HAZOP COVERSHEET
Department:
Process / System:
HAZOP No / Revision no.:
HAZOP Review team:
HAZOP COVERSHEET
Node No.
Node Description
Design Intention
Raw Material/ Chemical
Drawings / Layout No.
Equipment
Operating conditions
Available Control Schemes
Operating Par
Service / Utilities
Temperature 0C
LP Steam
CHWR
Prepared by Approved
Reviewed by by (Leader)
(Initiator)
Name, SignName,
& SignName,
& Date:Sign & Date:
CHBR
Date:
Note:
ZOP COVERSHEET
AZOP COVERSHEET
Operating Parameters
Pressure (bar) Flow Rate
Node No.: 1 Node Description:
PARAMETER:
DEVIATION /
CAUSES CONSEQUENCES
GUIDEWORD
More Flow
No/Less Flow
Reverse Flow
High Pressure
Low Pressure
High temperature
Low temperature
High Level
Low Level
High / Low mixing
Corrosion/ Erosion
Static buildup
Contamination
Reaction
Emergency
HAZOP WORKSHEET
Exiting
EXISTING SAFEGUARDS
S L RL RECOMMENDATIONS
After Recommendations
S L RL REMARK