Section: A
PROJECT NAME :A100- IRIS DATA CENTER
OSOOL ALROYAH GENERAL CONTRACTING
P.O. Box 93135 Abu Dhabi, UAE
COMPANY NAME Telephone: (+971) 2 5524430
Fax No: (+971) 2 5524435
E-mail: info@osoolalroyahuae.com
Document Title
METHOD STATEMENT FOR EXCAVATION WORKS
Document Ref No.
Consultant SUDLOWS
Client PIVOT ASSET HOLDING RSC LTD
Project Description A 100- IRIS DATA CENTER
File No.
Project Location ABU DHABI UAE
QA/QC Engineer Site Safety Manager Project Manager
00 24/8/2021
Revision Method Statement Risk Assessment Approved by
Revision Date Reviewed by
Details Prepared by Prepared by CONSULTANT
Controlled Copy Uncontrolled Copy
CONTRACTOR NAME: MENASCO MECHANICAL CONTRACTING LLC Section: B
PROJECT NAME : A 100- IRIS DATA CENTER
B SUMMARY OF CHANGES
Revision
Date Section No. Summary of Changes Page No.
No.
CONTRACTOR NAME: MENASCO MECHANICAL CONTRACTING LLC
Section: C
PROJECT NAME : A 100- IRIS DATA CENTER
C TABLE OF CONTENTS
Number
Section Description Revision
of Page
A Cover Page 1
B Summary of Changes 2
C Table of Contents 3
1 Scope & objectives 4
2 Reference 4
3 Health and safety hazards 4
4 Definitions 4
5 Responsibilities 4
6 Procedure / method to be employed 5
7 Manpower requirements 6
8 Material requirements 6
9 Equipment 6
10 Health and safety provisions 6
11 QC approvals and other documents 7
12 Distribution 7
13 Attachments 7
14 Risk assessment & control measures
15 Environmental aspect, impact & control measures
16 Inspection test plan
1.0 SCOPE & OBJECTIVES
The purpose of this procedure is to define how excavation shall be carried out under controlled condition.
Excavation includes, removal of soil, rock, debris and concrete from piles breaking and to haul/stored the
excavated soil by the approved third party for waste management by the Consultant Representative “M/S
Technical Overseas General Transport EST”.
2.0 REFERENCE
All related codes and standards referenced in the Project Specifications.
Contract drawings.
Approved shop drawings.
Program of works.
Approved project safety plan and procedures.
3.0 HEALTH AND SAFETY HAZARDS
Specific safety measures have to followed as applicable, and all the safety measures are covered
separately in the Project Safety Plan.
4.0 DEFINITIONS
ACE - WHITE SPACE
ASQ - INEX Contracting & Interiors LLC
MS - Method Statement
ITP - Inspection & Test Plan.
TBA - To be advised.
5.0 RESPONSIBILITIES
Project Procedure - QA/QC Engineer
Review of Procedure - Construction Manager
Approval of Procedure - Project Manager
Execution of Procedure - As described in the procedure
The Construction Manager will be responsible for the delegation of works to designated persons and
QA/QC Department will be the responsible for inspection and acceptance of any works.
6.0 PROCEDURE / METHOD TO BE EMPLOYED
6.1 Excavation Works
a. Before commencement of work ascertain the nature and location of all existing (above and underground)
services on site by visual survey or by reviewing the service layout drawing.
b. If any protection, rerouting, termination or removals of services are required for the smooth processing of
work, it shall be discussed and written approval shall be obtained from the Engineer as appropriate.
c. Provide safe barricade 1m away from the excavation area for the safe of all workers at designated area.
d. Surveyor to be mark in all perimeter of the building the require depth to be excavated up to formation level
of raft foundation.
e. Include in excavation, removal of soil, rock, pavement, demolished structures below grade, concrete debris
from pile breaking using excavator and jack hammer.
f. Once the raft foundation reaches the formation level the surveyor will set the coordinates and depth of
individual pile caps as per approved drawing prior to commence excavation up to formation level for pile
caps.
6.2 Disposal Works
a. Remove disturbed earth displaced by adjacent construction.
b. Segregate all the debris and excavated soil at the designated area.
c. The Contractor for the Waste Management “M/S Technical Overseas General Transport EST.” arrange the
daily hauling and removal of excavated soil and all foreign materials not require at site.
d. Dispose of all excess and unsuitable excavated materials away from site to a location approved by local
authorities.
e. Store excavated materials that are approved for use as fill in a segregated manner, so as not to obstruct
the site, and at sufficient distance from edge of excavation to ensure that the side of excavation is not
overloaded.
7 MANPOWER REQUIREMENTS
Equipment Operators
Foreman
Watchman
Helpers
Surveyor
Civil QC Personnel
Safety Officer
8 MATERIAL REQUIREMENTS
No materials for this activity.
9 EQUIPMENT
Excavator
Bobcat
Level machine& total station
Dump/hauling trucks
Hand Tools (Shovel, Pick Axe…etc.)
10 HEALTH AND SAFETY PROVISIONS
o All Works shall be controlled as the Safety Procedures. Safety equipment will be
worn at all times.
o Site Safety Officer will check and ensure all safety precautions are taken prior to
commencement of work.
o All the working platforms will be inspected by Site Safety Engineer
o The working area must be clearly marked with sufficient hazard boards, alarming
tape and cones if needed.
o Safety procedures are to be considered before, through and after completion of
the work to avoid any possibility of danger to the Humans or to the Construction.
o All work places will be cleaned from waste materials and ensuring clean and
healthy work environment, as well as maintained pre-access and egress in the
event of emergency.
11 QC APPROVALS AND OTHER DOCUMENTS
o Project HSE Plan
o All drawings shall be approved
o Calibration certificates for equipment and instruments
o Approved Contractor(s) for waste management
12 DISTRIBUTION
Copies of this method statement shall be issued to the following for implementation.
Construction Manager
Project Engineer
HSE Engineer.
QA/QC Engineer.
13 ATTACHMENTS
Risk Assessment & Control Measures
Environmental Aspect,Impact & Control Measures
Inspection Test Plan
The Method Statement shall be approved by Consultant prior to commence Excavation works for Raft
Foundation.
NOTE: Works shall not be limited to these procedures as new and more applicable methods maybe
employed during the work executions. In this case, proper notification or approval will be obtained from
Consultant as applicable.