -2372.10
2.1 122.1 -128.37 1572.02 -225.08 388.44
2.2 135.2 -89.77 3565.17 -176.16 2307.43
2.3 148.3 -49.74 5068.58 -129.53 3452.04
2.4 161.4 -8.89 5983.56 -82.53 4122.60
D = 2.5 174.5 35.45 6281.29 -35.45 4346.13
2.6 187.6 82.53 5983.56 8.89 4122.60
2.7 200.7 129.53 5068.58 49.74 3452.04
2.8 213.8 176.16 3565.17 89.77 2307.43
2.9 226.9 225.08 1572.02 128.37 388.44
E=3.0 240 275.12 -726.30 164.55 -2372.10
E'=3.0 240.0001 -149.38 -728.21 -249.41 -2372.10
3.1 250.9 -119.48 1086.98 -206.58 -268.39
3.2 261.8 -87.93 2691.45 -168.46 1173.23
3.3 272.7 -55.12 3905.74 -129.68 2109.82
3.4 283.6 -21.41 4699.70 -90.32 2736.91
F=3.5 294.5 13.68 5051.19 -50.49 3054.50
3.6 305.4 53.19 4968.13 -12.05 3062.59
3.7 316.3 93.14 4433.07 23.86 2761.18
3.8 327.2 133.46 3443.12 59.46 2150.27
3.9 338.1 174.04 1968.70 93.82 1229.86
G=4.0 349 214.79 0.00 125.58 0.00
17
DESIGN OF PRETENSIOND PRECAST I GIRDERS BRIDGE
Span := 349
nop := 32 Number of Nodes In the whole Bridge Point
Ls := 349⋅ ft Bridge Total Length
0 A=1.0
i := 0 .. nop 10.9 1.1
21.8 1.2
32.7
1.3
43.6 1.4
54.5 B=1.5
65.4 1.6
76.3 1.7
87.2
1.8
98.1 1.9
109 C=2.0
109.0001
C'=2.0
122.1 2.1
135.2 2.2
148.3 2.3
161.4 2.4
xx := 174.5 D = 2.5
187.6 2.6
200.7 2.7
213.8
2.8
Location in Foot Along the Bridge
Length along with Point numbering 226.9 2.9
240 E=3.0
x := xx ⋅ ft
i i
240.0001 E'=3.0
250.9 3.1
261.8 3.2
272.7 3.3
283.6 3.4
294.5 F=3.5
305.4 3.6
316.3 3.7
3.8
327.2
338.1 3.9
349 G=4.0
SECTIONAL PROPERTIES
Beam Dimensions
B1 := 28.in D3 := 10.in
B3 := 8.in D4 := 36.in
B4 := 42.in D5 := 4.in
D1 := 63.in D6 := 5.in
D2 := 8.in
fr = 0.679⋅ ksi
2
Apt := 0.217⋅ in Area Per Tendon
Centroied
3 2 3 2
+ B1⋅ D2⋅ yg −
D2
+ 0.50⋅ ( B1 − B3) ⋅ D3 yg − D2 +
D2 D3 D3
Ig := B1⋅ + ( B1 − B3) ⋅ +
12 2 36 3
5 4
Ig = 5.162 × 10 ⋅ in
Ig 3
Sgb := Sgb = 16270.823 ⋅ in
ygb
Ig 4 3
Sgt := Sgt = −1.65 × 10 ⋅ in
ygt
Ecd
nc := nc = 0.707 Modular Ratio - Deck to Girder
Ecg
beff := nc⋅ bd beff = 69.298⋅ in Effective Width of Deck
2
Ad := beff ⋅ hd Ad = 519.733 ⋅ in Effective Area of Deck
1 3 3 4
Id := ⋅ beff ⋅ hd Id = 2.436 × 10 ⋅ in Effective Second Moment of Inertia of Deck
12
hd
yd := D1 + yd = 66.75⋅ in Distance From Bottom to CG of Deck
2
3 2
Ac := Ag + Ad Ac = 1.522 × 10 ⋅ in Effective Area of Composite Section
Ag⋅ yg + Ad⋅ yd
yc := yc = 43.687⋅ in Distance From Bottom to CG of Composite Sec
Ac
2 2
Ic := Ig + Ag⋅ ( yc − yg) + Id + Ad⋅ ( yc − yd ) Effective Second Moment of Inertia of Composite
Sec
5 4
Ic = 9.385 × 10 ⋅ in
Ic 4 3
Scgb := = 2.148 × 10 ⋅ in Section Modulus at Girder Bottom
ycgb
Ic 4 3
Scgt := = −4.859 × 10 ⋅ in Section Modulus at Girder Top
ycgt
Ic 4 3
Scdt := = −3.5 × 10 ⋅ in Section Modulus at Deck Slab Top
ycdt
Prestressing Propertise
15.80 32
fpu
fpj := Jpers⋅ fpj = 202.5⋅ ksi Jacking Stress 12.71 32
100
8.29 32
3.875 32
3.875 32
3.875 32
3.875 32
3.875 32
8.29 32
12.71 32
15.80 32
15.251 44
12.55 44
8.68 44
4.82 44
4.82 44
ysbb := 4.82 nnos := 44
nos := nnos
i i
Number of Strands
4.82 44
4.82 44
2
Aps := nos ⋅ Apt Aps5 = 6.944⋅ in Total Area of Strands
i i
109 ft mid-span 8.68 44
Pj := −Aps ⋅ fpj
3
Pj5 = −1.406 × 10 ⋅ kip
Jacking Force 12.55 44
i i 109 ft mid-span 15.251 44
15.80 32
12.71 32
8.29 32
Distance between Girder Bottom and 3.875 32
Strands CG 3.875 32
3.875 32
ysb := ysbb ⋅ in ysb 16 = 4.82⋅ in
i i 3.875 32
3.875 32
Strands Eccentricity 8.29 32
12.71 32
es := ygb − ysb
i i 15.80 32
es0 = 15.924⋅ in Eccentricity for span (109 ft) ends, calculated at (Lt = 3.0 ft)
es11 = 16.473⋅ in Eccentricity for span (131 ft) ends, calculated at (Lt = 3.0 ft)
INTERNAL FORCES
Dead and Live Loads Moments
Dead and live load moments at supports were calculated at the transfer length (Lt = 3.0 ft) in order
to be used in serviceability checks
155.3 313.5
24.10
26.8
564.16 1138.79 87.68 97.42
1002.95 2024.52 148.63 165.14
1316.37 2657.19 182.84 203.16
1504.42 3036.78 190.32 211.47
1567.10 3163.32 171.07 190.08
1504.42 3036.78 125.09 138.99
1316.37 2657.19 52.38 58.20
1002.95 2024.52 −47.07 −52.30
564.16 1138.79 −173.25 −192.50
155.3 313.5 −284 −315.64
186.6 376.7 −286.4 −318.20
814.87 1644.88 −152.40 −169.34
1448.66 2924.23 −17.26 −19.18
1901.37 3838.06 79.27 88.08
2172.99 4386.35 137.19 152.43
MMg := 2263.54 MMDC1 := 4569.12 MMDC2 := 156.49 MMDW := 173.88
2172.99 4386.35 137.19 152.43
1901.37 3838.06 79.27 88.08
1448.66 2924.23 −17.26 −19.18
814.87 1644.88 −152.40 −169.34
186.6 376.7 −286.4 −318.20
155.3 313.5 −284 −315.64
564.16 1138.79 −173.25 −192.50
1002.95 2024.52 −47.07 −52.30
1316.37 2657.19 52.38 58.20
1504.42 3036.78 125.09 138.99
1567.10 3163.32 171.07 190.08
1504.42 3036.78 190.32 211.47
1316.37 2657.19 182.84 203.16
1002.95 2024.52 148.63 165.14
564.16 1138.79 87.68 97.42
155.3 313.5 24.10 26.8
Dead and live load moments at supports were calculated at the transfer length (Lt = 3.0 ft) in order
to be used in serviceability checks
3
MDC1 := MMDC1 ⋅ kip ⋅ ft MDC15 = 3.163 × 10 ⋅ kip ⋅ ft Deck + Girder Weight Moments
i i
MLne := MMLne ⋅ kip ⋅ ft MLne5 = −587.46⋅ kip ⋅ ft Live Load Negative Moments
i i
3
MLpo := MMLpo ⋅ kip ⋅ ft MLpo5 = 1.908 × 10 ⋅ kip ⋅ ft Live Load Positive Moments
i i
3
MUne := MMUne ⋅ kip ⋅ ft MUne5 = 3.425 × 10 ⋅ kip ⋅ ft Ultimate (STR I) Negative Moments
i i
3
MUpo := MMUpo ⋅ kip ⋅ ft MUpo5 = 7.793 × 10 ⋅ kip ⋅ ft Ultimate (STR I) Positive Moments
i i
PRESTRESS LOSSES
Elastic Losses
Ep
ng := ng = 6.069 Modular ratio
Ecgt
fcj :=
Pj
i
+
i ( i)
Pj ⋅ es
2
+
Mg ⋅ es
i i Concrete Stress at strands CG
i Ag Ig Ig
ΔfpES
i
ΔfpES% := ⋅ 100 ΔfpES%5 = 6.783
i fpj
γh := 1.70 − 0.01⋅ HU = 1
5
γst := = 0.714
1 + fcgt
1⋅ ksi
fpj ⋅ Apsi
ΔfpLT := 10.0⋅ ⋅ γh ⋅ γst + 12.0ksi⋅ γh ⋅ γst + ΔfpR = ... ⋅ ksi
i Ag
ΔfpLT5⋅ 100
ΔfpLT 5 = 20.995⋅ ksi ΔfpLT% := = 10.368
fpj
Total losses
ΔfpT
i
ΔfpT% := ⋅ 100 ΔfpT% 5 = 17.151
i fpj
Effective Prestressing
fpe
i
fpe% := ⋅ 100 fpe%5 = 82.849
i fpj
3
PTi := −Aps ⋅ fpes PTi5 = −1.311 × 10 ⋅ kip Prestressing force at Transfer
i i i
3
PTf := −Aps ⋅ fpe PTf 5 = −1.165 × 10 ⋅ kip Prestressing force at Final
i i i
Permissable Stresses
fcsa1 := −0.45⋅ fcg fcsa1 = −3.6⋅ ksi Girder allowable compressive stress -
for Permenant loads (DC1+DC2+DW)
fcsa2 := −0.60⋅ fcg fcsa2 = −4.8⋅ ksi Girder allowable compressive Stress-
for Permenant loads-SVC (I)
ftsa := 0.19⋅ fcg⋅ ksi ftsa = 0.537⋅ ksi Girder allowable tensile stress- SVC
(III)
fcsad1 := −0.45⋅ fcd fcsad1 = −1.8⋅ ksi Deck allowable compressive stress -
for Permenant loads (DC2+DW)
fcsad2 := −0.60⋅ fcd fcsad2 = −2.4⋅ ksi Deck allowable compressive Stress-
for Permenant loads-SVC (I)
ftsad := 0.19⋅ fcd ⋅ ksi ftsad = 0.38⋅ ksi Deck allowable tensile stress- SVC (III)
fcta := −0.60⋅ fcgt fcta = −3.6⋅ ksi Allowable Compressive Stress- Transfer
for Girder Weight
ftta := 0.0948⋅ fcgt⋅ ksi ftta = 0.232⋅ ksi Allowable Tensile Stress-Transfer
PTi PTi ⋅ es Mg
i i i i
fbt := + + Girder bottom transfer stresses
i Ag Sgb Sgb
PTi PTi ⋅ es Mg
i i i i Girder top transfer stresses
ftt := + +
i Ag Sgt Sgt
4 3
Sgb = 1.627 × 10 ⋅ in
Girder bottom section modulus
4 3
Sgt = −1.65 × 10 ⋅ in Girder top section modulus
3 2
Ag = 1.002 × 10 ⋅ in Girder area
Transfer stresses at supports span (109 ft)
3
PTi0 = −1.325 × 10 ⋅ kip
Initial prestressing force at support
fbt 0 = −2.505⋅ ksi Girder trensfer bottom stresses at support (< 3.60 ksi)
ftt 0 = −0.157⋅ ksi Girder trensfer top stresses at support (< 3.60 ksi)
3
PTi11 = −1.78 × 10 ⋅ kip Initial prestressing force at support
fbt 11 = −3.442⋅ ksi Girder trensfer bottom stresses at support (< 3.60 ksi)
ftt 11 = −0.135⋅ ksi Girder trensfer top stresses at support (< 3.60 ksi)
3
PTi5 = −1.311 × 10 ⋅ kip
Initial prestressing force at mid-span (109 ft)
3
Mg5 = 1.567 × 10 ⋅ kip ⋅ ft Girder own weight moment at mid-span (109 ft)
fbt 5 = −2.396⋅ ksi Girder trensfer bottom stresses at mid-span (< 3.60 ksi)
ftt 5 = −0.236⋅ ksi Girder trensfer top stresses at mid-span (< 3.60 ksi)
Transfer stresses at (131 ft) mid-span
3
PTi16 = −1.769 × 10 ⋅ kip
Initial prestressing force at mid-span (131 ft)
3
Mg16 = 2.264 × 10 ⋅ kip ⋅ ft Girder own weight moment at mid-span (131 ft)
fbt 16 = −3.022⋅ ksi Girder trensfer bottom stresses at mid-span (< 3.60 ksi)
ftt 16 = −0.527⋅ ksi Girder trensfer top stresses at mid-span (< 3.60 ksi)
Transfer Stresses
0 0
Girder Bottom Stresses
−3 −3
xi
ft
Span Distances
Compressive Stresses Under Permanent Loads
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi
fcgbp := + + + +
i Ag Sgb Sgb Scgb Scgb
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi
fcgtp := + + + +
i Ag Sgt Sgt Scgt Scgt
4 3
Sgb = 1.627 × 10 ⋅ in
Girder bottom section modulus
4 3
Sgt = −1.65 × 10 ⋅ in Girder top section modulus
3 2
Ag = 1.002 × 10 ⋅ in Girder area
4 3
Scgb = 2.148 × 10 ⋅ in Girder bottom section modulus - Composite
4 3
Scgt = −4.859 × 10 ⋅ in Girder top section modulus - Composite
4 3
Scdt = −3.5 × 10 ⋅ in Girder top section modulus - Composite
Permanent stresses at exterior supports
3
PTf 0 = −1.18 × 10 ⋅ kip
Final prestressing force at support
fcgbp 0 = −2.072⋅ ksi Girder Permanent bottom stresses at ext. support (< 3.60 ksi)
fcgtp 0 = −0.28⋅ ksi Girder Permanent top stresses at ext. support (< 3.60 ksi)
fcdtp0 = −0.012⋅ ksi Deck Permanent top stresses at ext. support (< 3.60 ksi)
3
PTf 10 = −1.18 × 10 ⋅ kip Final prestressing force at support
fcgbp 10 = −2.435⋅ ksi Girder Permanent bottom stresses at int. support (< 3.60 ksi)
fcgtp 10 = −0.119⋅ ksi Girder Permanent top stresses at int. support (< 0.54 ksi)
fcdtp10 = 0.145⋅ ksi Deck Permanent top stresses at int. support (< 0.38 ksi)
Permanent stresses at (109 ft) mid-span
3
PTi5 = −1.311 × 10 ⋅ kip Final prestressing force at mid-span (109 ft)
3
MDC15 = 3.163 × 10 ⋅ kip ⋅ ft MDC25 = 171.07⋅ kip ⋅ ft MDW5 = 190.08⋅ kip ⋅ ft
fcgbp 5 = −0.622⋅ ksi Girder Permanent bottom stresses at mid-span. support (< 3.60 ksi)
fcgtp 5 = −1.586⋅ ksi Girder Permanent top stresses at mid-span support (< 3.60 ksi)
fcdtp5 = −0.088⋅ ksi Deck Permanent top stresses at mid-span support (< 1.80 ksi)
3
PTi16 = −1.769 × 10 ⋅ kip Final prestressing force at mid-span (131 ft)
3
MDC116 = 4.569 × 10 ⋅ kip ⋅ ft MDC216 = 156.49⋅ kip ⋅ ft MDW16 = 173.88⋅ kip ⋅ ft
fcgbp 16 = −0.511⋅ ksi Girder Permanent bottom stresses at mid-span. support (< 3.60 ksi)
fcgtp 16 = −2.435⋅ ksi Girder Permanent top stresses at mid-span support (< 3.60 ksi)
fcdtp16 = −0.08⋅ ksi Deck Permanent top stresses at mid-span support (< 1.80 ksi)
Permanent Loads Stresses
0 0
Girder Bottom Stresses
fcgbpi fcgtpi
ksi ksi
−2 −2
−3 −3
xi
ft
Span Distances
Compressive Stresses at Service (SVC I)
Girder Bottom service stresses (SVC I), Live load positive moment
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi MLpoi
fcgbs_po := + + + + +
i Ag Sgb Sgb Scgb Scgb Scgb
Girder Top service stresses (SVC I), Live load positive moment
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi MLpoi
fcgts_po := + + + + +
i Ag Sgt Sgt Scgt Scgt Scgt
Slab Top service stresses (SVC I), Live load positive moment
Girder Bottom service stresses (SVC I), Live load negative moment
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi MLnei
fcgbs_ne := + + + + +
i Ag Sgb Sgb Scgb Scgb Scgb
Girder Top service stresses (SVC I), Live load negative moment
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi MLnei
fcgts_ne := + + + + +
i Ag Sgt Sgt Scgt Scgt Scgt
Slab Top service stresses (SVC I), Live load negative moment
4 3
Sgt = −1.65 × 10 ⋅ in Girder top section modulus
3 2
Ag = 1.002 × 10 ⋅ in Girder area
4 3
Scgb = 2.148 × 10 ⋅ in Girder bottom section modulus - Composite
4 3
Scgt = −4.859 × 10 ⋅ in Girder top section modulus - Composite
4 3
Scdt = −3.5 × 10 ⋅ in Girder top section modulus - Composite
3
PTf 0 = −1.18 × 10 ⋅ kip
Final prestressing force at support
fcgbs_po0 = −1.948⋅ ksi MLpo Girder SVCI bottom stresses at ext. support (< 4.80 ksi)
fcgts_po0 = −0.335⋅ ksi MLpo Girder SVCI top stresses at ext. support (< 4.80 ksi)
fcdts_po0 = −0.066⋅ ksi MLpo Deck SVCI top stresses at ext. support (< 2.40 ksi)
fcgbs_ne0 = −2.09⋅ ksi MLne Girder SVCI bottom stresses at ext. support (< 4.80 ksi)
fcgts_ne0 = −0.272⋅ ksi MLne Girder SVCI top stresses at ext. support (< 4.80 ksi)
−3
fcdts_ne0 = −4.461 × 10 ⋅ ksi
MLne Deck SVCI top stresses at ext. support (< 2.40 ksi)
SVC(I) stresses at intermediate supports
3
PTf 10 = −1.18 × 10 ⋅ kip Final prestressing force at support
fcgbs_po10 = −2.395⋅ ksi MLpo Girder SVCI bottom stresses at int. support (< 4.80 ksi)
fcgts_po10 = −0.137⋅ ksi MLpo Girder SVCI top stresses at int. support
fcdts_po10 = 0.128⋅ ksi MLpo Deck SVCI top stresses at int. support
fcgbs_ne10 = −3.489⋅ ksi MLne Girder SVCI bottom stresses at int. support (< 4.80 ksi)
fcgts_ne10 = 0.347⋅ ksi MLne Girder SVCI top stresses at int. support
fcdts_ne10 = 0.603⋅ ksi MLne Deck SVCI top stresses at int. support
3
PTi5 = −1.311 × 10 ⋅ kip Final prestressing force at mid-span (109 ft)
3
MDC15 = 3.163 × 10 ⋅ kip ⋅ ft MDC25 = 171.07⋅ kip ⋅ ft MDW5 = 190.08⋅ kip ⋅ ft
3
MLpo5 = 1.908 × 10 ⋅ kip ⋅ ft MLne5 = −587.46⋅ kip ⋅ ft Moments at mid-span
fcgts_po5 = −2.057⋅ ksi MLpo Girder SVCI top stresses at mid-span (< 4.80 ksi)
fcdts_po5 = −0.55⋅ ksi MLpo Deck SVCI top stresses at mid-span (< 2.40 ksi)
fcgbs_ne5 = −0.95⋅ ksi MLne Girder SVCI bottom stresses at mid-span (< 4.80 ksi)
fcgts_ne5 = −1.441⋅ ksi MLne Girder SVCI top stresses at mid-span (< 4.80 ksi)
3
PTi16 = −1.769 × 10 ⋅ kip Final prestressing force at mid-span (131 ft)
3
MDC116 = 4.569 × 10 ⋅ kip ⋅ ft MDC216 = 156.49⋅ kip ⋅ ft MDW16 = 173.88⋅ kip ⋅ ft
3
MLpo16 = 1.727 × 10 ⋅ kip ⋅ ft MLne16 = −691.71⋅ kip ⋅ ft Moments at mid-span
fcgts_po16 = −2.861⋅ ksi MLpo Girder SVCI top stresses at mid-span (< 4.80 ksi)
fcdts_po16 = −0.499⋅ ksi MLpo Deck SVCI top stresses at mid-span (< 2.40 ksi)
fcgbs_ne16 = −0.897⋅ ksi MLne Girder SVCI bottom stresses at mid-span (< 4.80 ksi)
fcgts_ne16 = −2.264⋅ ksi MLne Girder SVCI top stresses at mid-span (< 4.80 ksi)
0 0
Girder Bottom Stresses
−4 −4
xi
ft
Span Distances
0 0
Girder Bottom Stresses
fcgbs_nei− 2 − 2 fcgts_nei
ksi ksi
−4 −4
xi
ft
Span Distances
Tensile Stresses at Service (SVC III)
Girder Bottom service stresses (SVC III), Live load positive moment
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi 0.80⋅ MLpo
i
ftgbs_po := + + + + +
i Ag Sgb Sgb Scgb Scgb Scgb
Girder Top service stresses (SVC III), Live load positive moment
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi 0.80⋅ MLpo
i
ftgts_po := + + + + +
i Ag Sgt Sgt Scgt Scgt Scgt
Slab Top service stresses (SVC III), Live load positive moment
Girder Bottom service stresses (SVC III), Live load negative moment
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi 0.80⋅ MLne
i
ftgbs_ne := + + + + +
i Ag Sgb Sgb Scgb Scgb Scgb
Girder Top service stresses (SVC III), Live load negative moment
PTf
i
PTf ⋅ es
i i
MDC1
i MDC2i MDWi 0.80⋅ MLne
i
ftgts_ne := + + + + +
i Ag Sgt Sgt Scgt Scgt Scgt
Slab Top service stresses (SVC III), Live load negative moment
4 3
Sgt = −1.65 × 10 ⋅ in Girder top section modulus
3 2
Ag = 1.002 × 10 ⋅ in Girder area
4 3
Scgb = 2.148 × 10 ⋅ in Girder bottom section modulus - Composite
4 3
Scgt = −4.859 × 10 ⋅ in Girder top section modulus - Composite
4 3
Scdt = −3.5 × 10 ⋅ in Girder top section modulus - Composite
3
PTf 0 = −1.18 × 10 ⋅ kip
Final prestressing force at support
ftgbs_po 0 = −1.972⋅ ksi MLpo Girder SVCIII bottom stresses at ext. support NOT TEN.
ftgts_po0 = −0.324⋅ ksi MLpo Girder SVCIII top stresses at ext. support NOT TEN.
ftdts_po0 = −0.056⋅ ksi MLpo Deck SVCIII top stresses at ext. support
ftgbs_ne0 = −2.087⋅ ksi MLne Girder SVCIII bottom stresses at ext. support NOT TEN.
ftgts_ne0 = −0.273⋅ ksi MLne Girder SVCIII top stresses at ext. support NOT TEN.
−3
ftdts_ne0 = −6.037 × 10 ⋅ ksi
MLne Deck SVCIII top stresses at ext. support
SVC(III) stresses at intermediate supports
3
PTf 10 = −1.18 × 10 ⋅ kip Final prestressing force at support
ftgbs_po 10 = −2.403⋅ ksi MLpo Girder SVCIII bottom stresses at int. support
ftgts_po10 = −0.133⋅ ksi MLpo Girder SVCIII top stresses at int. support (< 0.537 ksi)
ftdts_po10 = 0.131⋅ ksi MLpo Deck SVCIII top stresses at int. support (< 0.38 ksi)
ftgbs_ne10 = −3.278⋅ ksi MLne Girder SVCIII bottom stresses at int. support
ftgts_ne10 = 0.254⋅ ksi MLne Girder SVCIII top stresses at int. support (< 0.537 ksi)
ftdts_ne10 = 0.511⋅ ksi MLne Deck SVCIII top stresses at int. support (< 0.38 ksi)
3
PTi5 = −1.311 × 10 ⋅ kip Final prestressing force at mid-span (109 ft)
3
MDC15 = 3.163 × 10 ⋅ kip ⋅ ft MDC25 = 171.07⋅ kip ⋅ ft MDW5 = 190.08⋅ kip ⋅ ft
3
MLpo5 = 1.908 × 10 ⋅ kip ⋅ ft MLne5 = −587.46⋅ kip ⋅ ft Moments at mid-span
ftgbs_po 5 = 0.231⋅ ksi MLpo Girder SVCIII bottom stresses at mid-span (< 0.537 ksi)
ftgts_ne5 = −1.47⋅ ksi MLne Girder SVCIII top stresses at mid-span NO TENSION
ftdts_ne5 = 0.026⋅ ksi MLne Deck SVCIII top stresses at mid-span (< 0.38 ksi)
3
PTi16 = −1.769 × 10 ⋅ kip Final prestressing force at mid-span (131 ft)
3
MDC116 = 4.569 × 10 ⋅ kip ⋅ ft MDC216 = 156.49⋅ kip ⋅ ft MDW16 = 173.88⋅ kip ⋅ ft
3
MLpo16 = 1.727 × 10 ⋅ kip ⋅ ft MLne16 = −691.71⋅ kip ⋅ ft Moments at mid-span
ftgbs_po 16 = 0.261⋅ ksi MLpo Girder SVCIII bottom stresses at mid-span (< 0.537 ksi)
ftgbs_ne16 = −0.82⋅ ksi MLne Girder SVCIII bottom stresses at mid-span NO TENSION
ftgts_ne16 = −2.298⋅ ksi MLne Girder SVCIII top stresses at mid-span NO TENSION
ftdts_ne16 = 0.054⋅ ksi MLne Deck SVCIII top stresses at mid-span (< 0.38 ksi)
SVC(III) Positive Moment Stresses
0 0
Girder Bottom Stresses
−4 −4
xi
ft
Span Distances
0 0
Girder Bottom Stresses
ftgbs_nei− 2 − 2 ftgts_nei
ksi ksi
−4 −4
xi
ft
Span Distances
Ultimate Moment of Resistance
Positive Moment
0.05
β1g := 0.85 − ( fcg − 4ksi) ⋅ = 0.65 Girder stress block factor
ksi
0.05
β1d := 0.85 − ( fcd − 4ksi) ⋅ = 0.85 Deck stress block factor
ksi
kb := 2⋅ 1.04 −
fpy
= 0.28
fpu
Aps ⋅ fpu
i
c1 := Trial N.A depth from deck top
i fpu
0.85⋅ fcd ⋅ β1d⋅ bd + kb⋅ Aps ⋅
i dps
i
Aps ⋅ fpu
( )
i
cc := if c1 ≤ hd N.A depth from deck top R-section
i fpu i
0.85⋅ fcd ⋅ β1d⋅ bd + kb⋅ Aps ⋅
i dps
i
Aps ⋅ fpu − 0.85⋅ β1d⋅ fcd ⋅ bd⋅ hd
i N.A depth from deck top T-section
hd + otherwise
fpu
0.85⋅ fcg⋅ β1g⋅ Btf + kb⋅ Aps ⋅
i dps
i
cc
fps := fpu⋅ 1 − kb⋅
i
= ...
i dps
i
cc
i
Mn := Aps ⋅ fps ⋅ dps − β1d⋅ if ( cc i ≤ hd)
i i i i 2
hd cc
( 0.85⋅ fcd ⋅ bd⋅ hd) ⋅ dps − + 0.85⋅ fcg⋅ Btf ⋅ β1g⋅ ( cc − hd) ⋅ dps − hd −
i
otherwise
i 2 i i 2
Mr := ϕpo⋅ Mn
i i
cc 5 = 6.441⋅ in N.A depth from deck top < deck thickness, R-section
2
fps5 = 262.692 ⋅ ksi Aps5 = 6.944⋅ in dps5 = 66.625⋅ in
3
Mr5 = 9.712 × 10 ⋅ kip ⋅ ft Mr > Mu (STR I) = 7793 kip-ft
cc 16 = 9.808⋅ in N.A depth from deck top < deck thickness, T-section
2
fps16 = 258.711 ⋅ ksi Aps16 = 9.548⋅ in dps16 = 65.68⋅ in
4
Mr16 = 1.48 × 10 ⋅ kip ⋅ ft Mr > Mu (STR I) = 9190 kip-ft
14000 14000
Positive Moments (STR I)
Ultimate Resistance
12000 12000
10000 10000
MUpo i Mri
8000 8000
kip⋅ ft kip⋅ ft
6000 6000
4000 4000
2000 2000
0 0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
Negative Moment
( hd − 2.5in − 1.0in)
ds := D1 + 1.0in + = 66⋅ in Effective depth of negative reinforcement
2
dp := 0.875in Bar # 7 diameter used in negai=tive Rft.
dp2
As := 28⋅ π⋅ = 16.837⋅ in2 Total steel area provided for negative moment
4
Bbf := B1 = 28⋅ in Girder bottom flange width
As⋅ fy
cne := = 8.163⋅ in Whiteny block depth (a) from girder bottom < 8" ok
0.85⋅ fcg⋅ β1g⋅ Bbf
4125 4125
Ultimate Resistance
2750 2750
1375 1375
MUnei − Mrne
0 0
kip⋅ ft kip⋅ ft
− 1375 − 1375
− 2750 − 2750
− 4125 − 4125
− 5500 − 5500
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
PTf PTf ⋅ es
i i i
fcpe := + Girder bottom stresses due to effective
i Ag Sgb prestressing
4 3
Sc := Scgb = 2.148 × 10 ⋅ in Composite section modulus at girder bottom
4 3
Snc := Sgb = 1.627 × 10 ⋅ in Girder bottom section modulus
Mcr := γ3 ⋅ γ1 ⋅ fr + γ2 ⋅ ( −fcpe) ⋅ Sc − Mdhc ⋅ − 1
Sc
i
i i
Snc
14000 14000
12000 12000
10000 10000
Mn i Mcri
8000 8000
kip⋅ ft kip⋅ ft
6000 6000
4000 4000
2000 2000
0 0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
Ultimate Shear Design
Mn
i
dvv := if cc > hd Distance between the
i ( 0.85⋅ fcd ⋅ bd⋅ hd) + 0.85⋅ fcg⋅ Btf ⋅ β1g⋅ cc − hd ( i ) i
resultants of the tensile
and compressive forces
Mrne
if ( i = 10 ∨ i = 11 ∨ i = 21 ∨ i = 22)
ϕne⋅ As⋅ fy
Mn
i
otherwise
Aps ⋅ fps
i i
(
dvi := max 0.90⋅ de , 0.72⋅ hc , dvv
i )
i
Effective shear depth
de10 = 66⋅ in
Effective depth at internal supports
dv10 = 63.347⋅ in Effective shear depth at internal supports
de0 = 54.7⋅ in
Effective depth at external supports
dv0 = 51.979⋅ in Effective shear depth at external supports
de16 = 65.68⋅ in
Effective depth at (131 ft) mid-span
dv16 = 60.663⋅ in Effective shear depth at at (131 ft) mid-span
The location of critical section for shear at supports is at distance (dv) from the face of the
support:
1- For edge supports dv = 52 in = 4.33 ft
2- For internal supports dv = 63.35 in = 5.30 ft
For simplicity, the shear forces are calculated at the transfer lenght (Lt = 3.0 ft)
Dead and live loads shear forces
Dead and live load shears at supports were calculated at the transfer length (Lt = 3.0 ft)
−109.70
−8.60
−9.55
−327.87
−92.87 −6.82 −7.58 −282.05
−69.65 −4.37 −4.85 −219.21
−46.43 −1.91 −2.13 −156.96
−23.22 0.54 0.60 −95.50
0.00 2.99 3.33 105.35
23.22 5.45 6.05 166.55
46.43 7.90 8.78 226.70
69.65 10.35 11.50 285.61
92.87 12.80 14.23 343.05
109.70 14.58 16.20 392.17
−133.13 −14.06 −15.63 −428.03
−111.61 −11.79 −13.10 −367.67
−83.71 −8.84 −9.83 −291.84
−55.81 −5.90 −6.55 −221.00
−27.90 −2.95 −3.28 −149.36
VVDC1 := 0.00 VVDC2 := 0.00 VVDW := 0.00 VVu := −77.54
27.90 2.95 3.28 149.36
55.81 5.90 6.55 221.00
83.71 8.84 9.83 291.84
111.61 11.79 13.10 367.67
133.13 14.06 15.63 428.03
−109.70 −14.58 −16.20 −392.17
−92.87 −12.80 −14.23 −343.05
−69.65 −10.35 −11.50 −285.61
−46.43 −7.90 −8.78 −226.70
−23.22 −5.45 −6.05 −166.55
0.00 −2.99 −3.33 −105.35
23.22 −0.54 −0.60 95.50
46.43 1.91 2.13 156.96
69.65 4.37 4.85 219.21
92.87 6.82 7.58 282.05
109.70 8.60 9.55 327.87
VDC1 := VVDC1 ⋅ kip VDC1 0 = −109.7⋅ kip Deck + Girder Weight Shear Force
i i
VDC2 := VVDC2 ⋅ kip VDC2 0 = −8.6⋅ kip Parapet Weight Shear Force
i i
VDW := VVDW ⋅ kip VDW0 = −9.55⋅ kip Wearing Weight Shear Force
i i
i (
Mmax := max MUne − Md , MUpo − Md
i i i i ) Mmax0 = 488.05⋅ kip ⋅ ft
0.135 8
The angle of inclination for depressed cables is
calculated as following: 0.135 8
0.135 8
1- For the span (109 ft), α = 53"/(0.3*109'*12)
0.135
α = 0.135 rad 8
0 0
2- For the span (131 ft), α= 51"/(0.3*131'*12) 0 0
α= 0.108 rad
0 0
0.135 8
0.135 8
Number of depressed strands:
0.135 8
1- For the span (109 ft), nos_dep = 8 strands 0.135 8
2-For the span (131 ft), nos_dep = 10 strands 0.108 10
0.108 10
0.108 10
0.108 10
0 0
αα := 0 nnos_dep := 0
0 0
0.108 10
0.108 10
α := αα
i i
Depresed strands inclination 0.108 10
at each point 0.108 10
Number of depressed strands 0.135 8
nos_dep := nnos_dep
i i at each point 0.135 8
0.135 8
Vp := α ⋅ nos_dep ⋅ ( fpe ⋅ Apt ) Prestressing vertical 0.135 8
i i i i
component 0 0
0 0
Vp5 = 0⋅ kip Prestresseng component at 0 0
mid-span 0.135 8
Vp0 = 39.812⋅ kip
Prestresseng component span 0.135 8
(109 ft) ends 0.135 8
0.135 8
Prestresseng component span
Vp11 = 37.9⋅ kip
(131 ft) ends
Flexural-shear cracking strength
i (
Vci := max Vcci , 0.06⋅ fcg⋅ ksi⋅ bv⋅ dv
i i)
3
Mmax0 = 488.05⋅ kip ⋅ ft Mcre0 = 4.773 × 10 ⋅ kip ⋅ ft
3
Vci 0 = 2.107 × 10 ⋅ kip Flexural-shear cracking strength at span (109 ft) end
Compressive stresses at CG of
PTf PTf ⋅ es ⋅ ( ycgb − ygb) Mdhc ⋅ ( ycgb − ygb) composite section under
i i i i
fpc := − − (Prestressing force and MDC1)
i Ag Ig Ig after losses, prestressing force
has a -Ve sign
(
Vcw := 0.06⋅ fcg⋅ ksi + 0.30⋅ fpc
i i )⋅bv⋅dvi + Vpi
Web shear cracking strength (tension field)
Vc0 = 213.81⋅ kip Nominal concrete shear strength at span (109 ft) end
1650 1650
1375 1375
Vcii Vcwi
1100 1100
kip kip
825 825
550 550
275 275
0 0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
270 270
Vui Vci
kip kip
180 180
90 90
0 0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
Calculating required reinfocement
Vu
i
Vs := − Vc Shear strength to be provided by reinforcement
i ϕv i
cotθ :=
i
1.0 if (Vci < Vcwi) ∨ (MUpoi > Mcrei) Angle of inclination of diagonal
fpc
i compression stress
min 1.80 , 1 + 3⋅ otherwise
fcg⋅ ksi
Vu − ϕv⋅ Vp
i i
vu := Ultimte shear stresses
i ϕv⋅ bv⋅ dv
i
π⋅ d_stirup2
A_stirup := n_legs⋅ = 0.393⋅ in2 Area of provided stirups
4
s_max :=
i (
min 0.80⋅ dv , 24in
i ) if (vui < 0.125⋅ fcg) Maximum allowed stirups spacing
min( 0.40⋅ dv , 12in) otherwise
i
( )
Used stirups spacing as the minimum of
s_used := min s_req , s_max
i i i s_req and s_max
3
Vci 0 = 2.107 × 10 ⋅ kip Flexural-shear cracking strength
cotθ0 = 1.8
2
in Required shear reinforcement (Av/s)
Av_s0 = 0.027⋅
in
0.02
Av_si
2
in
in
0.01
0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
20
15
s_usedi
in
10
0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
Nominal Shear Resistance Verses Ultimate Shear
500 500
300 300
Vui Vni
kip kip
200 200
100 100
0 0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
77
- The bridge consists of three spans having lengths of 113’, 123’ and 113’, respectively.
• Web, Dw * tw = 50 * 1/2 in
1
b- SEC-2, for negative moments regions:
• Web, Dw * tw = 50 * 1/2 in
- Deck slab thickness, ts, is 10.0 in (includes ½ in integral wearing surface which is not
- Haunch assumed to be 2.0 in depth, but not included in the composite section properties, and
1.2. Materials:
2
2. Cross section properties:
Effective span length is the actual span length for simply supported beams or the distance
between points of permanent dead load inflection for continuous spans. This length is nearly
equals 75% of the span length for a span continuous from one side, or 56% of the span for a
span continuous from both sides. These lengths are calculated from the bridge analysis
• , = 11 ∗ 12 + 2 = 134
3
2.2. Steel girder properties of sections:
a- SEC-1 Properties:
∗ ∗ ∗ . ∗( ) ∗ ∗( . ∗ )
- C.G to girder bottom, = .
= 19.26
.
15 ∗ + 15 ∗ 0.625 ∗ (51.3125 − 19.26)
= 24776.38
b- SEC-2 Properties:
∗ ∗ ∗ . ∗( ) ∗ ∗( . ∗ )
- C.G to girder bottom, = = 22.05
15 ∗ + 15 ∗ 2 ∗ (53 − 22.05)
= 56739.76
4
2.3. Composite girder properties of section:
∗ ∗ .
- Deck slab area, = = = 150.80
.
∗ ∗ .
- Deck slab moment of inertia, = = = 1134.10
∗ . ∗
∗ ∗ . ∗ . . ∗( . ∗ . . )
- C.G to girder bottom, = = . .
= 45.89
= 84705.77
.
- Top section modulus at slab, = = = 5547
.
.
- Top section modulus at girder, = = = 14770
.
.
- Bottom section modulus at girder, = = = 1846
.
- In support regions, the concrete deck experience tensile stresses, therefore there is no
5
6
3. Live load distribution factors:
Live load distribution factors will be calculated for bending moments and shear forces. The bending
moment distribution factors will be calculated three times. The first time considers the positive
bending moments for exterior spans, the second one considers the positive moments affecting the
interior span, and the last one for the support negative moments.
- Girder SEC-1 C.G. to Deck C.G distance, = + 0.50 ∗ = 32.37 + 0.5 ∗ 9.5 = 37.12
- Girder SEC-2 C.G. to Deck C.G distance, = + 0.50 ∗ = 31.95 + 0.5 ∗ 9.5 = 36.70
∗ ∗
- Longitudinal stiffness parameter used is, =
7
3.1.2. Check the applicability using AASHTO tabels:
. . . . .
= 0.06 + ∗ ∗ ∗ ∗ .
= 0.510
. . .
- For two or more lanes loaded, = 0.075 + ∗ ∗
. ∗ ∗
. . . . .
= 0.075 + ∗ ∗
. ∗ ∗ .
= 0.759
8
3.1.4. Positive moment distribution factor, interior span:
. . .
- For one lane loaded, = 0.06 + ∗ ∗ ∗ ∗
. . . . .
= 0.06 + ∗ ∗ ∗ ∗ .
= 0.495
. . .
- For two or more lanes loaded, = 0.075 + ∗ ∗
. ∗ ∗
. . . . .
= 0.075 + ∗ ∗
. ∗ ∗ .
= 0.741
. . .
- For one lane loaded, = 0.06 + ∗ ∗ ∗ ∗
. . . . .
= 0.06 + ∗ ∗ ∗ ∗ .
= 0.502
. . .
- For two or more lanes loaded, = 0.075 + ∗ ∗
. ∗ ∗
. . . . .
= 0.075 + ∗ ∗
. ∗ ∗ .
= 0.750
9
3.2. Shear distribution factors:
.
- For one lane loaded, = 0.36 + = 0.36 +
= 0.807
. .
- For two or more lanes loaded, = 0.20 + − = 0.20 + −
= 1.029
In this section, the previously calculated load distribution factors are applied to the live load
Live load distribution factors are applied to the bending moments and shear forces envelopes in
The exterior span positive bending moments are multiplied by a distribution factor of (g = 0.759
lanes), while the interior span positive bending moments are multiplied by a distribution factor
of (g = 0.741 lanes). The support region negative moments are multiplied by (g = 0.750 lanes).
The support region is defined as the distance between points of contra-flexure under a uniform
load on all spans, and this distance found from the SAP analysis file. The support region length
is 55.0 ft. which presents 25.0 ft. from the exterior span and 30.0 ft. from the interior span.
10
The figures below illustrates the used load distribution factors for bending moments and shear
forces, respectively.
Live loads bending moments and shear forces envelopes including the load distribution factors
are shown in the figures below. The generated tables are also presented below the internal forces
envelopes.
0
-350 0 35 70 105 140 175 210 245 280 315 350
-700
-1050 -569.96
-1400
-1750 -1977.77
-1977.77
-2100
Span Distances (ft)
11
Live Load Shear Envelopes [(Trucks + Lane Load)*(g)]
175
150 150.99 148.09
125 123.33
100
75
50
Shear (kips)
25
0
-25 0 35 70 105 140 175 210 245 280 315 350
-50
-75
-100
-125 -123.33 -150.99
-150 -148.09
-175
Span Distances (ft)
Distribution Factors Moving Loads Envelopes (Without DF) Moving Loads Envelopes * g (With DF)
Point Loc.
M(+ve) M(-ve) V V(+ve) M(+ve) V(-ve) M(-ve) V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 0.76 0.76 1.03 12.80 0.00 -119.86 0.00 13.17 0.00 -123.33 0.00
1.1 11.3 0.76 0.76 1.03 12.80 1166.36 -99.54 -144.67 13.17 885.26 -102.42 -109.81
1.2 22.6 0.76 0.76 1.03 19.55 1988.60 -80.74 -289.24 20.12 1509.34 -83.08 -219.53
1.3 33.9 0.76 0.76 1.03 30.23 2486.36 -62.35 -433.80 31.11 1887.15 -64.16 -329.26
1.4 45.2 0.76 0.76 1.03 41.67 2711.19 -44.54 -578.37 42.88 2057.79 -45.83 -438.98
B=1.5 56.5 0.76 0.76 1.03 57.29 2672.36 -27.64 -722.93 58.95 2028.32 -28.44 -548.71
1.6 67.8 0.76 0.76 1.03 74.87 2398.69 -18.62 -867.50 77.05 1820.61 -19.17 -658.43
1.7 79.1 0.76 0.76 1.03 91.70 1881.16 -10.61 -1012.07 94.36 1427.80 -10.92 -768.16
1.8 90.4 0.76 0.75 1.03 107.61 1161.03 -4.34 -1156.63 110.74 881.22 -4.47 -867.47
1.9 101.7 0.76 0.75 1.03 124.34 349.11 0.15 -1445.12 127.95 264.97 0.15 -1083.84
C=2.0 113 0.76 0.75 1.03 146.74 -80.01 0.71 -2637.03 150.99 -60.73 0.73 -1977.77
C'=2.0 113.0001 0.74 0.75 1.03 10.56 -80.01 -143.92 -2637.03 10.87 -59.29 -148.09 -1977.77
2.1 125.3 0.74 0.75 1.03 10.56 384.51 -120.64 -1423.77 10.87 284.93 -124.13 -1067.83
2.2 137.6 0.74 0.75 1.03 10.56 1180.98 -101.08 -1158.95 10.87 875.11 -104.01 -869.21
2.3 149.9 0.74 0.74 1.03 18.62 1858.49 -82.83 -1029.02 19.16 1377.14 -85.24 -762.51
2.4 162.2 0.74 0.74 1.03 28.70 2273.64 -63.84 -899.10 29.53 1684.77 -65.69 -666.23
D = 2.5 174.5 0.74 0.74 1.03 44.87 2397.88 -44.87 -769.18 46.17 1776.83 -46.17 -569.96
2.6 186.8 0.74 0.74 1.03 63.84 2273.64 -28.70 -899.10 65.69 1684.77 -29.53 -666.23
2.7 199.1 0.74 0.74 1.03 82.83 1858.49 -18.62 -1029.02 85.24 1377.14 -19.16 -762.51
2.8 211.4 0.74 0.75 1.03 101.08 1180.98 -10.56 -1158.95 104.01 875.11 -10.87 -869.21
2.9 223.7 0.74 0.75 1.03 120.64 384.51 -10.56 -1423.77 124.13 284.93 -10.87 -1067.83
E=3.0 236 0.74 0.75 1.03 143.92 -80.01 -10.56 -2637.03 148.09 -59.29 -10.87 -1977.77
E'=3.0 236.0001 0.76 0.75 1.03 -0.71 -80.01 -146.74 -2637.03 -0.73 -60.73 -150.99 -1977.77
3.1 247.3 0.76 0.75 1.03 -0.15 349.11 -124.34 -1445.12 -0.15 264.97 -127.95 -1083.84
3.2 258.6 0.76 0.75 1.03 4.34 1161.03 -107.61 -1156.63 4.47 881.22 -110.74 -867.47
3.3 269.9 0.76 0.76 1.03 10.61 1881.16 -91.70 -1012.07 10.92 1427.80 -94.36 -768.16
3.4 281.2 0.76 0.76 1.03 18.62 2398.69 -74.87 -867.50 19.17 1820.61 -77.05 -658.43
F=3.5 292.5 0.76 0.76 1.03 27.64 2672.36 -57.29 -722.93 28.44 2028.32 -58.95 -548.71
3.6 303.8 0.76 0.76 1.03 44.54 2711.19 -41.67 -578.37 45.83 2057.79 -42.88 -438.98
3.7 315.1 0.76 0.76 1.03 62.35 2486.36 -30.23 -433.80 64.16 1887.15 -31.11 -329.26
3.8 326.4 0.76 0.76 1.03 80.74 1988.60 -19.55 -289.24 83.08 1509.34 -20.12 -219.53
3.9 337.7 0.76 0.76 1.03 99.54 1166.36 -12.80 -144.67 102.42 885.26 -13.17 -109.81
G=4.0 349 0.76 0.76 1.03 119.86 0.00 -12.80 0.00 123.33 0.00 -13.17 0.00
12
4.2. Dead loads Internal forces (DC1, DC2 and DW):
Dead loads bending moments and shear forces plotted here are the same values previously
2000
1690.33 1690.33
1600
1200 870.37
800
244.27 244.27
400 125.78
Moment (kip-ft)
0
-400 0 35 70 105 140 175 210 245 280 315 350
-800 -347.00
-1200
-1600
-2000
-2400 -2401.27 -2401.27
-2800
Span Distances (ft)
125
119.00 106.40
100
76.50
75
50
25
Shear (kip)
15.38 11.05
0
0 35 70 105 140 175 210 245 280 315 350
-25
-17.20
-50
-75 -76.50
-100 -106.40 -119.00
-125
Span Distances (ft)
13
DC1 DC2 DW
Point Loc.
V M V M V M
A=1.0 0 -76.50 0.00 -6.19 0.00 -11.05 0.00
1.1 11.3 -56.93 754.32 -4.61 61.04 -8.23 109.01
1.2 22.6 -37.39 1287.16 -3.03 104.16 -5.40 186.01
1.3 33.9 -17.84 1599.17 -1.44 129.41 -2.58 231.09
1.4 45.2 1.70 1690.33 0.14 136.79 0.25 244.27
B=1.5 56.5 21.25 1560.66 1.72 126.30 3.07 225.53
1.6 67.8 40.80 1210.15 3.30 97.93 5.90 174.88
1.7 79.1 60.34 638.80 4.88 51.69 8.72 92.31
1.8 90.4 79.89 -153.39 6.47 -12.41 11.55 -22.17
1.9 101.7 99.44 -1166.42 8.05 -94.39 14.37 -168.56
C=2.0 113 119.00 -2401.27 9.63 -194.32 17.20 -347.00
C'=2.0 113.0001 -106.40 -2401.27 -8.61 -194.32 -15.38 -347.00
2.1 125.3 -85.10 -1222.91 -6.89 -98.96 -12.30 -176.72
2.2 137.6 -63.83 -307.10 -5.17 -24.85 -9.22 -44.38
2.3 149.9 -42.55 347.05 -3.44 28.09 -6.15 50.15
2.4 162.2 -21.28 739.54 -1.72 59.85 -3.08 106.87
D = 2.5 174.5 0.00 870.37 0.00 70.43 0.00 125.78
2.6 186.8 21.28 739.54 1.72 59.85 3.08 106.87
2.7 199.1 42.55 347.05 3.44 28.09 6.15 50.15
2.8 211.4 63.83 -307.10 5.17 -24.85 9.22 -44.38
2.9 223.7 85.10 -1222.91 6.89 -98.96 12.30 -176.72
E=3.0 236 106.40 -2401.27 8.61 -194.32 15.38 -347.00
E'=3.0 236.0001 -119.00 -2401.27 -9.63 -194.32 -17.20 -347.00
3.1 247.3 -99.44 -1166.42 -8.05 -94.39 -14.37 -168.56
3.2 258.6 -79.89 -153.39 -6.47 -12.41 -11.55 -22.17
3.3 269.9 -60.34 638.80 -4.88 51.69 -8.72 92.31
3.4 281.2 -40.80 1210.15 -3.30 97.93 -5.90 174.88
F=3.5 292.5 -21.25 1560.66 -1.72 126.30 -3.07 225.53
3.6 303.8 -1.70 1690.33 -0.14 136.79 -0.25 244.27
3.7 315.1 17.84 1599.17 1.44 129.41 2.58 231.09
3.8 326.4 37.39 1287.16 3.03 104.16 5.40 186.01
3.9 337.7 56.93 754.32 4.61 61.04 8.23 109.01
G=4.0 349 76.50 0.00 6.19 0.00 11.05 0.00
14
4.3. Steel Bridge factored design envelopes:
In this section, the dead loads (DC1, DC2 and DW) internal forces presented in section (4.2) are
- Using these load combinations with the tabulated values in Excel gives the following
1000
0
-1000 0 35 70 105 140 175 210 245 280 315 350
-2000
-3000
-4000
-5000
-6000 -7226.10 -7226.10
-7000
-8000
Span Distances (ft)
15
Shear Envelopes Load Combination (STR I)
500
450.81
425.98
400 335.77
300
200
100
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-100
-200
-300
-335.77
-400 -425.98
-450.81
-500
Span Distances (ft)
16
4.3.2. Load Combination (SVC II) results:
0
0 35 70 105 140 175 210 245 280 315 350
-1000
-2000
-3000
-4000
-5000 -5513.70 -5513.70
-6000
Span Distances (ft)
210
140
70
Shear (kips)
0
0 35 70 105 140 175 210 245 280 315 350
-70
-140
-210
-254.07
-280
-322.90 -342.11
-350
Span Distances (ft)
17
Load Combination SVC II
Point Loc.
V(+ve) M(+ve) V(-ve) M(-ve)
A=1.0 0 -76.62 0.00 -254.07 0.00
1.1 11.3 -52.65 2075.21 -202.92 781.62
1.2 22.6 -19.66 3539.48 -153.82 1291.94
1.3 33.9 18.57 4412.97 -105.27 1531.64
1.4 45.2 57.83 4746.52 -57.49 1500.71
B=1.5 56.5 102.67 4549.30 -10.94 1199.17
1.6 67.8 150.15 3849.75 25.08 626.99
1.7 79.1 196.61 2638.95 59.75 -215.80
1.8 90.4 241.85 957.62 92.09 -1315.68
1.9 101.7 288.18 -1084.90 122.05 -2838.36
C=2.0 113 342.11 -3021.55 146.77 -5513.70
C'=2.0 113.0001 -116.25 -3019.67 -322.90 -5513.70
2.1 125.3 -90.16 -1128.19 -265.66 -2886.77
2.2 137.6 -64.09 761.31 -213.43 -1506.30
2.3 149.9 -27.24 2215.57 -162.95 -565.97
2.4 162.2 12.32 3096.46 -111.47 40.16
D = 2.5 174.5 60.02 3376.47 -60.02 325.63
2.6 186.8 111.47 3096.46 -12.32 40.16
2.7 199.1 162.95 2215.57 27.24 -565.97
2.8 211.4 213.43 761.31 64.09 -1506.30
2.9 223.7 265.66 -1128.19 90.16 -2886.77
E=3.0 236 322.90 -3019.67 116.25 -5513.70
E'=3.0 236.0001 -146.77 -3021.55 -342.11 -5513.70
3.1 247.3 -122.05 -1084.90 -288.18 -2838.36
3.2 258.6 -92.09 957.62 -241.85 -1315.68
3.3 269.9 -59.75 2638.95 -196.61 -215.80
3.4 281.2 -25.08 3849.75 -150.15 626.99
F=3.5 292.5 10.94 4549.30 -102.67 1199.17
3.6 303.8 57.49 4746.52 -57.83 1500.71
3.7 315.1 105.27 4412.97 -18.57 1531.64
3.8 326.4 153.82 3539.48 19.66 1291.94
3.9 337.7 202.92 2075.21 52.65 781.62
G=4.0 349 254.07 0.00 76.62 0.00
18
DESIGN OF COMPOEITE STEEL I GIRDERS BRIDGE
Span := 349
nop := 32 Number of Nodes In the whole Bridge Point
Ls := 349⋅ ft Bridge Total Length
0 A=1.0
i := 0 .. nop 11.3 1.1
22.6 1.2
33.9
1.3
45.2 1.4
56.5 B=1.5
67.8 1.6
79.1 1.7
90.4
1.8
101.7 1.9
113 C=2.0
113.0001
C'=2.0
125.3 2.1
137.6 2.2
149.9 2.3
162.2 2.4
xx := 174.5 D = 2.5
186.8 2.6
199.1 2.7
211.4
2.8
Location in Foot Along the Bridge
Length along with Point numbering 223.7 2.9
236 E=3.0
x := xx ⋅ ft
i i
236.0001 E'=3.0
247.3 3.1
258.6 3.2
269.9 3.3
281.2 3.4
292.5 F=3.5
303.8 3.6
315.1 3.7
3.8
326.4
337.7 3.9
349 G=4.0
SECTIONAL PROPERTIES
Rh := 1.0 Hybird factor, web and flanges have the same material
Centroied
Bbfm ⋅ tbfm⋅
tbfm Dwm ttfm
+ Dwm⋅ twm⋅ 2 + tbfm + Btfm⋅ ttfm⋅ 2 + Dwm + tbfm
yncm_b :=
2
Ancm
yncm_b = 24.195⋅ in
twm⋅ Dwm3 2
ttfm3⋅ Btfm
+ twm⋅ Dwm⋅ yncm_b − − tbfm + + ttfm⋅ Btfm⋅ yncm_b
Dwm
Incm :=
12 2 12
4 4
Incm = 2.579 × 10 ⋅ in
Centroied
Bbfs ⋅ tbfs ⋅
tbfs Dws ttfs
+ Dws⋅ tws⋅ 2 + tbfs + Btfs⋅ ttfs⋅ 2 + Dws + tbfs
yncs_b :=
2
Ancs
yncs_b = 26.688⋅ in
Second Moment of Inertia
tws⋅ Dws3 2
ttfs3⋅ Btfs
+ tws⋅ Dws ⋅ yncs_b − − tbfs + + ttfs⋅ Btfs ⋅ yncs_b −
Dws ttfs
Incs := + Dws
12 2 12 2
4 4
Incs = 5.031 × 10 ⋅ in
Incs 3 3
Sncs_b := = 1.885 × 10 ⋅ in Mid-span NC bottom section Modulus
yncs_b
−Incs 3 3
Sncs_t := = −1.885 × 10 ⋅ in Mid-span NC top section Modulus
Dws + ttfs + tbfs − yncs_b
⋅ Hcm −
Bd⋅ hd hd
Ancm⋅ yncm_b +
ycstm_b :=
n 2 = 48.421⋅ in
Acstm
hd3⋅ Bd hd⋅ Bd hd
2
Icstm := Incm + Ancm⋅ ( ycstm_b − yncm_b ) + ⋅ ycstm_b − Hcm −
2
+
12⋅ n n 2
Icstm 3 3
Scstm_b := = 1.484 × 10 ⋅ in Mid-span short term bottom section Modulus
ycstm_b
−Icstm 4 3
Scstm_t := = −2.079 × 10 ⋅ in Mid-span short term top section Modulus
Hcm − ycstm_b − hd
−Icstm 3 3
Scstm_D := = −5.545 × 10 ⋅ in Mid-span short term deck section Modulus
Hcm − ycstm_b
Long Term
Bd⋅ hd 2 Long term cross sectional area
Acltm := Ancm + = 113.101 ⋅ in
3n
⋅ Hcm −
Bd⋅ hd hd
Ancm⋅ yncm_b +
ycltm_b :=
3n 2 = 40.281⋅ in
Acltm
hd3⋅ Bd hd⋅ Bd hd
2
Icltm := Incm + Ancm⋅ ( ycltm_b − yncm_b ) + ⋅ ycltm_b − Hcm −
2
+
3⋅ 12⋅ n 3n 2
Icltm 3 3
Scltm_b := = 1.389 × 10 ⋅ in Mid-span long term bottom section Modulus
ycltm_b
−Icltm 3 3
Scltm_t := = −4.826 × 10 ⋅ in Mid-span long term top section Modulus
Hcm − ycltm_b − hd
−Icltm 3 3
Scltm_D := = −2.652 × 10 ⋅ in Mid-span long term deck section Modulus
Hcm − ycltm_b
⋅ Hcs −
Bd⋅ hd hd
Ancs ⋅ yncs_b +
ycsts_b :=
n 2 = 46.975⋅ in
Acsts
hd3⋅ Bd hd⋅ Bd hd
2
Icsts := Incs + Ancs ⋅ ( ycsts_b − yncs_b ) + ⋅ ycsts_b − Hcs −
2
+
12⋅ n n 2
−Icsts 4 3
Scsts_t := = −1.728 × 10 ⋅ in Support short term top section Modulus
Hcs − ycsts_b − hd
−Icsts 3 3
Scsts_D := = −6.954 × 10 ⋅ in Support short term deck section Modulus
Hcs − ycsts_b
Long Term
Bd⋅ hd 2 Long term cross sectional area
Aclts := Ancs + = 148.601 ⋅ in
3n
⋅ Hcs −
Bd⋅ hd hd
Ancs ⋅ yncs_b +
yclts_b :=
3n 2 = 38.556⋅ in
Aclts
hd3⋅ Bd hd⋅ Bd hd
2
Iclts := Incs + Ancs⋅ ( yclts_b − yncs_b ) + ⋅ yclts_b − Hcs −
2
+
3⋅ 12⋅ n 3n 2
4 4
Iclts = 8.524 × 10 ⋅ in Long term moment of inertia
Iclts 3 3
Sclts_b := = 2.211 × 10 ⋅ in Support long term bottom section Modulus
yclts_b
−Iclts 3 3
Sclts_t := = −5.752 × 10 ⋅ in Support long term top section Modulus
Hcs − yclts_b − hd
−Iclts 3 3
Sclts_D := = −3.505 × 10 ⋅ in Support long term deck section Modulus
Hcs − yclts_b
INTERNAL FORCES
Dead and Live Loads Moments
0.00
0.00
0.00
754.32 61.04 109.01
1287.16 104.16 186.01
1599.17 129.41 231.09
1690.33 136.79 244.27
1560.66 126.30 225.53
1210.15 97.93 174.88
638.80 51.69 92.31
−153.39 −12.41 −22.17
−1166.42 −94.39 −168.56
−2401.27 −194.32 −347.00
−2401.27 −194.32 −347.00
−1222.91 −98.96 −176.72
−307.10 −24.85 −44.38
347.05 28.09 50.15
739.54 59.85 106.87
MMDC1 := 870.37 MMDC2 := 70.43 MMDW := 125.78
739.54 59.85 106.87
347.05 28.09 50.15
−307.10 −24.85 −44.38
−1222.91 −98.96 −176.72
−2401.27 −194.32 −347.00
−2401.27 −194.32 −347.00
−1166.42 −94.39 −168.56
−153.39 −12.41 −22.17
638.80 51.69 92.31
1210.15 97.93 174.88
1560.66 126.30 225.53
1690.33 136.79 244.27
1599.17 129.41 231.09
1287.16 104.16 186.01
754.32 61.04 109.01
0.00 0.00 0.00
0.00 0.00 0.00
0.00
−109.81 885.26 2731.92 990.55
−219.53 1509.34 4659.52 1633.99
−329.26 1887.15 5809.88 1931.16
−438.98 2057.79 6251.44 1882.09
−548.71 2028.32 5996.55 1486.75
−658.43 1820.61 5083.48 745.16
−768.16 1427.80 3500.24 −342.69
−867.47 881.22 1301.64 −1758.58
−1083.84 264.97 −1365.14 −3725.57
−1977.77 −60.73 −3871.28 −7226.10
−1977.77 −59.29 −3868.76 −7226.10
−1067.83 284.93 −1418.81 −3786.13
−869.21 875.11 1049.93 −2002.62
−762.51 1377.14 2954.15 −790.24
−666.23 1684.77 4107.89 −6.37
MMLne := −569.96 MMLpo := 1776.83 MMUpo := 4474.13 MMUne := 367.24
−666.23 1684.77 4107.89 −6.37
−762.51 1377.14 2954.15 −790.24
−869.21 875.11 1049.93 −2002.62
−1067.83 284.93 −1418.81 −3786.13
−1977.77 −59.29 −3868.76 −7226.10
−1977.77 −60.73 −3871.28 −7226.10
−1083.84 264.97 −1365.14 −3725.57
−867.47 881.22 1301.64 −1758.58
−768.16 1427.80 3500.24 −342.69
−658.43 1820.61 5083.48 745.16
−548.71 2028.32 5996.55 1486.75
−438.98 2057.79 6251.44 1882.09
−329.26 1887.15 5809.88 1931.16
−219.53 1509.34 4659.52 1633.99
−109.81 885.26 2731.92 990.55
0.00 0.00 0.00 0.00
3
MDC1 := MMDC1 ⋅ kip ⋅ ft MDC15 = 1.561 × 10 ⋅ kip ⋅ ft Deck + Girder Weight Moments
i i
MLne := MMLne ⋅ kip ⋅ ft MLne5 = −548.71⋅ kip ⋅ ft Live Load Negative Moments
i i
3
MLpo := MMLpo ⋅ kip ⋅ ft MLpo5 = 2.028 × 10 ⋅ kip ⋅ ft Live Load Positive Moments
i i
3
MUne := MMUne ⋅ kip ⋅ ft MUne5 = 1.487 × 10 ⋅ kip ⋅ ft Ultimate (STR I) Negative Moments
i i
3
MUpo := MMUpo ⋅ kip ⋅ ft MUpo5 = 5.997 × 10 ⋅ kip ⋅ ft Ultimate (STR I) Positive Moments
i i
Girder Check for Constructibility (DC1)
Snc_ten := Sncs_t if MDC1 < 0.0 NC support section top modulus, in tension
i i
Sncm_b otherwise NC mid-span section bottom modulus, in tension
1.25⋅ MDC1
i
fbu_ten := Tensile stresses along the bridge length
i Snc_ten
i
30
fbu_teni ϕf ⋅ Rh⋅ fy
ksi ksi
20 20
10
0 0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
Constructibility of Compression flange
the used section modulus here is the top section modulus for positive bending regions or the
bottom section modulus for negative moments
Snc_com := Sncs_b if MDC1 < 0.0 NC support section bottom modulus, in compression
i i
Sncm_t otherwise NC mid-span section top modulus, in compression
1.25⋅ MDC1
i
fbu_com := Compressive stresses along the bridge length
i Snc_com
i
bfc_c := Bbfs if MDC1 < 0.0 Compression flange width at support, bottom flange
i i
Btfm otherwise Copression flange width at mid-spans, top flange
tfc_c := tbfs if MDC1 < 0.0 Compression flange thick. at support, bottom flange
i i
ttfm otherwise Copression flange thick. at mid-spans, top flange
d_c := Dws + ttfs + tbfs if MDC1 < 0.0 Steel section depth at support
i i
Dwm + ttfm + tbfm otherwise Steel section depth at mid-spans
fbu_com
i
Dc_c := ⋅ d_c − tfc_c
i fbu_comi + fbu_teni i i Depth of web in compression
bfc_c
i
rts :=
i Effective radius of gyration for LTB
Dc_c ⋅ tw_c
12⋅ 1 + ⋅
1 i i
3 bfc_c ⋅ tfc_c
i i
Es
Lp := 1.0⋅ rts ⋅ Limiting unbraced length to achieve plastic Moment
i i fy
Es
Lr := π⋅ rts ⋅
i i fy
Fnc2 :=
i
Rb⋅ Rh⋅ fy if Lb_c < Lp ( i )
i
Lateral torsional Buckling resistance
bfc_c
i
λf := Flange slenderness ratio
i 2⋅ tfc_c
i
Es
λpf := 0.38⋅ = 9.152 Compacte slenderness ratio limit
fy
Es
λrf := 0.56⋅ = 16.12 Non-compact slenderness ratio limit
0.7fy
Fnc1 :=
i
Rb⋅ Rh⋅ fy if λf < λpf ( i ) Local buckling resistence for compression flanges
λf i − λpf
min1 − 1 −
0.7⋅ fy
⋅ ⋅ Rh⋅ Rb⋅ fy , ( Rb⋅ Rh⋅ fy) otherwise
Rh⋅ fy λrf − λpf
9
k_c :=
i 2
Dc_ci Bend-buckling coefficient
Dwm
tw_c
i
( ( ))
Allowable copressive stresses for
Fnc_c := ϕf ⋅ min Fnc1 , Fnc2 , Fcrw , Rh⋅ fy
i i i i compression flange during constrution
30 30
− fbu_comi Fnc_ci
ksi ksi
20 20
10 10
0 0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
Service stresses Check SVC (II)
Scst_top := Scsts_t if MDC1 < 0.0 Composite short-term support section top modulus
i i
Scstm_t otherwise Composite short-term mid-span section top modulus
Scst_bot := Scsts_b if MDC1 < 0.0 Composite short-term support section bottom modulus
i i
Scstm_b otherwise Composite long-term mid-span section bottom modulus
The steel section modulus is used for MDC1 for each section. The long term section modulus
for each section is used for MDC2+MDW. The short-term modulus for each section is used
for live loads positive moment envelopes
The steel section modulus is used for MDC1 for each section. The long term section modulus
for each section is used for MDC2+MDW. The steel section modulus for each section is used
for live loads moments because it is a negative envelope
40 40
20 20
Bottom Stresses
Top Stresses
fbs_top_poi fbs_bot_poi
0 0
ksi ksi
− 20 − 20
− 40 − 40
xi
ft
Span Distances
40 40
20 20
Bottom Stresses
Top Stresses
fbs_top_nei fbs_bot_nei
0 0
ksi ksi
− 20 − 20
− 40 − 40
xi
ft
Span Distances
Flexural Nominal Strength For Composite Sections, Positive Bending
Plastic Moment Capacity
In This section, the Plastic Moment Capacity of Mid-span composite section is calculated
3
Pw := Dwm ⋅ twm⋅ fy = 1.25 × 10 ⋅ kip Web ultimate capacity
3
Ps := 0.85⋅ fcd ⋅ Bd⋅ hd = 4.328 × 10 ⋅ kip Concrete deck ultimate capacity
Dwm Pt − Pc − Ps + 1 if ( Pt + Pw ≥ Pc + Ps)
Y := 2
Pw PNA in web
ttfm Pw + Pt − Ps + 1 if ( Pt + Pw + Pc ≥ Ps)
PNA in top flange
2 Pc
( hd) ⋅ otherwise
Pw + Pt + Pc
PNA in slab
Ps
dw := ( Y) if ( Pt + Pw ≥ Pc + Ps)
Distance between PNA and web
Dwm + ttfm − Y if ( Pt + Pw + Pc ≥ Ps)
2 CG
Dwm + ttfm − Y + hd otherwise
2
Dwm − Y + ttfm + hd if ( Pt + Pw ≥ Pc + Ps)
ds := 2 Distance between PNA and deck
2 CG
hd + Y if ( Pt + Pw + Pc ≥ Ps)
2
Y − hd otherwise
2
Dwm − Y if ( Pt + Pw ≥ Pc + Ps)
Dcp_comp := 2
Composite section depth of web in
0 otherwise compression at the plastic moment
hd
Dp_comp := ds + = 6.255⋅ in Depth of PNA measured from deck top fiber
2
3
Mp_comp = 8.087 × 10 ⋅ kip ⋅ ft Mid-span composite section plastic capacity
In This section, the Yeild Moment Capacity of Mid-span composite section is calculated
1.25⋅ MDC1
i
1.25⋅ MDC2 + 1.5⋅ MDW
i i
Additional moment
Mad_bot := Scstm_b⋅ fy − − causing yeilding at
i
Sncm_b Scltm_b bottom flange
Mad_top := −Scstm_t⋅ fy −
(1.25⋅ MDC1i) + (1.25⋅ MDC2i + 1.5⋅ MDWi) Additional moment
causing yeilding at top
i
Sncm_t Scltm_t flange
i (
My_bot := Mad_bot + 1.25⋅ MDC1 + MDC2 + 1.5⋅ MDW
i i i) i
Bottom flange yeild moment
capacity
i i (
My_top := Mad_top + 1.25⋅ MDC1 + MDC2 + 1.5⋅ MDW
i i) i
Top flange yeild moment capacity
i (
My := min My_bot , My_top
i i ) Yeild moment capacity, the minium of both values
3
My_bot5 = 5.383 × 10 ⋅ kip ⋅ ft Mid-span bottom flange yeild moment capacity
4
My_top5 = 4.341 × 10 ⋅ kip ⋅ ft Mid-span top flange yeild moment capacity
3
My5 = 5.383 × 10 ⋅ kip ⋅ ft Mid-span yeild moment capacity
Nominal Moment Capacity
2⋅ Dcp_comp Es
=0 3.76⋅ = 90.553
twm fy
Dt := Dwm + ttfm + tbfm + hd = 61.375⋅ in Total depth of the section, including deck
i (
Mn := min 1.3⋅ Rh⋅ My , Mp_comp if ( 0.10⋅ Dt ≥ Dp_comp)
i)
Mp_comp ⋅ 1.07 − 0.7⋅
Dp_comp
otherwise
Dt
Nominal Moment capacity, the minimum of two values
3
MUpo5 = 5.997 × 10 ⋅ kip ⋅ ft Mid-span maximum positive moment, (STR I)
3
Mn5 = 6.998 × 10 ⋅ kip ⋅ ft Mid-span nominal moment capacity
MUpo i ϕf ⋅ Mni
4500 4500
kip⋅ ft kip⋅ ft
2250 2250
0 0
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
Flexural Nominal Strength For Steel Sections, Negative Bending
Compression flange allowable stresses
Dc10 Es
2⋅ = 100 5.70⋅ = 137.274 Non-slender Web
tws fy
bfc_c
i
rtss :=
i Effective radius of gyration for LTB, for service stresses
Dc ⋅ tw_c
12⋅ 1 + ⋅
1 i i
3 bfc_c ⋅ tfc_c
i i
Es
Lps := 1.0⋅ rtss ⋅ Limiting unbraced length to achieve plastic Moment
i i fy
Es
Lrs := π⋅ rtss ⋅ Limiting unbraced length to achieve yield Moment
i i fy
Lbs := 24.5ft if MDC1 < 0.0 Distance between lateral bracing at support and at
i i
mid-span
19.375ft otherwise
Fncu2 :=
i
Rb⋅ Rh⋅ fy if Lbs < Lps ( i i) Lateral torsional Buckling resistance
Fncu1 :=
i
Rb⋅ Rh⋅ fy if λf < λpf ( i ) Local buckling resistence for compression flanges
λf i − λpf
min1 − 1 −
0.7⋅ fy
⋅ ⋅ Rh⋅ Rb⋅ fy , ( Rb⋅ Rh⋅ fy) otherwise
Rh⋅ fy λrf − λpf
9
k :=
i 2
Dci Web bend-buckling coefficient
Dwm
0.9⋅ Es⋅ k
Fcrwu := minfy,
i
i Dws
2 Nominal web bend-buckling resistance
tws
( ( ))
Allowable copressive stresses for
Fncu := ϕf ⋅ min Fncu1 , Fncu2 , Fcrwu , Rh⋅ fy
i i i i compression flange at ultimate
Ultimate STR (I) stresses due to live load positive bending moment envelopes
The steel section modulus is used for MDC1 for each section. The long term section modulus
for each section is used for MDC2+MDW. The short-term modulus for each section is used
for live loads positive moment envelopes
Ultimate STR (I) stresses due to live load negative bending moment envelopes
The steel section modulus is used for MDC1 for each section. The long term section modulus
for each section is used for MDC2+MDW. The steel section modulus for each section is used
for live loads moments because it is a negative envelope
20 20
fbu_bot_nei ( − Fncu) i
0 0
ksi ksi
− 20 − 20
− 40 − 40
xi
ft
Span Distances
11 11
fbu_top_nei ϕf ⋅ Rh⋅ fy
ksi ksi
− 11 − 11
− 33 − 33
− 55 − 55
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
STR(I) Bot. Flange Stresses-Positive LL Env.
20 20
fbu_bot_poi ( − Fncu)
i
0 0
ksi ksi
− 20 − 20
− 40 − 40
xi
ft
Span Distances
11 11
fbu_top_poi ϕf ⋅ Rh⋅ fy
ksi ksi
− 11 − 11
− 33 − 33
− 55 − 55
0 35 70 105 140 175 210 245 280 315 350
xi
ft
Span Distances
78
5'-11"
5'-11"
5'-11"
5'-11"
5'-11"
2'-3"
2'-3"
EL. 1331.76 EL. 1331.76 EL. 1331.76
18'-11"
PIER PIER
16'-8"
16'-8"
ABUTMENT EL. 1315.10 EL. 1315.10 EL. 1315.10 ABUTMENT
COMPOSITE PRE-STRESSED BRIDGE PROPOSED ELEVATION
1:200
CL. ABUTMENT 1 CL. PIER 1 CL. PIER 2 CL. ABUTMENT 2
Sta. 40+50.50 Sta. 41+59.50 Sta. 42+90.50 Sta. 43+99.50
349'
109' 131' 109'
7x8'-2" = 57'-2"
7x8'-2" = 57'-2"
4x27'-2.75"=109' 4x32'-9"=131' 4x27'-2.75"=109'
CAST IN-PLACE INTERNAL DIAPHRAGMS CAST IN-PLACE INTERNAL DIAPHRAGMS CAST IN-PLACE INTERNAL DIAPHRAGMS
COMPOSITE PRE-STRESSED BRIDGE PROPOSED ELEVATION
1:200
63'
1'-6" 12' 12' 12' 12' 12' 1'-6"
TRAFFIC LANE TRAFFIC LANE TRAFFIC LANE TRAFFIC LANE TRAFFIC LANE
EL. 1340.08 EL. 1340.08 EL. 1340.08
8"
8
5'-11"
5'-11"
4 3 5
EL. EL.
1334.00 1334.00
13 4 8 4 13
PRE-STRESSED
GIRDER
2'-11" 7x8'-2" = 57'-2" 2'-11" AASHTO GIR
33
GIRDERS SPACING TYPE V
63
63
AASHTO GIRDER
TYPE V 10 8 10
10
14' 40' 14'
8
28 28
COMPOSITE SECTION PRE-STRESSED GIRDER
28'-6"
1:20 1:20
EL. 1315.10 EL. 1315.10
6' 40' 6'
BRIDGE PROPOSED CROSS SECTION
1:50
SIMPLE END CONTINUOUS END
STIRRUPS SPACING 2" 11 # 4 @ 14" = 11'-8" 6 # 4 @ 20" = 10' 27 # 4 @ 23.4375" = 54'-8" 6 # 4 @ 20" = 10' 8 # 4 @ 16" = 10'-8" 11 # 4 @ 14" = 11'-8" 2" STIRRUPS SPACING
8" 3'-11" 8"
5'-3"
DEPRESSING POINTS SPACING 0.30 x L = 32'-8" 0.40 x L = 43'-7" 0.30 x L = 32'-8" DEPRESSING POINTS SPACING
PRECAST GIRDER LENGTH EXTERIOR SPAN L = 109' PRECAST GIRDER LENGTH
EXTERIOR PRECAST GIRDER REINFORCEMENT DETAILS
1:50
CONTINUOUS END CONTINUOUS END
STIRRUPS SPACING 2" 11 # 4 @ 14" = 11'-8" 8 # 4 @ 16" = 10'-8" 6 # 4 @ 20" = 10' 32 # 4 @ 24" = 66' 6 # 4 @ 20" = 10' 8 # 4 @ 16" = 10'-8" 11 # 4 @ 14" = 11'-8" 2" STIRRUPS SPACING
8" 3'-11" 8"
5'-3"
DEPRESSING POINTS SPACING 0.30 x L = 39'-4" 0.40 x L = 52'-5" 0.30 x L = 39'-4" DEPRESSING POINTS SPACING
PRECAST GIRDER LENGTH INTERIOR SPAN SPAN L = 131' PRECAST GIRDER LENGTH
INTERIOR PRECAST GIRDER REINFORCEMENT DETAILS
1:50
10 STRANDS 0.6" 8 STRANDS 0.6"
DRAPED DRAPED
2222
22222
STIRRUP # 4 STIRRUP # 4 STIRRUP # 4 STIRRUP # 4
@24" @14" @23.4375" @14"
44 STRANDS 0.6" 34 STRANDS 0.6" C.G of 32 STRANDS 0.6" 24 STRANDS 0.6" C.G of
STRAIGHT Strands STRAIGHT Strands
17.125
16.41
22222
22222
C.G of C.G of
2222
2222
3.875
4.82
Strands Strands
STRANDS ARRANGEMENTS STRANDS ARRANGEMENTS STRANDS ARRANGEMENTS STRANDS ARRANGEMENTS
MID-SPAN END-SPAN MID-SPAN END-SPAN
FOR INTERIOR SPAN FOR INTERIOR SPAN FOR EXTERIOR SPAN FOR EXTERIOR SPAN
1:20 1:20 1:20 1:20
CAST IN PLACE DECK 28#7 Girder Negative Rft.
Spaced @ 7", Extended 35' CAST IN PLACE DECK 28#7 Girder Negative Rft.
Each Side of support Spaced @ 7"
2.5
1
Slab Main Rft.
CAST IN PLACE Slab Main Rft.
DIAPHRAGM PRECAST GIRDER
PRECAST GIRDER PRECAST GIRDER
CONTINUITY SECTION
1:20
CONTINUITY DETAI ELEVATION
1:20
#[email protected]" (-Ve MAIN) #3@8" (TEMP) #3@8" (TEMP) #[email protected]" (-Ve MAIN)
#4@4" #[email protected]" (DIST) #[email protected]" (DIST) #4@4"
(+Ve MAIN) (+Ve MAIN)
DECK REINFORCEMENT DETAILS CROSS SECTION
1:50
#[email protected]" (-Ve MAIN)
5'
5'
5'
5'
5'
3'-2"
3'-2"
EL. 1331.76 EL. 1331.76 EL. 1331.76
19'-10"
PIER PIER
16'-8"
16'-8"
ABUTMENT EL. 1315.10 EL. 1315.10 EL. 1315.10 ABUTMENT
COMPOSITE STEEL BRIDGE PROPOSED ELEVATION
1:200
CL. ABUTMENT 1 CL. PIER 1 CL. PIER 2 CL. ABUTMENT 2
Sta. 40+50.50 Sta. 41+63.50 Sta. 42+86.50 Sta. 43+99.50
349'
PIERS SPACING 113' 123' 113' PIERS SPACING
STEEL SECTIONS LENGTHS SEC (1) L = 88' SEC (2) L = 50' 73' SEC (2) L = 50' SEC (1) L = 88' STEEL SECTIONS LENGTHS
5x11'-2" = 55'-10"
5x11'-2" = 55'-10"
CROSS FRAME SPACING 4x19'-4.5"=77'-6" 2x17'-9"=35'-6" 24'-6" 4x18'-6"=74' 24'-6" 2x17'-9"=35'-6" 4x19'-4.5"=77'-6" CROSS FRAME SPACING
FIELD SPLICE SPACING 84'-6" 60' 60' 60' 84'-6" FIELD SPLICE SPACING
COMPOSITE STEEL BRIDGE PROPOSED PLAN
1:200
0.875
16
51.875
50
63'
1
18
1'-6" 12' 12' 12' 12' 12' 1'-6"
TRAFFIC LANE TRAFFIC LANE TRAFFIC LANE TRAFFIC LANE TRAFFIC LANE
STEEL GIRDER
SEC (1)
EL. 1340.08 EL. 1340.08 EL. 1340.08 AT MID-SPAN
10"
10"
1:20
5'-2"
5'-2"
1.6875
20
3'-7" 5x11'-2" = 55'-10" 3'-7"
GIRDERS SPACING
53.375
50
14' 40' 14'
1.6875
29'-3"
20
STEEL GIRDER
EL. 1315.10 EL. 1315.10 SEC (2)
AT INTERIOR SUPPORT
1:20
6' 40' 6'
WEARING SURFACE CONCRETE SLAB
10
2
BRIDGE PROPOSED CROSS SECTION
1:50
STEEL GIRDER
51.875
18
COMPOSITE SECTION
1:20
#[email protected]" (-Ve MAIN) #3@8" (TEMP) #3@8" (TEMP) #[email protected]" (-Ve MAIN)
#5@8" #[email protected]" (DIST) #[email protected]" (DIST) #5@8"
(+Ve MAIN) (+Ve MAIN)
DECK REINFORCEMENT DETAILS CROSS SECTION
1:50
#[email protected]" (-Ve MAIN)