Daily Gantt Chart Template - TemplateLab

This daily Gantt chart template tracks the tasks and timeline for a landscaping and pond installation project from May 2nd to May 27th. It lists 9 tasks including contract signing, design/planning, grading/seeding, planting, and trimming/pruning. The chart shows the start and end date for each task, its duration in days, and tracks progress with black boxes.

Uploaded by

Skye Lee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
439 views1 page

Daily Gantt Chart Template - TemplateLab

This daily Gantt chart template tracks the tasks and timeline for a landscaping and pond installation project from May 2nd to May 27th. It lists 9 tasks including contract signing, design/planning, grading/seeding, planting, and trimming/pruning. The chart shows the start and end date for each task, its duration in days, and tracks progress with black boxes.

Uploaded by

Skye Lee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Reset Form Save Form Print Form

DAILY GANTT CHART TEMPLATE


Landscaping and Pond Installation John Smith 02-May-20 27-May-20
PROJECT NAME CLIENT NAME START DATE END DATE

05/01/2020
05/02/2020
05/03/2020
05/04/2020
05/05/2020
05/06/2020
05/07/2020
05/08/2020
05/09/2020
05/10/2020
05/11/2020
05/12/2020
05/13/2020
05/14/2020
05/15/2020
05/16/2020
05/17/2020
05/18/2020
05/19/2020
05/20/2020
05/21/2020
05/22/2020
05/23/2020
05/24/2020
05/25/2020
05/26/2020
05/27/2020
Task Duration
Task Name Start Date End Date
ID (In Days)

T01 Contract Signing 5/2/2020 5/2/2020 1 ■


T02 Design / Planning 5/3/2020 5/4/2020 2 ■■
T03 Mobilization 5/4/2020 5/5/2020 2 ■■
T04 Grading / Seeding 5/6/2020 5/11/2020 6 ■■■■■■
T05 Soil Preparation 5/10/2020 5/13/2020 4 ■■■■
T06 Planting 5/13/2020 5/16/2020 4 ■■■■
T07 Mulching 5/17/2020 5/19/2020 3 ■■■
T08 Edges / Borders 05/20/2020 5/20/2020 1 ■
T09 Trimming / Pruning 5/21/2020 5/21/2020 1 ■
T10 Fertilizing 5/22/2020 5/22/2020 1 ■
T11 Irrigation 5/22/2020 5/24/2020 3 ■■■
T12 Walkway 5/25/2020 5/25/2020 1 ■
T13 Pond Installation 5/25/2020 5/26/2020 2 ■■
T14 Acceptance 5/27/2020 5/27/2020 1 ■

Remarks:

Thirty (30) days warranty starts after acceptance of the project