Wondwossen Kifle
Wondwossen Kifle
Institute of Technology
MSc, Thesis On
August 2013
FACTORS AFFECTING TIME PERFORMANCE OF
LOCAL ROAD CONTRACTORS ON FEDERAL
ROAD CONSTRUCTION PROJECTS
By
Wondwossen Kifle
AAiT School of Civil & Env. Engineering COTM Stream
Acknowledgments
It might be honest to affirm that a research work could not have been carried out by oneself
without the help of the others. My deepest gratitude goes to my advisor, Dr. Ing. Wubishet
Jekale, for his endless support and interest on my research work. His thought for the
development of a modern construction industry for our country is something to emulate for all
participated in the sector. My heartfelt thanks also go to my friends for facilitating the data
collection of this research.
I would like also to thank the staff of the Ethiopian Road Authority for providing the data for this
research. This work might have not been possible if it was not for their help. A special thanks
goes to Ato Tesfaye Workineh for all his help
Last, but not least the support of my wife is invaluable and thus this work is dedicated to my
beloved sons Robel and Nahom
Factors affecting time performance of Local Road contractors on Federal road Construction projects I
AAiT School of Civil & Env. Engineering COTM Stream
Key Words
TP Time performance
DB Design Build
Factors affecting time performance of Local Road contractors on Federal road Construction projects II
AAiT School of Civil & Env. Engineering COTM Stream
Table of Content
Abstract.................................................................................................................................... VI
Factors affecting time performance of Local Road contractors on Federal road Construction projects III
AAiT School of Civil & Env. Engineering COTM Stream
5.1 General 55
5.2 Conclusion 55
5.3 Recommendation 56
Refference 59
Factors affecting time performance of Local Road contractors on Federal road Construction projects IV
AAiT School of Civil & Env. Engineering COTM Stream
Annexes
Questionnaire survey and responded questionnaire Annex 1
Table 1 Factors affecting construction time performance in different countries (p. 23)
Table 2 Main criteria and sub criteria for Contractor’s Prequalification and bid evaluation (p.29)
Table 6 Responded Parties with their top three factors that affect their project time performance
(p.48)
Table 7 showing top five ranking factors that affected time performance (p.48)
Factors affecting time performance of Local Road contractors on Federal road Construction projects V
AAiT School of Civil & Env. Engineering COTM Stream
ABSTRACT
In Ethiopia it is common problem to observe time performance problem in almost all road
construction projects either completed in the previous years or currently progressing and the
situations are still showing little or no improvements.
The factors that result in poor time performance has been dealt by different professional,
researchers largely on the magnitude of their effect of various nation construction projects. The
aim of this thesis is to identify and evaluate the main factors affecting the time performance of
road construction projects particularly on new and upgrading projects which have been executed
or being progressing under Ethiopian Roads Authority by local contractors. In the literature
review part of this research factors affecting the time performance have been identified and local
factors have been added from local experts’ recommendations through an interview. About 22
completed and/or on progress under the ERA, RSDP III and IV were sampled for analysis of
their time performance with the identified causing factors. A questionnaire survey was conducted
on the identified factors under major groups of planning, management, financial, technical,
material equipment and labor for the sampled projects. In addition, a case study has been
conducted on selected four projects to identify factors that affect the time performance on the
specific cases.
As per the weighted rank of the respondent, financial related problems, improper utilization of
advance payment followed by financial constraint for construction material and spare parts have
been agreed as very important factors that affect the time performance. Through the course of the
case study respondents have suggested that ERA shall assist in financing the project with setting
rules and regulation to tackle the improper advance payment utilization. In line with this the
researcher has learnt that ERA, the client pre-financed projects under the case study by taking
into account the seriousness of the issue. On the other hand, poor management which is
manifested as unrealistic resource allocation in the planning period and poor site coordination of
available resource during the construction period was ranked as the preceding factor.
Finally, selected respondents have been interviewed for their recommendation to curb the ranked
factors and to minimize their effect for the upcoming projects.
Factors affecting time performance of Local Road contractors on Federal road Construction projects VI
AAiT School of Civil & Env. Engineering COTM Stream
1.0 INTRODUCTION
Infrastructure development is primary plan for any developing country, and Ethiopia being one
of the developing nations will be anxious to implement the same. Among the major
infrastructures, construction of road across different parts of the country is taken as the first
requirement to facilitate development in other sector. Accordingly, for the successful and timely
completion of the government plan, the time performance of private local contractors in the
county has to be effective. The performance of every contractor is usually evaluated with respect
to the frame work set in the subject agreement mainly; time of completion, quality of work
performed, and amount of cost incurred for the construction. Project time performance is
considered as poor when the actual completion is found more than the contract time stipulated in
the initial agreement for the specific project. As per ERA’s RSDP report, almost all projects have
poor time performance even some may take above 100% of the contract time. Hence the purpose
of this research is to identify the factors that affect the time performance of the selected local
contractors that have been participated in the Federal Highway Project since July 2007: the study
entertains new and upgrading projects.
Studies on construction industries of developing countries have found a wide range of problems
with performance. George Ofori (1994) reviewed and reported poor project performance from
many developing countries. Aniekwu and Okpala (1988) identified factors that contribute to
poor results on projects in Nigeria, and Abedi and Haxnmond (1997) and the National
Construction Council in Tanzania (1993) gave accounts of the situation in Ghana and Tanzania
respectively. Different literature mentioned that multiple dimensional factors result in the poor
performance of major road project; some found extended even more than hundred (100) percent
of the original contract time.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 1
AAiT School of Civil & Env. Engineering COTM Stream
project. The unavailability of rental equipment, poor management of owned equipment and poor
workmanships are serious issues facing local contractors in most projects in Ethiopia. There are
many indicative factors for poor time performance of Ethiopian road construction such as poor
planning, poor site management, poor design, financial problem of the contractor and resources
shortage (ERA, RSDP report, 2011). The issues that contribute to untimely performance of
selected federal road construction by local firms that involved in the construction phase were
address by this research work.
Hence, as different scholars have attempted to identify the factors that contribute for poor time
performance for some other developing countries, this thesis would focus on factors that affect
time performance of selected completed and ongoing Federal Projects and possible
recommendations would also be forwarded to alleviate the difficulties. The main factors that
affect the time performance have been identified in the literature review from the work done by
different researchers in the past. Moreover, respondent’s interviews have also been considered to
add the local prevailing factors. Due to time and financial constraints and to minimize the scope
of research, this study focused only on completed as well as ongoing projects that have been
implemented through RSDP III and IV. Questionnaire surveys which had been distributed for
each of the three parties, client, consultants and contractors has been distributed followed by case
study on selected projects to rank and in order to analyze the effect of the indentified factor on
the project time performance.
Finally, possible recommendation is forwarded as per the foundation of the analysis in order to
curb the ranked factors and minimize the problem of time performance for future road projects.
The government of the Federal Democratic Republic of Ethiopia, through Ethiopian Roads
authority, ERA, had implemented three RSDPs (I, II, III) from 1997 to 2010. And since July
2010 it has started RSDP IV. However, although both the former and latter programs have been
believed to be affected by poor time performance of the local contractors participated in the
period, as to the best knowledge of the researcher the magnitude of the problem has not yet been
investigated. Thus, the main target of this study was to find out factors that affect time
performance by taking into account the construction contexts of Ethiopia.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 2
AAiT School of Civil & Env. Engineering COTM Stream
The Ethiopian government has recently adopted a strategy to improve contractor performance
that includes closer follow up mechanisms during mobilization; it expects the contractor to
complete a certain construction in a given period of time. In order to enhance the capacity of
local contractors and to make them complete their work as to the plan, the government provides
them with some initiatives such as pre-financing the projects to minimize financial problem of
the contractors.
RSDP IV has been prepared as part of the National Growth and Transformation Plan where
strong emphasis is placed on improving access to rural areas, improvement and maintenance of
the main and rural road networks. The plan provides an opportunity to transform the road sector
by significantly increasing rural accessibility and improving the condition and standard of the
country’s road network.
Hence, this research intended to investigate the factors that contribute to poor time performance
of local contractors in the federal road sector mainly on new construction and upgrading projects
based on data collected through questionnaires from the employer, the contractor and consultant
involved in the specific project. Case study on selected projects was made to check and analyze
time performance and to find out factors that affect the project time performance. Questionnaire
and interviews were used as the research tool to assess the stated problems on ongoing projects
(which have already been completed above 60%) and completed in the recent period.
The general objective of this study is to find out the factors affecting time performance of
ongoing and completed road projects that have been launched under ERA through RSDP III and
IV and constructed by local contractors.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 3
AAiT School of Civil & Env. Engineering COTM Stream
Generally, depending on the literature reviewed and the point of view of local respondents, the
main factors which could affect the time performance of the projects stated were addressed in
relation with major groups as: unrealistic target setting, management, finance, technique,
construction material, and equipment and labor factors. And these main categories could be
divided into related sub groups.
This research comprises of six main chapters and Annexes which are described as follows:
Factors affecting time performance of Local Road contractors on Federal road Construction projects 4
AAiT School of Civil & Env. Engineering COTM Stream
Chapter three described in detail methodology followed in this research study in order
to achieve the required objectives
Chapter four contains the analysis, description and discussion of the information
gathered through the questionnaire
Chapter five provides the conclusions and recommendations of the thesis
Chapter six deals with issue which recommend and proposed for further future
researcher
Finally annex included in the research is also attached with this thesis
Factors affecting time performance of Local Road contractors on Federal road Construction projects 5
AAiT School of Civil & Env. Engineering COTM Stream
2 LITERATURE REVIEW
2.1 Introduction
The construction industry, by nature, has many special problems and requirements. The
importance of taking measures to improve the performance of the construction industry has now
been recognized in several countries at various levels of socio-economic development.
These include: Australia (Australian Procurement and Construction Council, 1997), Hong Kong,
(Singapore Construction 21 Steering Committee) and the UK construction task force (Latham,
(1994) and Egan rethinking construction (1998)). The reviews have been given impetus by both
internal and external trends which indicate a challenging future for each of these construction
industries. The trends include the needs of an increasingly sophisticated economy, client
demands, technological and social change, and globalization leading to competitive pressures.
The initiative in Singapore, which has a successful construction industry development agency
(formed in 1984 originally as the Construction Industry and Development Board, which became
the Building and Construction Authority in 1999) is a good example of such efforts. The
Authority was appointed, with the following terms of reference: (i) to arrive at a vision and role
for the construction industry in the 21st century; (ii) to examine the current status of the
construction industry with regard to techniques, manpower, management practices and others
and benchmark it against the best standards in the world; (iii) to set concrete targets for the
construction industry and its workforce in Singapore by taking into account the gaps between
current reality and the intended vision; and (iv) to recommend strategies to meet the targets and
move the construction industry and workforce towards the intended vision.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 6
AAiT School of Civil & Env. Engineering COTM Stream
The Authority formulated a vision for Singapore’s construction industry for the 21st century: “To
Be a World Class Builder in the Knowledge Age”. Hence the report outcomes for the Singapore
construction industry: (i) a professional, productive and progressive industry; (ii) a knowledge
workforce; (iii) superior capabilities through synergistic partnerships; (iv) integrated process for
high buildability; (v) contributor to wealth through cost competitiveness; and (vi) construction
expertise as an export industry. Egan (1998) suggested that there are significant inefficiencies in
the construction industry which can be resolved by implementing a more systematized and
integrated project process in which waste in all its forms is significantly reduced and both quality
and efficiency improved. He recommended that process modeling could be used as a method to
improve the construction performance. Following the Latham and the Egan reports, the
construction industry has developed its own set of Key performance indicator to measure its
performance.
Performance measurement and its indicators had been studied for several years. Karim and
Marosszeky (1999) defined performance measurement as an operational management accounting
including financial and non-financial performance indicators. They stated that performance
measurement is a process of re-thinking and re-evaluation of business processes to achieve
significant performance improvements of projects. Reichelt and Lyneis (1999) defined
performance measurement as a model which treats projects as the complex dynamic system. The
key performance indicators are identified by DETR (2000) as an applicable indication of project
and/or company levels.
Project performance can be measured and evaluated using a large number of performance
indicators that could be related to various dimensions (groups) such as time, cost, quality, client
satisfaction, client changes, business performance, health and safety. These key performance
indicators enable for measurement of project and organizational performance throughout the
construction industry. These KPIs can then be used for benchmarking purposes, and will be a
key component of any organization move towards achieving best practice.
The key performance indicators also allow to trace which processes and capabilities must be
competitive and distinctive, and which merely need to be improved or maintained. (Cheung et al.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 7
AAiT School of Civil & Env. Engineering COTM Stream
2004). Time, cost and quality are, however, the three predominant key performance indicator.
Key performance indicators are further used to evaluate the performance of construction
projects. These indicators can be used as benchmark for evaluation of the firm’s performance for
any particular project and used as future career in the construction sector.
The performance of a specified project may be measured with the key performance indicators.
Hence construction companies will be able to benchmark their performance to enable them to
identify strength and weaknesses. The key performance indicators enable a comparison between
different projects and enterprises to identify the existence of particular patterns. Navon (2005)
defined performance measurement as a comparison between the desired and the actual
performances. Ugwu and Haupt (2007) classified the key performance indicators as site-specific
and project-specific: The key performance indicators may vary from project type and site
conditions as critical required by the project type. Early contractor involvement and early
supplier involvement give contractors and suppliers the opportunity to give advice and/or
specific idea earlier to improve performance.
Neely (2005) described that performance measurement is the process of quantifying the
efficiency and effectiveness of actions. For a performance measurement system to be regarded as
useful management process, it should act as a mechanism that enables assessment to be made,
provides useful information and detect problems, allowing judgment against certain
predetermined criteria to be performed.
In general the purpose of the Key Performance Indicators is to enable measurement of project
and organizational performance throughout the construction industry. This information can then
be used for benchmarking purposes, and will be a key component of any organization’s move
towards achieving best practice.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 8
AAiT School of Civil & Env. Engineering COTM Stream
Companies that engage in benchmarking do for two basic reasons; they either attempting to
gauge where they stand against key competitor, or they are looking to learn and incorporate
successful ideas from best class companies (Acord, 200). Benchmarking is a process of
continuous improvements based on the comparison of an organizations process or products with
that of identified as best practice. The best performance achieved in practice is the benchmark
(McGeorge and Palmer, 1997). Benchmarking is a process of continuous improvement based on
the comparison of a process with these identified as a best. Benchmark is a standard of
excellence or achievement used to compare and measure against. M.Will (2008), benchmark is
the process of comparing one’s performance against a benchmark to assess current performance
and generate a plan to drive improvements in order to drive performance towards the benchmark
level.
Hence the object of benchmarking is to understand the existing process and activities and then to
identify an external point of reference or standard by which that activity can be measured or
judged. Benchmarking is a management technique aimed at achieving superiority; hence it must
be formal and structured approach that is planned, implemented and monitored. Chan Albert and
Chan Daniel (2004) obtained that the accurate construction planning is a key determinant in
ensuring the delivery of a project on schedule and within budget. It is remarked that there is an
increasing global concern about benchmarking best practice measures of construction time
performance (CTP) for use by clients, consultants and contractors in the construction industry.
Researchers in construction management and practitioners in the construction industry have
begun to realize the importance of developing best practice benchmark measures such as
construction time performance.
So in order to evaluate project key performance indicators appropriate benchmark has to be set
for each performance with respect to each KPI. Among the KPIs construction time is one which
is used as measure project performance based on pre set benchmark.
2.4 Performance Measurements
Mbugua et al., (1999) and Love et al., (2000) have identified a distinction between performance
indicators, performance measures and performance measurement. According to Mbugua et al.,
(1999), performance indicators specify the measurable evidence necessary to prove that a
planned effort has achieved the desired result. In other words, when indicators can be measured
Factors affecting time performance of Local Road contractors on Federal road Construction projects 9
AAiT School of Civil & Env. Engineering COTM Stream
with some degree of precision and without ambiguity they are called measures. However, when
it is not possible to obtain a precise measurement, it is usual to refer to performance indicators.
Performance measures are the numerical or quantitative indicators (Sinclair and Zairi, (1995). On
the other hand, performance measurement is a systematic way of evaluating the inputs and
outputs in manufacturing operations or construction activity and acts as a tool for continuous
improvements (Sinclair and Zairi, 1995; Mbugua et al., 1999). In response to calls for continuous
improvements in performance, many performance measurements have emerged in management
literature. Some examples include: the financial measures (Kangari et al., 1992; Kay 1993;
Brown and Lavenrick 1994; and Kaka et al., 1995), client satisfaction measures (Walker, 1984;
Bititci, 1994; Kometa, 1995; Harvey and Ashworth, 1997; and Chinyio et al., 1998), employee
measures (Bititci, 1994; Shah and Murphy, 1995; and Abdel-Razek, 1997),project performance
measures (Belassi and Tukel, 1996) and industry measures (Latham, 1994; Egan, 1998;
Construction Productivity Network, 1998; and Construction Industry Board, 1998); as cited in
(Mbugua et al., 1999). Cordero (1990) classifies performance measurement based on the method
of measurement and area of measurement. The methods of measurement of performance can be
in terms of the technical performance, the commercial performance and the overall performance.
The areas of measurement are at the planning and design level, the marketing level and
manufacturing level etc., and for the overall performance are at the level of a firm or strategic
business unit. Furthermore, he proposes a model of performance measurements in terms of
outputs and resources to be measured at different levels. Outputs are measured to determine
whether they help to accomplish objectives (effectiveness) and resources are measured to
determine whether a minimum amount of resources is used in the production of outputs
(efficiency).
2.5 Project success
There is still a disagreement between project management researchers as to what constitute
project success and how it is to be measured. De Wit (1988) and Pinto (1988) mentioned that it is
still not clear how to measure project success since project stakeholders perceive success or
failure factors differently. C.S.Lim and M.Z.Mohamed (1999) believed that project success
should be viewed from different perspectives of the individual owner, developer, contractor,
user, and the general public and so on.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 10
AAiT School of Civil & Env. Engineering COTM Stream
According to Albert (2002); construction time has been perceived to be one of the most essential
performance indicators among numerous successful projects. Considerable efforts have been
Factors affecting time performance of Local Road contractors on Federal road Construction projects 11
AAiT School of Civil & Env. Engineering COTM Stream
dedicated to the issue of how to benchmark best practice measures of construction time
performance for the use in the construction industry. Previous works have modeled the project
constructions duration based solely on the scope factors principally represented by construction
cost. However, a recognized appreciation of other significant attributes contributing to the
construction time has paved the way for further study in which multi- dimensional prediction
models were established.
Andi and Susandi (2003) in the Petra Christtian University noted that construction time is one
key element of performance indicators of a construction project and define time performance
(TP) as comparison between actual time (AT) and planning time (PT) to finish a project.TP
greater than one indicates bad time performance but TP=1 or TP<1 indicated good or better time
performance, in which the project is finished on time or faster than planned. The scope of time
performance is limited during construction phase only, where the contractor is the main party
who is responsible for it. It is assumed also that the assignment of PT is correct.
Okuwoga (1998) stated that cost and time performances have been identified as general
problems in the worldwide construction industry.
The failure of any construction project is mainly related to the problems and failure in the
performance. Moreover, there are many reasons and factors which attribute to such problems.
Ogunlana et al, (1996) stated that the construction industry performance problems in developing
economies can be classified in three layers: problems of shortages or inadequacies in industry
infrastructure (mainly supply of resources), problems caused by clients and consultants and
problems caused by contractor incompetence/inadequacies. The problems shortages are usually
expressed in shortage of basic resources such as construction equipment, materials or even
skilled manpower. In Ethiopian, problems caused by the client is revealed through delay in
clearing right way obstruction on time but poor design and lack of proper supervision and
contract administration are problems created by the consultants. Okuwoga (1998) identified that
the performance problem is related to poor budgetary and time control. Long et al (2004)
remarked that performance problems arise in large construction projects due to many reasons
such as: incompetent designers/contractors, poor estimation and change management, social and
technological issues, site related issues and improper techniques and tools. Navon (2005) stated
that the main performance problem can be divided into two groups: (a) unrealistic target setting
Factors affecting time performance of Local Road contractors on Federal road Construction projects 12
AAiT School of Civil & Env. Engineering COTM Stream
(i.e., planning) or (b) causes originating from the actual construction (in many cases the causes
for deviation originate from both sources). The issue of proper target setting with the
consideration of the resources availability and capacity of the local firms is important.
Good planning before implementation is a critical requirement for successful delivery of any
project. However, there is an indication that there is often an insufficient time and effort for
planning construction projects, especially at tender or pre-contract stage. The planning approach
or procedure or process used by contractors also varies from company to company and project to
project. There seem to be no \best practice" or standardized procedure that is capable of
improving the accuracy of predictions of project cost and time.
“If everybody involved in a project can work to an agreed set of processes and procedures, the
industry will not only be more efficient, but it will be in a much better position to meet the
client's business needs and objectives" (Process Protocol level 2 (1999)).
The term planning is widely used in the construction industry and means different things to
different people. Collins Dictionary defines a plan as a scheme; way of proceeding; drawing;
mapping; or an arranging beforehand. Mawdesley et al (1997) defined a plan as a detailed
scheme or method for attaining an objective. “Detailed scheme" includes the method, the
activities to be carried out, the timing of the activities, the resources to be used and the finances
required.
Schwartz (1961) suggested “the term planning appeals by its suggestion of considered, orderly
and rational action. It implies tidiness, method, system, discipline, regularity and a measure of
exactness. It gives the impression that someone is in charge and has a hand on the wheel, and a
sense of direction and distinction. It represents cooperation and coordination, and contrast with
the inevitable disorder which generally obtains when people or organizations act independently
in their own interests with no overall framework into which they are constrained to fit".
(1) Physical planning (this includes the processes of programming, scheduling and organizing of
work that is required to complete a project). Programming is considered to be a diagram or a list
showing work to be done with associated times.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 13
AAiT School of Civil & Env. Engineering COTM Stream
(2) Financial planning (this is a plan that provides the amount of money that owes into and out of
the project and when this happens).
Planning is a process that incorporates the different planning function such as, staffing function,
organizing function, monitoring function and controlling function. The planning of construction
work is a continuous iterative process with milestones. At each milestone, certain planning
deliverables are produced either for communication purpose or as a contract document or both.
The milestones are normally synchronized with the stage of construction as: pre-tender, tender,
pre-contract, contract, pre-construction, construction, commissioning, and post-construction
stages in turn which each stage produces various planning deliverables done by the various
parties involved in the project. The planning especially at the initial stage is critical starting from
the assignment of experienced both in technical and managerial skilled project manager;
allocating sufficient budget for the project and proper determination of the project time. These all
are crucial for the future time performance of the project; either under estimated project cost or
construction duration will negatively affect the performance of the project.
In general terms, Construction planning is made up of four main parts: (1) Method statements;
(2) Programming and scheduling; (3) Organizational and systems set up; and (4) Site set up and
layout. Each of these parts is considered in the context of physical and financial requirements
and is made up of a number of components construction and post-construction ( K.Gidado 2002).
Hence the employer needs to understand that comprehensive pre-construction planning often
produce better performance in time and cost by eliminating none-value adding activities at a very
early stage when it is most cost effective to change methods, procedures or even design. It also
used to provide sufficient time and budget for the construction.
It will help to focus management's attention on the problems at role level during planning and
hence simplify the project key performance controlling function (control of time, cost, quality,
safety and end user satisfaction). Among other conditions, preconstruction planning at the right
amount of detail and at the right time is an essential ingredient for successful delivery of
projects. The other issue which requires proper consideration for better performance of the
Factors affecting time performance of Local Road contractors on Federal road Construction projects 14
AAiT School of Civil & Env. Engineering COTM Stream
project is the method of project delivery and bidding process. The history of contractual
arrangements has shown that due consideration is not given for appropriates.
Ironically, the countries of origin of these procurement arrangements have changed their
approaches. For example, after a comprehensive review of the UK construction industry, Latham
(1994) advocated the building of trust and a spirit of partnering in an industry characterized by
mistrust, rivalries and adversarialism. Moreover, the “traditional” procurement approach, which
is still predominant in the Commonwealth countries, is now only one of many possible ones.
Furthermore, the influences on the UK construction have come from other industrialized
countries, mainly the US. Rwelamila et al (2000) showed that the failure to consider and
incorporate cultural traits in the procurement systems of construction project adopted in Southern
Africa is a major contributor to the generally poor performance on projects. Studies in other
countries might reach similar conclusions.
Darren R. Hale (2009) indicated that different project delivery systems within relatively
homogeneous nature have shown different performance. Ibbs et al. (2003) concluded that DB
projects outperformed DBB with respect to time, but the results relating to cost were not as
convincing. Numerous studies have shown that time can be saved by using the DB project
delivery method (Songer and Molenaar 1996; Konchar and Sanvido 1998; Molenaar et al. 1999).
Songer and Molenaar (1996) used literature and survey results versus more empirical research.
Konchar and Sanvido (1998) collected and analyzed data for 351 U.S. projects comprised of six
facility types. They used a multivariate model to examine unit cost, construction speed, delivery
speed, cost growth, and schedule growth. They concluded that DBB projects were more likely to
Factors affecting time performance of Local Road contractors on Federal road Construction projects 15
AAiT School of Civil & Env. Engineering COTM Stream
have changes in schedule than DB. They also concluded that the DB project delivery method
would show cost benefits. Bennett et al. (1996) conducted a similar study in England that also
used multivariate analysis. They compared cost, schedule and quality performance, with their
results similar to Konchar and Sanvido. Molenaar et al. (1999) described the evolution of the DB
project delivery method and analyzed 104 public-sector Design/ time, and quality data for DB
projects, but they do not compare a similar sample of DBB projects within the same
organization.
Uhlik and Eller (1999) provide an excellent description of perceived benefits of using DB versus
DBB for military medical construction projects, but have no empirical data. They suggest that a
shift to DB would decrease the time to design and build new military medical facilities. In 2006,
Federal Highway Administration (FHwA) compared project performance of DB highway
projects against similar DBB highway projects. DB highway projects were first built under
Special Experimental Project 14 (SEP-14) after FHwA started using the DB method in 1990. The
cost of projects selected for comparison were less than $20 million and the researchers selected
11 pairs of comparable highway projects built under these two delivery methods. This report
analyzes the project performance using descriptive statistics. The study results show that DB
projects had higher cost growth but lower schedule growth in comparison to DBB projects
(USDOT-FHwA 2006). Another recent study compared performance of DB and DBB highway
projects with project cost higher than $50 million. The DB projects were selected all over the
US, whereas DBB projects were selected from the state of Texas. The total sample size of this
analysis was fifteen. The statistical analysis showed that the average cost growth for DB was
lower than DBB and statistically significant.
Hence selection of appropriate project delivery system which will best suited for a particular
project type, condition, available resources and manpower will be one of the milestones for
performance of a project. The organization structure of the contractor is also being considered
during the selection of project delivery system. In usual way the DB project needs the design
capacity of a contractor in which the contractor is expected to perform both design and
construction. In contrary the DBB may be easy for price quotation as the volume of each work
item is being known but for that of the DB it may require more engineering discipline for
estimation of price with no design on hand. The type of material to be excavated, subsurface
Factors affecting time performance of Local Road contractors on Federal road Construction projects 16
AAiT School of Civil & Env. Engineering COTM Stream
condition, number and type of drainage structures all are not known. Beside the type and
standard of the project shall also be properly specified to avoid design approval conflicts.
Dubem I.Ikediashi (2012) has reviewed the performance of Design and Build project with some
key performance indicator for the Nigeria construction projects. In his study he put a set of key
performance indicators for evaluating of DB projects and to perceive the performance failure of
traditional DBB project delivery system.
It can be learnt that project performance especially time performance are affected with two stage
of construction stage; pre construction stage and during construction period. The major factors
that affect time performance during the preconstruction stage are unrealistic target setting and
method of delivery with the appropriate procurement process. In order to evaluate the project
time performance it is essential to fix the project duration of a particular project which is
equivalent to the volume of work load, resources availability, site conditions, access, precedence
requirement of some activity or technical requirements of specialized works. In the Ethiopian
context basic problems with project duration is rested to the employer side. The contractor has no
any involvement or fixing the time required rather to obey and accept the allotted time and take
all the responsibility of performance failure.
The other factor of the pre tender is planning problems. The project delivery which is usually
adopted in the country is DBB with limited case of DB system. As different researches dealt with
each type of delivery system has great effect on each key performance indicators. Proper
planning during the pre tender stage is expected by the employer, planning for section of a
project, precedence of consecutive section, allocating sufficient budget, clearing of right of
obstructions, assignment of skilled and experienced project manager for monitoring. Insufficient
and poor terms of reference will lead to uncompleted and improper design which leads to
excessive variation during the implementation stage. Problems associated with selection of
designers, lead uncompleted and erroneous design. Too much design error will automatically
result negative impact of the time performance of a particular project. Semi-completed or
uncompleted design, specification or any document may lead a consequent factor for poor time
performance. Completed, detailed and clear design in the case of DBB delivered projects and
clearly stated specification in the case of DB best suited for that particular project. It is not
uncommon to observe semi-completed design and generalized specification adopted for different
Factors affecting time performance of Local Road contractors on Federal road Construction projects 17
AAiT School of Civil & Env. Engineering COTM Stream
project that result in poor time performance. The contractor with poor or lack of proper planning
before the tender stage is the other failure for his performance. The time allotted during tendering
will lead poor pricing and poor resource allocations; failure to understand the project with
respected to access, weather condition, material availability will lead poor bidding. Assignment
of skilled professional for the tendering by the contractor lead substandard document; fails to
check his capacity for that project to satisfy him before submitting his proposal.
Good planning before tendering will help the contractor to consider all the possible risks and to
plan for alternative mechanism for minimizing the risks. Poor planning is usually failure to
predict construction risks and result as one of major factor that affect his time performance
during constructions. Good planning also used to anticipate his resource handling to check
manpower requirements, equipment requirement either to purchase or to rent, material
requirement and his financial capacity with possible credit facilities.
Uncompleted or unreliable documents submitted by the employer and/or the designer may result
reduced performance or even suspension which in turn affected the time performance. Failure of
the employer or the engineer to deliver all required documents, drawings, test results to the
contractor on time will have its own impact. The availability and capacity of all required staff by
the contractor and supervision staff as required; assignment of project manager having all the
skill and experience is also vital.
Chan and Kumaraswamy (2002) remarked that studies in various countries appear to have
contributed significantly to the body of knowledge relating to time performance in the
construction projects over the past periods. And they proposed specific technological and
managerial strategies to increase speed of construction and so to upgrade the construction time
performance. It is remarked that effective communication, fast information transfer between
project participants, the better selection and training managers, detailed construction programs
can help to accelerate the performance.
Chan and Kumaraswamy (1996) stated that a number of unexpected problems and changes from
the original design arise during the construction phase, leading to problems in the cost and time
performance. It is found that poor site management, unforeseen site condition and low speed of
decision making are most significant factors causing delays and problems of time performance.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 18
AAiT School of Civil & Env. Engineering COTM Stream
Chan and Kumaraswamy (1999) remarked that project complexity, client type, experience of
team and communication are highly correlated with time performance.
Any project with lack of good planning is lacks proper mobilization of resources and poor site
management. There is a strong relation between project management and project performance.
Management in construction industry is considered as one of the most important factors affecting
performance of works.
Low Sui Pheng (2005), a project manager is vital and indispensable in any project. While project
management is only one of the many criteria upon which project performance is contingent, it is
also arguably the most significant as it is people formulating the processes and systems who
deliver the projects. Hence the skill, experience of the project manager for handling the project
with different characteristic of the project is vital. There have been widespread research studies
of personal managerial skills of a project manager affecting the performance of the project.
Research aims to study the area of improving a project manager’s performance by identifying the
working environment variables which affect his performance.
Poor site management is the output of lack of skilled and experienced project manger both
technically and managerial skill. The project manager who is key person is important for good
site management for better time performance and success of the project. Good and experienced
project manager provides the necessary tools for the company to utilize its resources and finance
more effectively and efficiently. A successful project requires effective leadership from the
project manager. He is responsible for carrying out the project by insuring that all project
activities are completed in accordance with time and budget requirements and at the highest level
of quality. The undisputed leader of the project team, the project manger has the ultimate
responsibility for the success or failure of the project.
“A good project manager will do what it takes to complete the assignment and met the overall
project objectives” DOTD Project Delivery Manual 2005
The project manager plans, schedule and directs the project; to have a successful project, a
capable project manger follow a project management process which includes project planning,
team build(staffing), directing functions and control measures.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 19
AAiT School of Civil & Env. Engineering COTM Stream
A number of studies have been conducted to examine factors impacting on project performance
in developing countries. Faridi and El-Sayegh (2006) reported that shortage of skills of
manpower, poor supervision and poor site management; unsuitable leadership, shortage and
breakdown of equipment among others contribute to construction delays in the United Arab
Emirates. The skill of professionals available for the implementation of that specific project has
great impact on time completion of specific project.
Most construction especially road projects utilize huge number of equipments. Benjamin (1991)
stated that equipment has long been considered as one of the key factors for improving
contractor’s capability in improving their work efficiently and effectively. But contractors
usually face difficulties in getting all the equipments they need, especially capital investments, in
the acquisition phase, due to financial constraints. As the project progress to the implementation
phase, the problems of the contractors also change. One of the major problems faced during this
stage is high breakdown of the equipments mainly due to unskilled operators as well as poor
training on equipment utilizations (Edward and Nicholas 2002).
The availability of skilled and experienced manpower for the implementation of a particular
project from the initiation to the commissioning stage is very crucial. Assignment of skilled
Factors affecting time performance of Local Road contractors on Federal road Construction projects 20
AAiT School of Civil & Env. Engineering COTM Stream
project manager for initial planning who will be appointed for preparing standard terms of
reference which used as bases for designer, setting appropriate criteria for selecting capable
engineer for design works. The number of capacity, experience of skilled professional who will
be participated in the design of particular project; a design team which organized full and skilled
professional will deliver completed and error free design documents with required specifications.
Design documents either no fully completed or numerous error has great impact for the
performance of the project during implementations. These erroneous documents are usually
resulted from inexperience and unskilled professional in different specialization required in the
design stage. Moreover problems associated either in best selection or lack of appropriate
professionals at each functional organizational level during the construction stage is also crucial
factors for performance of road project in the country. The management capacity of local
engineers is under scrutiny.
In most developing countries there is shortage of manager for construction or at the very least a
shortage of adequately qualified ones. Developing and upgrading manager is a considerably
difficult and time consuming process primarily because experience is so important. Effort to train
managers for developing nations in industrialized countries has not been too successful since
they are not geared to local conditions. The training in educational and specialized institutions in
the developing countries needs considerable upgrading and lacks practical, on the job aspect due
to lack of contract with the industry itself. More works also needs to be done in the area of
upgrading existing managers, in terms of improving their management skills, teaching them new
ones, and persuading them to adapt to technological changes. . In Ethiopia, for example, the
Ethiopian Roads Authority has a Training and Testing Branch which gives courses to upgrade
workers and supervisors. A rather interesting program somewhat along these lines in Kenya is
that o the National Construction Company, established by the government in 1967 to assist
African contractors by obtaining work for them, giving them advice and training, and providing
them with finance
As per case study performed in Vietnam, The major problems faced by contractors in developing
countries that affect their performance have been classified as: (1) problems imposed by the
industry’s infrastructure, (2) problems of inaccurate information and frequent changes in
instructions and failure to meet obligations on the part of clients and consultants, and (3)
Factors affecting time performance of Local Road contractors on Federal road Construction projects 21
AAiT School of Civil & Env. Engineering COTM Stream
problems imposed by their own shortcomings. Research into the delays experienced in high-rise
building construction projects in Thailand supports this classification. A recent study on East
Asia cross-border construction identified five groupings of obstacles as business environment
risk, regulatory restrictions, contractual arrangement, and differences in standards and culture. If
the problems and/or obstacles are not solved swiftly, they can cause delays and cost overruns in
projects, harm cooperative relationships, reduce efficiency, lead to claims and disputes, and
probably invoke litigation proceedings. Other studies relating to industry problems concern
causes of time delays and/or cost overruns. Stephen Ogunlana (2004) such studies have been
conducted worldwide from developed countries such USA and UK to developing countries.
Hanson et al. (2003) examined causes of client dissatisfaction in the South African building
industry and found that conflict, poor workmanship and incompetence of contractors to be
among the factors which would negatively impact on project performance.
Ofori (1984) revealed chronic delay in the payments of contractors for work done, lack of credit
facilities for the firm, poor communication structures and an unreliable material supply are
potential factors that could affect the performance of contractors.
As per the study in Malaysia the three main causes of time-delays were, in order, the number of
change orders, financial constraints and owners’ lack of experience in construction, Aftab
Hameed Memon (2010). It clear that repeated and too much variation orders and design
modification, financial constraint for purchasing construction, either to purchase or rent
equipment on the contractor side; inexperience client for initial planning or managing during the
implementation period are factors that affect the time performance of the project.
Since there are many parties involved in a project, the communication between the parties is very
crucial for the success of the project. Proper and effective communication between the parties
must be established during the planning stage. Any problem with communication can lead to
severe misunderstanding and therefore, delays in the execution of the project. Past studies such
as Sambasivan and Soon (2007) and Tumi et al. (2009) indicated that inadequate
communications among all project parties was an important reason for delays in the projects,
which impeded the job and resulted in problems in the project coordination and schedules.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 22
AAiT School of Civil & Env. Engineering COTM Stream
The World Bank in their procurement of audit of Ghana, the World Bank (1996, 2003), Westring
(1997) and Crown Agents (1998) have continuously reported documentary evidence of contracts
taking very lengthy periods to reach financial closure and also, often subjected to unnecessary
delays, poor coordination and communication structures, fiscal constraints and extensive systems
of controls and land ownership disputes.
Several literatures have grouped factors affecting construction time performance into categories
of; labors, materials, equipment, site conditions, managerial, financial and others. A research
paper conducted in the Western Australia by Kenny Wong (2012) has summarized the factors
affecting construction time in different countries with ranking order by different Authors.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 23
AAiT School of Civil & Env. Engineering COTM Stream
Factors affecting time performance of Local Road contractors on Federal road Construction projects 24
AAiT School of Civil & Env. Engineering COTM Stream
1. Improper planning
2. Lack of effective communication
3. Material shortage
4. Design errors
5. Financial problems
1. Inclement weather
2. Shortages of labor supply
3. Subcontracting system
1. Shortage of materials
2. Failure to pay for completed works
3. Poor contract management
1. Shortage of materials
2. Changes of design
3. Liaison problems among the
contracting parties
Factors affecting time performance of Local Road contractors on Federal road Construction projects 25
AAiT School of Civil & Env. Engineering COTM Stream
1. Poor design
2. Change orders/design
3. Inclement weather
4. Unforeseen site conditions
5. Late delivery
As different researches dealt with it, project time performance has affected by different factors
among which, unrealistic target setting(planning), causes originating from actual construction,
change from the original design, poor site management, unforeseen site conditions, delay in
decision making, project type or complexity, experience of staff especially project manager,
communication problems between participants, shortage and breakdown of equipments, payment
delay and lack of credit facilities, unreliable material supply and other factors will be analyzed
by this research for the Ethiopian road construction projects particularly for these executed by
local firms. This research is also focus on upgrading and new construction project mainly to
minimize time constraints.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 26
AAiT School of Civil & Env. Engineering COTM Stream
Benchmarking is an efficient tool for collecting data and information related to competitors’
business, financial situations and possibilities for business in the specific market sectors.
Benchmarking identifies production-related and other operations in the company that should be
improved and goes much beyond the traditional analysis of the competitors. It implies deeper
analysis of the best competitors, detailed examination of their achievements and how they did
them as well as analysis of operation capabilities and characteristics of competitors’ products
aimed at taking actions to improve their own performance and business. Benchmarking benefits
are well recognized and nowadays companies all over the world increasingly implement
benchmarking to improve continuously business functions and products and to strengthen their
positions into the global market. Performance measurement and information about performance
are very rare in the construction companies. In the last few years, specific performance
measurement systems for benchmarking in different countries - Brazil (SISIND), Chile (CDT),
United Kingdom (KPI) and USA (CII) were established. Based on their experiences, rules
supporting design and implementation of benchmarking system in the construction companies
were formulated. These rules are related to choice of indicators, procedures for data collection
and availability of the system to all participants in the project. More importantly, the
development of a benchmarking tool against best practice in time performance will allow
contractors to gauge the gap in performance and to set targets aimed at closing the gap and
eventually achieving superiority. Moreover best practice benchmarking will also use to
determine appropriate construction time setting. The client shall take all the possible
consideration during fixing which used the contractor to execute the work described by the plan
and specification.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 27
AAiT School of Civil & Env. Engineering COTM Stream
The use of risk assessment improves project and construction management practices by helping
transportation professionals to focus on the potential significant risk drivers in the planning
phase. This practice would also improve cost and schedule performance through better
management of potential risks. As per the study conducted in the US that the use of risk
assessment has improved project performance and construction management practices which in
turn led to low ratings of schedule impact of certain risk drivers. The use of risk assessment
lowered the rating of cost and schedule impact for the risk drivers of; changes to unforeseen site
environment requirements, poor coordination, inexperienced professional, unforeseen conditions,
inexperienced project manager and safety issues, Mohamed F.Diab Ph.D (2012)
Factors affecting time performance of Local Road contractors on Federal road Construction projects 28
AAiT School of Civil & Env. Engineering COTM Stream
Table 2: Main criteria and sub criteria for Contractor Prequalification and bid evaluation
Ellis and Herbsman (1991) has also suggested additional criteria using time as a means of
evaluation bids of highway construction contractors by a method that bidder enters a bid price
together with a time to finish the contract, the total combined project bid being covered into cost
terms by the formula
Factors affecting time performance of Local Road contractors on Federal road Construction projects 29
AAiT School of Civil & Env. Engineering COTM Stream
Client
Means Ends
Client goals
Measures Evaluation Attributes
Assessment Assessed
Time, Cost, Quality,
flexibility,
Information against information against complexity,
criteria client goals
Suitable
Contractors Collect information
about contractors Contractor
Source; Assessment and evaluation of contractor data against, Client goals using PERT approach by
Zedan Hatush and Martin Skitmore (1997)
It can be learnt from different researchers that more cooperative procurement procedures will
have positive effects on many aspects of project performance. The procedure from the design
stage, bid invitation, bid evaluation, subcontractor selection, compensation form and
performance evaluation have their impact with the project performance.
The design stage is very important for many aspect of project performance, such as life cycle
costs, project cost and schedule (Andi and Minato, 2003, Faridi and El-Sayegh, 2006). Adequacy
of plan and specifications and a design with high constructability have been indentified to
improve overall project performance (Chua et al., 1999). The client can choose varying degrees
of detail in the design work. The extremities are to specify the technology in detail (i.e. design-
bid-build contracts) or merely the performance and functions of the product (i.e. design-build
contracts). In design-bid-build contracts the client performs detailed design work together with
consultants before contractors are procured, in order to develop a solid base for competitive
Factors affecting time performance of Local Road contractors on Federal road Construction projects 30
AAiT School of Civil & Env. Engineering COTM Stream
bidding. In design-build contracts, contractors are procured very early based on the project brief
or sketchy drawings, after which the contractor performs detailed design. This facilitates
solutions with high constructability, due to contractor focused design (Tam, 2000). The
drawback is diminished client influence in the design work. Between these extremes, where
design relies heavily either on the client or the contractor, there are alternatives in which the
client and the contractors together with consultants cooperate in developing the detailed design.
As for design-build, the contractors need to be involved early in the design process. This
approach is often called joint specification (Eriksson and Nilsson, 2008) or concurrent
engineering, since it make parallel and integrated design and construction possible (Brown et al.,
2001).
In order to decrease the risk for defective design increased coordination between design and
contractors is suitable (Andi and Minto, 2003). Early involvement of contractors in concurrent
engineering facilitates cost savings and shortened project duration due to increased buildability.
Hence the higher the level of collaboration between client and contractors in the design stage
will result in better time performance. Focus on low bid price also increase the risk for cost and
schedule growth due to several change orders (Assaf and Al-Hejji, 2006, Wardani et al., 2006).
Factors related to competence and experience, such as poor site management, supervision and
planning on behalf of the contractor, are common causes of cost and time overruns (Chan and
Kumaraswamy, 1997, Odeh and Battaineh, 2002, Assaf and Al-Hejji, 2006, Sambasivan and
Soon, 2007) and poor customer satisfaction (Maloney, 2002). Careful partner selection (through
bid evaluation based on suitable soft parameters) considering desired competences, experiences
and attitudes can therefore reduce cost growth (Chua et al., 1997, Iyer and Jha, 2005, Wardani et
al., 2006) and time overruns (Chan and Kumaraswamy, 1997), and improve quality performance
(Yasamis et al., 2002), work environment (Ai Lin Teo et al., 2005), and innovation (Manley,
2008, Bosch-Sijtsema and Postma, 2009). Environmental management systems (EMS) may not
guarantee improved environmental performance (Tam et al., 2006a). Instead, relevant training,
expertise and commitment among management staff is the most important success factor for
improvements in this area (Shen and Tam, 2002, Tam et al., 2006b). Most clients are, however,
not committed to environmental performance, but for those who are, the inclusion of
environmental management aspects in tendering requirements is important (Shen and Tam,
Factors affecting time performance of Local Road contractors on Federal road Construction projects 31
AAiT School of Civil & Env. Engineering COTM Stream
2002). Hence, bid evaluation based on suitable soft parameters that consider various
environmental aspects can improve environmental performance. Compensation based on
incentives connected to different aspects of project objectives facilitates economical performance
(Tang et al., 2006), time performance (Eriksson, 2009), quality (Eriksson, 2009), innovation
(Dulaimi et al., 2003) and a good project performance in total (Olsen et al., 2005). The following
table summarized relationship between procurement procedures and project performance (the +
sign indicates logical relationship)
Factors affecting time performance of Local Road contractors on Federal road Construction projects 32
AAiT School of Civil & Env. Engineering COTM Stream
Performance-based contracting allows the opportunity for innovation by giving the contractor
freedom to choose the construction method and materials to be used, as long as the end product
meets the performance measure(s) stated in the contract.
Design-bid-build has been the default contracting approach used by the Ethiopian Roads
authority similar to most of other nation for construction of highway projects. Major limitation of
this approach includes little or no opportunity for contractors to use experience, innovation, and
new technology. Reference to study in the US (Brain Carpenter 2003), alternative contracting
approaches impetus by addressing some of the limitations including reducing construction time,
developing advanced and improved technologies relating to materials, construction equipments
and methods; encouraging contractor innovation, and reducing impacts to public. These
alternative contracting approaches includes warranties, design build, cots-plus-time and lane
rentals (Brain Carpenter 2003).
Alternative contracting approaches based on the type of project will improve time performance
either by involving the contractor in the design process or creating financial advantage for early
finish of the project.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 33
AAiT School of Civil & Env. Engineering COTM Stream
It will help to focus management's attention on the problems at role level during planning and
hence simplify the project controlling function (control of time, cost, quality, safety and waste),
which is normally implemented at role level. This will encourage proper supervision and create a
considerable depth of knowledge concerning the role processes on site. This could be captured
by the use IT database set in the TMS format and be used continually on future projects for
learning and evolving in an adaptive manner. There is a need of a radical change in the processes
used by contractors to cost projects. We may need to replace the current methods of
measurement with a more detailed approach that is driven by financial and physical planning
based upon current knowledge, experience and expertise. To reduce the cost implication of detail
pre-tender planning, tendering subcontractors may collectively employ a Project Planning
Consultant (PPC) to produce detailed plans for common elements, leaving individual bidders to
concentrate on other specialized elements. It must be remembered that good pre-construction
planning reduces project complexity. It may be true that time and cost may be up at the first
instance of implementation, but from then onwards the process would continue to improve
performance and ultimately save time and cost. All experiences have shown that an investment
in effective planning is always fruitful and recording of achievements offers opportunities for
improvement (Kassim Gidado 2004). The more proper the schedule, the better the productivity
of the labor and accordingly the better the time performance of a specific project will be.
An issue to fundamental important is that of the development of human resources and its has
become evident over the last decades that their underdevelopment is the major factor inhibiting
effective planning and implementation of construction projects in developing countries. The
Factors affecting time performance of Local Road contractors on Federal road Construction projects 34
AAiT School of Civil & Env. Engineering COTM Stream
problem is not only one of scarcity of skilled personnel at all levels but also of major
deficiencies at the managerial level, a situation aggravated by dearth of managerial competence
in the society at large. If we examine the issue of management deficiencies closely, we find that
it leads, amongst other things, to poor planning, organizational instability, excessive
bureaucracy, unnecessary legality, slow decision making and low productivity. The nature of
human resources problem and its pervasive effects indicate the need for extraordinary action to
upgrade managerial and technical skills, broaden their range and increase their totality.
Education and training are, consequently, needed at all level and across a wide spectrum of
technical disciplines. Programs of education and training at all levels should have as one of the
prime concerns of technology progress and changes which leads to development of innovative
methods and techniques which are compatible with the local condition. It has been recognized
that this deficiency can be reduced by the establishment of in-house or on-the-job programs in
the form of short courses, workshops and seminars. Besides, the other important is the increment
of labor productivity by means of better wages, close supervision and motivation mechanisms
Aftab Hameed Memon (2010).
As per the different research made in deferent developing counties, the availability of material on
the right time and quality has positive time performance value. The contractors should exercise
a good material management system which involves both suppliers, to appropriately deliver the
materials when needed and also the contractors to have a sound schedule for the deliveries and to
select and manage his suppliers. More over proper scheduling from the very early tending stage
and strict monitoring of equipment fleet management is among the crucial action to improve time
performance of the road construction project
Generally from the previous researches as indicated above the following remedial measures have
been considered for improvement mechanism for time performance;
Developing of benchmarking
Properly fixing of project duration
Use of risk assessment for expected risk drivers
Selecting proper procurement procedures
Factors affecting time performance of Local Road contractors on Federal road Construction projects 35
AAiT School of Civil & Env. Engineering COTM Stream
Finally, the paper formulates a number of recommendations in order to bridge the gap between
the different perceptions thus improving the level of project performance in the future.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 36
AAiT School of Civil & Env. Engineering COTM Stream
3 METHODOLOGY
3.1 Introduction
This study was conducted on major factors affecting time performance of local road contractors
in the federal road construction projects. The thesis basically dealt with the project either new
construction and/or upgrading of existing road in which the Ethiopian Roads Authority is a
client. In order to find out the possible factors affecting time performance, the research mainly
focused on local projects either fully completed or their current progress reached minimum of
sixty percent (60%) of the contract work load.
In the literature review, similar studies were conducted in different part of the world; researchers
time and time again dealt with the issues of project performance as a whole, identification of key
performance indicator, benchmarking of key performance indicator to attain project success,
factors affecting these performance indicators and some more on different managerial and
contractual measures to minimize these performance hindrance.
These different researches used different methodologies and methods to attain their objectives.
Most of them use questionnaires survey, interviewing of selected individuals or groups who have
participated in the sampled projects namely project managers, resident engineers and counterpart
engineers. By taking into consideration the practiced research format used by researchers in this
field of study, the researcher sampled twenty two projects to analyze the causes of their poor
time performance: Besides the researcher conducted case studies to strengthen the findings.
Moreover, two selected respondents who involved in more than three sampled projects were
asked to comment on the identified problems through questionnaire survey and case studies. This
was done to make the experts forward possible solutions for the identified problems on the basis
of their rich experience that they developed through their long year of services. This in turn made
the researcher to cross check the findings of the study at hand with scholarly suggestions of the
experts.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 37
AAiT School of Civil & Env. Engineering COTM Stream
Chan and Kumaraswamy (2002) have also conducted a survey in Hong Kong to determine and
evaluate the relative importance of the significant factors affecting the construction delay.
Basheka (2011) has also adopted to fold method to identify impact factors that are useful for
measuring contractors performance in Uganda; first a self administered questionnaires to a group
of construction professionals (Engineers, managers which are coordinated by the Uganda
National Roads Authority) and secondly conducted in depth interviews with the representative of
Uganda National association of Buildings and Civil Engineering Contractors and Ministry
officials.
For the purpose of this research, data were collected from aforementioned projects through case
study, questionnaire survey and interviews. During the case study an attempt was made to
examine both contract completion and ongoing projects through the reports forwarded by
consultants. Tendering and contract awarding procedure and regulation that mainly used by the
Ethiopian Roads Authority were also assessed. The research design used for this thesis was
largely both quantitative and descriptive. Information regarding the companies that performed
project in the federal highway project work in the past ten years and current ongoing project
were collected from the Ethiopian Roads authority. Moreover, survey data regarding with the
factors that contribute to poor time performance were collected through prepared questionnaires
to the contractor Project managers, Resident Engineers and Counterpart Engineers of the
sampled projects.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 38
AAiT School of Civil & Env. Engineering COTM Stream
This research is focused on factors affecting time performance of local road contractors who
involved in federal road construction projects mainly on new and/or upgrading work only. The
projects which were considered by this research were either fully completed under ERA’s RSDP
III or whose progress was above 60% under RSDP IV.
3.5 Population
The population for this study was local road construction projects mainly that of new
construction and/or upgrading whose employer are the Ethiopian Roads authority. The project
which had been completed under RSPD III (from July 2007 to June 2010) and projects whose
current progress reached more than 60% of the accomplishment under the program RSDP IV
(from 2010/11 to 2014/2015) were considered as a population of the research. Accordingly, a
total of twenty two projects were sampled out of thirty two populations which were listed by the
Ethiopian Roads Authority.
Sampling is the process of selecting a number of study units from a defined study population.
Often research focuses on a large population that, for practical reasons, it is only possible to
include some of its members in the investigation. Hence we will draw a sample from the total
population using Kish (1965) sample size calculating formula at 94% of confidence level;
Where:
For 32 projects
Factors affecting time performance of Local Road contractors on Federal road Construction projects 39
AAiT School of Civil & Env. Engineering COTM Stream
This means that the questionnaire should be distributed to 22 project participants’ of which three
personnel from each contracting parties; contractors’ project managers’, Resident Engineer and
Counterpart Engineer working on each the 22 project. From the listed projects ten of them were
dropped with systematic sampling method; take first two and drop the third continuously which
automatically reduced the ten projects from listed population.
A questionnaire is a type of survey where respondents write answers to questions posed by the
researcher on a question form. Properly designed questionnaires can be used as an effective and
affordable tool for gathering large amounts of data within a relatively short period (Hague 1993).
Constructing meaningful and interpretable questions is a complex process and requires careful
word selection to ensure that the questions are asked in such a way that they are fully understood
by the respondents. This research is basically descriptive type of research which involves
gathering of survey data and case study of limited projects.
There are two types of research strategies namely quantitative research and qualitative research
(Naoum, 2007). Quantitative approaches seek to gather factual data and to study relationships
between facts and how such facts and relationships accord with theories and the findings of any
research executed previously (Fellows and Liu as cited in Al-Najjar, J., 2008). This particular
research is often qualitative type of strategy which typically involves in-depth interviews, group
discussions, artifact studies, projective techniques, and observations without formal
measurement. A case study, which is an in-depth examination of one project, is a form of
qualitative research.
After the researcher was referring deferent related theories and conducting interviews with two
senior respondents, he developed questionnaire survey. (Attached in Annex 1). The questionnaire
Factors affecting time performance of Local Road contractors on Federal road Construction projects 40
AAiT School of Civil & Env. Engineering COTM Stream
was provided with a covering letter which explained the purpose of the study, the way of
responding, the aim of the research and the security of the information in order to encourage high
response.
For the case study data such as contract completion report from the client or the consultant for
completed project; progress report of the ongoing projects were collected. Based on the current
progress and condition of their time performance, identified factors for poor time performance
were analyzed as per the set questionnaires.
Yin (1994) identified six primary sources of evidence for case study research. The use of each of
these might require different skills from the researcher. Not all sources are essential in every case
study, but the importance of multiple sources of data to the reliability of the study is well
established (Stake, 1995; Yin, 1994). The six sources identified by Yin (1994) are:
documentation,
archival records,
interviews,
direct observation,
participant observation, and
Physical artifacts.
For the purpose of the case study, the following documents were collected for analysis:
Factors affecting time performance of Local Road contractors on Federal road Construction projects 41
AAiT School of Civil & Env. Engineering COTM Stream
Factors affecting time performance of Local Road contractors on Federal road Construction projects 42
AAiT School of Civil & Env. Engineering COTM Stream
4 DATA ANALYSIS
4.1 General information
Sixty six questionnaires were distributed to construction sectors mainly for twenty two for each
party that consist of client counterpart engineers, consultant resident engineers and contractor
project managers and/or project coordinators. The total respondent rate was found as 65%
comprised of forty three respondents; twelve from the client side, fourteen from the consultant
and seventeen from the contractor.
The respondents were generally involved on each respected project as counterpart engineers,
project managers, project coordinators and resident engineers and who have minimum of first
degree in civil engineering.
Part one of the questionnaire is to obtain general information about the involvement of the
respondents. It consist of information related to their organization type, their project delivery
system, method of procurements, method of planning and evaluation schedule, communication
method and practices, method of contract time determination and percentage of time
performance of their specific project. From the respondents, 27.91% is from the client side,
32.56% is from the consultant side and 39.53 % is from the contractor side.
As per the respondents; all projects except one (that mistake DBB for BOT) put into practice
Design Bid Build (DBB) as a system of delivery. Seven projects used CPM and Bar chart, four
projects used CPM and five projects used Bar chart methods are adopted for planning and
scheduling. It is responded that major projects were evaluated, monitored and/or updated in
Factors affecting time performance of Local Road contractors on Federal road Construction projects 43
AAiT School of Civil & Env. Engineering COTM Stream
most cases with weekly and monthly time intervals. Most common communication systems
were using letter, site meetings and verbal discussions. Most of the respondents noted that the
pre-construction planning is mostly crucial factor for poor time performance and they
recommended that it should be important to incorporate as part of the contract document. As per
the respondents, most project time performance was observed to have time performance
increment of 40 to 60% from the original contract time. More than 62% of the contractor project
managers responded that the contractor was highly responsible for the poor time performance.
As to the respondent the employer usually monitored the project in monthly basis. The client
usually adopted letters, site meetings and verbal discussions for communication practices. The
counterpart engineers also confirmed that the contractor was highly responsible for their project
time performance.
The consultants responded that the project time performance was usually monitored monthly and
quarterly time interval. The communication mechanisms were similar to that of the client. They
also indicated that the pre-construction planning was the crucial for project time performance,
but they did have reservation on the necessity of including the pre-construction planning in the
contract document part. Most resident engineers and consultant representatives (85.7% of the
respondents) firmly blamed the contractor for poor time performance.
Almost all projects except one, DB project, approached through the questionnaire revealed poor
time performance. Therefore, on the basis of the addressed findings so far and the data presented
below, it could be possible to say that there were undoubtedly certain factors that affect the time
performance in every project.
The factors that affect project time performance in this research were taken from the literature
review and with some addition from the expert interviews. The factors investigated under this
study were grouped under pre-construction planning, management factors, financial factors,
technical factor, material factors, equipment factors, and construction workers factors.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 44
AAiT School of Civil & Env. Engineering COTM Stream
The response from each party was separately evaluated for the ranking of the basic factors
affecting the project time performance.
Results have been divided and separately discussed for each party for each factors. Referred the
table 5 below; respondents were requested to rank the factors using a Likert scale as:
This five point scales were converted to a Relative Important Index(RII) for each individual
factor using the following formula, as adopted by Kumaraswany and Chan (1997, 1998), Assaf
et al (1995) and Iyer and Jha (2005):
Where w is the total weight given to each factor by the respondents, which ranges from 1 to 5
and is calculated by an addition of the various weightings given to a factor by the entire
respondent; H is the highest ranking available (i.e. 5 in this case) and N is the total number of
respondents that have answered the question. (The calculated RII for each factor is attached in
the annex of the thesis)
Factors affecting time performance of Local Road contractors on Federal road Construction projects 45
AAiT School of Civil & Env. Engineering COTM Stream
From the analysis , all respondents from each parties scored RII greater than 4(four) for;
unrealistic resources assignment, improper utilization of advance payment, budget shortage for
purchasing construction materials and spare parts and late delivery of materials in terms of the
degree of contribution to poor performance of project time. If the construction of a specific
project consist good planning, it will pave ways to anticipate the resource requirements, to check
manpower requirements, equipment requirement either purchased or rental, and to identify
material and financial requirement. It is common practice that 20% of the project amount is
released as advance payment by ERA in order to disburse for the project to facilitate
mobilization and similar expense especially at the beginning of that project. But the contractor
usually utilizes the part or full of the released amount for different purposes which do not go in
line with the already proposed plan such as purchasing of new equipments. Consequently, the
project fails to commence as scheduled and actual works start late which result in bad time
performance just at the beginning of the project. Thus, when advance payment is disbursed
improperly, the projects face financial shortage for purchasing construction materials and spare
parts. According to Alaghbari (2007), El-Razek (2008) and Sweis (2008) project which face
financial difficulties or cash flow shortage will result in poor time performance. Okpala and
Aniekwu (1998) has indicated that material shortage in the Nigerian projects has negative impact
on time performance of a project, similarly it is underlined that delay in material delivery was
one of the very important factor for bad performance of project in Ethiopia too.
The client responded (RII=4.33) for improper utilization of advance payment and rising material
cost as first factors for poor time performance since they make the contractors fail to commence
project and delay in mobilization. Similarly, the project managers also ranked (RII=4.59) first
claiming that they were tired of their head office for their inability to supply the required
resources on time. But the resident engineers ranked third (RII=4.29).
The client counter parts ranked first the rising of construction materials cost, but the contractor
project managers and the consultant ranked ninth (RII=3.88) and seventh (RII=3.93) respectively
for the rising cost of materials.
Similar to Chan and Kumaraswamy (1996) Poor estimation of quantities and unforeseen site
condition which are both design related problems with RII=4.25 and RII=4.17 are ranked second
and third by the counterpart engineers for their impact which usually leads the client for time
Factors affecting time performance of Local Road contractors on Federal road Construction projects 46
AAiT School of Civil & Env. Engineering COTM Stream
extension. The initial bid quantities have increased and the contractor need additional time for
the construction. Similar impact has concurred with the case study; two projects in the case study
were forced to extend from their original completion time mainly due to an increase volume of
rock excavation and change of unforeseen subsurface condition for bridge foundation.
The resident engineers ranked planning related problems such as; lack of budget allocation
(RII=4.57) followed by poor controlling of resources (RII=4.36) first and second factors for
project poor time performance. Tumi (2007) and Samasivan (200) have indicated that improper
planning ranked as the main factor for bad time performance. Chan (2002) has also indicated
poor site management in controlling of resources as key factor for project bad performance.
However, client has ranked ninth (RII=3.67) and seventh (RII=3.83) while contractor ranked
fourth (RII=4.24) and sixth (RII=4.06) respectively.
Besides, the improper utilization of advance payment, the consultant also ranked poor leadership
of project manager, equipment maintenance problem (RII=4.29) as the third factor for bad time
performance. Similarly, Low Sui Pheng (2005) stated the importance and impact of the project
manager for time performances of a project.
Similarly, the contractor project managers have responded, improper utilization of advance
payment (RII=4.59), financial problem for spare parts (RII=4.47) and budget shortage for
construction materials (RII=4.41) as the top three factors in the order for poor project time
performances. The project managers have replied all the top three factor in related to financial
problem; first just at the beginning of the project cash is disbursed out of the project and unable
them to commence the project followed by cash flow shortage. In the case study for four
projects it has been concurred that the employer has granted additional ten percent advance
payment(as pre-financing) to assist the contractor for material purchasing of fuel, cement,
bitumen and reinforcement bar. Moreover, having understood the contractor financial
management problems, the employer has been arranged these advance payment to be paid
directly to material suppliers up on delivery after signing supplementary agreements.
Generally, the following table 6 summarized the priority of the three parties
Factors affecting time performance of Local Road contractors on Federal road Construction projects 47
AAiT School of Civil & Env. Engineering COTM Stream
Table 6: Responded parties with their top three factors that affect their project time
performance
Rank of factors
Party
First Second Third
Financial and material Design related Design plus management
Client
related related
Management related Management related Management, Financial and
Consultant
equipment related
Contractor Financial related Financial related Financial related
Refer to the table below, a combined analysis has also made by combining all the three parties;
accordingly improper utilization of advance payment (RII=4.42) has ranked first followed by
budget shortage for spare part and construction material (RII=4.23) followed by poor financial
planning (RII=4.19) as the top three crucial factors for road construction projects.
Table 7: showing top five ranking factors affection time performance combined of each party
Factors affecting time performance of Local Road contractors on Federal road Construction projects 48
AAiT School of Civil & Env. Engineering COTM Stream
In the distributed questionnaires, most respondents has blamed the contractor for causing
problem of major factors such as financial, management, construction material, equipments and
workers related factors but the Engineer has taken responsibility for technical related factors.
The general respond of the three parties with respect to the main factors that affect project time
performance is elaborated and described as follows:
i) Financial
The responds of the three parties who involved in the project gave much weight for financial
related problems to directly associate to the project time performance. The Ethiopian Public
Procurement Agency (PPA) law allows and advances payment up to 30% of the project cost, and
it commonly releases 20% of the project cost as advance payment to be utilized strictly for that
specific project. However, as respondent points as “very important factor”, the financial problem
started at this stage immediately after the advance payment released for it is expended for
contractors’ other interest out of the project consumptions which automatically delayed the
contractor mobilization and the commencement following project preparatory work as per the
contractual schedule. In the case study, it was confirmed that every project was supplemented by
pre-financing; with newly modified supplementary agreement denied direct payment of the cash
to the contractor but critically reduce the contractor’s cash flow problem. From the newly
adapted supplementary agreements one can learn that improper utilization of advance payment
was leading the contractors to the problem of cash flow for the smooth progress of the projects.
In other words, the newly adapted supplementary agreement which came at the result of
mismanagement of advance payments by the contractors forced the client to provide the
contractor with materials in kind.
This argument was also confirmed even by the project managers. Generally, responses from
both parties show the existence of financial related factor; cash flow shortage for material and
equipment purchasing is very important factor for poor CTP; hence, poor financial management
followed by cash flow shortage contributed very important role to major project time
performance. But in the case study it was understood that most effect of project cash flow
problem were minimized by the employer’s additional advance payment.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 49
AAiT School of Civil & Env. Engineering COTM Stream
ii) Management
The problem of management in the construction may be manifested through problem of planning
and scheduling, controlling and monitoring, evaluation and motivating. Planning especially at
the beginning or pre-construction stage has crucially important for on time performance of a
project; physical planning for detail processes of programming, scheduling and organizing of
work that is required to complete a project and financial planning enables the amount of money
allotted to be used fairly throughout the life of the project. The respondents revealed that
management related factor either initial during the planning stage that assign unrealistic resource
and/or budget is the start of the deficiency which consequently lead to un avoidable delay of the
project. Moreover, selection of proper project manager, leadership and coordination capacity of
the project manager, poor controlling and evaluation of the different level of the organization,
unclear organizational relation with the head office are others major management related factors
which result delay of a project. Low Sui Pheng (2005) and Chan and Kumaraswamy (1996)
explained the impact in a similar way too.
In questionnaires survey, planning related factors have ranked as a very important factor
following poor controlling and coordination of the site resources. Management decision delay
which output project delay was responded through delay in clearing of right of way by the
employer was also weighted more than RII of 4.00 to contribute very important factor for project
delays.
The consultant ranked technical related factors as moderately important contributor, but the
contractors and client took them as very important to put their impact on the specific project TP.
In the questionnaires survey, the counterpart engineers responded that among the technical or
design related factors which expressed in poor estimation and lack of detailed design for
subsurface and material classification critically affected the completion of a project. It was also
concurred through the case study that three projects out of the four (seventy five percent) were
fully delayed by design related problem: either poor classification and quantification of
earthwork items or poor or incomplete design of bridge substructures.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 50
AAiT School of Civil & Env. Engineering COTM Stream
Both respondents from each party ranked late delivery of construction material as a very
important factor for project delay followed by rising cost of materials. The progress of
construction project is directly related with continuous supplies of construction material as per
the schedule and site consumption; otherwise, if there is any interruption of the same supply
could consequently result in delay and poor time performance. Lack of construction materials in
the local markets was ranked by respondent within the top ten factors. In the impact of shortage
of materials becomes more visible when we see what ERA did in the past to tackle the shortage
of cement in the local markets. As we all might know, ERA granted 180calender days of time
extension for almost all projects due to shortage of cement in the local market in the year 2010.
Ignatius (1990) at the University of West Indies stated that poor equipment management could
lead bad project time performance. Similarly, it was responded that poor equipment management
for utilization followed by bad maintenance schedule of mobilized construction equipments
ranked as the crucial and very important factors for poor CTP. Besides, among the four studied
projects, the completion of one project is still unpredictable due to some factors such as shortage
of equipments
High turnover and stability of construction workers followed by availability of skilled workers
with different specialization ranked as a very important factor for CTP.
A case study was conducted on four projects in order to check the identified factors on each
specific project. Similar to very important factor ranked through questionnaire survey, these
projects faced financial problem which was resolved by the employer by granting up to 10%
additional pre-financing assistance for purchasing material (fuel, cement, bitumen and or
explosive).
Factors affecting time performance of Local Road contractors on Federal road Construction projects 51
AAiT School of Civil & Env. Engineering COTM Stream
The four projects which were designed and constructed by different consultants and contractors
were studied for identification of the main factors that result in their poor time performance.
These projects vary from new construction on previously inaccessible route to the upgrading of
existing low standard road. They are also located geographically in the Northern, North Western,
Western and Southern part of the country having different weather condition: dry desert to highly
rainy months of the years. All projects were delivered as Designed Bid Build (DBB) with open
invitation contract awarding system and the contracts also awarded for least bid offered
contractor among the participants during the bid time.
During the preparation of this thesis, all projects were completed except one which is still on
progress. Moreover all four projects have poor time performances which are delayed from the
original agreed contract time varying from 39% to 91% except one which is expected to increase
above the current percentage due to the listed causes. The first project is fully delayed from the
initial contract time by 39% mainly due to client change of the scope of the project; initially it
was designed as DS5 gravel road with carriage width of 7m and it was changed to DS4 DBST
surface having 10m carriage width road after some portion of the project was executed. The
contractor was forced for re-work on widening of earthwork and drainage structures following
the scope modification. The second project was delayed by 90% in which all time has granted by
the Employer principally; volume of rock excavation increment (poor design in classification of
roadway excavation between soft and hard) and volume of drainage structures were increased
basically due to faulty hydrological assumption.
The third project was also performed by 49% of extra time basically associated with the problem
of one bridge design. The whole project was delayed for some period due to unexpected wet
weather, and the commencement of the bridge work was delayed due to increment of the river
water level on the scheduled months. The foundation of the bridge, which was investigated
during the design period, took significant period for investigation and design work after part of
the excavation was executed. Moreover, the location of the bridge which would have been easily
observed during the design time has result in negative impact on the performance of the project.
The fourth project which is still under progress has observed multiple factors and both the
contractor and the consultant representatives are pessimist for expected completion of the project
due to unresolved prevailing problems. Among the different factors, the base line for the
Factors affecting time performance of Local Road contractors on Federal road Construction projects 52
AAiT School of Civil & Env. Engineering COTM Stream
comparison, the contract time is totally incomparable to the project work load and its nature; the
project scope was also found to be problematic; 90km new and inaccessible project except the
two extreme ends would have been better awarded into two contracts. In the tender stage, the
criteria set by the employer for contractor selection seemed incomparable to the project nature
and work load; the project required more than triple resources mobilization beyond pre-tender
requirements. This lastly led the contractor for financial shortage since more than 90% of the
20% advance payment was disbursed for purchasing of heavy equipments. There was no pre-
tender planning by the contractor for the need of resources and proper pricing; the project
manager concurred that the contractor started to know the project nature as construction
progressed and faced the problem especially material shortage and access problems. During the
construction stage the effect of poor design, bad weather and contractor related problems
(management, financial, equipment and labor) are clearly visibly. The project workload is
increased due to poor design that manifested in terms of erroneous estimation of earthwork
quantities and failure to design a bridge on pre-determined foundation level. The project is
located in areas with extended rainy months (from five to six month in a year) that forced the
contractor to pend his construction and idle the resources. Even though the employer has
granted extension of time for weather and design related problem which result in the indicated
90% time performance increment, problem related to the contractor would undoubtedly increase
the completion date of the project more than 190%. The project entertained multiple
management problems: there is no valid work program, huge communication problems between
the site staff and head office, the number of mobilized equipment are incomparable to the project
work, material supply problem such as fuel and cement, cash flow for working capital, high
professionals’ turnover and shortage. The financial problem aggravated mainly poor price of the
contractor and improper utilization of the advance payment at the beginning of the project.
Moreover, the ERA’s contract pre-qualification criteria are not fully performance based which
allowed the contractor to participate and get another project and shared owned equipment which
further aggravated the problems.
Generally, the following facts were drawn by case study from these sampled projects thought to
be as the main factors that affect the time performance of the project;
Factors affecting time performance of Local Road contractors on Federal road Construction projects 53
AAiT School of Civil & Env. Engineering COTM Stream
Improper time fixing by the employer, it is surprising issue that all four
projects have different work load, nature and weather condition but similar
1095 calendar days of contract time
Lack of contractor pre-tender planning
Poor design, poor estimation and incomplete design
Loose ERA’s pre qualification criteria
Cash flow shortage and financial management problems which is more or less
solved by the employer
Adverse weather condition
Site Management problems
Resources shortage; material, equipment and labor
Material shortage in the local market like cement
In general, the employer shall take more responsibility to avoid the possible occurrences of time
performance from the initiation period by properly defining the scope of the project that will be
manageable by the capacity of the local contractors. The time allotted for the specific project
shall also be scientifically determined which will be equivalent to the volume of designed work
load of the project. More cooperative procurement procedures have positive effect on the
performance of a project hence it will be advantageous to adopt cooperative procurement
procedure from the design stage, bid invitation, bid evaluation and contractor selection stages.
The prequalification criteria for specific project are very important parameter that used to
investigate and assess the capabilities of a contractor to carry out the contract of a specific
project satisfactorily. This will done based on the information provided by the contractor for
different set of criteria such as financial soundness, technical ability, management capability and
reputation before the award of the project.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 54
AAiT School of Civil & Env. Engineering COTM Stream
Following the analysis of survey data results and the output of the case study, the crucial factors
affecting project time performances were identified and investigated in a great depth by
interviewing experienced professionals in order to forward possible recommendations for
upcoming projects. The interviews were made following the data collection and major time
performance ranking factors forwarded by the respondents were indentified. During the
interview sessions questions were specifically raised for respondents for their opinion on the
degree of agreement of the factor and their possible recommendation to improve the prevailing
poor time performance of the road construction sector in the upcoming projects
5.2 Conclusions
Setting detailed pre-construction planning that take into consideration the sources (owned or
rent) of equipment, set up project management team, assignment of proper project manager and
other professionals, authorization of the project manager, line of resource supply and monitoring
mechanism of the performance of the project team is found to be crucial. The project manager
with his/her site management team must have full authority of the decision making power.
The allotment of insufficient time to design the project will automatically result in poor design
which in turn brings incomplete and/or erroneous design which affects the daily performance of
the project during construction.
In most developed countries, as shown in the literature review, alternative project delivery
systems such as DB other than the usual DBB are practiced to improve time performance of road
construction projects. However, through the course of the present study, the researcher leaned
that applying DB project delivery system in Ethiopian context could be quite pre-matured due to
lack of design experience of the contractors and Lack of secondary data such as geological and
geographical data which makes estimation difficult.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 55
AAiT School of Civil & Env. Engineering COTM Stream
As per this research, it is found that financial related factors are the very important to affect the
time performance of the selected road projects. Moreover, financial management of projects that
result in poor time performance is expressed in improper utilization of advance payments; as the
advance is improperly utilized, the contractor fails to start as schedule, and the financial shortage
reduce the daily output which consequently result in delay of the project. This problem of
financial shortage is aggravated following lack of credit facilities. Short-term bank loan and/or
credit facilities from material suppliers especially bitumen, equipment sellers and renting firm in
important, but the Ethiopian situations is still far from the developed world and it is all the
responsibility of the main contractor which threat his financial capabilities. Besides, it is also
concurred by the case study that the Ethiopian Roads Authorities has implemented in recent year
to allow pre-financing for material purchasing with separate rules and regulations to alleviate the
financial problem and improper utilization of the advance payment. This financial assistance will
facilitate timely commencement of projects and smooth supply of construction material and
spare for smooth progress of the project without delay.
The planning related problems are addressed in many ways; planning is intentionally neglected
by contractor either due to shortage of professionals, or due to resource shortage. The resource
shortage usually results in assigning of unrealistic resource which usually incomparable to the
project work load or capacity problem of the contractor.
5.3 Recommendation
a) It is recommended that the client has to set equivalent criteria to the project
requirements, and avoid the participation of contractors with bad time performance or
arrange the project in to lots or sections in order to fit to the capacity of the local firm
b) It needs appropriate contractual clauses for proper utilization of the release amount of
advance payment explicitly for the specific project cash flow purpose.
c) Financial problem mainly due to lack of credit facilities for material, equipment or
bank loan and unavailability of subcontractor will result in problems on the capacity
of main contractors. It is recommended that till these banks loan and credit facilities
are available, the only proposal is further client assistance with pre-financing for
material purchasing. But the pre-financing should be implemented taking into strict
rules and regulations which set transparent guide line to contractors
Factors affecting time performance of Local Road contractors on Federal road Construction projects 56
AAiT School of Civil & Env. Engineering COTM Stream
d) Policy makers should set appropriate and convincing rules and regulations in order to
manage the inflow and outflow of cashes effectively. In addition, in line with creating
fertile and binding grounds, the concerned body needs to conduct trainings (short and
long terms) so that each party internalizes the rules and regulations.
e) Develop benchmark which used as reference for scheduling; such as equipment or
labor hourly output. Moreover proper recording is also necessary for future planning
data such as equipment and labor output
f) Poor and/or erroneous design has resulted in poor time performance; hence the
quality of project design needs improvement
g) The employer time fixing need some transparency to solve problems in some
projects
h) The respondents also commented on the current least bidder project awarding system
which increases low bidding and consequently cash shortage and poor time
performance.
i) The respondents proposed that the license criteria of the contractors need to revisited
with respect to the power, requirement of professionals more than financial and
resources requirements
j) The contractor shall require to check his capacity with detail pre-contract planning for
all resource requirements and satisfied himself for the project.
k) Professionals training should be given in various aspects of the project activities.
particularly, planning, designing, site management and equipment management
strictly demand the touch of professional, and they of course, deserve due attentions
from deferent parties.
l) Thus, care need to be taken in assigning proper and skill full project manager with
full delegation and accountability.
m) Finally the researcher is recommended the following issues for future researches
method and procedure of contract time determination,
method and procedure of time extension
effect of Procurement selection criteria and tendering methods on project time
performance for the Ethiopian conditions
Factors affecting time performance of Local Road contractors on Federal road Construction projects 57
AAiT School of Civil & Env. Engineering COTM Stream
Factors affecting time performance of Local Road contractors on Federal road Construction projects 58
AAiT School of Civil & Env. Engineering COTM Stream
References
1. Abdissa Dessa (2003). Claims in Ethiopian Construction industry. Thesis submitted to
Addis Ababa University, Addis Ababa, Ethiopia
2. Aftab Hameed Memon (2010). Factors affecting construction cost in Mara Large
construction project, International Journal of Sustainable Construction Engineering.
Vol.1 No.2, Quaid Awan University of Engineering , Pakistan
3. Akintoye,A and Takim, R. (2002); Performance indicators for successful construction
project performance, a Research in Construction Management Vol.2 pp.545-555
Glasgow,UK
4. Albert Chan (2002). Benchmarking project construction time performance, International
Journal of Project Management, Hong Kong
5. Brian.C, Deepak. G. and Edward.F (2003).Performance-Based Contracting for the
Highway Construction Industry, Columbus, OH, USA
6. D. McGeorge and A. Palmer (2002); Construction Management: New Direction, second
edition, Glasgow Caledonian University, Scotland, UK
7. Darren R. Hale, P.E. (2009). Empirical Comparison of Design/Build and
Design/Bid/Build Project Delivery Methods, Journal of Construction Engineering
Management, American Society of Civil Engineers, USA
8. Dubem I. Ikediashi (2012). Key performance indicators of DB project in Nigeria,
Department of Building University of Uyo, Nigeria
9. G. Ofori. (2000) Challenge of construction industries in developing countries.
Department of building, National University of Singapore
10. Imbert, I.D.C. (1990). Human issues affecting construction in Developing Countries,
Construction Management and Economics Vol.8 pp. 219-228
11. John Egan (1998) Re-thinking. Construction; Report of the Construction Task Force,
London, UK
12. Gidado, K. (2004). Enhancing the prime contractor’s pre-construction planning; Journal
of Construction Research Vol.5, University of Brighton, Brighton, UK
13. K. Wong and V. Vimonsatit (2012). A study of the factors affecting construction time in
Western Australia; Research and Essay vol.7(40), pp. 3390-3398, Department of Civil
Engineering Curtin University, Perth, Australia
Factors affecting time performance of Local Road contractors on Federal road Construction projects 59
AAiT School of Civil & Env. Engineering COTM Stream
14. Khaled Nassar (2012). Using Risk Assessment to Improve Highway Construction Project
Performance, Associated school of Construction, Cairo, Egypt
15. Low Sui Pheng (2005). Environmental factors and Work performance of Project manager
in the construction industry, International Journal of Project Management, National
University of Singapore, Singapore
16. Mohamed F.Diab (2012); Using Risk Assessment to improve Highway Construction
Project Performance, 48th ASC Annual International Conference, North Dakota State
University, USA
17. Nguyen Duy Long (2004). Large construction projects in developing Countries: a case
study from Vietnam, International Journal of Project Management, University of Hong
Kong
18. Per Erik Eriksson (2011). Effects of procurement on construction project performance,
Lulea University of Technology, Sweden
19. Ruth Apolot (2008), An Investigation into the Causes of Delay and Cost Overrun in
Uganda’s Public Sector Construction Projects, International Conference on advances in
Engineering and Technology pp. 305-312, Marerere University, Kampala, Uganda
20. Saleh Samir (2008). Factors affecting the performance of construction projects in Gaza
Strip, Msc. Thesis submitted to Islamic University of Gaza, Palestine
21. Shahrzad Khosravi (2011); a success measurement model for construction project,
International Conference on Financial Management and Economics Vol. 11, IACSII
press, Singapore
22. Susandi (2003). Lecture, On representing Factors influencing Time performance of Shop
House construction in Surabaya Vol.5 No.1, Indonesia
23. Wubishet Jekale (Dr.Ing) (2008). Time planning for construction projects: An
international Multi-Disciplinary Journal Vol.2 (4) pp. 88-122, Addis Ababa, Ethiopia.
24. Zedan Hatush and Martin Skitmore (1995): .Assessment and evaluation of contractor data
against client goals using PERT approach; Construction Management and Economic Vol.
15(4) pp. 327-340, surveying University of Salford, UK
Factors affecting time performance of Local Road contractors on Federal road Construction projects 60
AAiT School of Civil & Env. Engineering COTM Stream
Questionnaire
1.2 What was your project delivery system, please specify (DBB, DB, BOT etc)
____________________
1.3 please specify your project procurement method( open invitation,
_____________________
1.4 What kind of method did you use for project planning and scheduling?
Choose all appropriate
a. Bar Chart Method b.CPM c. any other method please
specify________________________________
1.5 How often your project being evaluated, monitored, updated and controlled?
Choose all appropriate
a. Daily b. Weekly c. Monthly d. Quarterly
e. NA
1.6 What were your communication practices with the parties and your staff in
the project? choose all appropriate
a. Letter b. Site meeting c. Verbal discussion d. if any
other method, please specify_____________________
1.7 Do you feel that pre-construction planning is crucial for better time
performance?
a. always b. often c. sometime
d. may not have any impact
1.8 Do you feel that pre-construction planning shall be included as part of
contract document
a. always b. often c. sometime
Factors affecting time performance of Local Road contractors on Federal road Construction projects 61
AAiT School of Civil & Env. Engineering COTM Stream
1.13 (Optional)
Date ______________________________
Factors affecting time performance of Local Road contractors on Federal road Construction projects 62
AAiT School of Civil & Env. Engineering COTM Stream
Instruction: please thick (√) or (X) in the space provided as per the scale given
below, you may check your choice as per your opinion and
experience in the construction sector
Scale indicators
1 Not important
2 Slightly important
3 Moderate Important
4 Very important
5 Extremely important
Scale Indicator
No Description of the factors
1 2 3 4 5
1 Unrealistic target setting (planning);
Factors affecting time performance of Local Road contractors on Federal road Construction projects 63
AAiT School of Civil & Env. Engineering COTM Stream
Scale Indicator
No Description of the factors
1 2 3 4 5
Vague or unclear speciation of the of the project
Scope of the project was not clearly defined or changed
every time
Adverse weather condition
Incremental weather condition on site
Problem during Construction
2 MANAGEMENT FACTORS
2. Coordination
Scale Indicator
No Description of the factors
1 2 3 4 5
5. Variation and changes
6. Documentation
8. please specify if any other management factors that affect project time
performance_____________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
Scale Indicator
No Description of the factors
1 2 3 4 5
3 FANANCIAL FACTORS
9. Problem of cash flow management
Factors affecting time performance of Local Road contractors on Federal road Construction projects 65
AAiT School of Civil & Env. Engineering COTM Stream
Scale Indicator
No Description of the factors
1 2 3 4 5
Failure of the client to pay payment resulted from claim
Claim Processing is extended not treated fairly
12. Lack of credit facilities
13. please specify if any other financial factors that affect project time
performance___________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________
Scale Indicator
No Description of the factors
1 2 3 4 5
4 TECHNICAL FACTORS
5 MATERIAL FACTORS
16. Procurement
Late in purchasing and delivery of construction material
Factors affecting time performance of Local Road contractors on Federal road Construction projects 66
AAiT School of Civil & Env. Engineering COTM Stream
Scale Indicator
No Description of the factors
1 2 3 4 5
Lack of material in local market (unreliable supplier)
Rising cost of material
17. Credit facilities
19. please specify if any other material related factors that affect project time
performance
________________________________________________________________________
________________________________________________________________________
________________________________________________________________
Scale Indicator
No Description of the factors
1 2 3 4 5
6 EQUIPMENT FACTORS
20. Availability
Factors affecting time performance of Local Road contractors on Federal road Construction projects 67
AAiT School of Civil & Env. Engineering COTM Stream
23. please specify if any other equipment related factors that affect project time
performance
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
Scale Indicator
No Description of the factors
1 2 3 4 5
7 CONSTRUCTION WORKERS
26. please specify if any other labor related factors that affect project time
performance
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
27. In your opinion is the resources mobilization for your project especially equipment is
sufficient in type and number as required by your project and as scheduled? Usually/ seldom,
Factors affecting time performance of Local Road contractors on Federal road Construction projects 68
AAiT School of Civil & Env. Engineering COTM Stream
30. In your opinion is the man powers mobilized for your project well understood the project
specification, contract document, detail drawing or need training, please note your
recommendation
________________________________________________________________________
________________________________________________________________________
__________________________________________________________
31. Do you fill the project delivery system for your project appropriate for the specific
situation or would have been better to other alternative contracting method please
specify and reason your recommendation
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
__________________________________________________________
Factors affecting time performance of Local Road contractors on Federal road Construction projects 69
AAiT School of Civil & Env. Engineering COTM Stream
Factors affecting time performance of Local Road contractors on Federal road Construction projects 70
AAiT School of Civil & Env. Engineering COTM Stream
Factors affecting time performance of Local Road contractors on Federal road Construction projects 71
AAiT School of Civil & Env. Engineering COTM Stream
Factors affecting time performance of Local Road contractors on Federal road Construction projects 72
AAiT School of Civil & Env. Engineering COTM Stream
The following guideline is undertaken to analysis a case study of the selected projects
As indicated in the methodology of this research, the following four projects have been
analyzed for factors that affect the time performance. All of the four projects have poor time
performance in which the project have completed or under progress on extended time beyond
their original contract completion period.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 73
AAiT School of Civil & Env. Engineering COTM Stream
The project is part of Tongo-Begi-Mugi project located in the western part of the country in west
Wollega Zone of the Oromiya Regional state which is dominated by rainy weather especially
from May to November. The project is design under categories of DS5 of the Ethiopian Roads
Authority roads classification with gravel wearing course surface finish. The total length of the
project is 90km which was fully inaccessible and majority part of the project stretch is covered
with forest. Gidami-Mugi project is started under the implementation of RSDP III and currently
on progress as part of RSDP IV. The project was delivered as design bill build (DBB) system
with open competitive procedure of contractor selection
Data taken from the Resident Engineer monthly progress report and archive records
VO1=4,546,663(omission),
VO2=14,850,359.56(addition),VO3=21,795,557.85(addition),VO4=8,477,743.98(
addition)
Factors affecting time performance of Local Road contractors on Federal road Construction projects 74
AAiT School of Civil & Env. Engineering COTM Stream
Increased quantity
The amount for Earthwork bill item has increased by ETB16,257,875 mainly the
encounter hard excavation which was not considered in the design stage
Minor drainage has increased by an amount of ETB 17,404,321.73 mainly due to
introduction of masonry and concrete retaining wall for high fill slope protection
Major drainage structure has increased by ETB 10,861,569 due the revision of
substructure detail for one bridge from Masonry to concrete abutment following
the foundation investigation
Adverse weather condition
Interview taken from the Resident Engineer and the project manager
There was no consideration of any rock/hard excavation and retaining wall for fills and/or cut
slope. In the initial time calculation impact of rainy weather condition with the resulting after
effect (the excess moisture content will not reduce after month of the rainy period due to high
forest coverage) was not properly considered in which both parties agree.
Moreover, even after the granted time extension and with the current condition, the contractor
will lagging behind time and there will be further extension of the completion date
The advance payment is fully utilized for purchasing of equipment which result in working
capital shortage and delay in purchasing and supply of construction materials
Scope definition; having 90km for one project and one stretch which has no any access.
The project is fully inaccessible, so the contractor has constructed his and the engineer’s
camp two times; at km 0+000 (one at beginning of the project) and move to middle of the
project when work progress and he get access with single payment
Improper contract duration (unrealistic contract time); no consideration for weather
condition, and access to and within the site and, no consideration for forest coverage effect.
The project is far from the head office which takes longer time for material supply, no
access through the project corridor which makes the preparatory work difficult. They
viewed that special consideration shall be given to new construction during time
calculation
Factors affecting time performance of Local Road contractors on Federal road Construction projects 75
AAiT School of Civil & Env. Engineering COTM Stream
Poor design; the variations are resulted from poor design mainly lack of detail site
investigation along the project route; hard excavation was not considered in the design
stage which forces the contractor for new resources mobilization and required additional
time.
Contractor pre tender planning; the contractor has not well understood the project site
condition during the tendering stage and at start of the project. The contractor fails to see
the whole route before his tender submission and unable to identify the availability of
material sources such as GWC, method of construction and proper billing
Adverse weather condition; the site area is dominated with five to six month of rainy
weather per year and more than one month time after effect. Equipment are usually idle
five to six month per year due to weather condition
Tender criteria; the requirement set for contractor selection was too small in comparison to
the project. The work load of the project requires huge resources in which the contractor
fail to mobilization with his capacity
Poor contractor site management, there is no proper planning and currently there is no
revised schedule even EOT is granted to the contractor
Shortage of professional and high turnover; in past three and half year of the project time
the project face high professional turnover and the project is now suffer in shortage of
Engineers, Forman and operators
Shortage of equipment; even the current deployed equipments are still not comparable to
the work load
Lack of communication; the area is far from town and difficult to communicate from the
head office and within site
The project is part of Arbaminch-Jinka road upgrading project located in the Southern part of the
country in the SNNPR state. The project is design under categories of DS4 of the Ethiopian
Roads Authority roads classification with double surface treatment wearing course surface finish.
The total length of the project is 90km which was initially have gravel access. The project is
started under the implementation of RSDP III and currently on progress as part of RSDP IV. The
Factors affecting time performance of Local Road contractors on Federal road Construction projects 76
AAiT School of Civil & Env. Engineering COTM Stream
project was delivered as design bill build (DBB) system with open competitive procedure of
contractor selection
Data taken from the A/Resident Engineer monthly progress report and archive records
Contract Duration =1095Calendar Day from May 6, 2006 to May 14, 2009
Contract Amount=ETB434, 567,292.42, including PS, 10% contingency and 15% VAT
Variation order issued to date;
Factors affecting time performance of Local Road contractors on Federal road Construction projects 77
AAiT School of Civil & Env. Engineering COTM Stream
automatically become too close to the existing road especially the Bailey bridge and endanger its
stability, hence horizontal alignment modification is required to preserve the exiting road and the
Bailey bridge for public traffic till the main construction is completed. Moreover, as a result of
heavy flood, the Jinka side river bank has scoured below the original design level and the design
abutment height become more than the permissible height for masonry wall. Hence revision was
made by increasing the span far from the river course to get reduced height.
Generally the original design for the Weito River Bridge lacks, detail foundation investigation
work during the design stage, the alignment didn’t considered sufficient gap to avoid any
interference to the exiting Bailey bridge which has been used for public traffic till the new road
is opened to traffic.
So, the project time performance increased by 33% mainly, incomplete design which lacks detail
subsurface investigation and alignment problem. Furthermore the client, ERA has granted
180calendaer day administrative for whole project due to cement supply problem in the country
in the year 2010 which increase the PTP further by 16%
Moreover, beside design problems, the project has not yet fully completed due to problem
associated supply and management, cash flow shortage.
Maytsebry-Dima Road project
Contract Duration =1095Calendar with the completion date of May, 14, 2012
Contract Amount=ETB258, 721,412.42, including PS, 10% contingency and 15% VAT
Variation order issued (four in number); 206,296,393.46
Revised contract amount=519,732,519.36
Factors affecting time performance of Local Road contractors on Federal road Construction projects 78
AAiT School of Civil & Env. Engineering COTM Stream
Percentage increment=79.74%
The total extension of time granted 425 Calendar days; mainly the Extension of time issued was
due to the issued variation basically change of the scope of the project standard
Revised completion date become July 13, 2013
Percentage of time increased=2520/1095=139%
Current elapsed time=1447 or 95.20% as per the revised contract time
From the above, it can be learnt that the project time performance has increased by 39% as a
result of the issued variation orders and
Causes for time extension
It can be learnt that the employer has changed the whole project scope from the DS5 gravel road
to DS4 double bituminous surface treatment road standard after the construction was started.
Furthermore the provision of fog spare is also supplemented as the project was under progress.
Hence the main factor for the project delay is the employer failure to properly defining the scope
of the project in the initial planning time. The project manager and the resident engineer in their
interview has concurred that the project has no any supply problem for daily execution of the
project and will be completed on the revised project time.
The project is part of Durbete-Kunzula-Dengelber-Gelego new Feeder road project located in the
Amehra regional state in North West part of the country. The project is design under categories
of DS5 of the Ethiopian Roads Authority roads classification with gravel wearing course surface
finish. The total length of the project is 147km which was initially have no any access. The
project is started under the implementation of RSDP II and completed in the year as part of
Factors affecting time performance of Local Road contractors on Federal road Construction projects 79
AAiT School of Civil & Env. Engineering COTM Stream
RSDP IV. The project was delivered as design bill build (DBB) system with open competitive
procedure of contractor selection
Data taken from the Resident Engineer monthly progress report and archive records
Contract Duration =1095Calendar Day from October 10, 2005 to October 09, 2008
Contract Amount=ETB341, 479,872.47, including PS, 10% contingency and 15% VAT
Variation order issued to date;
Total granted time was 993Calendar days; mainly the Extension of time issued was due to
increase volume of rock excavation and drainage structure; pipe culverts has changed to slab and
slab is also changed to bridge and cement shortage in the local market
Revised completion date become June 29, 2011
Percentage of time increased=2088/1095=190.70%
Causes for time extension
Increased quantity
o The original volume of rock excavation has increase
o Due to hydrology error additional pipes culverts are included, pipes culverts
have changed to slab and some slab culverts are increased their size
Shortage of cement in the local market, ERA has granted 6month administrative time
extension
The resident engineer has confirmed that design error is observed mainly in classification of
roadway excavation in stretch which was designed as soft excavation has significantly changed
to roach as work progress. Hydrological design has miss some structure and/or underestimate
their capacity which result in additional drainage structure works. Generally, the overall project
load has increased by 12.28% in which earthwork has increased by 18%, minor drainage has
increased by 67.86% and Major drainage has increased by 31.16%
Factors affecting time performance of Local Road contractors on Federal road Construction projects 80
AAiT School of Civil & Env. Engineering COTM Stream
An interview guideline and interview for possible mitigation measures of poor time
performance
Following the analysis of survey data results, for major factor affecting project time
performances were investigated in a great depth by interviewing experienced professional to
alleviate the problem and possible recommendation for upcoming projects. These also lead to
possible list of measure that will mitigate the problems. This stage of the study was achieved
through a series of in-depth interviews, which was already indicated in the research
methodology. Accordingly, two senior professional which have been participating in the
local road construction sector for more than twenty years were selected for interview; one
being the general manager of local consulting firm and the other being general manager of
one GC1 contractor.
The interview was made following the data collection and major time performance ranking
factor from the respondents are indentified. Question was specifically raised for expert
interview for their opinion on the degree of agreement of the factor for their possible
recommendation to improve the prevailing poor time performance of the road construction
sector in the upcoming project.
literature has shown in the developed nation an alternative project delivery system such
as DB has considered as option to improve construction project time performance; they
responded that the develop nation have sufficient secondary data; Arial photo,
Geographical and Geological maps which facilitate the estimation for proper biding. But
for the Ethiopian situation these secondary data are not available on easily updated
condition which make problem for the contractor in addition to their low level of design
capacity of the local contractor. They responded that the alternative project delivery
system not yet expected to merit any time performance with the two main situations lacks
of secondary data and low design capacity of the local firm.
The criteria set for the contract during the tendering is not incomparable to the work load,
the contractor has lack experience, resource but fulfill the bidding criteria set by the
employer. It recommended that the client has set equivalent criteria to the project
requirement and avoid the participation of contractors with bad performance or arrange
Factors affecting time performance of Local Road contractors on Federal road Construction projects 81
AAiT School of Civil & Env. Engineering COTM Stream
the project in to lots or section to a minimum the capacity of the local firm. Moreover
tender floatation shall also consider the capacity of the local firm.
Among the many poor planning followed by lack commitment, coordination and
monitoring is among the factors that results poor time performance. The head office,
especially the owner and the site management has no clear structural arrangement, poor
coordination. It is not uncommon to observe problem related to planning, controlling,
communication in every project; detailed pre-construction planning is the crucial issue in
consideration to the source (owned or rent) of equipment, set up project management
team, assignment of proper project manager and other professional, authorization of the
project manager, line of resource supply and monitoring mechanism of the performance
of the project team. The project manager with his site management team must have full
authority of the decision making power.
The time given to the design will automatically result poor design which in turn result
incomplete design, and/or erroneous design which affect the daily performance of the
project during construction. The client has to give due consideration during design to
minimize the amount of variation which impact the performance during construction.
Improper advance utilization by the contractor which is very important factor for poor
time performance need strict control by the employer; so it need contractual clauses for
proper utilization of the release amount explicitly for the specific project cash flow
purpose.
Financial problem mainly due to credit facilities for material, equipment or bank loan and
unavailability of subcontractor will results to problem on the capacity of the main
contractors; from the literature review it learnt that the capacity of the main contractor
can be improved through subcontracting for suppliers and different specialization. Short-
term bank loan and/or credit facilities from material suppliers, equipment sellers and
renting firm, but the Ethiopian situations still far from the develop world and all the
responsibility rest on the main contractor which threat his financial capabilities. Hence
till these banks loan and credit facilities are available the only proposal is further
increment of the current advance payment amount up to 40% but with strict bounding
clause for disbursement to the project purpose or provide assistance through pre-
financing for material purchasing.
Factors affecting time performance of Local Road contractors on Federal road Construction projects 82
AAiT School of Civil & Env. Engineering COTM Stream
Factors affecting time performance of Local Road contractors on Federal road Construction projects 83
AAiT School of Civil & Env. Engineering COTM Stream
Declaration
I the undersigned, declare that this thesis entitled “FACTORS AFFECTING TIME
PERFROMANCE OF LOCAL ROAD CONTRACTORS ON FEDERAL ROAD
CONSTRUCTION PROJECTS” is my original work. This thesis has not been presented for any
other university and is not concurrently submitted in candidature of any other degree, and that all
sources of material used for the thesis have been duly acknowledged.
Signature: _____________________________________________
Factors affecting time performance of Local Road contractors on Federal road Construction projects 84
AAiT School of Civil & Env. Engineering COTM Stream
Annexes
Factors affecting time performance of Local Road contractors on Federal road Construction projects
AAiT School of Civil & Env. Engineering COTM Stream
Annex 1
Factors affecting time performance of Local Road contractors on Federal road Construction projects
AAiT School of Civil & Env. Engineering COTM Stream
Annex 2
(Case study guidelines and analysis)
Factors affecting time performance of Local Road contractors on Federal road Construction projects
AAiT School of Civil & Env. Engineering COTM Stream
Annex 3
(Interview guidelines and interview)
Factors affecting time performance of Local Road contractors on Federal road Construction projects
AAiT School of Civil & Env. Engineering COTM Stream
Annex 4
(Interview guidelines and interview)
Factors affecting time performance of Local Road contractors on Federal road Construction projects