Commissioning Service Department
Commissioning Standard Test Formats
Description: RING MAIN UNIT TEST Record No.:
Bay no.: Drawing ref.: Sheet: 1 of 4
Contractor: Contract no.: Substation No :
1. GENERAL DATA & INFORMATION:
Sl no. :
Make :
Type :
Capacity :
Voltage rating :
Phase connection :
Frequency : 60 HZ
2. MECHANICAL CHECK AND VISUAL INSPECTION:
(As Per TCS – P – 105 Rev – 01,Item 3.40.1)
Item Description Remarks
1 Check for Damage/Defects to the body or fuses
2 Check Nameplates Information For Correctness
3 Check Quality For Paint Work
Check Tightness Of All Bolted Connections (by Torque wrench
4
method)
5 Check That All Grounding Are Securely Connected
6 Check the interlock system
7 Check the level of insulation medium (SF6,OIL,..etc)
3. ELECTRICAL TEST:
(As Per TCS – P – 105 Rev – 01,Item 3.40.2)
3.1. INSULATION RESISTANCE TEST
Insulation Checked with 5kv for 1 Min and measured values in (MΩ)
R phase - earth Y phase - earth B Phase - earth. Remarks
Criteria:
Tested by: ENG. Witnessed by: ENG.
Signature & Date: Signature & Date:
Commissioning Service Department
Commissioning Standard Test Formats
Description: RING MAIN UNIT TEST Record No.:
Bay no.: Drawing ref.: Sheet: 2 of 4
Contractor: Contract no.: Substation No :
3.2. CONTACT RESISTANCE TEST:
Connection points Phases Measured resistance at 100 ADC Remarks
Criteria:
3.2.1. INSULATION RESISTANCE BEFORE AND AFTER H.V. TEST ( 5 KV ):
Ite Value in G Ω
Description
m Before After
1 With all switches closed, test between poles and earth
2 With all switches closed, test between 2 poles and 3rd earth
3 Test across opened switching device (one side ground )
injection bay at 1 in closed position
4 Injection at bay 1 in opened position bay 2 in closed position &
grounded
Criteria:
3.2.2. HIGH VOLTAGE TEST:
Injecting phase Applying Voltage Leakage Current Time Remarks
R
Y 30 KV 60 sec
B
* Voltage should carry out at 80% applied at the approved Factory Test
Result.
Criteria:
4. TESTING FOR CABLE RING CURRENT TRANSFORMER
Tested by: ENG. Witnessed by: ENG.
Signature & Date: Signature & Date:
Commissioning Service Department
Commissioning Standard Test Formats
Description: RING MAIN UNIT TEST Record No.:
Bay no.: Drawing ref.: Sheet: 3 of 4
Contractor: Contract no.: Substation No :
4.1. GENERAL DATA & INFORMATION:
Type:
Aux. Supply:
Manufacturer:
Contact no.:
Current range:
4.2.INSULATION RESISTANCE TEST:
Applied 1000 V in Measured value in
Remarks
secondary 1 min (MΩ)
5. EARTH FAULT INDICATOR:
Current injected check earth fault indicator
25 A operated
Check earth fault indicator flag reset by depressing the reset Plunger
5.1. GENERAL DATA & INFORMATION:
Type:
Aux. Supply:
Manufacturer:
Contact no.:
Current range:
5.2. PICK UP TEST
Setting ( A ) Pick - Up value ( A )
50
25
5.3. TIMING TEST:
Tested by: ENG. Witnessed by: ENG.
Signature & Date: Signature & Date:
Commissioning Service Department
Commissioning Standard Test Formats
Description: RING MAIN UNIT TEST Record No.:
Bay no.: Drawing ref.: Sheet: 4 of 4
Contractor: Contract no.: Substation No :
Optd. Time (ms) Flag reset time (sec)
Injected current (A)
Setting Meas. Limit Meas.
50
100 10> t <30sec
25
'- Time taken at contact 9, 10 N/O
'- Alarm check on Annunciator at Control Panel ____
Tested by: ENG. Witnessed by: ENG.
Signature & Date: Signature & Date: