0% found this document useful (0 votes)
104 views2 pages

17.non Conformance Report

This document is a non-conformance report from a subcontractor working on the Disi-Mudawarra to Amman Water Conveyance System Project in Jordan. It details an issue found during an audit and proposes corrective actions to address the non-conformity. The subcontractor must provide details of the problem, propose a way to fix it, then sign off once corrective action is taken.

Uploaded by

asem sawalmeh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views2 pages

17.non Conformance Report

This document is a non-conformance report from a subcontractor working on the Disi-Mudawarra to Amman Water Conveyance System Project in Jordan. It details an issue found during an audit and proposes corrective actions to address the non-conformity. The subcontractor must provide details of the problem, propose a way to fix it, then sign off once corrective action is taken.

Uploaded by

asem sawalmeh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

GAMA GÜÇ SİSTEMLERİ MÜHENDİSLİK VE TAAHHÜT A. Ş.

DISI – MUDAWARRA TO AMMAN WATER CONVEYANCE SYSTEM PROJECT

Section: Ref. No.


Sub-Contractor: Time & DATE :
FORM 0017: NON-CONFORMANCE REPORT / CORRECTIVE ACTION REQUEST

Details of Non – Conformity:

Auditor Signature:
Proposed Remedial Action:

Corrective Action:

Signature: Time & DATE :


GAMA GÜÇ SİSTEMLERİ MÜHENDİSLİK VE TAAHHÜT A. Ş.